CN106549284A - The lead installation method of carbon brush and lead wire mounting structure - Google Patents

The lead installation method of carbon brush and lead wire mounting structure Download PDF

Info

Publication number
CN106549284A
CN106549284A CN201510931626.9A CN201510931626A CN106549284A CN 106549284 A CN106549284 A CN 106549284A CN 201510931626 A CN201510931626 A CN 201510931626A CN 106549284 A CN106549284 A CN 106549284A
Authority
CN
China
Prior art keywords
lead
cutting edge
brush
installing hole
periphery cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510931626.9A
Other languages
Chinese (zh)
Other versions
CN106549284B (en
Inventor
浮森悟
梅文成
宫城保寿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuji Carbon Manufacturing Co Ltd
Original Assignee
Fuji Carbon Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuji Carbon Manufacturing Co Ltd filed Critical Fuji Carbon Manufacturing Co Ltd
Publication of CN106549284A publication Critical patent/CN106549284A/en
Application granted granted Critical
Publication of CN106549284B publication Critical patent/CN106549284B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R39/00Rotary current collectors, distributors or interrupters
    • H01R39/02Details for dynamo electric machines
    • H01R39/36Connections of cable or wire to brush
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R43/00Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R43/00Apparatus or processes specially adapted for manufacturing, assembling, maintaining, or repairing of line connectors or current collectors or for joining electric conductors
    • H01R43/12Manufacture of brushes

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Motor Or Generator Current Collectors (AREA)
  • Manufacture Of Motors, Generators (AREA)
  • Finish Polishing, Edge Sharpening, And Grinding By Specific Grinding Devices (AREA)
  • Drilling And Boring (AREA)

Abstract

Offer lead (103) is difficult to the lead installation method and lead wire mounting structure of the carbon brush for departing from.With the decline of drill bit for machining (10), straight hole (21) is cut out on body of the brush (101) by top cutting edge (13), and the helicla flute (22) of the inwall extension along straight hole is cut out by the first periphery cutting edge (14) and the second periphery cutting edge (15).And, in step (D) is stopped, drill bit for machining is rotated with the state for stopping lifting, therefore, wide diameter portion (23) is formed in the bottom of straight hole by the first periphery cutting edge and the second periphery cutting edge, the internal diameter of the wide diameter portion is bigger than spiral fluted external diameter.Copper powder (111) is filled in the base end part insertion lead installing hole by lead and to around which, and then pressurization compression filling copper powder and by lead be fixed on lead installing hole (20) it is interior when, as the base end part of lead is blocked by helicla flute and wide diameter portion, so lead is difficult to from lead installing hole depart from.

Description

The lead installation method of carbon brush and lead wire mounting structure
Technical field
The present invention relates to the lead installation method and lead wire mounting structure of carbon brush.
Background technology
As a form of carbon brush, in Japanese Unexamined Patent Publication 2006-50772 publications, Japanese Unexamined Patent Publication Following carbon brush is disclosed in 2008-154453 publications, Japanese Unexamined Patent Publication 2011-50142 publications etc.:It is logical Cross and the base end part insertion of lead is formed in the lead installing hole of body of the brush, and copper powder is filled to lead Pressurization compression is carried out after installing hole, so that lead is fixed on body of the brush.
Generally, this kind of lead installing hole is processed on body of the brush using the drill bit 100 shown in Fig. 6.Such as Shown in Fig. 7, have using the lead installing hole 102 that the drill bit 100 is processed on body of the brush 101 straight Shape.Lead 103 is arranged in the lead installing hole 102 using lead erecting device 110.Lead Erecting device 110 have for store copper powder 111 receive ware 112, and receive ware 112 bottom surface open The pipes 114 that mouth 113 is liftably fitted together to.
The action of the step of by making lead erecting device 110 to schematically show in Fig. 8, by lead 103 It is fixed in the lead installing hole 102 of body of the brush 101.First, make to be inserted with step (A) and draw The pipe 114 of line 103 declines so that pipe 114 enters lead installing hole 102, and then by from the top of pipe 114 The base end part of the lead 103 that distal process goes out is pressed against the bottom hole of lead installing hole 102, draws so as to shape temporarily The base end part of line 103.
Then, in step (B), make pipe 114 rise and open the reception ware 112 closed by pipe 114 Bottom surface opening 113, and then from receive ware 112 to lead installing hole 102 import copper powder 111, because This, the gap filling copper powder 111 between the base end part and lead installing hole 102 of lead 103.
Then, in step (C), pipe 114 is made to decline and close reception ware 112 by pipe 114 again Opening 113, so as to stop from receive ware 112 to lead installing hole 102 import copper powder 111.
And, in step (D), decline pipe 114, and the top of pipe 114 is pacified by voltage lead wires Fill the copper powder 111 in hole 102 and carry out pressurization compression, hereafter, in step (E), make pipe again 114 rise and extract from lead installing hole 102.Through a series of step (A)~(E), will draw The base end part of line 103 is fixed in the lead installing hole 102 of body of the brush 101.
Patent documentation 1:Japanese Unexamined Patent Publication 2006-50772 publications
Patent documentation 2:Japanese Unexamined Patent Publication 2008-154453 publications
Patent documentation 3:Japanese Unexamined Patent Publication 2011-50142 publications
The content of the invention
Due to utilize the conventional processing of drill bit 100 lead installing hole 102 be shaped as it is straight, so drawing The base end part of line 103 is difficult to be blocked by the inwall of lead installing hole 102.Therefore, pressurization compression copper powder 111 And the fixing force when base end part of lead 103 is fixed on body of the brush 101 is low, so as to easily from lead Installing hole 102 departs from.On the other hand, if strong pressurizing copper powder 111 and compress, though fixing force increase, But there is the breakage because of high plus-pressure of body of the brush 101.
The present invention is proposed in view of the above problems, be its object is to, there is provided lead is difficult to the carbon brush for departing from Lead installation method and lead wire mounting structure.
Invention described in technical scheme 1 provides a kind of lead installation method of carbon brush, and the carbon brush is to pass through The insertion of the base end part of lead is formed in the lead installing hole of body of the brush, and conductive powder is filled to drawing Pressurization compression is carried out after line installing hole, so that lead is fixed on carbon brush obtained from body of the brush, the carbon The lead installation method of brush is characterised by,
Using the following drill bit for machining for processing the lead installing hole of carbon brush, the drill bit for machining sets It is set to:
The top of drill main body is provided with the diameter top axle portion less than the diameter of drill main body, and Leading edge is provided with the top axle portion, the leading edge includes top cutting edge, the first periphery cutting edge, from The continuous second periphery cutting edge of one periphery cutting edge,
Top cutting edge, the first periphery cutting edge and the second periphery cutting edge are arranged on comprising drill main body Rotation centerline datum level on, and top cutting edge is configured in the side of rotation centerline, first Periphery cutting edge and the second periphery cutting edge are configured in the opposite side of rotation centerline,
With the inside corner portion of the inside corner portion of top cutting edge and the first periphery cutting edge in rotation The mode connected on heart line arranges top cutting edge and the first periphery cutting edge, and in the datum level It is interior, the angle of top cutting edge and the first periphery cutting edge into regulation,
First periphery cutting edge and the second periphery cutting edge form the triangle of the angle each other in regulation Both sides, and it is prominent to the side of the top axle portion that the top corner part of the triangle for being formed is divided from both sides;
The lead installation method of the carbon brush has following operation:
Lead installing hole manufacturing procedure, as the crow flies enters inside with from the surface of body of the brush for processing Helicla flute that straight hole, the inwall along straight hole extend, the bottom for being formed in straight hole and internal diameter compares spiral fluted The lead installing hole of the big wide diameter portion of external diameter, including:
Decline step, the decline for making drill bit for machining rotate to specify relative to body of the brush Speed declines,
Stop step, when drill bit for machining drops to the depth of regulation relative to body of the brush, make to add Work drill bit continues rotation but stops declining,
Up step, and then stops operation, rotates drill bit for machining with than declining The fireballing rate of climb rises.
Insertion operation, by the base end part insertion lead installing hole of lead,
Filling procedure, fills conductive powder to around the lead in insertion lead installing hole,
Fixed work order, carries out pressurization compression to the conductive powder of filling to lead installing hole and fixes lead On body of the brush.
Invention described in technical scheme 2 is on the basis of the invention described in technical scheme 1, it is characterised in that
The radius x of interval y and the top axle portion between the rotation centerline and the top corner part is full Sufficient formula:y/x≥1.9.
Invention described in technical scheme 3 is on the basis of the invention described in technical scheme 1, it is characterised in that
Top cutting edge and the first periphery cutting edge angulation are 110~130 °, and the first periphery is cut Sharpener and the second periphery cutting edge angulation are 80~100 °.
Invention described in technical scheme 4 provides a kind of lead wire mounting structure of carbon brush, and the carbon brush is to pass through The insertion of the base end part of lead is formed in the lead installing hole of body of the brush, and conductive powder is filled to drawing Pressurization compression is carried out after line installing hole, so that lead is fixed on carbon brush obtained from body of the brush, the carbon The lead wire mounting structure of brush is characterised by,
The lead installing hole is with entering internal straight hole as the crow flies from the surface of body of the brush, along straight hole The inwall helicla flute for extending, the bottom for being formed in straight hole and expanding bigger than spiral fluted external diameter of internal diameter Portion.
According to the present invention of technical scheme 1, the top ends of the main body of drill bit for machining are provided with diameter ratio The little top axle portion of the diameter of main body, on top, axle portion is provided with the first periphery cutting edge and the second periphery is cut Sharpener, and the first periphery cutting edge and the second periphery cutting edge form the triangle of the angle each other in regulation The both sides of shape, and the top corner part of the triangle for being formed is divided from both sides dash forward to the side of the top axle portion Go out, therefore, with the rotation of drill bit for machining, top axle portion is vibrated and is rotated.
Therefore, in operation is declined, with the decline of drill bit for machining, by top cutting edge in body of the brush On cut out straight hole, and cut by the first triangle periphery cutting edge and the second periphery Knife, cuts out the helicla flute of the inwall extension along straight hole.
In step is stopped, drill bit for machining is rotated with the state for stopping lifting, therefore, outside first All cutting edges and the second periphery cutting edge form wide diameter portion in the bottom of straight hole, and the internal diameter of the wide diameter portion compares spiral shell The external diameter of spin slot is big.
Used with processing by the spiral fluted spacing formed by the first periphery cutting edge and the second periphery cutting edge The rising or falling speed of drill bit accelerates and becomes big.Also, spiral fluted spacing is bigger, top axle portion is got over to axle center Side significantly vibrates, therefore, spiral fluted external diameter diminishes.On the other hand, if the lifting of drill bit for machining Slow, spiral fluted spacing diminishes, the vibration to the center axis of top axle portion diminishes, therefore, spiral shell The external diameter of spin slot becomes big.In operation is risen, drill bit is risen with the rate of climb faster than decrease speed, because This, in operation is risen along straight hole the spiral fluted gap ratio that formed of inwall in operation is declined institute The spiral fluted spacing of formation is big.Therefore, even if declining the part of the spiral fluted formed in operation It is damaged in operation is risen, but major part retained.
So, by using the drill bit for machining of the present invention via decline step, stopping step, rising step Rapid each step is processing body of the brush so that lead installing hole is processed on body of the brush, the lead is installed The spiral that hole extends with the straight hole inside being entered from the surface of body of the brush as the crow flies, along the inwall of straight hole Groove, the bottom for the being formed in straight hole and internal diameter wide diameter portion bigger than spiral fluted external diameter.
In insertion operation by the lead installing hole of the base end part insert structure of lead, in filling work procedure to drawing Conductive powder is filled around line, in pressurization operation pressurization compression conductive powder, so that lead is fixed on In lead installing hole, thus, as the base end part of lead is blocked by helicla flute and wide diameter portion, so lead It is difficult to from lead installing hole depart from.
According to the invention of technical scheme 2, the prominent size of the side to top axle portion of top corner part becomes Greatly, when drill bit for machining rotates, top axle portion is easily vibrated.
According to the invention of technical scheme 3, in processing, spiral fluted shape is difficult to avalanche.Additionally, the One periphery cutting edge and triangle formed by the second periphery cutting edge hold positioned at when drill bit for machining rotates The position for easily vibrating.
Description of the drawings
Fig. 1 is that the lead of the lead installation method for illustrating the carbon brush for one embodiment of the present of invention is installed The side view of the drill bit for machining in hole.
Fig. 2 is the front view for illustrating same drill bit for machining.
Fig. 3 is the processing side of the lead installing hole for schematically showing the carbon brush using same drill bit for machining The explanatory diagram of method.
Fig. 4 is the axonometric chart of an example for illustrating the lead installing hole processed using same processing method.
Fig. 5 is to schematically show lead is fixed on the lead installing hole processed using same processing method The explanatory diagram of interior step.
Fig. 6 is the side view of the drill bit for machining of the lead installing hole for illustrating conventional.
Fig. 7 is to schematically show the lead installing hole and lead installation processed using same drill bit for machining The explanatory diagram of device.
Fig. 8 is to schematically show lead is fixed on the lead processed using same drill bit for machining The explanatory diagram of the step in installing hole.
The explanation of reference:
10:The drill bit for machining of lead installing hole
11:The main body of drill bit for machining
12:Top axle portion
12A:Leading edge
13:Top cutting edge
14:First periphery cutting edge
15:Second periphery cutting edge
16:Inside corner portion
17:Top corner part
20:Lead installing hole
21:Straight hole
22:Helicla flute
23:Wide diameter portion
101:Body of the brush
103:Lead
110:Lead erecting device
111:Copper powder
112:Receive ware
113:Bottom surface opening
L:Rotation centerline
S:Datum level
Specific embodiment
Below, based on the description of the drawings present invention.Figures 1 and 2 show that an enforcement for the present invention The drill bit for machining 10 of the processing method of the lead installing hole of the carbon brush of example.In the drill bit for machining 10 The top ends of main body 11 are provided with the diameter top axle portion 12 less than the diameter of main body 11.Top axle portion 12 diameter is about the half of the diameter of main body 11.The top axle portion 12 is provided with leading edge 12A, should Leading edge 12A includes top cutting edge 13, the first periphery cutting edge 14, connects from the first periphery cutting edge 14 The second continuous periphery cutting edge 15.
Top cutting edge 13, the first periphery cutting edge 14 and the second periphery cutting edge 15 are arranged on and include In the datum level S of the rotation centerline L of drill main body 11.Top cutting edge 13 is arranged on center of rotation The side of line L, the first periphery cutting edge 14 and the second periphery cutting edge 15 are arranged on rotation centerline L Opposite side, the inner side of the inside corner portion 16 of top cutting edge 13 and the first periphery cutting edge 14 is turned Corner 16 connects.
First periphery cutting edge 14 and the second periphery cutting edge 15 are set to, and in datum level S form three Angular both sides and the top corner part 17 of the triangle for being formed is divided from both sides dash forward to the side of top axle portion 12 Go out.
Also, the radius x of the interval y and top axle portion 12 between rotation centerline L and top corner part 17 Size relationship be set as, meet formula:y/x≥1.9.
With top cutting edge 13 and the first periphery cutting edge 14, angulation θ 1 is in the datum level 110~130 ° of mode arranges two cutting edges 13,14.In addition, with 14 He of the first periphery cutting edge Second periphery cutting edge 15 angulation θ 2 in the datum level S arranges two for 80~100 ° of mode Individual cutting edge 14,15.In addition, top cutting edge 13, the first periphery cutting edge 14 and the second periphery The relief angle of cutting edge 15 is set to 20 °.
The structure of drill bit for machining 10 is as described above, Fig. 3 is schematically shown using the processing brill 10 (A)~(E) the step of lead installing hole 20 are processed in the main body 101 of carbon brush.First, In decline operation (A), (B), (C), drill bit for machining 10 is made relative to body of the brush 101 While being rotated with fixing speed while the decrease speed to specify declines.Also, work as drill bit for machining 10 Stop declining when dropping to the depth of regulation relative to body of the brush 101.In the stopping operation (D), As declining operation (A)~(C), drill bit for machining 10 continues rotation.Stop operation (D) Afterwards, the state for making drill bit for machining 10 to keep rotating rises.Processing in operation (E) is risen It is fast with decrease speed of the rate of climb ratio of drill bit 10 in operation (A)~(C) is declined, so as to It is enough rapidly to extract drill bit for machining 10 from body of the brush 101.
According to the present embodiment, the diameter top end shaft less than the diameter of main body is set in the top ends of main body 11 Portion 12, on top, axle portion 12 arranges the first periphery cutting edge 14 and the second periphery cutting edge 15, and First periphery cutting edge 14 and the second periphery cutting edge 15 form two of the triangle each other in predetermined angular Side and divided from both sides the triangle for being formed top corner part 17 it is prominent to the side of top axle portion 12, therefore, With the rotation of drill bit for machining 10, top axle portion 12 is vibrated and is rotated.Therefore, with step (A)~ (C) decline of the drill bit for machining 10 in, is cut on body of the brush 101 by top cutting edge 13 Processing straight hole 21, and pass through 15 machining edge of the first periphery cutting edge 14 and the second periphery cutting edge The helicla flute 22 that the inwall of straight hole 21 extends.Also, in operation (D) is stopped, processing is bored 10 to keep stopping the state rotation of lifting, therefore, by the first periphery cutting edge 14 and second outside All cutting edges 15 form wide diameter portion 23 in the bottom of straight hole 21, and the internal diameter of the wide diameter portion 23 compares helicla flute 22 external diameter is big.Fig. 4 shows the shape of the lead installing hole 20 processed using drill bit for machining 10 One example.
The spacing of the helicla flute 22 formed by the first periphery cutting edge 14 and the second periphery cutting edge 15 Accelerating with the rising or falling speed of drill bit for machining 10 and becoming big.Also, the spacing of helicla flute 22 is bigger, then The external diameter of helicla flute 22 is less.On the other hand, if the rising or falling speed of drill bit for machining 10 is slack-off, spiral shell The spacing of spin slot 22 diminishes, as a result, the external diameter of helicla flute 22 becomes big.In up step, processing Risen with the rate of climb faster than decrease speed with drill bit 10, therefore, along straight hole in up step The gap ratio of the helicla flute 22 formed by 21 inwall is declining between the helicla flute 22 formed in step Away from big.Therefore, even if a part for the helicla flute 22 formed in decline step is in up step Breakage, but major part retained.
As described above, by using the present embodiment drill bit for machining 10 via decline step (A), (B), (C) the step of, stopping step (D), up step (E) is processing body of the brush 101 so that Lead installing hole 20 is processed on body of the brush 101, the lead installing hole 20 is with from body of the brush 101 Surface enters internal straight hole 21, the helicla flute 22 that the inwall along straight hole 21 extends, formation as the crow flies In the bottom of straight hole 21 and the internal diameter wide diameter portion 23 bigger than the internal diameter of straight hole 21.
Then, illustrate fixed in the lead installing hole 20 processed using drill bit for machining 10 based on Fig. 5 The step of lead 103.First, make under the pipe 114 of insertion leaded 103 in insertion operation (A) Drop, and make pipe 114 enter lead installing hole 20, and then the lead 103 that will be projected from the top of pipe 114 Base end part be pressed against lead installing hole 20 bottom wide diameter portion 23, so as to interim formed leads 103 Base end part.Then, in filling work procedure (B), (C), (D), pipe 114 is made to increase, and Open the opening 113 of the bottom surface of the reception ware 112 closed by pipe 114, and then from receiving ware 112 to drawing Line installing hole 20 imports copper powder 111, so as to the gap between lead 103 and lead installing hole 20 is filled out Copper powder 111 is filled, after copper powder 111 of ormal weight are filled, declines pipe 114 again, and utilize pipe 114 Closing receives the opening 113 of ware 112, so as to stop that copper is imported from reception ware 112 to lead installing hole 20 Powder 111.Then, in fixed work order (E), further decline pipe 114, on the top for making pipe 114 End and side face press copper powder 111 and after the compression copper powder 111 that pressurizes, pipe 114 is risen and is installed from lead Hole 20 is extracted, so as to be fixed on the base end part of lead 103 in the lead installing hole 20 of body of the brush 101. As the base end part of lead 103 is blocked by helicla flute 22 and wide diameter portion 23, so being difficult to from lead install Hole 20 departs from.

Claims (4)

1. the lead installation method of a kind of carbon brush, the carbon brush are to insert shape by the base end part by lead Into in the lead installing hole of body of the brush, and conductive powder is filled to lead installing hole carry out pressurization pressure Contracting, so that lead is fixed on carbon brush obtained from body of the brush, the spy of the lead installation method of the carbon brush Levy and be,
Using the following drill bit for machining for processing the lead installing hole of carbon brush, the drill bit for machining sets It is set to:
The top of drill main body is provided with the diameter top axle portion less than the diameter of drill main body, and Leading edge is provided with the top axle portion, the leading edge includes top cutting edge, the first periphery cutting edge, from The continuous second periphery cutting edge of one periphery cutting edge,
Top cutting edge, the first periphery cutting edge and the second periphery cutting edge are arranged on comprising drill main body Rotation centerline datum level on, and top cutting edge is configured in the side of rotation centerline, first Periphery cutting edge and the second periphery cutting edge are configured in the opposite side of rotation centerline,
With the inside corner portion of the inside corner portion of top cutting edge and the first periphery cutting edge in rotation The mode connected on heart line arranges top cutting edge and the first periphery cutting edge, and in the datum level It is interior, the angle of top cutting edge and the first periphery cutting edge into regulation,
First periphery cutting edge and the second periphery cutting edge form two of the triangle each other in predetermined angular Side, and it is prominent to the side of the top axle portion that the top corner part of the triangle for being formed is divided from both sides;
The lead installation method of the carbon brush has following operation:
Lead installing hole manufacturing procedure, as the crow flies enters inside with from the surface of body of the brush for processing Helicla flute that straight hole, the inwall along straight hole extend, the bottom for being formed in straight hole and internal diameter compares spiral fluted The lead installing hole of the big wide diameter portion of external diameter, including:
Decline step, the decline for making drill bit for machining rotate to specify relative to body of the brush Speed declines,
Stop step, when drill bit for machining drops to the depth of regulation relative to body of the brush, make to add Work drill bit continues rotation but stops declining,
Up step, and then stops operation, rotates drill bit for machining with than declining The fireballing rate of climb rises.
Insertion operation, by the base end part insertion lead installing hole of lead,
Filling procedure, fills conductive powder to around the lead in insertion lead installing hole,
Fixed work order, carries out pressurization compression to the conductive powder of filling to lead installing hole and fixes lead On body of the brush.
2. the lead installation method of carbon brush as claimed in claim 1, it is characterised in that
The radius x of interval y and the top axle portion between the rotation centerline and the top corner part is full Sufficient formula:y/x≥1.9.
3. the lead installation method of carbon brush as claimed in claim 1, it is characterised in that
Top cutting edge and the first periphery cutting edge angulation are 110~130 °, and the first periphery is cut Sharpener and the second periphery cutting edge angulation are 80~100 °.
4. a kind of lead wire mounting structure of carbon brush, the carbon brush are to insert shape by the base end part by lead Into in the lead installing hole of body of the brush, and conductive powder is filled to lead installing hole carry out pressurization pressure Contracting, so that lead is fixed on carbon brush obtained from body of the brush, the spy of the lead wire mounting structure of the carbon brush Levy and be,
The lead installing hole is with entering internal straight hole as the crow flies from the surface of body of the brush, along straight hole The inwall helicla flute for extending, the bottom for being formed in straight hole and expanding bigger than spiral fluted external diameter of internal diameter Portion.
CN201510931626.9A 2015-09-18 2015-12-15 The lead installation method and lead wire mounting structure of carbon brush Active CN106549284B (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2015184642A JP6153266B2 (en) 2015-09-18 2015-09-18 Carbon brush lead wire mounting structure
JP2015-184642 2015-09-18

Publications (2)

Publication Number Publication Date
CN106549284A true CN106549284A (en) 2017-03-29
CN106549284B CN106549284B (en) 2018-11-27

Family

ID=58364915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510931626.9A Active CN106549284B (en) 2015-09-18 2015-12-15 The lead installation method and lead wire mounting structure of carbon brush

Country Status (2)

Country Link
JP (1) JP6153266B2 (en)
CN (1) CN106549284B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115365765A (en) * 2022-07-29 2022-11-22 广联航空工业股份有限公司 Deep hole machining method with position precision requirement

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57189267U (en) * 1981-05-26 1982-12-01
JPH04164509A (en) * 1990-10-24 1992-06-10 Kenji Yamamoto Drill having no chisel edge
JP2001252826A (en) * 2000-03-06 2001-09-18 Honda Motor Co Ltd Threading method and spot facing method
JP2005014360A (en) * 2003-06-25 2005-01-20 Yunika Kk Drill
JP2005153131A (en) * 2003-11-28 2005-06-16 Tecnisco Ltd Drilling tool and drilling method
JP2006082199A (en) * 2004-09-17 2006-03-30 Makino J Kk Tapping tool with drill bit and screw hole machining method
JP4416880B2 (en) * 1999-10-01 2010-02-17 本田技研工業株式会社 Re-grinding method for thread cutting tools
JP2011050142A (en) * 2009-08-26 2011-03-10 Aupack Co Ltd Carbon brush and method of manufacturing the same

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60141409A (en) * 1983-12-27 1985-07-26 Nobuyuki Shinkai Boring head

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57189267U (en) * 1981-05-26 1982-12-01
JPH04164509A (en) * 1990-10-24 1992-06-10 Kenji Yamamoto Drill having no chisel edge
JP4416880B2 (en) * 1999-10-01 2010-02-17 本田技研工業株式会社 Re-grinding method for thread cutting tools
JP2001252826A (en) * 2000-03-06 2001-09-18 Honda Motor Co Ltd Threading method and spot facing method
JP2005014360A (en) * 2003-06-25 2005-01-20 Yunika Kk Drill
JP2005153131A (en) * 2003-11-28 2005-06-16 Tecnisco Ltd Drilling tool and drilling method
JP2006082199A (en) * 2004-09-17 2006-03-30 Makino J Kk Tapping tool with drill bit and screw hole machining method
JP4703149B2 (en) * 2004-09-17 2011-06-15 マキノジェイ株式会社 Screw hole machining method
JP2011050142A (en) * 2009-08-26 2011-03-10 Aupack Co Ltd Carbon brush and method of manufacturing the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115365765A (en) * 2022-07-29 2022-11-22 广联航空工业股份有限公司 Deep hole machining method with position precision requirement
CN115365765B (en) * 2022-07-29 2023-11-21 广联航空工业股份有限公司 Deep hole machining method with position precision requirement

Also Published As

Publication number Publication date
CN106549284B (en) 2018-11-27
JP2017060338A (en) 2017-03-23
JP6153266B2 (en) 2017-06-28

Similar Documents

Publication Publication Date Title
CN205364072U (en) Drilling device
EP2620123B1 (en) Tool for milling bone tissue, especially for sinus lifting according to the summers technique or for positioning extra-short implants
JPS59209337A (en) Dental support with spiral groove
CN106549284A (en) The lead installation method of carbon brush and lead wire mounting structure
CN103994259A (en) Diaphragm valve housing and method for producing a diaphragm valve housing
CN106541168A (en) Drill bit for machining and processing method
CN108135674B (en) Drilling device for tooth implantation
CN107322716B (en) Bamboo internal segment flush trimmer
JP2014161595A (en) Dental drill
KR101182335B1 (en) Perforation drill of upper jawbone
CN205651419U (en) Novel tapping machine with shock -absorbing structure
US8828002B2 (en) Fenestration burr
CN207726174U (en) Vibrate pot automatic backflow structure
CN202606938U (en) Micro drill
CN106944636B (en) A kind of wire rod clamping device
CN205700926U (en) Meat grinder
CN104924202B (en) A kind of centrifugal bistrique
CN206809356U (en) Drill bit extension rod and there is its drill bit assembly
CN215409178U (en) Screw pump helical casing with keyway balanced structure
CN108016827A (en) Vibrate pot automatic backflow structure
CN105382311B (en) A kind of method for reducing casing installation side milling and cutting deformation
CN220313807U (en) Punching dust collection device for decoration and fitment
CN205278268U (en) Belt pulley connection mechanism
CN220482147U (en) Hollow glass perforating device
CN109967799A (en) A kind of pneumatic thread machining device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant