CN106556757A - EMUs neutral-section passing system dynamic simulant test system and method for testing - Google Patents

EMUs neutral-section passing system dynamic simulant test system and method for testing Download PDF

Info

Publication number
CN106556757A
CN106556757A CN201610929815.7A CN201610929815A CN106556757A CN 106556757 A CN106556757 A CN 106556757A CN 201610929815 A CN201610929815 A CN 201610929815A CN 106556757 A CN106556757 A CN 106556757A
Authority
CN
China
Prior art keywords
wireless
signal
vehicle
modules
receiving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610929815.7A
Other languages
Chinese (zh)
Other versions
CN106556757B (en
Inventor
郝春梅
于海波
王波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Changchun Railway Vehicles Co Ltd
Original Assignee
CRRC Changchun Railway Vehicles Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRRC Changchun Railway Vehicles Co Ltd filed Critical CRRC Changchun Railway Vehicles Co Ltd
Priority to CN201610929815.7A priority Critical patent/CN106556757B/en
Publication of CN106556757A publication Critical patent/CN106556757A/en
Application granted granted Critical
Publication of CN106556757B publication Critical patent/CN106556757B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/005Testing of electric installations on transport means

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Electric Propulsion And Braking For Vehicles (AREA)

Abstract

EMUs neutral-section passing system dynamic simulant test system and method for testing belong to railway systems automatic neutral-section passing system technical field of measurement and test, the system includes control device, triggering device and four U-shaped fixed mounts, and control device includes power supply, master controller, wireless sending module, No. two wireless sending modules, No. three wireless sending modules and No. four wireless sending modules;Triggering device includes a triggering device, No. two triggering devices, No. three triggering devices and No. four triggering devices;Each triggering device is arranged in the vehicle-mounted inducing receiver of correspondence of EMUs by a U-shaped fixed mount.Using the test system of the present invention, undue phase study can be carried out in rail track arbitrary region, no longer by rail track conditionality, dynamic undue phase study, processing ease simple with test method can be completed, many advantages, such as success of the test rate is up to 100%, low cost.

Description

EMUs neutral-section passing system dynamic simulant test system and method for testing
Technical field
The invention belongs to railway systems automatic neutral-section passing system technical field of measurement and test, and in particular to a kind of EMUs cross split-phase System Dynamic Model test system and method for testing.
Background technology
During EMUs GFX-3A neutral-section passing system dynamic tests, it is desirable to which motor-car is with the travel speed more than 70km/h by dividing Phase region, as shown in figure 1, two magnetic ties are respectively laid in regular railway region before and after phase-separating section, one end of every magnetic tie sets There is an electromagnetism box, the position of four electromagnetism box G1, G2, G3, G4 mode as shown in Figure 1 is distributed in the both sides of railway.EMUs turn Two vehicle-mounted inducing receivers are respectively provided with to the both sides of frame lower end, with EMUs direct of travel as front, four vehicle-mounted sensings connect Left forward side is located in receiving device is vehicle-mounted inducing receiver T1, and positioned at right forward side is vehicle-mounted inducing receiver T2, is located at Left rear side is vehicle-mounted inducing receiver T3, and be located behind right side is vehicle-mounted inducing receiver T4.Motor-car drives towards phase-separating section When, when vehicle-mounted inducing receiver T2, vehicle-mounted inducing receiver T4 are sequentially passed through above magnetic tie, the two successively receives electromagnetism box The electromagnetic signal that G1 sends, when vehicle-mounted inducing receiver T1, vehicle-mounted inducing receiver T3 are sequentially passed through above magnetic tie, the two elder generation The electromagnetic signal that electromagnetism box G2 sends is received afterwards, and vehicle-mounted inducing receiver T2, vehicle-mounted inducing receiver T4, vehicle-mounted sensing are received Device T1, vehicle-mounted inducing receiver T3 send corresponding disconnection main circuit breaker according to the electromagnetic signal for receiving and block trailer system Signal processor of the signal to EMUs, after signal processor reception signal carries out logical process, notifies motor-car set control system Implement to disconnect main circuit breaker and block trailer system, vehicle enters phase-separating section.In the same manner, after motor-car rolls phase-separating section away from, vehicle-mounted sensing When receptor T2, vehicle-mounted inducing receiver T4 are sequentially passed through above magnetic tie, the two successively receives the electricity that electromagnetism box G3 sends Magnetic signal, when vehicle-mounted inducing receiver T1, vehicle-mounted inducing receiver T3 are sequentially passed through above magnetic tie, the two successively receives electricity The electromagnetic signal that magnetic holder G4 sends, it is vehicle-mounted inducing receiver T2, vehicle-mounted inducing receiver T4, vehicle-mounted inducing receiver T1, vehicle-mounted Inducing receiver T3 sends the signal of corresponding closure main circuit breaker and trailer system of lifting a blockade according to the electromagnetic signal for receiving To the signal processor of EMUs, after signal processor reception signal carries out logical process, notify that motor-car set control system is implemented Closure main circuit breaker and trailer system of lifting a blockade, so as to complete the overall process that motor-car is tested by phase-separating section.Regular railway line 30 kilometers of distance just has a phase-separating section, and experiment railway division required during test is considerably long, and cost is very high, All hosts factory Test circuit cannot all meet undue phase study condition, and before causing vehicle release, GFX-3A crosses split-phase dynamic test always Blank, therefore, existing GFX-3A neutral-section passing systems method of testing generally need by train driving to undue phase section just Rule railway line is carried out up, quite time-consuming effort.
Also, when testing in regular railway line and testing GFX-3A neutral-section passing systems, if cross phase splitting device breaking down, Vehicle is easy to go out phase-separating section and causes to draw electric arc, burns neutral section insulator, thus causes electric substation to trip, and interruption of power supply is caused Driving accident.Therefore it provides it is a kind of before EMUs dispatch from the factory verify neutral-section passing system function it is whether working properly, stable, can The test method leaned on seems particularly significant, while being also each main engine plants difficult problem to be solved.
The content of the invention
If in order to solve it is existing vehicle is driven to carry out in regular railway line neutral-section passing system test method exist Neutral-section passing system breaks down, and vehicle is easy to go out phase-separating section and causes to draw electric arc, burns neutral section insulator, thus causes electric substation Tripping operation, interruption of power supply cause the technical problem of driving accident, the present invention to provide a kind of EMUs neutral-section passing system dynamic analog and survey Test system and method for testing.
The technical scheme taken by present invention solution technical problem is as follows:
EMUs neutral-section passing system dynamic simulant test system, which includes that control device, triggering device and four U-shapeds are fixed Frame, control device include power supply, master controller, wireless sending module, No. two wireless sending modules, a No. three wireless transmission moulds Block and No. four wireless sending modules;Triggering device includes:By a wireless receiving module, a battery and a solenoid structure Into a triggering device, No. two triggering devices being made up of No. two wireless receiving modules, C-size battery and No. two solenoids, No. three triggering devices being made up of No. three wireless receiving modules, No. three batteries and No. three solenoids, by No. four wireless receiving moulds No. four triggering devices that block, No. four batteries and No. four solenoids are constituted;Number triggering device, No. two triggering devices, No. three touch Transmitting apparatus, No. four triggering devices are arranged on vehicle-mounted inducing receiver T2 of EMUs, car by a U-shaped fixed mount correspondence respectively Carry in inducing receiver T4, vehicle-mounted inducing receiver T1, vehicle-mounted inducing receiver T3;Power supply is electrically connected with master controller, and which is used for Power to master controller;Master controller, wireless sending module, wireless receiving module, battery, an electromagnetic wire Circle is sequentially electrically connected, and number wireless sending module of main controller controls sends a trigger to a wireless receiving module, and one Number wireless receiving module drives a battery to connect a solenoid according to the trigger for receiving;Master controller, No. two nothings Line sending module, No. two wireless receiving modules, C-size battery, No. two solenoids are sequentially electrically connected, No. two nothings of main controller controls Line sending module sends No. two triggers to No. two wireless receiving modules, and No. two wireless receiving modules are according to the triggering letter for receiving Number drive C-size battery connect No. two solenoids;Master controller, No. three wireless sending modules, No. three wireless receiving modules, three Number battery, No. three solenoids are sequentially electrically connected, and No. three wireless sending modules of main controller controls send No. three triggers to three Number wireless receiving module, No. three wireless receiving modules drive No. three batteries to connect No. three electromagnetic wires according to the trigger for receiving Circle;Master controller, No. four wireless sending modules, No. four wireless receiving modules, No. four batteries and No. four solenoids are sequentially electrically connected, No. four wireless sending modules of main controller controls send No. four triggers to No. four wireless receiving modules, No. four wireless receiving moulds Tuber drives No. four batteries to connect No. four solenoids according to the trigger for receiving.
The invention has the beneficial effects as follows:Using this test method, need not renovate rail track, install GFX-3A additional undue Phase ground installation and device, can carry out undue phase study in rail track arbitrary region, no longer by rail track conditionality, i.e., Dynamic undue phase study can be completed, simple with test method, processing ease, success of the test rate are up to 100%, and cost is low all Many advantages.
Description of the drawings
Electromagnetism box distribution schematic diagram when Fig. 1 is existing EMUs GFX-3A neutral-section passing system dynamic tests.
Fig. 2 is the operation principle schematic diagram of EMUs neutral-section passing system dynamic simulant test system of the present invention.
Specific embodiment
Below in conjunction with the accompanying drawings the present invention is described in further details.
As shown in Fig. 2 the EMUs neutral-section passing system dynamic simulant test system of the present invention includes control device, triggering dress Put and four U-shaped fixed mounts, control device includes power supply, master controller, wireless sending module, a No. two wireless transmission moulds Block, No. three wireless sending modules and No. four wireless sending modules;Triggering device includes:By a wireless receiving module, No. one it is electric The triggering device that pond and a solenoid are constituted, by No. two wireless receiving modules, C-size battery and No. two solenoids No. two triggering devices for constituting, No. three triggering dresses being made up of No. three wireless receiving modules, No. three batteries and No. three solenoids Put, No. four triggering devices being made up of No. four wireless receiving modules, No. four batteries and No. four solenoids;A number triggering device is led to A U-shaped fixed mount is crossed in vehicle-mounted inducing receiver T2 of EMUs, No. two triggering devices pass through a U-shaped fixed mount In vehicle-mounted inducing receiver T4 of EMUs, No. three triggering devices are arranged on EMUs by a U-shaped fixed mount In vehicle-mounted inducing receiver T1, No. four triggering devices are arranged on the vehicle-mounted inducing receiver of EMUs by a U-shaped fixed mount On T3.
The method of testing of EMUs neutral-section passing system dynamic simulant test system of the present invention comprises the steps:
Step one, EMUs speed reached split-phase require when, startup power supply, test system enter simulation EMUs sail Enter the pattern of phase-separating section, number wireless sending module of main controller controls sends a trigger to a wireless receiving mould Block, a wireless receiving module drive a battery to connect a solenoid, an electromagnetic wire according to the trigger for receiving Enclose the electric disconnected induced signal that warns to vehicle-mounted inducing receiver T2, vehicle-mounted inducing receiver T2 is by the advance notice for receiving disconnected sensing Signal passes to the signal processor of EMUs, and signal processor enters the disconnected pattern of advance notice according to the signal for receiving;
After step 2,2s~6s, after optimal setting 2s, No. two wireless sending modules of main controller controls send No. two and touch No. two wireless receiving modules are signaled to, No. two wireless receiving modules drive C-size battery to connect two according to the trigger for receiving Number solenoid, No. two solenoids obtain the electric disconnected induced signal that warns to vehicle-mounted inducing receiver T4, and vehicle-mounted sensing is received Device T4 is passed to the signal processor of EMUs by the advance notice for receiving disconnected induced signal, and signal processor enters according to the signal for receiving Row logical process, if signal processor exports the disconnected induced signal of advance notice, does not do output function, otherwise signal processor output The disconnected induced signal of advance notice, notifies that motor-car set control system disconnects main circuit breaker and blocks trailer system;
After step 3,2s~6s, after optimal setting 2s, No. three wireless sending modules of main controller controls send No. three and touch No. three wireless receiving modules are signaled to, No. three wireless receiving modules drive No. three batteries to connect three according to the trigger for receiving Number solenoid, No. three solenoids obtain electric sending and force disconnected induced signal to vehicle-mounted inducing receiver T1, and vehicle-mounted sensing is received The disconnected induced signal that forces for receiving is passed to the signal processor of EMUs by device T1, and signal processor enters according to the signal for receiving Row logical process, if signal processor exports the disconnected induced signal of advance notice, does not do output function, otherwise signal processor output Disconnected induced signal is forced, notifies that motor-car set control system turns off main circuit breaker and blocks trailer system;
After step 4,2s~6s, after optimal setting 2s, No. four wireless sending modules of main controller controls send No. four and touch No. four wireless receiving modules are signaled to, No. four wireless receiving modules drive No. four batteries to connect four according to the trigger for receiving Number solenoid, No. four solenoids obtain electric sending and force disconnected induced signal to vehicle-mounted inducing receiver T3, and vehicle-mounted sensing is received The disconnected induced signal that forces for receiving is passed to the signal processor of EMUs by device T3, and signal processor enters according to the signal for receiving Row logical process, if signal processor has been exported forces disconnected induced signal, does not do output function, otherwise signal processor output Disconnected induced signal is forced, notifies that motor-car set control system disconnects main circuit breaker immediately and blocks trailer system;
After step 5,6s~20s, after optimal setting 6s, test system enters the mould that simulation EMUs sail out of phase-separating section Formula, number wireless sending module of main controller controls send a trigger to a wireless receiving module, and No. one wirelessly connects Receiving module drives battery to connect a solenoid according to the trigger for receiving, and solenoid is obtained and electric sends pre- extensive The pre-restore induced signal of reception is passed to EMUs to vehicle-mounted inducing receiver T2, vehicle-mounted inducing receiver T2 by multiple induced signal Signal processor, signal processor according to the signal for receiving enter pre-restore pattern;
After step 6,2s~6s, after optimal setting 2s, No. two wireless sending modules of main controller controls send No. two and touch No. two wireless receiving modules are signaled to, No. two wireless receiving modules drive C-size battery to connect two according to the trigger for receiving Number solenoid, No. two solenoids obtain the electric pre-restore induced signal that sends to vehicle-mounted inducing receiver T4, and vehicle-mounted sensing is received Device T4 is passed to the signal processor of EMUs by the pre-restore induced signal of reception, and signal processor enters according to the signal for receiving Row logical process, if signal processor has exported pre-restore induced signal, does not do output function, otherwise signal processor output Pre-restore induced signal, notifies motor-car set control system closure main circuit breaker trailer system of lifting a blockade;
After step 7,2s~6s, after optimal setting 2s, No. three wireless sending modules of main controller controls send No. three and touch No. three wireless receiving modules are signaled to, No. three wireless receiving modules drive No. three batteries to connect three according to the trigger for receiving Number solenoid, No. three solenoids obtain electric sending and force recovery induced signal to vehicle-mounted inducing receiver T1, and vehicle-mounted sensing connects Receive device T1 and the recovery induced signal that forces for receiving is passed to into the signal processor of EMUs, signal processor is according to the letter for receiving Number logical process is carried out, if signal processor has exported pre-restore induced signal, do not do output function, otherwise signal processor Output forces recovery induced signal, notifies that motor-car set control system closes main circuit breaker and trailer system of lifting a blockade at once;
After step 8,2s~6s, after optimal setting 2s, No. four wireless sending modules of main controller controls send No. four and touch No. four wireless receiving modules are signaled to, No. four wireless receiving modules drive No. four batteries to connect four according to the trigger for receiving Number solenoid, No. four solenoids obtain electric sending and force recovery induced signal to vehicle-mounted inducing receiver T3, and vehicle-mounted sensing connects Receive device T3 and the recovery induced signal that forces for receiving is passed to into the signal processor of EMUs, signal processor is according to the letter for receiving Number logical process is carried out, if signal processor has been exported forces recovery induced signal, do not do output function, otherwise signal processing Device output forces recovery induced signal, notifies that motor-car set control system closes main circuit breaker and trailer system of lifting a blockade immediately, Complete EMUs neutral-section passing system dynamic simulant test method.
The method of testing of the present invention is in the state of ground does not have electromagnetism box to wait split-phase test equipment, using wireless controlled Mode processed according to number triggering device of sequencing contro, No. two triggering devices, No. three triggering devices, the connection of No. four triggering devices and Disconnect, so realize vehicle on any tram-line road can true overall process of the simulating vehicle into and out of phase-separating section, realize dispatching from the factory The purpose of front authenticated split-phase systemic-function.

Claims (2)

1. EMUs neutral-section passing system dynamic simulant test system, it is characterised in that the system includes control device, triggering device With four U-shaped fixed mounts, control device include power supply, master controller, wireless sending module, No. two wireless sending modules, No. three wireless sending modules and No. four wireless sending modules;Triggering device includes:By a wireless receiving module, a battery and The triggering device that a number solenoid is constituted, is made up of No. two wireless receiving modules, C-size battery and No. two solenoids No. two triggering devices, No. three triggering devices being made up of No. three wireless receiving modules, No. three batteries and No. three solenoids, by No. four triggering devices that No. four wireless receiving modules, No. four batteries and No. four solenoids are constituted;Number triggering device, No. two touch Transmitting apparatus, No. three triggering devices, No. four triggering devices are arranged on the vehicle-mounted sense of EMUs respectively by a U-shaped fixed mount correspondence Answer in receptor T2, vehicle-mounted inducing receiver T4, vehicle-mounted inducing receiver T1, vehicle-mounted inducing receiver T3;
Power supply is electrically connected with master controller, and which is used to power to master controller;
Master controller, wireless sending module, wireless receiving module, battery, a solenoid are sequentially electrically connected, Number wireless sending module of main controller controls sends a trigger to a wireless receiving module, a wireless receiving mould Tuber drives a battery to connect a solenoid according to the trigger for receiving;
Master controller, No. two wireless sending modules, No. two wireless receiving modules, C-size battery, No. two solenoids are sequentially electrically connected, No. two wireless sending modules of main controller controls send No. two triggers to No. two wireless receiving modules, No. two wireless receiving moulds Tuber drives C-size battery to connect No. two solenoids according to the trigger for receiving;
Master controller, No. three wireless sending modules, No. three wireless receiving modules, No. three batteries, No. three solenoids are sequentially electrically connected, No. three wireless sending modules of main controller controls send No. three triggers to No. three wireless receiving modules, No. three wireless receiving moulds Tuber drives No. three batteries to connect No. three solenoids according to the trigger for receiving;
Master controller, No. four wireless sending modules, No. four wireless receiving modules, No. four batteries and No. four solenoids are sequentially electric Even, No. four wireless sending modules of main controller controls send No. four triggers to No. four wireless receiving modules, and No. four wirelessly connect Receiving module drives No. four batteries to connect No. four solenoids according to the trigger for receiving.
2. the method for testing based on the EMUs neutral-section passing system dynamic simulant test system described in claim 1, its feature exist In the method comprises the steps:
Step one, when EMUs speed reached split-phase and required, startup power supply, test system enter simulation EMUs and sail into point The pattern of phase region, number wireless sending module of main controller controls send a trigger to a wireless receiving module, and one Number wireless receiving module drives a battery to connect a solenoid according to the trigger for receiving, and a solenoid obtains electric The advance notice for receiving disconnected induced signal is passed to vehicle-mounted inducing receiver T2, vehicle-mounted inducing receiver T2 by the disconnected induced signal that warns To the signal processor of EMUs, signal processor enters the disconnected pattern of advance notice according to the signal for receiving;
After step 2,2s~6s, it is wireless to No. two that No. two wireless sending modules of main controller controls send No. two triggers Receiver module, trigger driving C-size battery connection No. two solenoids of No. two wireless receiving modules according to reception, No. two Solenoid obtains the advance notice that the electric disconnected induced signal that warns will be received to vehicle-mounted inducing receiver T4, vehicle-mounted inducing receiver T4 Disconnected induced signal passes to the signal processor of EMUs, and signal processor carries out logical process according to the signal for receiving, if letter Number processor exports the disconnected induced signal of advance notice, then do not do output function, the otherwise disconnected induced signal of signal processor output advance notice, Notify that motor-car set control system disconnects main circuit breaker and blocks trailer system;
After step 3,2s~6s, it is wireless to No. three that No. three wireless sending modules of main controller controls send No. three triggers Receiver module, No. three batteries No. three solenoids of connection of trigger driving of No. three wireless receiving modules according to reception, No. three Solenoid obtains electric sending and forces disconnected induced signal to vehicle-mounted inducing receiver T1, and vehicle-mounted inducing receiver T1 is forced reception Disconnected induced signal passes to the signal processor of EMUs, and signal processor carries out logical process according to the signal for receiving, if letter Number processor exports the disconnected induced signal of advance notice, then do not do output function, and otherwise signal processor output forces disconnected induced signal, Notify that motor-car set control system turns off main circuit breaker and blocks trailer system;
After step 4,2s~6s, it is wireless to No. four that No. four wireless sending modules of main controller controls send No. four triggers Receiver module, No. four batteries No. four solenoids of connection of trigger driving of No. four wireless receiving modules according to reception, No. four Solenoid obtains electric sending and forces disconnected induced signal to vehicle-mounted inducing receiver T3, and vehicle-mounted inducing receiver T3 is forced reception Disconnected induced signal passes to the signal processor of EMUs, and signal processor carries out logical process according to the signal for receiving, if letter Number processor has been exported and has forced disconnected induced signal, then do not do output function, and otherwise signal processor output forces disconnected induced signal, Notify that motor-car set control system disconnects main circuit breaker immediately and blocks trailer system;
After step 5,6s~20s, test system enters the pattern that simulation EMUs sail out of phase-separating section, main controller controls one Number wireless sending module sends a trigger to a wireless receiving module, and a wireless receiving module is according to touching for receiving Signal and drive a battery to connect a solenoid, a solenoid obtains the electric pre-restore induced signal that sends to vehicle-mounted sense Answer receptor T2, vehicle-mounted inducing receiver T2 that the pre-restore induced signal of reception is passed to the signal processor of EMUs, signal Processor enters pre-restore pattern according to the signal for receiving;
After step 6,2s~6s, it is wireless to No. two that No. two wireless sending modules of main controller controls send No. two triggers Receiver module, trigger driving C-size battery connection No. two solenoids of No. two wireless receiving modules according to reception, No. two Solenoid obtains the electric pre-restore induced signal that sends to vehicle-mounted inducing receiver T4, and vehicle-mounted inducing receiver T4 is pre- extensive by what is received Multiple induced signal passes to the signal processor of EMUs, and signal processor carries out logical process according to the signal for receiving, if letter Number processor has exported pre-restore induced signal, then do not do output function, otherwise signal processor output pre-restore induced signal, Notify motor-car set control system closure main circuit breaker trailer system of lifting a blockade;
After step 7,2s~6s, it is wireless to No. three that No. three wireless sending modules of main controller controls send No. three triggers Receiver module, No. three batteries No. three solenoids of connection of trigger driving of No. three wireless receiving modules according to reception, No. three Solenoid obtains electric sending and forces recovery induced signal to vehicle-mounted inducing receiver T1, and vehicle-mounted inducing receiver T1 is strong by what is received Compel to recover the signal processor that induced signal passes to EMUs, signal processor carries out logical process according to the signal for receiving, If signal processor has exported pre-restore induced signal, output function is not done, otherwise signal processor output forces recovery sense Induction signal, notifies that motor-car set control system closes main circuit breaker and trailer system of lifting a blockade at once;
After step 8,2s~6s, it is wireless to No. four that No. four wireless sending modules of main controller controls send No. four triggers Receiver module, No. four batteries No. four solenoids of connection of trigger driving of No. four wireless receiving modules according to reception, No. four Solenoid obtains electric sending and forces recovery induced signal to vehicle-mounted inducing receiver T3, and vehicle-mounted inducing receiver T3 is strong by what is received Compel to recover the signal processor that induced signal passes to EMUs, signal processor carries out logical process according to the signal for receiving, If signal processor has been exported forces recovery induced signal, output function is not done, otherwise signal processor output forces recovery Induced signal, notifies that motor-car set control system closes main circuit breaker and trailer system of lifting a blockade immediately, completes EMUs undue Phase system dynamic simulant test method.
CN201610929815.7A 2016-10-31 2016-10-31 EMU neutral-section passing system dynamic simulant test system and test method Active CN106556757B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610929815.7A CN106556757B (en) 2016-10-31 2016-10-31 EMU neutral-section passing system dynamic simulant test system and test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610929815.7A CN106556757B (en) 2016-10-31 2016-10-31 EMU neutral-section passing system dynamic simulant test system and test method

Publications (2)

Publication Number Publication Date
CN106556757A true CN106556757A (en) 2017-04-05
CN106556757B CN106556757B (en) 2019-01-18

Family

ID=58443260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610929815.7A Active CN106556757B (en) 2016-10-31 2016-10-31 EMU neutral-section passing system dynamic simulant test system and test method

Country Status (1)

Country Link
CN (1) CN106556757B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107741541A (en) * 2017-10-12 2018-02-27 中车株洲电力机车有限公司 A kind of rail traffic vehicles built-in field intensity near-field test method and system
CN108919781A (en) * 2018-07-12 2018-11-30 沈阳铁路信号有限责任公司 The self checking method and realization circuit of EMU auto-passing neutral section control system
CN110823607A (en) * 2019-11-18 2020-02-21 中车长春轨道客车股份有限公司 Novel method for passing split-phase test of motor train unit
CN112014675A (en) * 2020-09-02 2020-12-01 中车大同电力机车有限公司 Detection circuit and detection device of automatic passing neutral section system
CN113567776A (en) * 2021-06-10 2021-10-29 广东白云学院 Detection method and system for automatic passing split-phase signal processor

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201040496Y (en) * 2007-02-08 2008-03-26 宁涛 Detecting device for electric locomotive automatic passing neutral section system
CN201357765Y (en) * 2009-02-26 2009-12-09 温应群 Automatic onboard neutral-section passing device of double heat-computer backup
CN101811451A (en) * 2010-04-16 2010-08-25 南车株洲电力机车有限公司 Method for controlling passing neutral section of locomotive
CN102650572A (en) * 2012-05-14 2012-08-29 南京拓控信息科技有限公司 Detecting system for auto-passing phase-splitting function of electric locomotive
CN203344967U (en) * 2013-07-24 2013-12-18 长沙铁山轨道交通科技有限公司 Automatic passing neutral section system of electric locomotive
CN204296494U (en) * 2014-12-08 2015-04-29 黎英豪 Electric locomotive automatic passing over of neutral section checkout gear

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201040496Y (en) * 2007-02-08 2008-03-26 宁涛 Detecting device for electric locomotive automatic passing neutral section system
CN201357765Y (en) * 2009-02-26 2009-12-09 温应群 Automatic onboard neutral-section passing device of double heat-computer backup
CN101811451A (en) * 2010-04-16 2010-08-25 南车株洲电力机车有限公司 Method for controlling passing neutral section of locomotive
CN102650572A (en) * 2012-05-14 2012-08-29 南京拓控信息科技有限公司 Detecting system for auto-passing phase-splitting function of electric locomotive
CN203344967U (en) * 2013-07-24 2013-12-18 长沙铁山轨道交通科技有限公司 Automatic passing neutral section system of electric locomotive
CN204296494U (en) * 2014-12-08 2015-04-29 黎英豪 Electric locomotive automatic passing over of neutral section checkout gear

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107741541A (en) * 2017-10-12 2018-02-27 中车株洲电力机车有限公司 A kind of rail traffic vehicles built-in field intensity near-field test method and system
CN108919781A (en) * 2018-07-12 2018-11-30 沈阳铁路信号有限责任公司 The self checking method and realization circuit of EMU auto-passing neutral section control system
CN108919781B (en) * 2018-07-12 2020-10-27 沈阳铁路信号有限责任公司 Self-checking method and implementation circuit of automatic neutral section passing control system of motor train unit
CN110823607A (en) * 2019-11-18 2020-02-21 中车长春轨道客车股份有限公司 Novel method for passing split-phase test of motor train unit
CN110823607B (en) * 2019-11-18 2021-03-16 中车长春轨道客车股份有限公司 Method for passing split-phase test of motor train unit
CN112014675A (en) * 2020-09-02 2020-12-01 中车大同电力机车有限公司 Detection circuit and detection device of automatic passing neutral section system
CN112014675B (en) * 2020-09-02 2023-08-29 中车大同电力机车有限公司 Detection circuit and detection device of automatic passing neutral section system
CN113567776A (en) * 2021-06-10 2021-10-29 广东白云学院 Detection method and system for automatic passing split-phase signal processor
CN113567776B (en) * 2021-06-10 2022-05-27 广东白云学院 Detection method and system for automatic passing split-phase signal processor

Also Published As

Publication number Publication date
CN106556757B (en) 2019-01-18

Similar Documents

Publication Publication Date Title
CN106556757A (en) EMUs neutral-section passing system dynamic simulant test system and method for testing
CN203344967U (en) Automatic passing neutral section system of electric locomotive
CN201272259Y (en) Vehicle mounted autopassing phase separation apparatus
CN104080685B (en) The control device of circuit breaker of electric car
CN207942943U (en) A kind of knee positioning and recognizing device of electric vehicle bow formula charging system
CN107745658A (en) A kind of short marshalling electric EMU joins method for controlling passing neutral section and system again
CN204178239U (en) A kind of Intelligent Mobile Robot guider
CN104865486B (en) A kind of Regional Towing cuts off module test system
CN111273565A (en) Vehicle operation simulation system
CN105946626A (en) Powered device and system for urban track traffic
CN106672017A (en) Rail transit turnout remote control system based on mobile terminal and method
CN107825970A (en) A kind of electric automobile section formula mobile wireless charging station
CN111002847A (en) Mobile wireless charging system and method for electric automobile
CN102253308A (en) Method for determining asymmetric short circuit fault of long stator according to negative sequence voltage
CN109435707A (en) The power supply circuit and railroad vehicle of railroad vehicle
CN102592489A (en) Skill training system for commissioning operation of traction motor of high-speed motor train unit and control method
CN113381461A (en) Charging control method and device and electric automobile
CN202130328U (en) Automatic power on/off device used for underground electric locomotive wirings controlled by low-frequency carrier signals
CN2787499Y (en) Vehicular automatic neutral-section passing system
CN106569072A (en) Track traffic automatic passing over phase-splitter equipment testing system and testing method
CN203761144U (en) Rail transit non-contact power supplying device with honeycomb type coil
CN204142893U (en) Distribution single-phase earth fault locating system
CN203832512U (en) Field axle-counting short-circuit steel rail type track circuit shunting system
CN102610133B (en) Training system and control method for operating skills in debugging of pantograph of high-speed motor train unit
CN103795156A (en) Rail transit non-contact power supply device with honeycomb-type coils and power supply method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant