Prior art keywords
equipment
data
next step
state
judged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610951795.3A
Other languages
Chinese (zh)
Inventor
王扬
章斌
王伟
李妍
董阳
孙轶凡
蒋喆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610951795.3A priority Critical patent/CN106503812A/en
Publication of CN106503812A publication Critical patent/CN106503812A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of composition of infrastructure device management operational system and operational approach.Which includes setting up data base on infrastructure device condition line:Whole infrastructure devices are divided into:Stock is standby, do not put into operation, in fortune, retired, live continue to employ, wait to scrap and scrap totally seven kinds of states;A data base is set up to the equipment of each state respectively;Operation management:During actual daily O&M, operation is updated according to data on line of the practical situation that patrols and examines under line in respective data base respectively to this seven kinds of status devices, consistent to ensure the offline upper data of line.Effect of the present invention:Can effectively reduce and patrol and examine workload, it is convenient that real time information is obtained, and job note is transmitted without the need for operation maintenance personnel, issue handling is made to get up to maintain continuity, the probability of Data duplication typing is reduced, the O&M efficiency of equipment control maintenance is substantially increased, it is ensured that the concordance of on-line off-line data.

Description

A kind of composition of infrastructure device management operational system and operational approach
Technical field
The invention belongs to device management techniques field, more particularly to a kind of composition of infrastructure device management operational system and Operational approach.
Background technology
There are problems that during the equipment daily management O&M of power system a lot, such as 1) due to traditional tour Or maintenance place is away from IT operational systems, so as to lead to not the latest Status for timely and accurately obtaining equipment, therefore to pipe The personnel requirement of the actual inspection device of reason is very high;Some systems need to patrol and examine repeatedly daily, difficult due to obtaining information in real time, because This causes to patrol and examine workload huge.2) lack smooth work order closed-loop process, therefore how to ensure that patrol officer's work order (makes an inspection tour work Single, maintenance work order) continuity for operating, the repetition typing for reducing data and manual errors, to complete the close loop maneuver of work order, Ensure the integrity of operation, it has also become the problem for directly affecting maintenance work efficiency for urgently processing.Work on hand pattern is logical Cross, record on paper, the mode that submits on line, so as to shelve the continuity of issue handling, Data duplication typing is asked Topic is serious, greatly reduces O&M efficiency.3) the offline upper Data Consistency of line, discovering device account information when patrolling and examining under line (such as equipment is stored in the positional information change of rack) is inconsistent with data on line, and existing way is by a series of multiple on line Miscellaneous operation is updated, it is desirable to provide easily update mode under line, ensures the concordance of the offline upper data of line.In the face of such as Such problem, is badly in need of the method for management equipment on a set of line.
Content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of infrastructure device management operational system composition and Operational approach.
In order to achieve the above object, the composition and operational approach of the infrastructure device management operational system that the present invention is provided includes The following steps for carrying out in order:
Step 1) set up data base on infrastructure device condition line:Whole infrastructure devices are divided into:Stock is standby, do not put into operation, In fortune, retired, live continue to employ, wait to scrap and scrap totally seven kinds of states;Then one is set up to the equipment of each state respectively Data base;And labelling has been carried out to the marker bit of all devices all in accordance with use state;
Step 2) operation management:During actual daily O&M, according to the practical situation that patrols and examines under line respective Operation is updated to data on the line of this seven kinds of status devices respectively in data base, consistent to ensure the offline upper data of line.
In step 2) in, described stock's stand-by equipment state updates operation for successively in the every of stock's resting state The operation that one equipment is carried out successively, which comprises the following steps:
Step 1.1) judge whether this equipment is received?If it is judged that be "Yes", then stock's stand-by equipment data -1, Do not put into operation device data+1, and 1.4) next step goes to step, and is otherwise directly entered next step;
Step 1.2) judge whether this equipment puts into operation?If it is judged that be "Yes", then stock's stand-by equipment data -1, 1.4) fortune device data+1, next step go to step, and are otherwise directly entered next step;
Step 1.3) judge whether this equipment is scrapped?If it is judged that be "Yes", then stock's stand-by equipment data -1, treat 1.4) write-off equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 1.4) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is received is:The device flag position that has received is 0;
Wherein:The decision method whether described equipment puts into operation is:The device flag position that has put into operation is 1;
Wherein:The decision method whether described equipment is scrapped is:Equipment and scene in original stock continues to employ equipment warp Technical appraisement is crossed, if time limit equipment life arrives, sequence to be scrapped is entered, that is, is defined as scrapping, written-off equipment mark Note position is 2.
In step 2) in, the described equipment state that do not put into operation updates operation for successively to setting in each of state that do not put into operation The standby operation for carrying out successively, which comprises the following steps:
Step 2.1) judge whether this equipment puts into operation?If it is judged that be "Yes", then the device data -1 that do not put into operation, fortune 2.3) device data+1, next step go to step, and are otherwise directly entered next step;
Step 2.2) judge whether this equipment is given back?If it is judged that being "Yes", then do not put into operation device data -1, stock 2.3) stand-by equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 2.3) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is given back is:Returned device flag position is 3.
In step 2) in, described is that each equipment for being in fortune state is entered successively in fortune equipment state renewal operation Capable operation, which comprises the following steps:
Step 3.1) judge whether this equipment is retired?If it is judged that be "Yes", then in fortune device data -1, retired set 3.2) standby data+1, next step go to step, and are otherwise directly entered next step;
Step 3.2) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The whether retired decision method of described equipment is:Retired device flag position is 4.
In step 2) in, it is that each equipment in retired state is carried out successively that described retired state updates operation Operation, which comprises the following steps:
Step 4.1) judge whether this equipment is scrapped?If it is judged that be "Yes", then retired device data -1, wait to scrap 4.3) device data+1, next step go to step, and are otherwise directly entered next step;
Step 4.2) judge whether this equipment is given back?If it is judged that being "Yes", then retired device data -1, stock are standby With data+1,4.3) next step goes to step, and otherwise, data+1 are continued to employ at retired device data -1, scene, subsequently into next step;
Step 4.3) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is scrapped is:Written-off device flag position is 2.
In step 2) in, it is to set to continuing to employ each of state in scene that described scene continue to employ equipment state to update operation The standby operation for carrying out successively, which comprises the following steps:
Step 5.1) judge whether this equipment puts into operation?If it is judged that be "Yes", then scene continue to employ device data -1, 5.4) fortune device data+1, next step go to step, and are otherwise directly entered next step;
Step 5.2) judge whether this equipment is given back?If it is judged that being "Yes", then device data -1, storehouse are continued to employ in scene Stand-by equipment data+1 are deposited, 5.4) next step goes to step, and is otherwise directly entered next step;
Step 5.3) judge whether this equipment is scrapped?If it is judged that being "Yes", then scene is continued to employ device data -1, is treated 5.4) write-off equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 5.4) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is scrapped is:Written-off device flag position is 2.
In step 2) in, described treats that write-off equipment state updates operation for successively to setting in each of state to be scrapped The standby operation for carrying out successively, which comprises the following steps:
Step 6.1) judge whether this equipment completes asset of equipments and scrap?If it is judged that being "Yes", then wait to scrap to set 6.2) standby data -1, write-off equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 6.2) return, this renewal of the equipment terminates, and returns and continues to be updated operation to next equipment, until completing this State armamentarium updates.
Wherein:Whether described equipment completes asset of equipments rejection judgment method:The equipment of sequence to be scrapped is through money Product had both been can be determined that after scrapping program to be scrapped for completing asset of equipments.
The composition and operational approach effect of the infrastructure device management operational system that the present invention is provided:Can effectively reduce and patrol and examine Workload, it is convenient that real time information is obtained, and transmits job note without the need for operation maintenance personnel, makes issue handling get up to maintain continuity, subtract Lack the probability of Data duplication typing, substantially increase the O&M efficiency of equipment control maintenance, it is ensured that on-line off-line data Concordance.
Description of the drawings
Based on Fig. 1, equipment control operational system constitutes schematic diagram;
Fig. 2 is that stock's resting state updates flow chart;
Fig. 3 updates flow chart for the state that do not put into operation;
Fig. 4 is to transport retired state renewal flow chart;
Fig. 5 is that retired state updates flow chart;
Fig. 6 continues to employ state for scene and updates flow chart;
Fig. 7 is that state to be scrapped updates flow chart.
Specific embodiment
The composition of the infrastructure device management operational system for the present invention being provided with specific embodiment below in conjunction with the accompanying drawings and behaviour It is described in detail as method.
It is following that the composition and operational approach of the infrastructure device management operational system that the present invention is provided includes carrying out in order Step:
Step 1) set up data base on infrastructure device condition line:Infrastructure device management operational system structure according to Fig. 1 Whole infrastructure devices are divided into into schematic diagram:Stock is standby, do not put into operation, in fortune, retired, live continue to employ, wait to scrap and scrap altogether Seven kinds of states;Then a data base is set up to the equipment of each state respectively;And set to all in accordance with use state Standby marker bit has carried out labelling;
Step 2) operation management:During actual daily O&M, according to the practical situation that patrols and examines under line respective Operation is updated to data on the line of this seven kinds of status devices respectively in data base, consistent to ensure the offline upper data of line;Institute The renewal operation that states includes:Stock's stand-by equipment state updates the operation 1, equipment state that do not put into operation and updates operation 2, sets in fortune state 4, scene is operated to continue to employ equipment state renewal operation 5 and treat write-off equipment state more for operation 3, retired equipment state renewal is updated New operation 6;
As shown in Fig. 2 in step 2) in, described stock's stand-by equipment state updates operation 1 for successively to being in stock The operation that each equipment of resting state is carried out successively, which comprises the following steps:
Step 1.1) judge whether this equipment is received?If it is judged that be "Yes", then stock's stand-by equipment data -1, Do not put into operation device data+1, and 1.4) next step goes to step, and is otherwise directly entered next step;
Step 1.2) judge whether this equipment puts into operation?If it is judged that be "Yes", then stock's stand-by equipment data -1, 1.4) fortune device data+1, next step go to step, and are otherwise directly entered next step;
Step 1.3) judge whether this equipment is scrapped?If it is judged that be "Yes", then stock's stand-by equipment data -1, treat 1.4) write-off equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 1.4) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is received is:The device flag position that has received is 0;
Wherein:The decision method whether described equipment puts into operation is:The device flag position that has put into operation is 1;
Wherein:The decision method whether described equipment is scrapped is:Equipment and scene in original stock continues to employ equipment warp Technical appraisement is crossed, if time limit equipment life arrives, sequence to be scrapped is entered, that is, is defined as scrapping, written-off equipment mark Note position is 2.
As shown in figure 3, in step 2) in, the described equipment state that do not put into operation updates operation 2 for successively in not putting into operation The operation that each equipment of state is carried out successively, which comprises the following steps:
Step 2.1) judge whether this equipment puts into operation?If it is judged that be "Yes", then the device data -1 that do not put into operation, fortune 2.3) device data+1, next step go to step, and are otherwise directly entered next step;
Step 2.2) judge whether this equipment is given back?If it is judged that being "Yes", then do not put into operation device data -1, stock 2.3) stand-by equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 2.3) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is given back is:Returned device flag position is 3.
As shown in figure 4, in step 2) in, described is to being in the every of fortune state in fortune equipment state renewal operation 3 The operation that one equipment is carried out successively, which comprises the following steps:
Step 3.1) judge whether this equipment is retired?If it is judged that be "Yes", then in fortune device data -1, retired set 3.2) standby data+1, next step go to step, and are otherwise directly entered next step;
Step 3.2) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The whether retired decision method of described equipment is:Retired device flag position is 4.
As shown in figure 5, in step 2) in, it is to setting in each of retired state that described retired state updates operation 4 The standby operation for carrying out successively, which comprises the following steps:
Step 4.1) judge whether this equipment is scrapped?If it is judged that be "Yes", then retired device data -1, wait to scrap 4.3) device data+1, next step go to step, and are otherwise directly entered next step;
Step 4.2) judge whether this equipment is given back?If it is judged that being "Yes", then retired device data -1, stock are standby With data+1,4.3) next step goes to step, and otherwise, data+1 are continued to employ at retired device data -1, scene, subsequently into next step;
Step 4.3) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is scrapped is:Written-off device flag position is 2.
As shown in fig. 6, in step 2) in, it is to continuing to employ in scene that described scene continue to employ equipment state to update operation 5 The operation that each equipment of state is carried out successively, which comprises the following steps:
Step 5.1) judge whether this equipment puts into operation?If it is judged that be "Yes", then scene continue to employ device data -1, 5.4) fortune device data+1, next step go to step, and are otherwise directly entered next step;
Step 5.2) judge whether this equipment is given back?If it is judged that being "Yes", then device data -1, storehouse are continued to employ in scene Stand-by equipment data+1 are deposited, 5.4) next step goes to step, and is otherwise directly entered next step;
Step 5.3) judge whether this equipment is scrapped?If it is judged that being "Yes", then scene is continued to employ device data -1, is treated 5.4) write-off equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 5.4) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing This state armamentarium updates.
Wherein:The decision method whether described equipment is scrapped is:Written-off device flag position is 2.
As shown in fig. 7, in step 2) in, described treat that write-off equipment state updates operation 6 for successively in waiting to scrap The operation that each equipment of state is carried out successively, which comprises the following steps:
Step 6.1) judge whether this equipment completes asset of equipments and scrap?If it is judged that being "Yes", then wait to scrap to set 6.2) standby data -1, write-off equipment data+1, next step go to step, and are otherwise directly entered next step;
Step 6.2) return, this renewal of the equipment terminates, and returns and continues to be updated operation to next equipment, until completing this State armamentarium updates.
Wherein:Whether described equipment completes asset of equipments rejection judgment method:The equipment of sequence to be scrapped is through money Product had both been can be determined that after scrapping program to be scrapped for completing asset of equipments.

Claims (7)

1. a kind of infrastructure device manages the composition and operational approach of operational system, it is characterised in that:Described infrastructure device management The composition and operational approach of operational system include the following steps for carrying out in order:
Step 1) set up data base on infrastructure device condition line:Whole infrastructure devices are divided into:Stock is standby, do not put into operation, fortune, Retired, live continue to employ, wait to scrap and scrap totally seven kinds of states;Then data are set up to the equipment of each state respectively Storehouse;And labelling has been carried out to the marker bit of all devices all in accordance with use state;
Step 2) operation management:During actual daily O&M, according to the practical situation that patrols and examines under line in respective data Operation is updated to data on the line of this seven kinds of status devices respectively in storehouse, consistent to ensure the offline upper data of line.
2. infrastructure device according to claim 1 manages the composition and operational approach of operational system, it is characterised in that:In step Rapid 2) in, described stock's stand-by equipment state updates operation for entering to each equipment in stock's resting state successively successively Capable operation, which comprises the following steps:
Step 1.1) judge whether this equipment is received?If it is judged that be "Yes", then stock's stand-by equipment data -1, do not throw 1.4) fortune device data+1, next step go to step, and are otherwise directly entered next step;
Step 1.2) judge whether this equipment puts into operation?If it is judged that be "Yes", then stock's stand-by equipment data -1, set in fortune 1.4) standby data+1, next step go to step, and are otherwise directly entered next step;
Step 1.3) judge whether this equipment is scrapped?If it is judged that be "Yes", then stock's stand-by equipment data -1, wait to scrap 1.4) device data+1, next step go to step, and are otherwise directly entered next step;
Step 1.4) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing this shape State armamentarium updates;
Wherein:The decision method whether described equipment is received is:The device flag position that has received is 0;
Wherein:The decision method whether described equipment puts into operation is:The device flag position that has put into operation is 1;
Wherein:The decision method whether described equipment is scrapped is:Equipment and scene in original stock continues to employ equipment through skill Art identification, if time limit equipment life arrives, enters sequence to be scrapped, that is, is defined as scrapping, written-off device flag position For 2.
3. infrastructure device according to claim 1 manages the composition and operational approach of operational system, it is characterised in that:In step Rapid 2) in, the described equipment state that do not put into operation updates operation for being carried out to each equipment in the state that do not put into operation successively successively Operation, which comprises the following steps:
Step 2.1) judge whether this equipment puts into operation?If it is judged that be "Yes", then the device data -1 that do not put into operation, in fortune equipment 2.3) data+1, next step go to step, and are otherwise directly entered next step;
Step 2.2) judge whether this equipment is given back?If it is judged that being "Yes", then the device data -1 that do not put into operation, stock are standby 2.3) device data+1, next step go to step, and are otherwise directly entered next step;
Step 2.3) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing this shape State armamentarium updates;
Wherein:The decision method whether described equipment is given back is:Returned device flag position is 3.
4. infrastructure device according to claim 1 manages the composition and operational approach of operational system, it is characterised in that:In step Rapid 2) in, it is described that to update operation in fortune equipment state be operation that each equipment for being in fortune state is carried out successively, its Comprise the following steps:
Step 3.1) judge whether this equipment is retired?If it is judged that be "Yes", then in fortune device data -1, retired number of devices According to+1,3.2) next step goes to step, and is otherwise directly entered next step;
Step 3.2) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing this shape State armamentarium updates;
Wherein:The whether retired decision method of described equipment is:Retired device flag position is 4.
5. infrastructure device according to claim 1 manages the composition and operational approach of operational system, it is characterised in that:In step Rapid 2) in, it is the operation carried out successively by each equipment in retired state that described retired state updates operation, and which includes The following steps:
Step 4.1) judge whether this equipment is scrapped?If it is judged that be "Yes", then retired device data -1, treat write-off equipment 4.3) data+1, next step go to step, and are otherwise directly entered next step;
Step 4.2) judge whether this equipment is given back?If it is judged that be "Yes", then retired device data -1, the standby number of stock According to+1,4.3) next step goes to step, and otherwise, data+1 are continued to employ at retired device data -1, scene, subsequently into next step;
Step 4.3) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing this shape State armamentarium updates;
Wherein:The decision method whether described equipment is scrapped is:Written-off device flag position is 2.
6. infrastructure device according to claim 1 manages the composition and operational approach of operational system, it is characterised in that:In step Rapid 2) in, described scene continue to employ equipment state update operation be that each equipment for continuing to employ state in scene is carried out successively Operation, which comprises the following steps:
Step 5.1) judge whether this equipment puts into operation?If it is judged that being "Yes", then scene is continued to employ device data -1, is set in fortune 5.4) standby data+1, next step go to step, and are otherwise directly entered next step;
Step 5.2) judge whether this equipment is given back?If it is judged that be "Yes", then to continue to employ device data -1, stock standby at scene With device data+1,5.4) next step goes to step, and is otherwise directly entered next step;
Step 5.3) judge whether this equipment is scrapped?If it is judged that being "Yes", then scene is continued to employ device data -1, waits to scrap 5.4) device data+1, next step go to step, and are otherwise directly entered next step;
Step 5.4) return, this renewal of the equipment terminates, returns and continue to be updated operation to next equipment, until completing this shape State armamentarium updates;
Wherein:The decision method whether described equipment is scrapped is:Written-off device flag position is 2.
7. infrastructure device according to claim 1 manages the composition and operational approach of operational system, it is characterised in that:In step Rapid 2) in, described treat that write-off equipment state updates operation for being carried out to each equipment in state to be scrapped successively successively Operation, which comprises the following steps:
Step 6.1) judge whether this equipment completes asset of equipments and scrap?If it is judged that being "Yes", then treat write-off equipment number According to -1, write-off equipment data+1,6.2) next step goes to step, and is otherwise directly entered next step;
Step 6.2) return, this renewal of the equipment terminates, and returns and continues to be updated operation to next equipment, until completing this state Armamentarium updates;
Wherein:Whether described equipment completes asset of equipments rejection judgment method:The equipment of sequence to be scrapped is through assets report Both can be determined that after useless program and scrapped for completing asset of equipments.
CN201610951795.3A 2016-10-27 2016-10-27 A kind of composition of infrastructure device management operational system and operational approach Pending CN106503812A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610951795.3A CN106503812A (en) 2016-10-27 2016-10-27 A kind of composition of infrastructure device management operational system and operational approach

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610951795.3A CN106503812A (en) 2016-10-27 2016-10-27 A kind of composition of infrastructure device management operational system and operational approach

Publications (1)

Publication Number Publication Date
CN106503812A true CN106503812A (en) 2017-03-15

Family

ID=58321323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610951795.3A Pending CN106503812A (en) 2016-10-27 2016-10-27 A kind of composition of infrastructure device management operational system and operational approach

Country Status (1)

Country Link
CN (1) CN106503812A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101202649A (en) * 2006-12-14 2008-06-18 英业达股份有限公司 Method for collecting and managing equipment information
CN104218679A (en) * 2014-09-12 2014-12-17 国家电网公司 Remote automatic transformer substation polling method based on remote viewing system
CN105844449A (en) * 2016-04-08 2016-08-10 国家电网公司 IT equipment overall process management design method based on layered model

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101202649A (en) * 2006-12-14 2008-06-18 英业达股份有限公司 Method for collecting and managing equipment information
CN104218679A (en) * 2014-09-12 2014-12-17 国家电网公司 Remote automatic transformer substation polling method based on remote viewing system
CN105844449A (en) * 2016-04-08 2016-08-10 国家电网公司 IT equipment overall process management design method based on layered model

Similar Documents

Publication Publication Date Title
CN108032876B (en) Station transportation scheduling method and system
CN110059777A (en) A kind of power equipment fortune inspection auxiliary system based on RFID technique
CN109634229A (en) A kind of intelligent plant manufacturing management system based on big data
CN205909870U (en) Intelligent power distribution looped netowrk cabinet monitored control system based on internet of things
CN106354110B (en) A kind of free Row control system and method for stock yard
CN108229913A (en) Factory's manufacturing execution system based on mobile terminal
CN102820707B (en) Topological automatic identification system for distribution network
CN101645148A (en) Construction order management method applied to operation support system and management system thereof
CN111702944B (en) Concrete prefabricated part production tracing system and control method
CN110097196A (en) Intelligent operation and maintenance management method and system
CN206877133U (en) Carrier delivering system
CN106933196A (en) Either simplex sequence automatic factory and control method
CN106603997A (en) Fixed asset management and production dispatching system for video monitoring service
CN112687022A (en) Intelligent building inspection method and system based on video
CN106959680B (en) A kind of centralized control and information management system for high-fineness ratio solid propellant
CN102111508A (en) Fault processing method and system as well as fault scheduling equipment
CN104635506A (en) Equipment simulation method of semiconductor production line conveying system
CN106503812A (en) A kind of composition of infrastructure device management operational system and operational approach
CN105096403A (en) Tour-inspection method and system for secondary intelligent water supply equipment
CN205485578U (en) Single process automation mill
CN104164555A (en) Visualization and interactive sequence control system and method of medium and thick plate heat treatment production line
CN105635155A (en) Method and device for detecting state of composition equipment in robot terminal
CN116703104A (en) Material box robot order picking method and device based on decision-making big model
CN202978420U (en) Automatic identification system for distribution network topology
CN203276301U (en) Prefabricated pipeline whole-course information monitoring device based on two-dimension code

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170315

RJ01 Rejection of invention patent application after publication