CN106594386A - 一种非开挖钻顶联合穿跨越管道铺设方法 - Google Patents
一种非开挖钻顶联合穿跨越管道铺设方法 Download PDFInfo
- Publication number
- CN106594386A CN106594386A CN201611207078.6A CN201611207078A CN106594386A CN 106594386 A CN106594386 A CN 106594386A CN 201611207078 A CN201611207078 A CN 201611207078A CN 106594386 A CN106594386 A CN 106594386A
- Authority
- CN
- China
- Prior art keywords
- well
- jacking
- construction
- received well
- horizontal directional
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/024—Laying or reclaiming pipes on land, e.g. above the ground
- F16L1/028—Laying or reclaiming pipes on land, e.g. above the ground in the ground
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Earth Drilling (AREA)
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611207078.6A CN106594386B (zh) | 2016-12-23 | 2016-12-23 | 一种非开挖钻顶联合穿跨越管道铺设方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611207078.6A CN106594386B (zh) | 2016-12-23 | 2016-12-23 | 一种非开挖钻顶联合穿跨越管道铺设方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106594386A true CN106594386A (zh) | 2017-04-26 |
CN106594386B CN106594386B (zh) | 2019-03-01 |
Family
ID=58603492
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611207078.6A Active CN106594386B (zh) | 2016-12-23 | 2016-12-23 | 一种非开挖钻顶联合穿跨越管道铺设方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106594386B (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107191675A (zh) * | 2017-07-21 | 2017-09-22 | 中铁二十三局集团第二工程有限公司 | 铁路站场电化区段管道铺设施工工法 |
CN107524217A (zh) * | 2017-09-18 | 2017-12-29 | 金丹 | 一种自动铺管车 |
CN108952570A (zh) * | 2018-05-31 | 2018-12-07 | 广州市电力工程有限公司 | 基于精确定向钻技术的复合非开挖施工方法 |
CN108980461A (zh) * | 2018-09-07 | 2018-12-11 | 中水电第十工程局(郑州)有限公司 | 一种受限空间下顶管施工中的起重吊装施工工艺 |
CN109506042A (zh) * | 2018-11-30 | 2019-03-22 | 江苏谷登重型机械装备科技有限公司 | 一种分动器及其施工装置 |
WO2020049473A1 (en) | 2018-09-06 | 2020-03-12 | Geohidroterv Kft. | Jet-system pipe laying procedure and device for implementing the procedure |
CN111794764A (zh) * | 2020-06-30 | 2020-10-20 | 广东省第一建筑工程有限公司 | 一种顶拉施工方法 |
CN111911712A (zh) * | 2020-07-03 | 2020-11-10 | 广州市第一市政工程有限公司 | 一种拉顶管式非开挖管道施工方法 |
CN116255504A (zh) * | 2023-05-15 | 2023-06-13 | 中铁四局集团有限公司 | 一种单侧造斜的水平定向钻管道施工方法 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09196233A (ja) * | 1996-01-17 | 1997-07-29 | Tokyo Gas Co Ltd | 鋼管の引込み工法 |
CA2145126C (en) * | 1994-03-22 | 1998-07-28 | Frank E. Fuller | Pipe laying system and method |
CN1506605A (zh) * | 2002-12-12 | 2004-06-23 | 上海市机械施工公司 | 地下顶管二工序施工方法 |
CN1865650A (zh) * | 2006-06-22 | 2006-11-22 | 刘明明 | 水平螺旋钻机与水平定向钻机协同工作顶管施工方法 |
CN201875282U (zh) * | 2010-11-17 | 2011-06-22 | 代丽华 | 气动曲线穿孔机 |
US20130175092A1 (en) * | 2012-01-05 | 2013-07-11 | Merlin Technology, Inc. | Directional drilling target steering apparatus and method |
DE102012003120A1 (de) * | 2012-02-16 | 2013-08-22 | Rüdiger Kögler | Verfahren und Vorrichtungen zur Verlegung von Rohrleitungen im Boden |
CN103527850A (zh) * | 2013-11-01 | 2014-01-22 | 浙江富浩管业有限公司 | 超大口径pe排水管的非开挖施工*** |
CN104864177A (zh) * | 2015-03-27 | 2015-08-26 | 中国地质大学(武汉) | 一种非开挖钻顶结合管道穿越方法 |
-
2016
- 2016-12-23 CN CN201611207078.6A patent/CN106594386B/zh active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2145126C (en) * | 1994-03-22 | 1998-07-28 | Frank E. Fuller | Pipe laying system and method |
JPH09196233A (ja) * | 1996-01-17 | 1997-07-29 | Tokyo Gas Co Ltd | 鋼管の引込み工法 |
CN1506605A (zh) * | 2002-12-12 | 2004-06-23 | 上海市机械施工公司 | 地下顶管二工序施工方法 |
CN1865650A (zh) * | 2006-06-22 | 2006-11-22 | 刘明明 | 水平螺旋钻机与水平定向钻机协同工作顶管施工方法 |
CN201875282U (zh) * | 2010-11-17 | 2011-06-22 | 代丽华 | 气动曲线穿孔机 |
US20130175092A1 (en) * | 2012-01-05 | 2013-07-11 | Merlin Technology, Inc. | Directional drilling target steering apparatus and method |
DE102012003120A1 (de) * | 2012-02-16 | 2013-08-22 | Rüdiger Kögler | Verfahren und Vorrichtungen zur Verlegung von Rohrleitungen im Boden |
CN103527850A (zh) * | 2013-11-01 | 2014-01-22 | 浙江富浩管业有限公司 | 超大口径pe排水管的非开挖施工*** |
CN104864177A (zh) * | 2015-03-27 | 2015-08-26 | 中国地质大学(武汉) | 一种非开挖钻顶结合管道穿越方法 |
Non-Patent Citations (1)
Title |
---|
贾春磊等: "水平定向钻顶管结合工法的可行性分析", 《地质科技情报》 * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107191675A (zh) * | 2017-07-21 | 2017-09-22 | 中铁二十三局集团第二工程有限公司 | 铁路站场电化区段管道铺设施工工法 |
CN107524217A (zh) * | 2017-09-18 | 2017-12-29 | 金丹 | 一种自动铺管车 |
CN108952570A (zh) * | 2018-05-31 | 2018-12-07 | 广州市电力工程有限公司 | 基于精确定向钻技术的复合非开挖施工方法 |
WO2020049473A1 (en) | 2018-09-06 | 2020-03-12 | Geohidroterv Kft. | Jet-system pipe laying procedure and device for implementing the procedure |
CN108980461A (zh) * | 2018-09-07 | 2018-12-11 | 中水电第十工程局(郑州)有限公司 | 一种受限空间下顶管施工中的起重吊装施工工艺 |
CN108980461B (zh) * | 2018-09-07 | 2020-05-01 | 中电建十一局工程有限公司 | 一种受限空间下顶管施工中的起重吊装施工工艺 |
CN109506042A (zh) * | 2018-11-30 | 2019-03-22 | 江苏谷登重型机械装备科技有限公司 | 一种分动器及其施工装置 |
CN111794764A (zh) * | 2020-06-30 | 2020-10-20 | 广东省第一建筑工程有限公司 | 一种顶拉施工方法 |
CN111794764B (zh) * | 2020-06-30 | 2021-07-23 | 广东省第一建筑工程有限公司 | 一种顶拉施工方法 |
CN111911712A (zh) * | 2020-07-03 | 2020-11-10 | 广州市第一市政工程有限公司 | 一种拉顶管式非开挖管道施工方法 |
CN116255504A (zh) * | 2023-05-15 | 2023-06-13 | 中铁四局集团有限公司 | 一种单侧造斜的水平定向钻管道施工方法 |
CN116255504B (zh) * | 2023-05-15 | 2023-08-11 | 中铁四局集团有限公司 | 一种单侧造斜的水平定向钻管道施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106594386B (zh) | 2019-03-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106594386B (zh) | 一种非开挖钻顶联合穿跨越管道铺设方法 | |
CN104864177B (zh) | 一种非开挖钻顶结合管道穿越方法 | |
AU2021100936A4 (en) | Process of putting screen pipe in directionally drilled branch hole of soft coal seam | |
CN104832208B (zh) | 用于煤矿井下松软煤层中长距离水平钻孔的防塌方法 | |
CN101915104A (zh) | 一种采用tbm进行深埋隧洞掘进的岩爆防治方法 | |
CN106499368A (zh) | 一种深海海底表层天然气水合物开采方法 | |
CN207598243U (zh) | 一种盾构掘进防喷涌装置 | |
CN105971662A (zh) | 一种l型钻孔分段压裂弱化煤层顶板的抽采瓦斯方法 | |
CN106437582A (zh) | 钢索取心钻机和能代替槽井探的绿色新工法 | |
CN103603670A (zh) | 超深覆土盾构穿越复杂地层施工方法 | |
CN105370208A (zh) | 一种水下钻爆船及其钻孔施工方法 | |
CN104929136A (zh) | 城区复杂地下障碍工况咬合桩围护施工方法 | |
CN104196453B (zh) | 煤层气开发井 | |
CN106437612A (zh) | 顺层瓦斯抽采钻孔封孔方法及其封孔结构 | |
CN104790918A (zh) | 复杂地形条件下丛式井与水平井联合地面开采煤层气方法 | |
CN102797469A (zh) | 一种应用具有土压平衡功能的tbm施工斜井的方法 | |
CN206888992U (zh) | 一种水底矿山盾构隧道组合对接结构形式 | |
CN108894765A (zh) | 深水浅层天然气水合物开采的主辅井结构及其方法 | |
CN105201517A (zh) | 隧道高强度管棚超前支护施工方法 | |
CN111322075B (zh) | 一种竖井掘进机用壁后回填注浆*** | |
CN205101006U (zh) | 隧道高强度管棚超前支护结构 | |
CN206957712U (zh) | 一种不良地质层竖井反井钻机导孔施工*** | |
CN208346822U (zh) | 注浆装置 | |
CN110939408A (zh) | 一种优化的采空区煤层气地面抽采井身结构及固井方法 | |
CN202706971U (zh) | 钻头打捞器 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20210906 Address after: 100027 Chaoyangmen North Street, Chaoyang District, Chaoyang District, Beijing Patentee after: SINOPEC Group Patentee after: SINOPEC OILFIELD SERVICE Corp. Patentee after: SINOPEC PETROLEUM ENGINEERING Corp. Patentee after: CHINA University OF GEOSCIENCES (WUHAN CITY) Address before: 257029 No. 49, Jinan Road, Dongying City, Shandong Province Patentee before: SINOPEC PETROLEUM ENGINEERING Corp. Patentee before: CHINA University OF GEOSCIENCES (WUHAN CITY) |