CN106522445A - Method and structure for preventing continuous collapse of slab-column structure - Google Patents

Method and structure for preventing continuous collapse of slab-column structure Download PDF

Info

Publication number
CN106522445A
CN106522445A CN201610953230.9A CN201610953230A CN106522445A CN 106522445 A CN106522445 A CN 106522445A CN 201610953230 A CN201610953230 A CN 201610953230A CN 106522445 A CN106522445 A CN 106522445A
Authority
CN
China
Prior art keywords
reinforcing bar
plate
column
slab
diagonal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610953230.9A
Other languages
Chinese (zh)
Inventor
刘永军
张思敏
吴敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Jianzhu University
Original Assignee
Shenyang Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Jianzhu University filed Critical Shenyang Jianzhu University
Priority to CN201610953230.9A priority Critical patent/CN106522445A/en
Publication of CN106522445A publication Critical patent/CN106522445A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/43Floor structures of extraordinary design; Features relating to the elastic stability; Floor structures specially designed for resting on columns only, e.g. mushroom floors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The invention discloses a method and a structure for preventing continuous collapse of a slab-column structure. The method includes: providing a standby load transmission path; locally damaging a surrounding structure having enough redundancy to support new path transmission load. The structure is characterized in that diagonal column-penetrating rebars are arranged at slightly-upward positions of neutral axis of a slab, and each two adjacent column-penetrating rebars in the slab are connected into a whole at a slab-column joint. The method and the structure have the advantages that by adopting technology of adding the diagonal column-penetrating rebars into columns in the slab-column structure, the objective of preventing transverse or longitudinal continuous collapse of the slab-column structure after a punching shear failure is achieved.

Description

A kind of method and structure of anti-plate-column structure continuous collapse
Technical field
The present invention relates to the technology for penetrating destruction and continuous collapse of plate-column structure node is prevented, it is more particularly to a kind of diagonal Prick post steel bar stress.
Background technology
Reinforced Concrete Slab Column structure typically refers to the structure being made up of floor and pillar, with common frame structure not Together, it is that underfloor does not have beam the characteristics of plate-column structure, has the advantages that structural system is simple, Path of Force Transfer is succinct, therefore, space Low with interfloor height, speed of application is fast, the advantages of be easy to separate room, it is adaptable to underground garage, multi-storied garage, multilamellar factory Room, public building.In recent years, with the development of technology, occur in that Slab Column-shear Wall Structures, sheet-pile-core wall structure etc. are new Mixing plate-column structure, is widely used in the building such as high-rise residential, garage.
As the design thickness of plate is limited, and floor does not have the support of beam, there was only the connection of plate and post, cause at Column border node At slab-column connections, internal force is big, and stress is complicated, becomes the weak link of structure.On July 8th, 2010, Ontario, Canada One double-deck garage, a small crane are strayed into parking lot, cause one of slab-column connections to penetrate destruction, and then cause remaining Five nodes penetrate destruction, form continuous collapse.On November 17th, 2014, one underground garage of Jinan City, Shandong Province Changqing District is on ground During the backfill of lower room, as backfill piles up excessive, the bearing capacity of garage top floor is exceeded, result in pillar and send out Life penetrates destruction, eventually forms large area continuous collapse.
The content of the invention
In plate-column structure, all than larger, on plate, load will finally pass to pillar to the span of plate, therefore, at slab-column connections Internal force is very big, and stress is complicated, is the weak link in plate-column structure.Before there is punching failure in node, pillar and floor Between active force be mainly moment of flexure and shearing, node occur punching failure after, can there is of short duration transition stage, through destruction The reinforcing bar of the conical surface can produce certain dowel action, and with the draw stage of reinforcing bar, the active force between pillar and floor is main It is the pulling force of reinforcing bar, on stigma, node has " bearing capacity is participated in after punching failure " for floor meeting " suspension ".If reinforcing bar because Lack of support and break or extract from reinforcing bar, when pillar thoroughly loses the supporting role to floor, pillar can pass through building Plate and make floor slump downwards under gravity.After slab-column connections penetrate destruction, at adjacent node, internal force can be obvious Increase, and then punching failure may occur and destruction is penetrated, so as to cause, plate-column structure is laterally consecutive to collapse.For multilamellar sheet-pile , there is the laterally consecutive floor for collapsing and can slump on next layer of floor, cause the intermediate node of lower floor's floor and pillar in structure Place's internal force increase, and then be longitudinally continuous and collapse.In order to prevent the laterally or longitudinally continuous of plate-column structure to destroy, the present invention is specially Profit provides a kind of structure of anti-plate-column structure continuous collapse, it is therefore an objective to even if after pillar and plate penetrate destruction, matched somebody with somebody steel Muscle can also sustain the plate being pierced, it is impossible to the laterally consecutive ductility collapsed, improve total occurs immediately, is taken precautions against natural calamities with reaching Purpose.
Before diagonal prick post reinforcing bar is not set up, a pillar passes through the stress prick post reinforcing bar of top and bottom by plate Four pillars around load transmission, it is assumed that therewith just to four share power for N1, the power that other diagonal pillars are shared is N2, then the relation between N1, N2 beContrast plate-column structure do not set up diagonal prick post reinforcing bar before, just to four Root pillar institute power should beIn this case, pillar is reducedThen pillar bearing load reduces percentage Rate is
The technical proposal for solving the technical problem of the invention is:Prevent the structure that plate-column structure occurs continuous collapse from setting In respect of 2 main points, the first provides standby load bang path for structure first;Which two is that local failure surrounding structure has foot Enough degree more than needed support new route transmission load.Three technical schemes are proposed according to the two main points:It is right that the first increases in plate Angle prick post reinforcing bar, contrast are original, and when pillar occurs punching failure with plate, the load on plate can pass to week by diagonal reinforcing bar More pillars are enclosed, is no longer only four of surrounding, even if this model is pierced laterally collapse.Second Plant is then that other steel bar stresses in oblique reinforcing bar and plate are waled (or welding) with reinforcing bar near pillar to form annular steel Muscle cage.Reinforced binding around pillar is exactly lived by this steel hoop purpose, and after being conducive to pillar take-through plate, on plate, load is more Uniform and stable passes to pillar around;The third then allows for the plate finite thickness of plate-column structure itself, if increasing right again Angle steel muscle, certainly will occur the intensive phenomenon of reinforcing bar at bearing, be to solve this technical problem, be not passed through can oblique reinforcing bar Pillar, welds to form continuous bar-mat reinforcement using above-mentioned steel hoop therewith, and being reached with this prevents plate-column structure from continuously breaking Bad problem.(figure may be referred to accompanying drawing) wherein, in plate and pillar junction, diagonal prick post reinforcing bar can be matched somebody with somebody using formula is bent up Muscle method, had so both improve the utilization rate of reinforcing bar, can also prevent the punching failure of plate-column structure.
The invention has the beneficial effects as follows:By the technology for increasing oblique prick post reinforcing bar to plate-column structure center pillar, prevention is reached Plate-column structure continues to occur laterally after there is punching failure or is longitudinally continuous the purpose collapsed, and makes the fire-resistance of structure, antidetonation etc. Disaster Defense Capability is significantly improved, and this kind of method economically feasible, technology are simple, it is easy to grasp, and is easy to construction, can be widely used for ground The plate-column structures such as Underground Garage are taken precautions against natural calamities in consolidation process.It is effectively improved domestic and international plate-column structure opposing continuous collapse damage capability not enough Present situation, plate-column structure and its safe condition of mixed structure is mutually coordinated with the urban economy with stable development.
Description of the drawings:
Accompanying drawing 1 is:Diagonal one profile of prick post reinforcing bar scheme;
Accompanying drawing 2 is;Diagonal two profile of prick post reinforcing bar scheme;
Accompanying drawing 3 is;Diagonal three profile of prick post reinforcing bar scheme;
Accompanying drawing 4 is;Diagonal prick post reinforcing bar sectional detail drawing at the bearing;
In figure, 1 is diagonal prick post reinforcing bar, and 2 is distribution bar, and 3 is steel hoop cage, and 4 is post, and 5 is floor.
Specific embodiment:
1. in plate, distribution bar is see the table below in addition to indicating:
2. plate span centre length is placed on short reinforcing bar to reinforcing bar;Bearing director is placed under the negative muscle of short to negative muscle.Floor Enough Zhi Tie, cushion block should be set before pouring, to guarantee the accurate of reinforcement location in plate.
3. the bar-mat reinforcement colligation of plate is identical with basis, and two-way slab reinforcing bar cross point completely should be tied up.It should be noted that the negative steel on plate top Muscle (face reinforcement) will prevent from being operated
4., when the arrangement of double-deck or multilamellar occurs in Reinforcement, the short steel with diameter 15mm should be padded between two placing of reinforcements When muscle, such as longitudinal reinforcement are with diameter greater than 25mm, bar dowel diameter specifications and longitudinal reinforcement same size.
5. note to arrange that (plate neutral axis is managed in plate neutral axis deflection during the oblique prick post reinforcement construction that the present invention is mentioned By above not stressing, if steel bar arrangement is on neutral axis, Essential Action is not had).
6. the steel hoop arrangement and method for construction that the present invention is mentioned is as follows:
(1) first, adjacent diagonal prick post reinforcing bar is held together with φ 12HRB335 reinforcing bars, forms discontinuous circumferential band Muscle;
(2) again the adjacent reinforcing bar for having tied up is held together with the reinforcing bar of same size, forms continuous ring-shaped stirrup;
(3) diagonal prick post reinforcing bar can make bent-up bar, 45 degree of transfer angle at bearing.

Claims (4)

1. a kind of method of anti-plate-column structure continuous collapse, it is characterised in that:Standby load bang path is provided for structure;Office Portion's destruction surrounding structure has have more than needed enough degree to support new route transmission load.
2. a kind of structure for realizing claim 1 methods described, is characterized in that:Floor neutral axis deflection it is upper install it is right Angle prick post reinforcing bar, in sheet-pile junction, prick post bar connecting adjacent in floor is integral.
3. structure according to claim 2, is characterized in that:In diagonal prick post reinforcing bar and plate, other steel bar stresses form ring Shape steel reinforcement cage.
4. structure according to claim 3, is characterized in that:Diagonal prick post reinforcing bar is not passed through pillar, using described annular Reinforcing bar welds to form continuous bar-mat reinforcement therewith, and in plate and pillar junction, diagonal prick post reinforcing bar can be utilized and bend up formula arrangement of reinforcement Method, 45 degree of transfer angle.
CN201610953230.9A 2016-10-27 2016-10-27 Method and structure for preventing continuous collapse of slab-column structure Pending CN106522445A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610953230.9A CN106522445A (en) 2016-10-27 2016-10-27 Method and structure for preventing continuous collapse of slab-column structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610953230.9A CN106522445A (en) 2016-10-27 2016-10-27 Method and structure for preventing continuous collapse of slab-column structure

Publications (1)

Publication Number Publication Date
CN106522445A true CN106522445A (en) 2017-03-22

Family

ID=58325677

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610953230.9A Pending CN106522445A (en) 2016-10-27 2016-10-27 Method and structure for preventing continuous collapse of slab-column structure

Country Status (1)

Country Link
CN (1) CN106522445A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6385930B1 (en) * 1999-07-16 2002-05-14 Carl-Erik Broms Concrete structure and method of making it
CN2858823Y (en) * 2006-01-05 2007-01-17 官锦禄 Building shockproof structure improvement
RU2382154C1 (en) * 2008-10-16 2010-02-20 Государственное образовательное учреждение высшего профессионального образования "Российский университет дружбы народов" (РУДН) Girderless ceiling
CN203230191U (en) * 2013-04-12 2013-10-09 清华大学 Reinforced structure for resisting progressive collapse of existing concrete structure
CN105926764A (en) * 2016-06-13 2016-09-07 姚攀峰 Industrialized pre-processed regenerative structural system and method for constructing same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6385930B1 (en) * 1999-07-16 2002-05-14 Carl-Erik Broms Concrete structure and method of making it
CN2858823Y (en) * 2006-01-05 2007-01-17 官锦禄 Building shockproof structure improvement
RU2382154C1 (en) * 2008-10-16 2010-02-20 Государственное образовательное учреждение высшего профессионального образования "Российский университет дружбы народов" (РУДН) Girderless ceiling
CN203230191U (en) * 2013-04-12 2013-10-09 清华大学 Reinforced structure for resisting progressive collapse of existing concrete structure
CN105926764A (en) * 2016-06-13 2016-09-07 姚攀峰 Industrialized pre-processed regenerative structural system and method for constructing same

Similar Documents

Publication Publication Date Title
CN107060067B (en) Superimposed precast reinforced concrete structure system and construction method thereof
CN202831402U (en) Concrete filled steel tubular column with inner-connected circular pipe and outer-sleeved concrete filled steel tube
CN101457548A (en) Node for connecting round steel tube concrete column with reinforced concrete floor and method for making same
CN102704598A (en) Composite shear wall with concrete-filled steel tube frames and double steel plates with concealed bracings and construction method thereof
CN103437458A (en) Precast concrete double-plate shear wall with built-in oblique supports and construction method thereof
CN102071747A (en) Joint of square steel tube concrete column and reinforced concrete floor and production method thereof
CN113216409A (en) Connecting structure of precast concrete tubular pile column with diagonal bracing and hollow floor or flat floor
CN107190635A (en) Concrete-filled steel tube with dumbbell sections assembled pier and the connection structure and method with cushion cap
CN105369892B (en) A kind of steel tube concrete superposed frame structure system
CN201406767Y (en) Node for connecting circular concrete-filled tubular column and reinforced concrete floor
CN103485443A (en) Window-shaped-steel-plate concrete shear wall and manufacturing method thereof
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN207017483U (en) The full precast shear wall structural system of regenerative steel skeleton
CN108086535A (en) A kind of assembled square steel tube steel plate concrete combined shear wall
CN105752864B (en) Derrick crane adheres to node and its construction method
CN207176718U (en) A kind of assembled heel join node
CN207377233U (en) A kind of triple Aseismic Structure Systems of preprocessing
CN203640061U (en) Node connecting structure of reinforced concrete column of basement
CN206503378U (en) Newly-increased outrigger constructing structure
CN210597882U (en) Lattice type steel reinforced concrete combined column beam column node
CN214994078U (en) Large-diameter pile column structure for reverse construction method engineering
CN116084587A (en) Steel wire mesh shear wall and construction method thereof
CN107354998B (en) Foundation-free joint and construction method thereof
CN106522445A (en) Method and structure for preventing continuous collapse of slab-column structure
CN206157974U (en) Prevent plate -column structure progressive collapse's structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170322