CN106522361A - Combined installation method for multi-layer heavy steel space corridor - Google Patents

Combined installation method for multi-layer heavy steel space corridor Download PDF

Info

Publication number
CN106522361A
CN106522361A CN201611120657.7A CN201611120657A CN106522361A CN 106522361 A CN106522361 A CN 106522361A CN 201611120657 A CN201611120657 A CN 201611120657A CN 106522361 A CN106522361 A CN 106522361A
Authority
CN
China
Prior art keywords
vestibule
corridor
fabric
installation method
combined installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611120657.7A
Other languages
Chinese (zh)
Inventor
陈晓明
夏凉风
李福荣
张宇
郑祥杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201611120657.7A priority Critical patent/CN106522361A/en
Publication of CN106522361A publication Critical patent/CN106522361A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0046Loggias

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a combined installation method for a multi-layer heavy steel space corridor. The combined installation method for the multi-layer heavy steel space corridor comprises the steps that firstly, a corridor bottom layer structure is assembled on the ground or on the top surface of a structure below the corridor through a crane; secondly, the corridor bottom layer structure is lifted in place through an integral lifting system and fixed to tower buildings around; and thirdly, high-altitude in-site installation of an upper structure of the corridor is conducted through equipment such as a tower crane. Compared with a traditional technique, the combined installation method has the advantages that construction technological requirements for the existing steel space corridor can be met, the construction progress can be greatly accelerated, high-altitude work safety risks in the construction process are reduced, and the structural deformation control difficulty in the construction process is lowered.

Description

The combined installation method of the heavy aerial steel vestibule of multilayer
Technical field
The invention belongs to executive information systems technical field of construction, is related generally to one kind and is carried using the aerial vestibule of multilayer Rise the combined installation method of the heavy aerial steel vestibule of multilayer for increasing empty original position installation Technology.
Background technology
With the needs of current building function, the steel vestibule between connected buildings is to large span, large-tonnage, many number of plies directions Development, such steel vestibule generally may be partitioned into upper and lower two parts composition.Its special structure has in work progress The features such as high-altitude installation difficulty is big, installation accuracy has high demands, malformation control is difficult, security isolation has high demands.Traditional construction Though technique can meet the construction requirement of this kind of structure, its construction progress, precision, security protection a series of problems, such as be difficult to Preferably ensured.Aerial steel vestibule heavy for this multilayer at present has following two installation methods:
First, high-altitude original position Method for Installation:Install from high building side toward vestibule central authorities high-altitude is in situ.This installation method exist with Lower shortcoming:
1st, gallery structure Deformation control difficulty in work progress is big;
2nd, job safety hidden danger of soaring aloft is big;
3rd, installation rate is slow, and installation accuracy is poor.
2nd, Integral Lifting:Vestibule after the completion of assembly, is integrally lifted in place using hoisting mechanism on the ground.This peace Dress method is suffered from the drawback that:
1st, ground structural-load-carrying capacity is had high demands;
2nd, lift mechanism lifts ability is had high demands;
3rd, in lifting process, gallery structure front face area is big, and wind-resistance measures have high demands.
The content of the invention
The purpose of the present invention is:For the defect existing for traditional construction technology, propose that one kind is connected in the air using multilayer Corridor is lifted increases empty original position installation Technology, and its method can meet the construction technology of current this multilayer heavy-duty steel vestibule will Ask, can also greatly improve construction speed, reduce work progress high-altitude working safety risk and reduce the structure in work progress Deformation control difficulty.
The technical scheme is that:First with crane in ground or vestibule rectangular structure top surface assembly vestibule bottom Structure;Recycle Integral lifting system to lift in place assembled good vestibule fabric, and fix with periphery high building;It is subsequently sharp High-altitude installation in situ is carried out with crane to vestibule superstructure.
This combined installation method of the present invention, on the basis of above-mentioned technical proposal, also including following preferred version:
The method specifically includes following steps:
A, platform is set up in the lower section in vestibule designed elevation plane projection face above ground or vestibule substructure;
B, assembly is carried out to vestibule fabric above the platform set up;
C, while vestibule fabric is assembled, on the outside of high building, Integral lifting system is set, will be upper by this system State vestibule fabric to be lifted in place;
D, vestibule fabric and periphery high building are connected, height is carried out to vestibule superstructure using derrick crane Empty installation in situ.
Advantages of the present invention is:Compared to traditional handicraft, this method can not only meet the construction of current this aerial steel vestibule Technological requirement, while can also greatly improve construction speed, reduces the high-altitude working safety risk in work progress and reduction is applied Malformation control difficulty during work.
Description of the drawings
The invention will be described further with specific embodiment below in conjunction with the accompanying drawings:
Fig. 1 to Fig. 8 is installation procedure demonstration graph in the embodiment of the present invention, and the arrow in wherein Fig. 2 is represented to vestibule bottom The direction of improvement of truss.
Specific embodiment
Fig. 1 to Fig. 8 shows that of the combined installation method of the heavy aerial steel vestibule of this multilayer of the invention is concrete real Example is applied, which mainly includes the following steps that:
Step a, as shown in figure 1, vestibule designed elevation plane projection face lower section on ground or vestibule substructure Side sets up platform, and above the platform set up carries out assembly to vestibule fabric.
Step b, as shown in Figure 1, Figure 2 and Figure 3, while vestibule fabric is assembled, arranges overall on the outside of high building Above-mentioned vestibule fabric is lifted in place by lift system by this system.
Step c, as shown in figure 4, vestibule fabric and periphery high building are connected.
Step d, as shown in Fig. 5, Fig. 6, Fig. 7 and Fig. 8, vestibule superstructure is entered using the derrick crane above high building Row high-altitude is in situ to install.
In the present embodiment, above-mentioned Integral lifting system includes lifting means with steel strand wires are lifted etc..
Certainly, above-described embodiment technology design only to illustrate the invention and feature, its object is to make people much of that Solution present disclosure is simultaneously implemented according to this, can not be limited the scope of the invention with this.It is all according to major technique of the present invention Equivalent transformation or modification that the Spirit Essence of scheme is done, should all be included within the scope of the present invention.

Claims (2)

1. the combined installation method of the heavy aerial steel vestibule of a kind of multilayer, it is characterised in that first with crane on ground or Vestibule rectangular structure top surface assembly vestibule fabric;Integral lifting system is recycled to lift assembled good vestibule fabric In place, and with periphery high building fix;High-altitude installation in situ is carried out to vestibule superstructure followed by crane.
2. the combined installation method of the heavy aerial steel vestibule of multilayer according to claim 1, it is characterised in that the method has Body is comprised the following steps:
A, platform is set up in the lower section in vestibule designed elevation plane projection face above ground or vestibule substructure;
B, assembly is carried out to vestibule fabric above the platform set up;
C, while vestibule fabric is assembled, Integral lifting system is set on the outside of high building, by this system by above-mentioned company Corridor fabric is lifted in place;
D, vestibule fabric and periphery high building are connected, high-altitude are carried out to vestibule superstructure using derrick crane former Install position.
CN201611120657.7A 2016-12-07 2016-12-07 Combined installation method for multi-layer heavy steel space corridor Pending CN106522361A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611120657.7A CN106522361A (en) 2016-12-07 2016-12-07 Combined installation method for multi-layer heavy steel space corridor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611120657.7A CN106522361A (en) 2016-12-07 2016-12-07 Combined installation method for multi-layer heavy steel space corridor

Publications (1)

Publication Number Publication Date
CN106522361A true CN106522361A (en) 2017-03-22

Family

ID=58342678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611120657.7A Pending CN106522361A (en) 2016-12-07 2016-12-07 Combined installation method for multi-layer heavy steel space corridor

Country Status (1)

Country Link
CN (1) CN106522361A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060105A (en) * 2017-05-10 2017-08-18 中国建筑第二工程局有限公司 A kind of lifting construction method of multiple steel vestibules between high building
CN113494127A (en) * 2021-07-09 2021-10-12 上海宝冶集团有限公司 Construction method for layered lifting of large-span open-web corridor steel platform

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046758A (en) * 2013-01-18 2013-04-17 上海建工一建集团有限公司 Method for constructing multichannel interval load-carrying mega truss door structure
CN103075025A (en) * 2013-01-30 2013-05-01 中国十九冶集团有限公司 Wholly lifting construction method for asymmetric structure of huge overhang steel of high-rise building
CN103912128A (en) * 2014-02-28 2014-07-09 中国建筑第五工程局有限公司广州分公司 Construction method of high-altitude one-piece steel truss
CN105781124A (en) * 2014-12-15 2016-07-20 五冶集团上海有限公司 Method for installing corridor with ultra-high double-tower steel structure
CN106065661A (en) * 2016-06-13 2016-11-02 中建六局第三建筑工程有限公司 Large span unsettled steel corridor construction engineering method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046758A (en) * 2013-01-18 2013-04-17 上海建工一建集团有限公司 Method for constructing multichannel interval load-carrying mega truss door structure
CN103075025A (en) * 2013-01-30 2013-05-01 中国十九冶集团有限公司 Wholly lifting construction method for asymmetric structure of huge overhang steel of high-rise building
CN103912128A (en) * 2014-02-28 2014-07-09 中国建筑第五工程局有限公司广州分公司 Construction method of high-altitude one-piece steel truss
CN105781124A (en) * 2014-12-15 2016-07-20 五冶集团上海有限公司 Method for installing corridor with ultra-high double-tower steel structure
CN106065661A (en) * 2016-06-13 2016-11-02 中建六局第三建筑工程有限公司 Large span unsettled steel corridor construction engineering method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060105A (en) * 2017-05-10 2017-08-18 中国建筑第二工程局有限公司 A kind of lifting construction method of multiple steel vestibules between high building
CN107060105B (en) * 2017-05-10 2018-11-13 中国建筑第二工程局有限公司 A kind of lifting construction method of multiple steel vestibules between high building
CN113494127A (en) * 2021-07-09 2021-10-12 上海宝冶集团有限公司 Construction method for layered lifting of large-span open-web corridor steel platform

Similar Documents

Publication Publication Date Title
CN106759845B (en) A kind of construction method of Steel corridor
CN105781124B (en) A kind of Super High two tall buildings Steel corridor installation method
KR101923924B1 (en) Rope type elevator of high speed and heavy road and mast structure for constructing high-rise building
CN103979383A (en) Multi-layer lifting platform for building construction
CN109098454B (en) Hydraulic lifting construction method for high-altitude large-span curved roof
CN201825671U (en) Hoisting trolley for track plate
CN103243930A (en) System and method for modularized construction of super high-rise steel structures
CN107974944A (en) A kind of Y types road-cum-rail bridge floorings hanging apparatus and hanging method
CN102121273A (en) Hydraulic lifting inversion method for reinforced concrete chimney steel inner cylinder
CN103899093A (en) Step-by-step hoisting construction method of mega-frame steel truss beam
CN106522361A (en) Combined installation method for multi-layer heavy steel space corridor
CN205348727U (en) A promote formula operation platform for in shaft
CN107762159A (en) Large-span steel truss high-altitude sliding in place method
CN107190990A (en) Factory building steel column installation method under a kind of confined space
CN106544959A (en) The construction method of the lifting sections of the king-tower containing saddle and bridge main tower saddle
CN106013453A (en) Construction method for large-span overhung ultra-limit structure
CN103086276A (en) Construction method for hoisting bridge type crane in high-rise well tower type building
CN104775363A (en) Assembling method of upper tower column reinforcing steel bar segment
CN109339399B (en) Sectional construction method of steel structure in elevator hoistway
CN205369875U (en) A operation protection platform collet for in shaft
CN106968371B (en) A kind of construction method of the high wing articulated structure drifted by wind of curtain wall construction
CN103669867B (en) Building body and outer decoration construction discrepancy in elevation adjustable double-layer operating platform and installation method
CN105298500B (en) The method of headframe is changed to by steel headframe suitable for underground mining lifting system
CN205348729U (en) A instrument formula operation protection platform for in shaft
CN205348728U (en) A promote formula operation platform bearing structure for in shaft

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170322