CN106571645A - 发电机一次***核相方法 - Google Patents
发电机一次***核相方法 Download PDFInfo
- Publication number
- CN106571645A CN106571645A CN201610925759.XA CN201610925759A CN106571645A CN 106571645 A CN106571645 A CN 106571645A CN 201610925759 A CN201610925759 A CN 201610925759A CN 106571645 A CN106571645 A CN 106571645A
- Authority
- CN
- China
- Prior art keywords
- phase
- phase checking
- phasing tester
- electric generator
- secondary phasing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/40—Synchronising a generator for connection to a network or to another generator
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01R—MEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
- G01R29/00—Arrangements for measuring or indicating electric quantities not covered by groups G01R19/00 - G01R27/00
- G01R29/18—Indicating phase sequence; Indicating synchronism
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Tests Of Circuit Breakers, Generators, And Electric Motors (AREA)
Abstract
本发明公开了一种发电机一次***核相方法,其是在发电机转速达到额定转速,启动励磁***发电机出口电压达到额定电压的条件下,在发电机出口断路器进行如下核相操作:步骤a、第一副核相器的两端分别接A‑A相,第二副核相器的两端分别接B‑B相,观察两个核相器的表计的指示变化是否相同;步骤b、第一副核相器不变,第二副核相器的两端分别接C‑C相,观察两个核相器的表计的指示变化是否相同;如果步骤a和步骤b中第一副核相器和第二副核相器的表计的指示变化均相同,判断核相结果正确;反之,判断核相结果错误。该方法所需参与人员少,可以降低对现场环境的影响,操作简单,容易观察核相器表计的变化情况。
Description
技术领域
本发明涉及发电机技术领域,特别是涉及一种发电机一次***核相方法。
背景技术
发电机组与***并网时必须检查三个条件:一是发电机与***的电压差小于规定的值;二是发电机与***的频率差小于规定的值;三是发电机与***的相位差小于规定的值。其中第三个条件与相序密切相关,即发电机组与***的相序必须一致,这不仅要求一次相序正确,同时二次***无误才能保证并网成功。因此发电机组的并网必然涉及到核相的有关问题。核相的任务是保证同期***的接线正确、一次***的相序正确、一次、二次***的电压统一。从原则上讲只要发电机组的一次相序正确就可以并网,但一次测点的相序正确不一定能保证二次同期***的正确。二次***的相序正确也不一定能保证一次、二次***一致,也不一定能保证断路器两侧的一次***一致。同步发电机一次***的核相工作由于相角差随时间变化,使发电机与待并***同相电压随时间也在变化,无法使用单相高压核相器进行核相。发电机准同期并列的理想条件为并列断路器两侧电源三个状态量全部相等,即频率相等、电压幅值相等、相角差为零。
电力***中通常所使用的发电机一次***核相方法主要采用:1、发电机-变压器组带母线零起升压核相;2、发电机带母线的零起升压核相;3、同时利用一次、二次电压进行核相等,由于条件苛刻、措施复杂、不易实施等问题在我厂无法推广,早年前对于发电机大修或改造时,利用人工标记相序方法进行,此方法为保证正确性,需进行多次、多人的确认,比较繁琐且无其他方法加以确认,同时,如遇到中间一次***环节同时变更,此方法将实施较为困难,存在局限性。
发明内容
为了解决以上技术问题,本发明提供一种发电机一次***核相方法。
本发明提供一种发电机一次***核相方法,其是在发电机转速达到额定转速,启动励磁***发电机出口电压达到额定电压的条件下,在发电机出口断路器进行如下核相操作:
步骤a、第一副核相器的两端分别接A-A相,第二副核相器的两端分别接B-B相,观察第一副核相器和第二副核相器的表计的指示变化是否相同;
步骤b、第一副核相器不变,第二副核相器的两端分别接C-C相,观察第一副核相器和第二副核相器的表计的指示变化是否相同;
如果步骤a和步骤b中第一副核相器和第二副核相器的表计的指示变化均相同,判断核相结果正确;如果步骤a和步骤b中任意一个步骤中第一副核相器和第二副核相器的表计的指示变化不同,判断核相结果错误。
本发明提供的发电机一次***核相方法是采用双组单相高压核相器核相法,采用两组核相器分两步进行操作,最后通过每步骤中的两个核相器的表计的指示变化判断核相结果是否正确。相对于现有技术,本发明提供的方法所需参与人员少,可以降低对现场环境的影响,操作简单,容易观察核相器表计的变化情况,容易实施。
附图说明
图1为本发明提供的发电机一次***核相方法中步骤a的操作示意图;
图2为本发明提供的发电机一次***核相方法中步骤b的操作示意图。
具体实施方式
为了使本技术领域的人员更好地理解本发明方案,下面结合附图和具体实施方式对本发明作进一步的详细说明。
在一种具体的实施方式中,本发明提供了一种发电机一次***核相方法,该方法是在发电机转速达到额定转速,启动励磁***发电机出口电压达到额定电压的条件下,在发电机出口断路器进行如下核相操作:
步骤a、第一副核相器的两端分别接A-A相,第二副核相器的两端分别接B-B相,观察第一副核相器和第二副核相器的表计的指示变化是否相同;
步骤b、第一副核相器不变,第二副核相器的两端分别接C-C相,观察第一副核相器和第二副核相器的表计的指示变化是否相同;
如果步骤a和步骤b中第一副核相器和第二副核相器的表计的指示变化均相同,即同步摆动,判断核相结果正确;如果步骤a和步骤b中任意一个步骤中第一副核相器和第二副核相器的表计的指示变化不同,判断核相结果错误。
发电机准同期并列的理想条件为并列断路器两侧电源电压三个状态量全部相等,即
(1)ωG=ωX或fG=fX(即频率相等)
(2)UG=UX(即电压幅值相等)
(3)δe=0(即相角差为零)
设发电机电压为ug=Umsinωgt,***电压为us=Umsinωst,则滑差电压的包络线函数为:
U=2Umsin(ωt/2)=2Umsin(δt/2) ---式(1)
其中
式中ωg为发电机电压角频率;
ωs为***电压角频率。
根据式(1)可以得出结论:一次电压的相序正确、相别正确时三相滑差电压同时进入峰谷点;一次电压的相序、相别出现任意错误时,三相滑差电压的相位相差120°。
可知滑差电压随时间变化而发生周期性变化,核相器在发电机与***之间进行核相时,表计直接反应两端电压变化情况,即随时间反复摆动,当采用三组核相器对发电机与***之间进行核相试验,如相序、相别正确,则三组表计将同步周期摆动,即同时达到最高点、同时达到最低点,如相序、相别错误,则三组表计将发生两两之间不同步周期摆动。
据此,本发明提供上述发电机一次***核相方法,该方法是采用双组单相高压核相器核相法,采用两组核相器分两步进行操作,最后通过每步骤中的两个核相器的表计的指示变化判断核相结果是否正确。相对于现有技术,本发明提供的方法所需参与人员少,可以降低对现场环境的影响,操作简单,容易观察核相器表计的变化情况,容易实施。
以上对本发明所提供的发电机一次***核相方法进行了详细介绍。本文中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干改进和修饰,这些改进和修饰也落入本发明权利要求的保护范围内。
Claims (1)
1.一种发电机一次***核相方法,其特征在于,
在发电机转速达到额定转速,启动励磁***发电机出口电压达到额定电压的条件下,在发电机出口断路器进行如下核相操作:
步骤a、第一副核相器的两端分别接A-A相,第二副核相器的两端分别接B-B相,观察第一副核相器和第二副核相器的表计的指示变化是否相同;
步骤b、第一副核相器不变,第二副核相器的两端分别接C-C相,观察第一副核相器和第二副核相器的表计的指示变化是否相同;
如果步骤a和步骤b中第一副核相器和第二副核相器的表计的指示变化均相同,判断核相结果正确;如果步骤a和步骤b中任意一个步骤中第一副核相器和第二副核相器的表计的指示变化不同,判断核相结果错误。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610925759.XA CN106571645A (zh) | 2016-10-31 | 2016-10-31 | 发电机一次***核相方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610925759.XA CN106571645A (zh) | 2016-10-31 | 2016-10-31 | 发电机一次***核相方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106571645A true CN106571645A (zh) | 2017-04-19 |
Family
ID=58534416
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610925759.XA Pending CN106571645A (zh) | 2016-10-31 | 2016-10-31 | 发电机一次***核相方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106571645A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108196139A (zh) * | 2018-01-19 | 2018-06-22 | 山东钢铁集团日照有限公司 | 一种小型发电机组并网核相方法 |
CN110504712A (zh) * | 2019-08-21 | 2019-11-26 | 西安热工研究院有限公司 | 一种燃气电厂π型同源核相***及方法 |
CN110572101A (zh) * | 2019-09-25 | 2019-12-13 | 潍柴动力股份有限公司 | 一种三相交流电机相序的校验方法及*** |
CN111707879A (zh) * | 2020-05-14 | 2020-09-25 | 上海二十冶建设有限公司 | 利用双电源在线核相检测装置对发电机并网核相的方法 |
CN112834835A (zh) * | 2019-11-22 | 2021-05-25 | 上海梅山钢铁股份有限公司 | 一种发电机无冲击并网的线序检测方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1737583A (zh) * | 2005-07-27 | 2006-02-22 | 江苏省电力公司常州供电公司 | 户内环网柜智能核相的方法 |
CN203658476U (zh) * | 2014-01-15 | 2014-06-18 | 天津市华电电力器材厂 | 一种高压核相器 |
CN105676009A (zh) * | 2016-03-24 | 2016-06-15 | 国网山东省电力公司济南供电公司 | 一种三相式环网柜二次核相器及其核相方法 |
-
2016
- 2016-10-31 CN CN201610925759.XA patent/CN106571645A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1737583A (zh) * | 2005-07-27 | 2006-02-22 | 江苏省电力公司常州供电公司 | 户内环网柜智能核相的方法 |
CN203658476U (zh) * | 2014-01-15 | 2014-06-18 | 天津市华电电力器材厂 | 一种高压核相器 |
CN105676009A (zh) * | 2016-03-24 | 2016-06-15 | 国网山东省电力公司济南供电公司 | 一种三相式环网柜二次核相器及其核相方法 |
Non-Patent Citations (1)
Title |
---|
李增光等: ""用高压核相器测定发电机相序的方法"", 《电世界》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108196139A (zh) * | 2018-01-19 | 2018-06-22 | 山东钢铁集团日照有限公司 | 一种小型发电机组并网核相方法 |
CN110504712A (zh) * | 2019-08-21 | 2019-11-26 | 西安热工研究院有限公司 | 一种燃气电厂π型同源核相***及方法 |
CN110504712B (zh) * | 2019-08-21 | 2021-08-31 | 西安热工研究院有限公司 | 一种燃气电厂π型同源核相***及方法 |
CN110572101A (zh) * | 2019-09-25 | 2019-12-13 | 潍柴动力股份有限公司 | 一种三相交流电机相序的校验方法及*** |
CN110572101B (zh) * | 2019-09-25 | 2021-06-22 | 潍柴动力股份有限公司 | 一种三相交流电机相序的校验方法及*** |
CN112834835A (zh) * | 2019-11-22 | 2021-05-25 | 上海梅山钢铁股份有限公司 | 一种发电机无冲击并网的线序检测方法 |
CN112834835B (zh) * | 2019-11-22 | 2022-09-06 | 上海梅山钢铁股份有限公司 | 一种发电机无冲击并网的线序检测方法 |
CN111707879A (zh) * | 2020-05-14 | 2020-09-25 | 上海二十冶建设有限公司 | 利用双电源在线核相检测装置对发电机并网核相的方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106571645A (zh) | 发电机一次***核相方法 | |
Rietveld et al. | Measurement infrastructure to support the reliable operation of smart electrical grids | |
Tatcho et al. | A novel hierarchical section protection based on the solid state transformer for the future renewable electric energy delivery and management (FREEDM) system | |
CN101887074B (zh) | 三相电压暂降发生器 | |
Meliopoulos et al. | Wide area dynamic monitoring and stability controls | |
CN115542146B (zh) | 发电机组出口开关装置同期测试方法、装置、设备及介质 | |
Teng et al. | IEEE9 buses system simulation and modeling in PSCAD | |
CN102944762B (zh) | 发电机组投运前同期点两侧回路相序调试方法 | |
Gedra et al. | Unified power engineering laboratory for electromechanical energy conversion, power electronics, and power systems | |
Adhikari et al. | Analysis of transient overvoltages and Self Protection Overvoltage of PV inverters through RT-CHIL | |
Park et al. | Co-simulation of OpenDSS and RTDS to realise real-time simulation of large distribution networks | |
US11143704B2 (en) | Power generation system test apparatus and method | |
Juárez-Caltzontzin et al. | Theoretical and Experimental Analysis of the Short Circuit Current Components in Salient Pole Synchronous Generators | |
Salehi et al. | Design and implementation of laboratory-based smart power system | |
Wei et al. | Short circuit current analysis of DFIG with crowbar under unsymmetrical grid fault | |
Ojaghi et al. | Performance analysis of saturated induction motors by virtual tests | |
CN104730357A (zh) | 一种光伏发电逆变器并网测试装置 | |
Chowdhury et al. | Enhancing power and energy systems concepts with laboratory experience | |
Bi et al. | Large scale power system simulation and PMU testing using a real time digital simulator | |
KR101733710B1 (ko) | 대용량 동기기 기동장치 제어기 시험 장치 | |
Huang | Electromagnetic transient and electromechanical transient stability hybrid simulation: design, development and its applications | |
CN110554297A (zh) | 一种利用低压电检查大型高压电动机差动保护电流回路的方法 | |
CN110221165B (zh) | 一种电机差动保护试验新方法 | |
Finney et al. | Electromagnetic torque from event report data—A measure of machine performance | |
Rothstein et al. | Combined-Hardware-in-the-Loop system and its test-bench verification |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170419 |
|
RJ01 | Rejection of invention patent application after publication |