CN106592606A - Foundation pit support construction method suitable for three-free-face building envelope - Google Patents

Foundation pit support construction method suitable for three-free-face building envelope Download PDF

Info

Publication number
CN106592606A
CN106592606A CN201710044540.3A CN201710044540A CN106592606A CN 106592606 A CN106592606 A CN 106592606A CN 201710044540 A CN201710044540 A CN 201710044540A CN 106592606 A CN106592606 A CN 106592606A
Authority
CN
China
Prior art keywords
foundation pit
construction
foundation
excavated
building enclosure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710044540.3A
Other languages
Chinese (zh)
Inventor
鲁彬
杨森
易立
刘攀
温元平
臧熙伟
陈海勇
李壮
张蔚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Development Investment Group Co Ltd
Original Assignee
China Railway Development Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Development Investment Group Co Ltd filed Critical China Railway Development Investment Group Co Ltd
Priority to CN201710044540.3A priority Critical patent/CN106592606A/en
Publication of CN106592606A publication Critical patent/CN106592606A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention relates to a foundation pit support construction method suitable for a three-free-face building envelope. The construction method comprises the following construction steps: (1) constructing fender posts and top beams of a foundation pit, wherein three faces of the fender posts of the foundation pit are in a free state in an underground ground floor; (2) carrying out earth excavation of the foundation pit, and constructing breast beams and concrete supports, wherein the supports in the foundation pit are all made of reinforced concrete; and (3) excavating to the bottom of the foundation pit and pouring a concrete cushion and a concrete bottom plate. According to the invention, reinforced concrete supports are adopted, so that the stress form of the building envelope is changed, pressed and pulled characteristics of the reinforced concrete supports are fully expressed, the safety of a supporting structure of the foundation pit is improved, and the integrity of the supporting structure is better; and in addition, the supporting problem caused during the excavation process of the three-free-face deep foundation pit is better solved, so that the excavation construction is safer and more reasonable.

Description

It is a kind of to be suitable to the three foundation ditch Construction of Supporting methods for facing sky building enclosure
【Technical field】
The present invention relates to the construction method that a kind of foundation ditch is supported, and in particular to a kind of to be suitable to three bases for facing sky building enclosure Hole Construction of Supporting method, belongs to architectural engineering construction technique field.
【Background technology】
As the step of urbanization does not stop to stride forward, the development in city is more and more faster, and underground space development will be in city Critical role is occupied in city's construction.In deep-foundation pit engineering, it is country rock that the periphery of foundation ditch is typically surrounding, the supporter of employing System is generally all that form, the support below of first support Guan Liang+reinforced concrete support all adopts bracing members, only pressurized Not tension;Or using baffle plate supporting between anchor cable+stake.
However, in urban architecture compact district, complicated surrounding enviroment make excavation of foundation pit to face various problems, its It is middle than it is more prominent be exactly that foundation pit enclosure stake outer portion region does not have country rock, the state in sky is faced.If adopting in this case Inner support system is bracing members, and bracing members are unable to tension, then be possible to base in having where free face Short side is faced to (dorsad foundation ditch inner side) deformation in hole, so that bracing members come off, causes security incident.
Therefore, be to solve above-mentioned technical problem, it is necessory to provide a kind of innovation be suitable to three face sky building enclosure Foundation ditch Construction of Supporting method, to overcome the defect of the prior art.
【The content of the invention】
To solve the above problems, it is an object of the invention to provide a kind of three foundation ditches for facing sky building enclosure that are suitable to are supported Construction method, it is whole with fender post, base plate, Guan Liang one frame structure of composition in the form of waist rail+reinforced concrete support Body, increased the stability of foundation ditch support.
For achieving the above object, the technical scheme taken of the present invention is:It is a kind of to be suitable to three foundation ditches for facing sky building enclosure Construction of Supporting method, it includes following construction procedure:
1), construction foundation pit fender post and Guan Liang, foundation pit enclosure stake has three faces in facing dummy status in the negative one layer of underground;
2), pit earthwork is excavated, construct waist rail and concrete support, and internal support of foundation pit is all using armored concrete Support;
3) bottom of foundation ditch, cast plain concrete cushion layer and base plate, are excavated to.
The present invention the three foundation ditch Construction of Supporting methods for facing sky building enclosure that are suitable to be further:The step 1) in, Foundation pit enclosure stake is cast-in-situ bored pile;Pit earthwork excavates palpus fender post and reaches and can carry out after design requirement.
The present invention the three foundation ditch Construction of Supporting methods for facing sky building enclosure that are suitable to be further:The step 2) in, The waist rail and per pass reinforced concrete support that the foundation pit enclosure stake, Guan Liang, per pass are supported forms a whole stress system.
The present invention the three foundation ditch Construction of Supporting methods for facing sky building enclosure that are suitable to be further:The step 2) in, Before pit earthwork is excavated, sump and intercepting ditch composition top drainage system are provided with the outside of foundation ditch;Protect in digging process Building enclosure, the cubic metre of earth and stone in the range of building enclosure 300mm is removed using excavated by manual work.
The present invention the three foundation ditch Construction of Supporting methods for facing sky building enclosure that are suitable to also be:The step 2) in, work as base Hole earth excavation can carry out applying for waist rail and concrete support to waist rail designed elevation;After reaching waist rail designed elevation, Waist rail embedded ribs are dug out with hydraulic breaker and pneumatic pick machine, when cutting, concrete is cut on pile body from horizontal direction first, while from On down in layer slowly cut, till waist rail embedded ribs are dug out, dug with air compressor machine will cut face blow and spray totally, will Embedded ribs are adjusted to design attitude.
Compared with prior art, the present invention has the advantages that:
1) present invention all adopts reinforced concrete support, changes the stress form of building enclosure, gives full play to reinforcing bar Concrete compression tension characteristic, while improving the safety of foundation pit supporting construction, supporting construction globality is preferable.
2) under similar conditions the scope of application is wider for the present invention, for features as poor geologic condition, surrounding enviroment are complicated and cause to face For the foundation ditch in empty face, advantageously.
3) present invention can provide it is a kind of it is safe, can it is pressurized and can tension be suitable to three face sky building enclosure The design and construction method that foundation ditch is supported.
【Description of the drawings】
Fig. 1 be the present invention step 2) after the completion of schematic diagram.
Fig. 2 be the present invention step 3) after the completion of schematic diagram.
【Specific embodiment】
Refer to shown in Figure of description 1 and accompanying drawing 2, the present invention is suitable to three foundation ditches for facing sky building enclosure for a kind of Support construction method, it includes following construction procedure:
1), construction foundation pit fender post 1 and Guan Liang 2, foundation pit enclosure stake 1 has three faces in facing sky shape in underground negative one layer 3 State, i.e., without rock mass or only very thin rock mass, such as Fig. 1.
2), pit earthwork is excavated, construction waist rail 4 and concrete support 5, it is contemplated that have three to face sky in underground negative one layer 3 The presence in face, internal support of foundation pit all adopts reinforced concrete support, can not only pressurized but also tension, support profile such as Fig. 2.
3) bottom of foundation ditch, cast plain concrete cushion layer and base plate 6, such as Fig. 2, are excavated to.
Further, the step 1) in, fender post 1 is cast-in-situ bored pile;Excavation of foundation pit palpus fender post reaches design will Can carry out after asking.
In the step (2), waist rail 4 and per pass reinforced concrete support 5 that foundation pit enclosure stake 1, Guan Liang 2, per pass are supported Form a whole stress system, it is ensured that three face the safety of the foundation ditch of dummy status and globality, can be pressurized and can receive Draw, it is better than traditional bracing members mechanical property.
Sky, traditional bracing members are faced because underground negative one layer 3 has three, it is impossible to which meeting not only pressurized but also tension stress will Ask, so pressure and pulling force just can only can be born using armored concrete.
Before Excavation Process, sump and the composition top drainage system of intercepting ditch 7 should be provided with the outside of foundation ditch, it is to avoid Hole other places shows that water is flowed in foundation ditch;
Strict protection building enclosure 1 is answered in digging process, the cubic metre of earth and stone in the range of building enclosure 300mm is using artificial Excavate;
Applying for waist rail 4 and concrete support 5 is carried out by after 4 designed elevation of waist rail is excavated to;
Reach the designed elevation of waist rail 4 after, dig out waist rail embedded ribs with hydraulic breaker and pneumatic pick machine, when cutting, first from Horizontal direction cuts concrete on pile body, while in layer slowly cut from top to bottom, till waist rail embedded ribs are dug out, chisel Complete air compressor machine will cut face and blow and spray totally, and embedded ribs are adjusted to into design attitude.
Near free face 8 during construction reinforced bar concrete support, it should strengthen monitoring, carry out information-aided construction.
In the step (3), base plate 6 being carried out in time and being poured, base plate 6 has one after the completion of pouring equivalent to hole bottom position The effect of support, to periphery fender post 1 very strong constraint is played.Base plate 6 is constituted with fender post 1, reinforced concrete support 5, waist rail 4 One entirety, can strengthen the non-deformability of the foundation pit enclosure structure.
Specific embodiment above is only the preferred embodiment of this creation, all in this wound not to limit this creation Any modification, equivalent substitution and improvements for being done etc. within the spirit of work and principle, should be included in this creation protection domain it It is interior.

Claims (5)

  1. It is 1. a kind of to be suitable to the three foundation ditch Construction of Supporting methods for facing sky building enclosure, it is characterised in that:Including following construction procedure:
    1), construction foundation pit fender post and Guan Liang, foundation pit enclosure stake has three faces in facing dummy status in the negative one layer of underground;
    2), pit earthwork is excavated, and construct waist rail and concrete support, internal support of foundation pit all adopts reinforced concrete support;
    3) bottom of foundation ditch, cast plain concrete cushion layer and base plate, are excavated to.
  2. 2. the three foundation ditch Construction of Supporting methods for facing sky building enclosure are suitable to as claimed in claim 1, it is characterised in that:It is described Step 1) in, foundation pit enclosure stake is cast-in-situ bored pile;Pit earthwork excavates palpus fender post and reaches and can carry out after design requirement.
  3. 3. the three foundation ditch Construction of Supporting methods for facing sky building enclosure are suitable to as claimed in claim 1, it is characterised in that:It is described Step 2) in, the waist rail and per pass reinforced concrete support that the foundation pit enclosure stake, Guan Liang, per pass are supported forms a whole and receives Power system.
  4. 4. the three foundation ditch Construction of Supporting methods for facing sky building enclosure are suitable to as claimed in claim 1, it is characterised in that:It is described Step 2) in, before pit earthwork is excavated, sump and intercepting ditch composition top drainage system are provided with the outside of foundation ditch;Excavated Building enclosure is protected in journey, the cubic metre of earth and stone in the range of building enclosure 300mm is removed using excavated by manual work.
  5. 5. the three foundation ditch Construction of Supporting methods for facing sky building enclosure are suitable to as claimed in claim 1, it is characterised in that:It is described Step 2) in, after pit earthwork is excavated to waist rail designed elevation by carry out applying for waist rail and concrete support;Reach waist After beam designed elevation, waist rail embedded ribs are dug out with hydraulic breaker and pneumatic pick machine, when cutting, first from horizontal direction on pile body Concrete is cut, while in layer slowly cutting from top to bottom, till waist rail embedded ribs are dug out, having dug will be cut with air compressor machine Face blows and sprays totally, and embedded ribs are adjusted to into design attitude.
CN201710044540.3A 2017-01-19 2017-01-19 Foundation pit support construction method suitable for three-free-face building envelope Pending CN106592606A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710044540.3A CN106592606A (en) 2017-01-19 2017-01-19 Foundation pit support construction method suitable for three-free-face building envelope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710044540.3A CN106592606A (en) 2017-01-19 2017-01-19 Foundation pit support construction method suitable for three-free-face building envelope

Publications (1)

Publication Number Publication Date
CN106592606A true CN106592606A (en) 2017-04-26

Family

ID=58586267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710044540.3A Pending CN106592606A (en) 2017-01-19 2017-01-19 Foundation pit support construction method suitable for three-free-face building envelope

Country Status (1)

Country Link
CN (1) CN106592606A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288136A (en) * 2017-08-17 2017-10-24 中国建筑第八工程局有限公司 The structure and its method of building foundation pit protection
CN111075452A (en) * 2019-12-23 2020-04-28 重庆市轨道交通设计研究院有限责任公司 Geotechnical mixed vertical shaft engineering supporting system and vertical shaft construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5850226A (en) * 1981-09-21 1983-03-24 Marubeni Kenzai Lease Kk Brace receiver
CN105804084A (en) * 2016-03-25 2016-07-27 中铁三局集团广东建设工程有限公司 Excavation construction method of small foundation pit near excavated deep foundation pit
CN205776249U (en) * 2016-05-27 2016-12-07 中国建筑西南勘察设计研究院有限公司 A kind of combined inner supporting structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5850226A (en) * 1981-09-21 1983-03-24 Marubeni Kenzai Lease Kk Brace receiver
CN105804084A (en) * 2016-03-25 2016-07-27 中铁三局集团广东建设工程有限公司 Excavation construction method of small foundation pit near excavated deep foundation pit
CN205776249U (en) * 2016-05-27 2016-12-07 中国建筑西南勘察设计研究院有限公司 A kind of combined inner supporting structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈克济: "《地铁工程施工技术》", 30 June 2014, 中国铁道出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288136A (en) * 2017-08-17 2017-10-24 中国建筑第八工程局有限公司 The structure and its method of building foundation pit protection
CN111075452A (en) * 2019-12-23 2020-04-28 重庆市轨道交通设计研究院有限责任公司 Geotechnical mixed vertical shaft engineering supporting system and vertical shaft construction method

Similar Documents

Publication Publication Date Title
CN105839643B (en) A kind of tunnel construction method of use pattern foundation pit supporting structure
CN107762535B (en) Cut-and-cover tunnel secretly does construction technology under complicated geological environment
CN105464686B (en) Multi-layer underground space curtain posture excavating construction method and supporting construction under existing facility
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN102704957A (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN204371354U (en) The compound supporting and protection structure of a kind of Karst Tunnel
CN101509261B (en) Method for pile plate base for ultra-high voltage electric power line steel tower on soft foundation
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN103696784A (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN105604576A (en) Soft rock stratum underground excavation large-section tunnel construction method and supporting system
CN110685286A (en) Deep foundation pit supporting construction process for adjacent road under complex geological condition
CN102758458A (en) Underground continuous wall repairing method
CN111677515B (en) Construction method for breaking open cut foundation pit wall into hole from pile support supporting system by adopting shallow-buried underground excavation method
CN108867692A (en) The protection of city big cross section open trench tunnel Nearby Structure and tunnel foundation pit method for digging
CN106592606A (en) Foundation pit support construction method suitable for three-free-face building envelope
CN114482099A (en) Steel sheet pile cofferdam construction method
CN204282399U (en) A kind of subway space enclosing structure
CN109826230A (en) A kind of town road pipeline reinforcement protection structure and its construction method
CN110259456B (en) Karst cave treatment method for tunnel construction
CN107574836A (en) Cross the constructing structure and construction method of urban road underpass
CN105421488B (en) The construction method of sole plate support replacement in the combined fender construction system of underground
KR100360462B1 (en) Method to construct a structure on soft soil and the structure thereof
CN109653193B (en) Reverse construction method for underground continuous wall
CN211080248U (en) Deep foundation pit supporting structure of adjacent road under complex geological condition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170426