CN106522961B - jacking construction device - Google Patents
jacking construction device Download PDFInfo
- Publication number
- CN106522961B CN106522961B CN201610978164.0A CN201610978164A CN106522961B CN 106522961 B CN106522961 B CN 106522961B CN 201610978164 A CN201610978164 A CN 201610978164A CN 106522961 B CN106522961 B CN 106522961B
- Authority
- CN
- China
- Prior art keywords
- ring structure
- ring
- side portal
- plate
- vertical shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 51
- 239000000945 filler Substances 0.000 claims abstract description 19
- 230000000694 effects Effects 0.000 claims abstract description 12
- 230000007246 mechanism Effects 0.000 claims abstract description 9
- 229920001971 elastomer Polymers 0.000 claims description 67
- 239000011499 joint compound Substances 0.000 claims description 7
- 230000008859 change Effects 0.000 claims description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 5
- 239000004519 grease Substances 0.000 claims description 3
- 239000004744 fabric Substances 0.000 claims 1
- 230000008878 coupling Effects 0.000 abstract description 49
- 238000010168 coupling process Methods 0.000 abstract description 49
- 238000005859 coupling reaction Methods 0.000 abstract description 49
- 238000000034 method Methods 0.000 description 10
- 238000010586 diagram Methods 0.000 description 7
- 238000007789 sealing Methods 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 4
- 210000004262 dental pulp cavity Anatomy 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 239000000243 solution Substances 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 230000008569 process Effects 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 125000004122 cyclic group Chemical group 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 229910000975 Carbon steel Inorganic materials 0.000 description 1
- 244000043261 Hevea brasiliensis Species 0.000 description 1
- 239000010962 carbon steel Substances 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 229920003052 natural elastomer Polymers 0.000 description 1
- 229920001194 natural rubber Polymers 0.000 description 1
- 238000012163 sequencing technique Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a kind of jacking construction devices, belong to technical field of tunnel construction.Described device includes: tunnel side portal ring structure, vertical shaft side portal ring structure and the annular seal inner tube of a tyre for having telescopic resilience, is provided with the annular seal inner tube of a tyre on the inner wall of tunnel side portal ring structure and on the inner wall of vertical shaft side portal ring structure;Valve mechanism is provided with outside tunnel side portal ring structure and vertical shaft side portal ring structure, valve mechanism is connected with the corresponding annular seal inner tube of a tyre, for filling default filler in the corresponding annular seal inner tube of a tyre.The present invention expands it and generates stiction to tube coupling by filling default filler into the annular seal inner tube of a tyre for have certain telescopic resilience, enhances the retaining effect to tube coupling.
Description
Technical field
The present invention relates to technical field of tunnel construction, in particular to a kind of jacking construction device.
Background technique
In technical field of tunnel construction, it can usually be related to jacking construction operation, jacking construction is mainly by main top
Oil cylinder overcomes the frictional force of tube coupling and surrounding soil to the thrust of tube coupling, and tube coupling is headed into from tunnel portal and presets position in tunnel
It sets, finally retracts main top oil cylinder.
It during jacking construction, needs to be sealed tunnel portal, and prevents during main top oil cylinder is retracted
Only tube coupling retreats.Currently, generalling use jacking construction device as shown in Figure 1 carries out portal sealing and tube coupling retaining, the device
Including the fixed ring flat-plate 01 of portal, portal ring structure 02, cord rubber ring 03, connecting rod 04 and tube coupling backstopping device 05.Tube coupling stops
It moves back logical 05 connecting rod 04 excessively of device to connect with portal ring structure 02, is provided with cord rubber ring between two portal ring structures 02
03, and be fixed at tunnel portal by the fixed ring flat-plate 01 of portal, tunnel portal is sealed by cord rubber ring 03, and
Tube coupling retaining is realized by tube coupling backstopping device 05.
In the implementation of the present invention, the inventor finds that the existing technology has at least the following problems:
Main top oil cylinder is since stress release is easy to cause tube coupling to retreat during retracting, and tube coupling backstopping device then passes through
Hydraulic mechanism compresses tube coupling to realize tube coupling retaining, and retaining effect is poor.
Summary of the invention
In order to solve the problems, such as that the prior art is poor to tube coupling retaining effect, the embodiment of the invention provides a kind of jacking constructions
Device.The technical solution is as follows:
On the one hand, a kind of jacking construction device is provided, described device includes:
Tunnel side portal ring structure, vertical shaft side portal ring structure and the annular seal inner tube of a tyre for having telescopic resilience, institute
It states on the inner wall of tunnel side portal ring structure and is provided with the ring-type on the inner wall of the vertical shaft side portal ring structure
Seal the inner tube of a tyre;
It is provided with valve mechanism outside the tunnel side portal ring structure and the vertical shaft side portal ring structure, it is described
Valve mechanism is connected with the corresponding annular seal inner tube of a tyre, for filling default filler into the corresponding annular seal inner tube of a tyre.
Optionally, the jacking construction device further include: have the annular slice cover tire of telescopic resilience, the annular slice
Cover tire is wrapped in outside the annular seal inner tube of a tyre.
Optionally, the jacking construction device further include: the first cord rubber ring and adjusting pressing plate;
The vertical shaft side portal ring structure is set gradually on the end face far from the tunnel side portal ring structure
State the first cord rubber ring and the adjusting pressing plate, the adjusting pressing plate is arranged on the first cord rubber ring, and described the
Activity on the inside of one cord rubber ring, outside is fixed;
The adjusting pressing plate can change the adjusting pressing plate pressure along the radial motion of the vertical shaft side portal ring structure
Make the area of the active side of the first cord rubber ring.
Optionally, the jacking construction device further include: connection bolt and pressure ring plate, the first cord rubber ring socket
On the outer wall of the vertical shaft side portal ring structure, fixed by the pressure ring plate;
The adjusting pressing plate is provided on the pressing plate ring;
The pressure ring plate and described adjust are provided with for the through-hole for connecting bolt and passing through on pressing plate, wherein described
It is provided in the through-hole of pressure ring plate for connecting bolted screw thread with described, the through-hole adjusted on pressing plate is strip
Hole, the length direction in the strip hole is parallel to the radial direction of the vertical shaft side portal ring structure, and is greater than the pressure ring plate
The diameter of through-hole.
Optionally, the jacking construction device further include:
The fixed ring flat-plate of portal and waterproof ring flat-plate;
The fixed ring flat-plate of the portal is fixed on Tunnel doorway;
The tunnel side portal ring structure is arranged in far from the vertical shaft side portal ring structure in the waterproof ring flat-plate
On end face, the waterproof ring flat-plate is located between the fixed ring flat-plate of the portal and the tunnel side portal ring structure.
Optionally, the waterproof ring flat-plate is detachably connected with the fixed ring flat-plate of the portal using bolt.
Optionally, the outside of the tunnel side portal ring structure and the vertical shaft side portal ring structure is welded with more
A floor.
Optionally, the jacking construction device further include:
Second cord rubber girth sheets;
It is arranged between the tunnel side portal ring structure and adjacent two end faces of the vertical shaft side portal ring structure
There is the second cord rubber ring.
Optionally, the tunnel side portal ring structure and adjacent two end faces of the vertical shaft side portal ring structure,
And the through-hole passed through for bolt is provided on the second cord rubber ring, the second cord rubber ring is solid by bolt
It is scheduled between the tunnel side portal ring structure and adjacent two end faces of the vertical shaft side portal ring structure.
Optionally, the default filler is mud, water or grease.
Technical solution provided by the invention has the benefit that
A kind of jacking construction device provided by the invention, the device include having in the annular seal of certain telescopic resilience
Tire is arranged in portal ring structure inner ring, has and default filler can be filled in the annular seal inner tube of a tyre of certain telescopic resilience,
It can make its expansion by filling default filler into the annular seal inner tube of a tyre for have telescopic resilience, and wrap up tube coupling, in turn
Stiction is generated to tube coupling, main top oil cylinder is solved and starts to lead to tube coupling retrogressing during retracting due to stress release
Problem effectively raises device to the retaining effect of tube coupling.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment
Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for
For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings other
Attached drawing.
Fig. 1 is a kind of jacking construction apparatus structure schematic diagram that the prior art provides;
Fig. 2 is a kind of main view of jacking construction device provided in an embodiment of the present invention;
Fig. 3 is a kind of jacking construction device Section A-A structural schematic diagram that embodiment illustrated in fig. 2 provides;
Fig. 4 is a kind of jacking construction device Section A-A concrete structure schematic diagram that embodiment illustrated in fig. 2 provides;
Fig. 5 is a kind of top view of jacking construction device provided in an embodiment of the present invention;
Fig. 6 is a kind of adjusting pressure plate structure schematic diagram of jacking construction device provided in an embodiment of the present invention;
Fig. 7 is that a kind of adjusting pressing plate for jacking construction device that embodiment illustrated in fig. 4 provides adjusts schematic diagram;
Fig. 8 be according to fig. 2 provided by a kind of application method flow chart of jacking construction device.
The drawings herein are incorporated into the specification and forms part of this specification, and shows and meets implementation of the invention
Example, and be used to explain the principle of the present invention together with specification.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention
Formula is described in further detail.
The embodiment of the present invention provides a kind of jacking construction device, as shown in Fig. 2, it illustrates provided in an embodiment of the present invention
A kind of main view of jacking construction device, the jacking construction device include:
Tunnel side portal ring structure 1, vertical shaft side portal ring structure 2, further, as shown in figure 3, it illustrates figures
A kind of Section A-A structural schematic diagram of jacking construction device shown in 2, which further includes having in the annular seal of telescopic resilience
Tire 3.
It is provided on the inner wall of tunnel side portal ring structure 1 and vertical shaft side portal ring structure 2 and has telescopic resilience
The annular seal inner tube of a tyre 3.
Valve mechanism 5, tunnel are provided on the side wall of tunnel side portal ring structure 1 and vertical shaft side portal ring structure 2
Valve mechanism 5 on the side wall of side portal ring structure 1 and vertical shaft side portal ring structure 2 has telescopic resilience with corresponding
The annular seal inner tube of a tyre 3 is connected to, for filling default filler to have the annular seal inner tube of a tyre 3 of telescopic resilience.Wherein, tunnel side
Portal ring structure and vertical shaft side portal ring structure can be U-frame frame steel loop, and U-frame frame steel loop has stronger crushing resistance
Can, and stable structure.
In embodiments of the present invention, valve mechanism 5 is connect with external high pressure pump (not drawing in Fig. 2), which will pump
The fluid injection sent has the annular seal inner tube of a tyre 3 of certain telescopic resilience, and while adjusting in a certain range can play to tunnel
The sealing of road portal and the retaining effect in tunnel.
Optionally, having the default filler in the annular seal inner tube of a tyre of telescopic resilience is mud, water or grease, Ke Yigen
It is selected according to the situation in practical application, it is not limited in the embodiment of the present invention.
Optionally, as shown in figure 3, the jacking construction device further include: have the annular slice cover tire 4 of telescopic resilience,
The annular slice cover tire 4 for having telescopic resilience is wrapped in the outside for having the annular seal inner tube of a tyre 3 of telescopic resilience.
Specifically, this have telescopic resilience annular slice cover tire can by can shape-changing material be made, preferably rubber
Material, by annular slice cover tire, deformation occurs to generate stiction to tube coupling, and then play the retaining effect to tube coupling.
It should be noted that above-mentioned tunnel side portal ring structure and vertical shaft side portal ring structure respectively with have it is certain
The annular slice cover tire of telescopic resilience is connected by screw bolts.To fasten the annular slice cover tire for having certain telescopic resilience, prevent
Only it is subjected to displacement under the stiction generated with tube coupling.
In conclusion a kind of jacking construction device provided in an embodiment of the present invention, which includes having centainly flexible bullet
Property the annular seal inner tube of a tyre, be arranged in portal ring structure inner ring, having can in the annular seal inner tube of a tyre of certain telescopic resilience
Default filler is filled, its expansion can be made by filling default filler into the annular seal inner tube of a tyre for have telescopic resilience,
And tube coupling is wrapped up, and then stiction is generated to tube coupling, it solves main top oil cylinder and starts during retracting due to stress release
And the problem of causing tube coupling to retreat, device is effectively raised to the retaining effect of tube coupling.
Further, as shown in Fig. 2, the outside of tunnel side portal ring structure 1 and vertical shaft side portal ring structure 2 is welded
It is connected to multiple floors 14.
It should be noted that the floor is rectangular steel plates, two end is respectively welded at the outer of portal ring structure
Portion two sides are used to support portal ring structure, and the structure of whole device can be made more stable.
Specifically, as shown in figure 4, it illustrates a kind of signals of the Section A-A specific structure of jacking construction device shown in Fig. 2
Figure, jacking construction device further include: the first cord rubber ring 6 and adjusting pressing plate 7;Vertical shaft side portal ring structure 2 is far from tunnel
It is disposed with the first cord rubber ring 6 on the end face of side portal ring structure 1 and adjusts pressing plate 7, adjusts the setting of pressing plate 7 the
On one cord rubber ring 6, the first cord rubber ring 6 inside A activity, outside B is fixed;Adjusting pressing plate 7 can be along vertical shaft side portal
The radial X of ring structure 2 is moved, and changes the area for adjusting the active side that pressing plate 7 suppresses the first cord rubber ring 6.
In embodiments of the present invention, the outside of the first cord rubber ring is rubber cyclic structure, and is bolted on
On the outer wall of vertical shaft side portal ring structure, inside is raised drops rubber structure, movable, can be used for wrapping up tube coupling
And formed and sealed in conduit jacking outer rim, prevent underground water or mud leakage during push pipe.
Further, it adjusts pressing plate to be arranged on the first cord rubber ring, and can be along vertical shaft side portal ring structure
Radial motion, the quantity that pressing plate is adjusted in the embodiment of the present invention can have multiple, and particular number can be managed according in practical application
The diameter of section is selected, and the embodiment of the present invention is it is not limited here.Tube coupling jacking that is exemplary, being 2400 millimeters in diameter
In operation, corresponding adjusting pressing plate quantity is 30 pieces, if the tube coupling diameter selected, less than 2400 millimeters, corresponding reduce is adjusted
Save the quantity of pressing plate;If the tube coupling diameter selected is greater than 2400 millimeters, the quantity for adjusting pressing plate is accordingly increased.
Specifically, Fig. 5 is a kind of top view of jacking construction device provided in an embodiment of the present invention, multiple adjusting pressures in figure
7 groups of plate merge to form annular adjustment structure, adjust the compacting of pressing plate 7 first cord rubber ring (not drawing in Fig. 5) by changing
The area of active side makes the internal diameter of the annular adjustment structure change.
Specifically, as shown in figure 4, jacking construction device further include: connection bolt 8 and pressure ring plate 9, the first cord rubber ring
6 are socketed on the outer wall of vertical shaft side portal ring structure 2, fixed by pressure ring plate 9;It is provided on pressing plate ring 9 and adjusts pressing plate 7;Into
One step, as shown in fig. 6, being additionally provided with the through-hole 13 passed through for connection bolt 8 on pressure ring plate 9 and adjusting pressing plate 7, wherein pressure
Be provided in the through-hole 13 of ring flat-plate 9 for connect bolt 8 connection screw thread, adjust pressing plate 7 on through-hole 13 be strip hole, item
The length direction in shape hole is parallel to the radial X of vertical shaft side portal ring structure 2 as shown in Figure 2, and is greater than the through-hole of pressure ring plate 9
13 diameter.
It can to adjust pressing plate by being provided with the through-hole passed through for connection bolt on pressure ring plate and adjusting pressing plate
Regulative mode is more simple and easy to operate, and the length of through-hole can then make adjusting pressing plate form fixed adjustable range.
Specifically, as shown in fig. 7, it illustrates a kind of adjusting pressing plate tune of Fig. 4 of the present invention jacking construction device provided
Schematic diagram is saved, before the first root canal section 15 enters the first cord rubber ring 6, all adjusting pressing plates 7 is adjusted and makes the institute to be formed
It is maximum to state annular adjustment structure internal diameter D, after 15 front end of the first root canal section enters the first cord rubber ring 6, adjusts all tune
Section pressing plate 7 makes the annular adjustment structure internal diameter D to be formed identical as the diameter d of tube coupling 15, and push pipe process hereafter
Middle holding internal diameter is constant.Effective compacting can be formed to the first cord rubber ring 6 during push pipe in this way, solved
It is main to push up during oil cylinder is retracted since changes of voids is (due to void ratio tube coupling and the tunnel stratum of main top oil cylinder and tunnel stratum
Gap it is big and caused by changes of voids) make mud leakage that the first cord rubber ring 6 be caused to turn up, destroy tunnel portal sealing
The problem of.
Specifically, as shown in figure 4, jacking construction device further include: the fixed ring flat-plate 10 of portal and rubber waterproof ring flat-plate 11;Hole
The fixed ring flat-plate 10 of door is fixed on Tunnel doorway;Rubber waterproof ring flat-plate 11 is arranged in tunnel side portal ring structure 1 far from vertical shaft
On the end face of side portal ring structure 2, rubber waterproof ring flat-plate 11 is located at the fixed ring flat-plate 10 of portal and tunnel side portal ring structure 1
Between, the fixed ring flat-plate 10 of portal is fixed on Tunnel doorway.
In embodiments of the present invention, it after the assembling of other components of jacking construction device, can be mounted on by bolt
On the fixed ring flat-plate of portal.Rubber waterproof ring flat-plate is as anti-between tunnel side portal ring structure and vertical shaft side portal ring structure
Wet part can prevent the gap of water or mud between tunnel side portal ring structure and vertical shaft side portal ring structure from letting out
Dew, improves the leakproofness of device.
Further, rubber waterproof ring flat-plate is detachably connected with the fixed ring flat-plate of portal using bolt, and it is solid to can be convenient portal
Determine the disassembly and installation of ring flat-plate, and makes the replacement of rubber waterproof ring flat-plate more convenient.
Specifically, as shown in figure 4, adjacent two ends of tunnel side portal ring structure 1 and vertical shaft side portal ring structure 2
Be provided with the second cord rubber ring 12 between face, tunnel side portal ring structure 1 and vertical shaft side portal ring structure 2 it is adjacent two
The through-hole (not marking in Fig. 4) passed through for bolt, the second cord rubber are provided on a end face and the second cord rubber ring 12
Cushion rubber 12 be bolted on tunnel side portal ring structure 1 and adjacent two end faces of vertical shaft side portal ring structure 2 it
Between.
It should be noted that the second cord rubber ring of setting can cooperatively form double sealing with the first cord rubber ring,
Keep the sealing effect of whole device more preferable.
It should be noted that in embodiments of the present invention, have the annular seal inner tube of a tyre of certain telescopic resilience, have it is flexible
Rubber material used in the fixed ring flat-plate of annular slice cover tire, the first cord rubber ring, the second cord rubber ring and the rubber of elasticity
Can be natural rubber, shore hardness be 60+5 degree, elongation 280%, be permanently deformed less than 10%, brittle temperature be-
25 degrees Celsius to 60 degrees Celsius.Involved steel plate materials are all made of 235 structural carbon steel of common Q in the embodiment of the present invention, surrender
Intensity is 235MPa (megapascal).
The application method of the jacking construction device provided in the embodiment of the present invention can according to the structure difference of the device into
Row is appropriate to be adjusted, and the embodiment of the present invention is illustrated the application method of jacking construction device shown in Fig. 2 by taking Fig. 2 as an example, it is assumed that
It needs to push into tube coupling into predeterminated position in tunnel, then as shown in figure 8, its step are as follows:
Jacking construction device is mounted on Tunnel doorway by the fixed ring flat-plate of portal by step 801.
Step 802 adjusts all adjusting pressing plates, and the cyclic structure internal diameter formed it into is maximum.
Specifically, adjusting the quantity of pressing plate can have multiple, particular number can be according to the diameter of tube coupling in practical application
It is selected, multiple adjusting pressing plate groups merge to form annular adjustment structure, pass through to change and adjust pressing plate and suppress the first cord rubber
The area of the active side of cushion rubber makes the internal diameter of the annular adjustment structure change.Enter the first cord in the first root canal section
Before rubber ring, adjust it is all to adjust the annular adjustment structure internal diameter that pressing plates to be formed maximum, can be convenient in this way tube coupling into
Enter.
The front end of tube coupling is put into Tunnel doorway, and adjusts all adjusting pressing plates, the ring-type formed it by step 803
Inside diameter is identical as tube coupling diameter.
Specifically, adjusting all adjusting pressing plates after the first root canal section front end enters the first cord rubber ring and making shape
At annular adjustment structure internal diameter it is identical as the diameter of tube coupling, and push pipe hereafter during keep the internal diameter constant, in this way
Effective compacting can be formed to the first cord rubber ring during push pipe, avoid during main top oil cylinder is retracted by
In changes of voids mud is revealed, to solve the problems, such as that the first cord rubber ring turns up, it is therefore prevented that tunnel portal sealing
It is destroyed.
End in contact after step 804, main top oil cylinder front end and tube coupling starts push pipe.
It should be noted that in step 804, needed replacing if cord rubber ring damages during push pipe,
First stop the movement of main top oil cylinder, and injects filler into the annular seal inner tube of a tyre for having certain telescopic resilience from valve and be allowed to
Tube coupling is expanded and wrapped up, then demounting bolt carries out the replacement of cord rubber ring, after replacement, will be provided with by valve centainly flexible
Filler in the annular seal inner tube of a tyre of elasticity discharges and starts the movement of main top oil cylinder, continues push pipe.
Further, if carrying out push pipe operation in the biggish situation of hydraulic pressure in long-distance pipe jacking operation or tunnel,
Before step 804, filler can also be injected into the annular seal inner tube of a tyre for have certain telescopic resilience by valve and be allowed to
Expand and wrap up tube coupling, in this way can to avoid during main top oil cylinder push pipe due in tunnel pressure it is excessive and lead to tube coupling
It retreats.
Step 805, behind tube coupling top to predeterminated position, first pass through valve into the annular seal inner tube of a tyre for having telescopic resilience
Injection filler is allowed to expand and wrap up tube coupling, then main top oil cylinder is retracted.
After step 806, main top oil cylinder exit tunnel portal, it will be provided in the annular seal inner tube of a tyre of telescopic resilience by valve
Filler release.
In conclusion a kind of jacking construction device provided in an embodiment of the present invention, which includes having centainly flexible bullet
Property the annular seal inner tube of a tyre, be arranged in portal ring structure inner ring, having can in the annular seal inner tube of a tyre of certain telescopic resilience
Default filler is filled, its expansion can be made by filling default filler into the annular seal inner tube of a tyre for have telescopic resilience,
And tube coupling is wrapped up, and then stiction is generated to tube coupling, it solves main top oil cylinder and starts during retracting due to stress release
And the problem of causing tube coupling to retreat, device is effectively raised to the retaining effect of tube coupling.
It should be noted that the sequencing of the application method step of jacking construction device provided in an embodiment of the present invention can
To carry out appropriate adjustment, step according to circumstances can also accordingly be increased and decreased, and anyone skilled in the art exists
The invention discloses technical scope in, the method that can readily occur in variation should be covered by the protection scope of the present invention, because
This is repeated no more.
It is apparent to those skilled in the art that for convenience and simplicity of description, the push pipe of foregoing description
The specific work process of constructing device, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all in spirit of the invention and
Within principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (9)
1. a kind of jacking construction device characterized by comprising
Tunnel side portal ring structure, vertical shaft side portal ring structure and the annular seal inner tube of a tyre for having telescopic resilience, the tunnel
On the inner wall of road side portal ring structure and the annular seal is provided on the inner wall of the vertical shaft side portal ring structure
The inner tube of a tyre;
Valve mechanism, the valve are provided with outside the tunnel side portal ring structure and the vertical shaft side portal ring structure
Structure is connected with the corresponding annular seal inner tube of a tyre, for filling default filler into the corresponding annular seal inner tube of a tyre;
The jacking construction device further include:
Has the annular slice cover tire of telescopic resilience, the annular slice cover tire is wrapped in outside the annular seal inner tube of a tyre.
2. the apparatus according to claim 1, which is characterized in that the jacking construction device further include:
First cord rubber ring and adjusting pressing plate;
The vertical shaft side portal ring structure is disposed with described on the end face far from the tunnel side portal ring structure
One cord rubber ring and the adjusting pressing plate, the adjusting pressing plate are arranged on the first cord rubber ring, first curtain
Activity on the inside of cloth rubber ring, outside is fixed;
The adjusting pressing plate can change the adjusting pressing plate and suppress institute along the radial motion of the vertical shaft side portal ring structure
State the area of the active side of the first cord rubber ring.
3. the apparatus of claim 2, which is characterized in that the jacking construction device further include:
Bolt and pressure ring plate are connected,
The first cord rubber ring is socketed on the outer wall of the vertical shaft side portal ring structure, is fixed by the pressure ring plate;
The adjusting pressing plate is provided on the pressing plate ring;
The pressure ring plate and described adjust are provided with for the through-hole for connecting bolt and passing through on pressing plate, wherein the pressure ring
It is provided in the through-hole of plate for connecting bolted screw thread with described, the through-hole adjusted on pressing plate is strip hole, institute
The length direction for stating strip hole is parallel to the radial direction of the vertical shaft side portal ring structure, and be greater than the through-hole of the pressure ring plate
Diameter.
4. the apparatus according to claim 1, which is characterized in that the jacking construction device further include:
The fixed ring flat-plate of portal and rubber waterproof ring flat-plate;
The fixed ring flat-plate of the portal is fixed on Tunnel doorway;
The tunnel side portal ring structure is arranged in far from the vertical shaft side portal ring structure in the rubber waterproof ring flat-plate
On end face, the rubber waterproof ring flat-plate is located between the fixed ring flat-plate of the portal and the tunnel side portal ring structure.
5. device according to claim 4, which is characterized in that
The rubber waterproof ring flat-plate is detachably connected with the fixed ring flat-plate of the portal using bolt.
6. the apparatus according to claim 1, which is characterized in that
The outside of the tunnel side portal ring structure and the vertical shaft side portal ring structure is welded with multiple floors.
7. the apparatus according to claim 1, which is characterized in that the jacking construction device further include:
Second cord rubber ring;
It is arranged between the tunnel side portal ring structure and adjacent two end faces of the vertical shaft side portal ring structure
State the second cord rubber ring.
8. device according to claim 7, which is characterized in that
The tunnel side portal ring structure and adjacent two end faces and described second of the vertical shaft side portal ring structure
The through-hole passed through for bolt is provided on cord rubber ring, the second cord rubber ring is bolted on the tunnel
Between side portal ring structure and adjacent two end faces of the vertical shaft side portal ring structure.
9. the apparatus according to claim 1, which is characterized in that the default filler is mud, water or grease.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610978164.0A CN106522961B (en) | 2016-11-08 | 2016-11-08 | jacking construction device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610978164.0A CN106522961B (en) | 2016-11-08 | 2016-11-08 | jacking construction device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106522961A CN106522961A (en) | 2017-03-22 |
CN106522961B true CN106522961B (en) | 2018-12-28 |
Family
ID=58349651
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610978164.0A Active CN106522961B (en) | 2016-11-08 | 2016-11-08 | jacking construction device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106522961B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109237134A (en) * | 2018-10-19 | 2019-01-18 | 上海宝冶建筑工程有限公司 | A kind of antipriming of jacking construction |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1793611A (en) * | 2005-12-27 | 2006-06-28 | 上海市隧道工程轨道交通设计研究院 | Water-proof method for shield tunnel outlet |
CN102011600A (en) * | 2010-10-28 | 2011-04-13 | 上海建工集团股份有限公司 | Watertight device of heading machine for passing in and out door opening |
CN103266898A (en) * | 2013-04-26 | 2013-08-28 | 中交第二航务工程局有限公司 | Shield tunnel portal sealing device and shield tunnel portal sealing method |
CN104343455A (en) * | 2013-08-05 | 2015-02-11 | 中铁十八局集团第一工程有限公司 | Long-distance curved jacking pipe and pipe roof construction technique |
CN105240019A (en) * | 2015-09-24 | 2016-01-13 | 中国石油天然气集团公司 | Pipe jacking construction method |
-
2016
- 2016-11-08 CN CN201610978164.0A patent/CN106522961B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1793611A (en) * | 2005-12-27 | 2006-06-28 | 上海市隧道工程轨道交通设计研究院 | Water-proof method for shield tunnel outlet |
CN102011600A (en) * | 2010-10-28 | 2011-04-13 | 上海建工集团股份有限公司 | Watertight device of heading machine for passing in and out door opening |
CN103266898A (en) * | 2013-04-26 | 2013-08-28 | 中交第二航务工程局有限公司 | Shield tunnel portal sealing device and shield tunnel portal sealing method |
CN104343455A (en) * | 2013-08-05 | 2015-02-11 | 中铁十八局集团第一工程有限公司 | Long-distance curved jacking pipe and pipe roof construction technique |
CN105240019A (en) * | 2015-09-24 | 2016-01-13 | 中国石油天然气集团公司 | Pipe jacking construction method |
Also Published As
Publication number | Publication date |
---|---|
CN106522961A (en) | 2017-03-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106193044A (en) | A kind of body segmenting slip casting method | |
US3267967A (en) | Pipe repair tool | |
CN113250723A (en) | Monitoring and coupling integrated protection device for rock burst of deep mine | |
CN210410920U (en) | Civil engineering construction waste treatment device | |
CN106522961B (en) | jacking construction device | |
KR101272127B1 (en) | Height adjustable repairing packer for driving at plates with different height and non-excavation repairing method using the same | |
CN104818723A (en) | Anti-sliding pile for slope support | |
CN106764057A (en) | Mutual-inserting type relay well | |
CN107700472B (en) | Hydraulic demoulding rubber water stop joint box for underground continuous wall construction and demoulding method thereof | |
CN102953744A (en) | Hollow grouting yielding anchor rod | |
CN113305141A (en) | High-pressure jet grouting injection in-situ repair system and method | |
KR102088963B1 (en) | Reinforced steel pipe one shot grouting | |
CN104563954A (en) | Steel pipe expansion recovery type external casing packer | |
CN108824453A (en) | Interior pin ratchet self-locking device and the bracing members comprising it | |
DE102011009266A1 (en) | Tubbing ring for lining tunnel, has resilient outbreak edge portion that is provided to allow deformation/expansion of crumble shell in direction of cavity | |
CN204038962U (en) | A kind of automatic compensation type stretch-draw jack | |
CN104563953A (en) | Double-layer steel pipe expansion type pipe external casing packer | |
CN114457795A (en) | Pile foundation reinforcing structure capable of resisting train vibration and construction method | |
CN215419469U (en) | Install convenient cable and wear roof sealing device | |
KR102115509B1 (en) | Reinforced steel pipe one shot grouting | |
CN211371634U (en) | Plug with anti-blocking function for rubber pipeline | |
CN107740905B (en) | Leakage stopping device and method for water pipeline | |
CN103276734A (en) | Removing type anchorage device | |
CN202900297U (en) | Hollow grouting yielding anchor rod | |
CN111502702A (en) | Concrete filling device for roadway steel support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |