CN106498847A - A kind of prefabricated bent cap and attachment structure and the method for attachment of prefabricated stand column - Google Patents

A kind of prefabricated bent cap and attachment structure and the method for attachment of prefabricated stand column Download PDF

Info

Publication number
CN106498847A
CN106498847A CN201611180768.7A CN201611180768A CN106498847A CN 106498847 A CN106498847 A CN 106498847A CN 201611180768 A CN201611180768 A CN 201611180768A CN 106498847 A CN106498847 A CN 106498847A
Authority
CN
China
Prior art keywords
prefabricated
stand column
link slot
bent cap
prefabricated stand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611180768.7A
Other languages
Chinese (zh)
Other versions
CN106498847B (en
Inventor
葛继平
高飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Institute of Technology
Original Assignee
Shanghai Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Institute of Technology filed Critical Shanghai Institute of Technology
Priority to CN201611180768.7A priority Critical patent/CN106498847B/en
Publication of CN106498847A publication Critical patent/CN106498847A/en
Application granted granted Critical
Publication of CN106498847B publication Critical patent/CN106498847B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

A kind of prefabricated bent cap and attachment structure and the method for attachment of prefabricated stand column, including prefabricated stand column and prefabricated bent cap, preform lid erection is on prefabricated stand column, prefabricated bent cap is provided with link slot, lower ending opening of the upper end open of link slot more than link slot, also, the area of lower ending opening is less than the upper surface area of prefabricated stand column;Some presstressed reinforcing steels are embedded with prefabricated stand column, presstressed reinforcing steel stretches out prefabricated stand column certain length, and the presstressed reinforcing steel for stretching out is distributed in bell mouth shape in link slot, fill ultra-high performance concrete in link slot.The construction technology of the present invention is simple, and construction precision requires low, safe and reliable, efficient quick, and rapid construction is significant.

Description

A kind of prefabricated bent cap and attachment structure and the method for attachment of prefabricated stand column
Technical field
The present invention relates to engineering bridge technical field, more particularly to the attachment structure of a kind of prefabricated bent cap and prefabricated stand column and Method of attachment.
Background technology
With wideling popularize and development for precast concrete, domestic many architectural engineerings begin to use precast assembly skill Art, is constructed by through engineering approaches production and assembled in situ, can achieve the construction objects such as safety durable, quick construction, low-carbon environment-friendly, can Building waste and building sewage is greatly decreased, is reduced building noise, is improved construction quality, become the green ring that country advocates energetically Protect energy saving building.For precast assembly bridge pier, node connecting portion is the weak link in whole bridge pier, if processed not When easily causing to destroy under high-intensity earthquake, therefore for this key position needs to pay special attention to.
Normal concrete is vibrated coagulation with instruments such as shock clubs in construction as a kind of heterogeneous material of porous Soil, so as to concrete compaction, but has leaked or has shaken if shaking, and just occurs that the quality such as cavity, honeycomb, pitted skin lack Fall into, there is ultra-high performance concrete (UHPC) Self-leveling and high intensity can overcome these normal defects.UHPC is promoted Application is reinforcing energy-saving and emission-reduction, the effective way of Air Pollution prevention and control, it is possible to increase construction quality, extends Building life cycle, carries Ability of preventing and reducing natural disasters is risen, is conducive to the adjustment for promoting cement industry structure.Although high performance concrete cost is slightly higher, but if only It is to be applied topically to key position, higher cost performance can be obtained.
Fixed press anchorage product is ripe, extensively applies.The class of the arrangement of fixed press anchorage and common stretching end anchorage Same, directly can be embedded in concrete.Strain in areas of plasticity hinge reinforcing bar is larger, and reinforcing bar easily enters yield situation, if Plastic hinge this regional area adopts presstressed reinforcing steel, because its intensity is high, presstressed reinforcing steel can be delayed to enter yield situation, can be made Precast pier has self-resetting capability.During the seismic loading being subjected in future, the residual displacement of bridge pier can be caused less, carried High anti-seismic ability.
Content of the invention
In view of the drawbacks described above that prior art is present, the present invention provides the connection knot of a kind of prefabricated bent cap and prefabricated stand column Structure and method of attachment.
To achieve these goals, the technical solution adopted in the present invention is:
A kind of prefabricated bent cap and the attachment structure of prefabricated stand column, including prefabricated stand column and prefabricated bent cap, the prefabricated bent cap It is erected on the prefabricated stand column, the prefabricated bent cap is provided with link slot, the upper end open of the link slot is more than the connection The lower ending opening of groove, also, the area of the lower ending opening is less than the upper surface area of the prefabricated stand column;The prefabricated stand column Some piece presstressed reinforcing steels are inside embedded with, and the presstressed reinforcing steel stretches out the prefabricated stand column certain length, the presstressed reinforcing steel for stretching out It is distributed in bell mouth shape in the link slot, in the link slot, fills ultra-high performance concrete.
Preferably, the presstressed reinforcing steel is distributed and in a ring in the presstressed reinforcing steel on the cross section of the prefabricated stand column The outer steel bar stress for being equipped with annular spread.
Preferably, the presstressed reinforcing steel is embedded in the prefabricated stand column by fixed press anchorage.
Preferably, the presstressed reinforcing steel adopts prestress wire.
Preferably, passing through epoxy resin between the bottom of the edge of the upper surface of the prefabricated stand column and the prefabricated bent cap Layer connection.
A kind of prefabricated bent cap and the method for attachment of prefabricated stand column, implement attachment structure described above, and its step is:
1) preparation of prefabricated stand column;
2) preparation of prefabricated bent cap;
3) epoxy lipid layer is applied at the edge of the top surface of prefabricated stand column, then by preform lid erection on prefabricated stand column, and The presstressed reinforcing steel for stretching out prefabricated stand column is all embedded in link slot, and prefabricated bent cap is positioned;
4) after prefabricated bent cap is properly positioned, the presstressed reinforcing steel colligation that stretches out is distributed in link slot into bell mouth shape, Then ultra-high performance concrete is poured into into link slot;
5) after pouring into ultra-high performance concrete in link slot, when the ultra-high performance concrete in link slot reaches design by force Degree more than 100% when, tensioning is carried out to prestress wire with post stretching, sealing off and covering anchorage is then carried out.
Using the Advantageous Effects that above-mentioned technical proposal is brought it is:
By the present invention in that using presstressed reinforcing steel so that node district stress performance is greatly improved;
The present invention makes full use of high-strength prestress steel strand wires, and in the case of large deformation, join domain has self-resetting capability And its flexible performance is good, construction precision require relatively low;
The present invention pours into grout sleeve and link slot using ultra-high performance concrete UHPC, takes full advantage of superelevation in construction The high fluidity of performance concrete and good anti-isolation, Qinshui ability, the on the other hand characteristic of its microdilatancy having can be with Strengthen the reliability of connection;
The construction technology of the present invention is simple, and construction precision requires low, safe and reliable, efficient quick, and rapid construction is had Important meaning.
Description of the drawings
Fig. 1 is the facade layout drawing of the attachment structure of the prefabricated bent cap and prefabricated stand column of one embodiment of the invention;
Fig. 2 is the plane graph of the prefabricated bent cap of one embodiment of the invention;
Fig. 3 is the elevation of the prefabricated bent cap of one embodiment of the invention;
Fig. 4 is the I-I sectional views of the prefabricated bent cap of one embodiment of the invention;
Fig. 5 is the steel bar stress structural map of the prefabricated stand column of one embodiment of the invention;
Fig. 6 is the presstressed reinforcing steel layout drawing of the prefabricated stand column of one embodiment of the invention;
Fig. 7 is the elevation of the prefabricated stand column of one embodiment of the invention;
Fig. 8 is the II-II sectional views of the prefabricated stand column of one embodiment of the invention;
Fig. 9 is the welding figure of the prefabricated bent cap top steel bar stress of one embodiment of the invention.
In figure, the prefabricated bent caps of 1-;2- prefabricated stand columns;3- link slots;4- stirrups;5- presstressed reinforcing steels;6- fixed press anchorages; 7- epoxy resin layers;The first steel bar stresses of 10-;The second steel bar stresses of 11-.
Specific embodiment
For making the object, technical solutions and advantages of the present invention clearer, below in conjunction with each reality of the accompanying drawing to the present invention The mode of applying is explained in detail.
Please comprehensive reference Fig. 1-9, a kind of prefabricated bent cap and prefabricated stand column attachment structure, including prefabricated stand column 2 and prefabricated Bent cap 1, prefabricated bent cap 1 are erected on prefabricated stand column 2, are provided with link slot 3 in prefabricated bent cap 1, and the upper end open of link slot 3 is more than The lower ending opening of link slot 3, also, the area of lower ending opening is less than the upper surface area of prefabricated stand column 2, is that prefabricated bent cap 1 hangs Fulcrum is provided during dress;Some presstressed reinforcing steels 5 are embedded with prefabricated stand column 2, presstressed reinforcing steel 5 stretches out 2 certain length of prefabricated stand column, The presstressed reinforcing steel 5 for stretching out is distributed in link slot 3 into bell mouth shape by 4 colligation of stirrup, fills UHPC in link slot 3.The design Used in have high-yield strength presstressed reinforcing steel 5, in the case of the 1 occurred level displacement of prefabricated bent cap, areas of plasticity hinge have There is self-resetting capability, so prefabricated bent cap 1 and prefabricated stand column 2 connect more reliable, safety;By pouring into toward in link slot 3 The characteristics of UHPC, self-compaction uniform using UHPC, it is fully contacted can prestress wire and the link slot 3 of prefabricated bent cap 1, Stress performance is improved, the safety of engineering has been ensured.
Presstressed reinforcing steel 5 adopts prestress wire, prestress wire to be embedded in prefabricated stand column by fixed press anchorage 6 In 2.Fixed press anchorage 6 includes fixing anchor slab and extruded sleeve, and the head of prestress wire puts extruded sleeve, by special machine Tool extruding, prestress wire of holding with a firm grip after making extruded sleeve generation plastic deformation, a relay of prestressed steel strand wires is by extruding Set passes to component, i.e. prefabricated stand column 2 by fixed anchor slab.
Connected (such as Fig. 1 by epoxy resin layer 7 between the bottom of the edge of the upper surface of prefabricated stand column 2 and prefabricated bent cap 1 Shown).
Presstressed reinforcing steel 5 is distributed on the cross section of prefabricated stand column 2 in a ring and is equipped with annular point in the outer of presstressed reinforcing steel 5 Second steel bar stress 11 (as shown in Figure 7 and Figure 8) of cloth.
The outer of 1 cross-sectional area of prefabricated bent cap is uniformly equipped with the first steel bar stress 10 (as shown in figures 4 and 9).
A kind of prefabricated bent cap and the method for attachment of prefabricated stand column, using above-mentioned attachment structure, its step is:
1) preparation of prefabricated stand column 2;
2) preparation of prefabricated bent cap 1;
3) epoxy lipid layer is applied at the edge of the top surface of prefabricated stand column 2, then prefabricated bent cap 1 is erected on prefabricated stand column 2, And the presstressed reinforcing steel 5 for stretching out prefabricated stand column 2 is all embedded in link slot 3, and prefabricated bent cap 1 is positioned;
4) after prefabricated bent cap 1 is properly positioned, the presstressed reinforcing steel 5 in the link slot 3 of prefabricated bent cap 1 is in loudspeaker by stirrup 4 Mouth shape distribution colligation, and first steel bar stress 10 on 1 top of prefabricated bent cap is welded, then pour into into link slot 3 UHPC;
5) after perfusion UHPC in link slot 3, when the UHPC in link slot 3 reaches more than the 100% of design strength, use Post stretching carries out tensioning to prestress wire, then carries out sealing off and covering anchorage again.
The advantage of do so, on the one hand further improves self-resetting capability;The concrete pulling of another aspect areas of plasticity hinge Stress very little, easily ftractures, after tensioning, using the partial prestressing for applying in advance, can improve the cracking lotus of areas of plasticity hinge Carry, improve service behaviour.
The above, the only present invention preferably specific embodiment, but protection scope of the present invention is not limited thereto, Any those familiar with the art the invention discloses technical scope in, the change or replacement that can readily occur in, Should all be included within the scope of the present invention.Therefore, protection scope of the present invention should be with scope of the claims It is defined.

Claims (6)

1. the attachment structure of a kind of prefabricated bent cap and prefabricated stand column, it is characterised in that:Including prefabricated stand column and prefabricated bent cap, described On the prefabricated stand column, the prefabricated bent cap is provided with link slot to preform lid erection, and the upper end open of the link slot is more than The lower ending opening of the link slot, also, the area of the lower ending opening is less than the upper surface area of the prefabricated stand column;Described Some presstressed reinforcing steels are embedded with prefabricated stand column, and the presstressed reinforcing steel stretches out the prefabricated stand column certain length, and that stretched out is described Presstressed reinforcing steel is distributed in bell mouth shape in the link slot, fills ultra-high performance concrete in the link slot.
2. attachment structure as claimed in claim 1, it is characterised in that:The presstressed reinforcing steel is in the cross section of the prefabricated stand column On in a ring distribution and the outer steel bar stress for being equipped with annular spread in the presstressed reinforcing steel.
3. attachment structure as claimed in claim 1, it is characterised in that:The presstressed reinforcing steel is embedded in by fixed press anchorage In the prefabricated stand column.
4. attachment structure as claimed in claim 1, it is characterised in that:The presstressed reinforcing steel adopts prestress wire.
5. attachment structure as claimed in claim 1, it is characterised in that:The edge of the upper surface of the prefabricated stand column and described pre- Connected by epoxy resin layer between the bottom of bent cap processed.
6. the method for attachment of a kind of prefabricated bent cap and prefabricated stand column, implements the connection any one of the claims 1-5 Structure, its step is:
1) preparation of prefabricated stand column;
2) preparation of prefabricated bent cap;
3) epoxy lipid layer is applied at the edge of the top surface of prefabricated stand column, then by preform lid erection on prefabricated stand column, and will stretch The presstressed reinforcing steel for going out prefabricated stand column is all embedded in link slot, and prefabricated bent cap is positioned;
4) after prefabricated bent cap is properly positioned, the presstressed reinforcing steel colligation that stretches out is distributed in link slot into bell mouth shape, then Ultra-high performance concrete is poured into into link slot;
5) after pouring into ultra-high performance concrete in link slot, when the ultra-high performance concrete in link slot reaches design strength When more than 100%, tensioning is carried out to prestress wire with post stretching, then carry out sealing off and covering anchorage.
CN201611180768.7A 2016-12-19 2016-12-19 A kind of connection structure and connection method of prefabricated bent cap and prefabricated stand column Expired - Fee Related CN106498847B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611180768.7A CN106498847B (en) 2016-12-19 2016-12-19 A kind of connection structure and connection method of prefabricated bent cap and prefabricated stand column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611180768.7A CN106498847B (en) 2016-12-19 2016-12-19 A kind of connection structure and connection method of prefabricated bent cap and prefabricated stand column

Publications (2)

Publication Number Publication Date
CN106498847A true CN106498847A (en) 2017-03-15
CN106498847B CN106498847B (en) 2019-01-22

Family

ID=58333150

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611180768.7A Expired - Fee Related CN106498847B (en) 2016-12-19 2016-12-19 A kind of connection structure and connection method of prefabricated bent cap and prefabricated stand column

Country Status (1)

Country Link
CN (1) CN106498847B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107167289A (en) * 2017-05-17 2017-09-15 上海应用技术大学 A kind of great cantilever precast assembly bent cap load test method
CN108532445A (en) * 2018-07-04 2018-09-14 深圳市市政设计研究院有限公司 A kind of connecting structure and its construction method of prefabricated bent cap and Precast Pier Columns
CN109024249A (en) * 2018-08-16 2018-12-18 福建工程学院 A kind of connector uses the spigot-and-socket construction precast assembly bridge pier of cast-in-place UHPC material
CN110219486A (en) * 2019-07-10 2019-09-10 福州大学 A kind of prestressing force assembled UHPC bicycle shed construction and its construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100748636B1 (en) * 2006-08-30 2007-08-14 차진이 Concrete pier having copping and constructing method therefor
CN102493335A (en) * 2011-12-02 2012-06-13 天津城市建设学院 Prefabricating prestress steel tube confined concrete pier
CN204589787U (en) * 2015-04-28 2015-08-26 北京城建设计发展集团股份有限公司 The prefabricated bent cap of the T-shaped pier of Bridges on Urban Rail Transit
CN105088937A (en) * 2014-05-08 2015-11-25 郑州大学 Hollow slab bridge with hinge joint having opposite grooves and building method of hollow slab bridge
KR20160005257A (en) * 2014-07-04 2016-01-14 (주)에스앤씨산업 Precast Coping, the Combination Structure of Column and Coping, and its Construction Method
CN105442434A (en) * 2015-12-21 2016-03-30 上海市城市建设设计研究总院 Slot type connecting structure for prefabricated stand column and prefabricated cover beam of bridge and splicing method for prefabricated stand column and prefabricated cover beam
CN106049259A (en) * 2016-06-16 2016-10-26 安徽省交通规划设计研究总院股份有限公司 Bridge integrally-assembled pier and construction method
CN206273875U (en) * 2016-12-19 2017-06-23 上海应用技术大学 A kind of attachment structure of prefabricated bent cap and prefabricated stand column

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100748636B1 (en) * 2006-08-30 2007-08-14 차진이 Concrete pier having copping and constructing method therefor
CN102493335A (en) * 2011-12-02 2012-06-13 天津城市建设学院 Prefabricating prestress steel tube confined concrete pier
CN105088937A (en) * 2014-05-08 2015-11-25 郑州大学 Hollow slab bridge with hinge joint having opposite grooves and building method of hollow slab bridge
KR20160005257A (en) * 2014-07-04 2016-01-14 (주)에스앤씨산업 Precast Coping, the Combination Structure of Column and Coping, and its Construction Method
CN204589787U (en) * 2015-04-28 2015-08-26 北京城建设计发展集团股份有限公司 The prefabricated bent cap of the T-shaped pier of Bridges on Urban Rail Transit
CN105442434A (en) * 2015-12-21 2016-03-30 上海市城市建设设计研究总院 Slot type connecting structure for prefabricated stand column and prefabricated cover beam of bridge and splicing method for prefabricated stand column and prefabricated cover beam
CN106049259A (en) * 2016-06-16 2016-10-26 安徽省交通规划设计研究总院股份有限公司 Bridge integrally-assembled pier and construction method
CN206273875U (en) * 2016-12-19 2017-06-23 上海应用技术大学 A kind of attachment structure of prefabricated bent cap and prefabricated stand column

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107167289A (en) * 2017-05-17 2017-09-15 上海应用技术大学 A kind of great cantilever precast assembly bent cap load test method
CN108532445A (en) * 2018-07-04 2018-09-14 深圳市市政设计研究院有限公司 A kind of connecting structure and its construction method of prefabricated bent cap and Precast Pier Columns
CN109024249A (en) * 2018-08-16 2018-12-18 福建工程学院 A kind of connector uses the spigot-and-socket construction precast assembly bridge pier of cast-in-place UHPC material
CN109024249B (en) * 2018-08-16 2023-10-24 福建工程学院 Socket type structure prefabricated assembly pier with joint made of cast-in-situ UHPC material
CN110219486A (en) * 2019-07-10 2019-09-10 福州大学 A kind of prestressing force assembled UHPC bicycle shed construction and its construction method

Also Published As

Publication number Publication date
CN106498847B (en) 2019-01-22

Similar Documents

Publication Publication Date Title
CN105780935B (en) Prefabricated assembled steel tube confinement energy consumption connecting node and construction method
CN106498847B (en) A kind of connection structure and connection method of prefabricated bent cap and prefabricated stand column
CN104790424B (en) The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof
CN206737141U (en) A kind of bolt connection assembled integral node
CN106988483A (en) A kind of assembled steel reinforced Concrete U Vierendeel girder and its construction method
CN103711330B (en) A kind of prestressing force assembling precast reinforced concrete frame reinforces the method for existing structure
CN109914234B (en) Precast segment shear-resistant spliced concrete pier connected through bolts
CN205894313U (en) Prefabricated assembled steel pipe retrains frame node entirely
CN106758786A (en) A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier
CN206941858U (en) Band is encorbelmented the structure of attached prestressing force assembled power consumption frame strengthening outside plate framework
CN109853364A (en) A kind of the precast segment assembly bridge pier connection structure and method of shearing resistance
CN206273875U (en) A kind of attachment structure of prefabricated bent cap and prefabricated stand column
CN105275096A (en) Prefabricated pieced two-way slab construction method
CN115045181A (en) Socket joint type node connection method and structure for prefabricated pier column and bearing platform in middle and high intensity region
CN210216126U (en) Pier connection structure is assembled in prefabricated section of cutting
CN209924484U (en) Device with sleeve prefabricated part for reinforcing damaged reinforced concrete column
CN112921789A (en) Structure structure of self-resetting socket-and-spigot type ECC (error correction code) mixed bridge pier and splicing method thereof
CN209907185U (en) Bolted prefabricated segment shear-resistant assembled concrete pier
CN110792032A (en) Steel hoop structure for additionally arranging steel bent cap on pier stand column and installation method
CN108729541A (en) Connect beam type Building block construction method
CN108999077A (en) The circumferential weld connection structure and its circumferential weld connection method of prefabricated stand column and adjacent members
CN205205847U (en) Frame construction of stake cushion cap
CN109898540B (en) Wet joint structure among bridge pier, bearing platform and pile foundation and construction process thereof
CN210856913U (en) FRP (fiber reinforced plastic) confined concrete hollow self-resetting-mild steel extrusion energy dissipation pier structure
CN107299721A (en) A kind of precast concrete open tubular column node connecting structure and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190122