CN106451518B - A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire - Google Patents

A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire Download PDF

Info

Publication number
CN106451518B
CN106451518B CN201610893959.1A CN201610893959A CN106451518B CN 106451518 B CN106451518 B CN 106451518B CN 201610893959 A CN201610893959 A CN 201610893959A CN 106451518 B CN106451518 B CN 106451518B
Authority
CN
China
Prior art keywords
scheme
alternative
main
electrical
connecting wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610893959.1A
Other languages
Chinese (zh)
Other versions
CN106451518A (en
Inventor
李隽�
王菲
韩丰
李晖
刘建琴
蒋维勇
戚庆茹
王峤
左鹏
杨林
朱毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
State Grid Economic and Technological Research Institute
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
State Grid Economic and Technological Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd, State Grid Economic and Technological Research Institute filed Critical State Grid Corp of China SGCC
Priority to CN201610893959.1A priority Critical patent/CN106451518B/en
Publication of CN106451518A publication Critical patent/CN106451518A/en
Application granted granted Critical
Publication of CN106451518B publication Critical patent/CN106451518B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/36Arrangements for transfer of electric power between ac networks via a high-tension dc link
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/60Arrangements for transfer of electric power between AC networks or generators via a high voltage DC link [HVCD]

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire, 1) it is the following steps are included: carry out fail-safe analysis to pre-set each converter station DC fields electrical main connecting wire alternative;2) according to the cost of relevant device each in main electrical scheme alternative level and quantity, to the carry out economic analysis of main electrical scheme alternative;3) according to the design feature of main electrical scheme alternative, power distribution equipment arrangement, relay protection and control mode, Dexterity analysis is carried out to main electrical scheme alternative;4) according to reliability, economy and the flexibility of each converter substation scheme's alternative, the scheme of each converter station DC fields electrical main connecting wire is determined;5) according to the scheme of each converter station DC fields electrical main connecting wire, the scheme of flexible direct current power grid DC fields electrical main connecting wire is obtained.The present invention can select optimal Main Wire Connection Scheme based on various factors, and adapt to Fast Construction and the development of the following flexible direct current power grid.

Description

A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire
Technical field
The present invention relates to a kind of in electrical network field determines the method and system of DC fields electrical main connecting wire, especially with regard to A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire.
Background technique
Flexible DC transmission, can be to wattful power generally using full control power electronic devices using voltage source converter Rate and reactive power carry out independent quickly control.Based on wholly-controled device (IGBT) and the big essential characteristic of high frequency modulated technology two, Flexible direct current also has reactive compensation and commutation failure problem, active and idle function on the basis of having the advantages that customary DC Rate independent control, trend invert the technical advantages such as convenient and efficient, method of operation transformation is flexible.Currently, it is soft to have gone into operation both at home and abroad Property DC engineering is substantially both ends chain type or the relatively simple topological structures such as multiterminal are emanant, not proper direct current Power grid has the flexible direct current power grid of typical mesh topology structure, there is no engineering practice at present.
According to the difference of DC Line Fault reset mode, there are half-bridge converter valves to cooperate dc circuit breaker for flexible direct current power grid (half-bridge scheme) and full-bridge converter valve cooperate Fast mechanical switch (full-bridge scheme) two schemes.Wherein, full-bridge scheme is in failure It needs to be latched whole converter stations in reset procedure, the operation of AC and DC power grid is caused to impact;In contrast, half-bridge scheme exists When removing DC Line Fault, it can not be latched or be only latched a few converter station, very little, Neng Gougeng are influenced caused by operation of power networks The requirement of the following complicated DC grid operation control of good adaptation, is the developing direction of the following DC grid.Dc circuit breaker is It is applied in the power system, but the problems such as there are voltage class and not high breaking capacity, is suitable for ± 500kV voltage class Dc circuit breaker be still in the development stage.
DC fields are one of important components of converter station.The direct current for the flexible DC transmission engineering gone into operation both at home and abroad Field electricity main wiring design is relatively easy, and does not carry out the correlative study of DC fields main electrical scheme moulder moisture substantially, usually adopts With simple wiring or single bus scheme;Main cause is that return number less for equipment and outlet in DC fields, and due to not having high pressure Dc circuit breaker, direct current system operation are relatively easy.With the development and building of global energy internet, flexible direct current power grid Scale will it is increasingly huge, electric network composition is increasingly complicated, converter station goes out line number and number of elements and will be continuously improved, flexible direct current electricity The method of operation of net and converter station is by more sophisticated.Therefore, it is necessary to flexible direct current power grid DC fields electrical main connecting wire type selecting Carry out special design and research.
Summary of the invention
In view of the above-mentioned problems, the object of the present invention is to provide a kind of determining flexible direct current power grid DC fields electrical main connecting wires Method and system can select optimal Main Wire Connection Scheme based on various factors, and adapt to the following flexible direct current power grid Fast Construction and development.
To achieve the above object, the present invention takes following technical scheme: a kind of determining flexible direct current power grid DC fields are electrical The method of main electrical scheme, which is characterized in that 1) it according to pre-set each converter station DC fields the following steps are included: electrically lead The parameter preset of main electrical scheme topological structure and relevant device in wiring alternative carries out reliability to main electrical scheme alternative Analysis;2) according to the cost of relevant device each in main electrical scheme alternative level and quantity, the work of main electrical scheme alternative is calculated Journey initial cost and annual cost obtain the economy of main electrical scheme alternative;3) according to the design feature of main electrical scheme alternative, match Electric installation arrangement, relay protection and control mode carry out Dexterity analysis to main electrical scheme alternative;4) according to each converter station Reliability, economy and the flexibility of DC fields electrical main connecting wire alternative determine that electrically master connects each converter station DC fields The scheme of line;5) according to the scheme of each converter station DC fields electrical main connecting wire, flexible direct current power grid DC fields is obtained and are electrically led The scheme of wiring.
Preferably, in the step 1), the alternative of each converter station DC fields electrical main connecting wire is according to each Function and flexible direct current the Electric Power Network Planning setting of a converter station.
Preferably, the alternative of each converter station DC fields electrical main connecting wire includes single bus scheme, double-bus Wiring, angle scheme and 3/2 wiring.
Preferably, in the step 1), carrying out fail-safe analysis to main electrical scheme alternative, specific step is as follows: according to The structure of main electrical scheme alternative carries out trouble correlation analytic, obtains the common mode idle time of each equipment component;According to main electrical scheme The dependability parameter of each relevant device in alternative obtains the fundamental analysis result of main electrical scheme alternative;It is standby to main electrical scheme It selects in scheme previously selected equipment to carry out sensitivity analysis and it is alternative to be obtained according to the responsive parameter of selected equipment for main electrical scheme The sensitivity analysis result of scheme;According to the fundamental analysis result of main electrical scheme alternative and sensitivity analysis as a result, being led The reliability of wiring alternative.
Preferably, when the dependability parameter of each equipment includes failure rate, mean repair time, maintenance rate and maintenance Between;The fundamental analysis result includes system blackout failure rate, System average interruption duration, availability, power failure probability, has a power failure and put down Equal time, power failure frequency, loss electric energy and annual operating cost.
Preferably, in the step 3), the flexibility of main electrical scheme alternative is by operational flexibility, maintenance flexibility and expansion Build flexibility composition.
Preferably, according to main electrical scheme alternative in management and running, investment and excision generator and load it is flexible Degree, determines the operational flexibility of main electrical scheme alternative.
Preferably, safe inspection is carried out according to stoppage in transit breaker, bus and the relay protection device to main electrical scheme alternative When repairing, the influence to operation of power networks and power supply is caused, determines the maintenance flexibility of main electrical scheme alternative.
Preferably, according to the workload of main electrical scheme alternative later period enlarging and to the influence of system power supply, master is determined The enlarging flexibility of wiring alternative.
A kind of system of determining flexible direct current power grid DC fields electrical main connecting wire, which is characterized in that it include memory module, Fail-safe analysis module, economy module, Dexterity analysis module and Main Wire Connection Scheme module;The memory module is for storing The alternative of pre-set each converter station DC fields electrical main connecting wire;The fail-safe analysis module is used for according in advance The default ginseng of main electrical scheme topological structure and relevant device in each converter station DC fields electrical main connecting wire alternative being arranged Number carries out fail-safe analysis to the alternative of main electrical scheme, and the economy module is used for according to each in main electrical scheme alternative The cost of equipment is horizontal and quantity obtains the economy of main electrical scheme alternative, and the Dexterity analysis module is used to be connect according to master Design feature, power distribution equipment arrangement, relay protection and the control mode of line alternative carry out main electrical scheme alternative flexible Property analysis;The Main Wire Connection Scheme module is used for reliability, economy and spirit according to each converter substation scheme's alternative Activity determines the scheme of each converter station DC fields electrical main connecting wire, and according to each converter station DC fields electrical main connecting wire Scheme obtains the scheme of flexible direct current power grid DC fields electrical main connecting wire.
The invention adopts the above technical scheme, which has the following advantages: 1, of the invention from main electrical scheme alternative Reliability, economy and flexibility are evaluated, and are realized and are stood erectly the comprehensive assessment of flow field Main Bus Wiring Scheme to the change of current, and The influence of the factors such as different main electrical scheme structures and all kinds of novel devices can be assessed, the quick of the following flexible direct current power grid is adapted to Construction and development.2, the present invention is assessed from the flexibility of main electrical scheme alternative, so that the electricity main wiring design recommended Scheme has better harmony and adaptability.3, the present invention is assessed from the economy of main electrical scheme alternative, Neng Gouman Sufficient engineering go into operation year and distant view year operation, in terms of technical requirements.
Detailed description of the invention
Fig. 1 is the topological structure single line schematic diagram of the present embodiment Zhangbei County flexible direct current power grid;
Fig. 2 is that the present embodiment Zhangbei County stands erectly the electrical single female connection plan schematic diagram in flow field;
Fig. 3 is that the present embodiment Zhangbei County stands erectly the electrical double bus wiring scheme for double schematic diagram in flow field;
Fig. 4 is that the present embodiment Zhangbei County stands erectly flow field electrically angular line connection plan schematic diagram;
Fig. 5 is that the present embodiment Zhangbei County stands erectly the electrical 3/2 connection plan schematic diagram in flow field.
Specific embodiment
The present invention is described in detail below with reference to the accompanying drawings and embodiments.
The present invention provides a kind of determining flexible direct current power grid DC fields electrical main connecting wire method, the specific steps of which are as follows:
1) according to main electrical scheme topological structure in pre-set each converter station DC fields electrical main connecting wire alternative with And the parameter preset of relevant device, fail-safe analysis is carried out to main electrical scheme alternative;
2) according to the cost of equipment each in main electrical scheme alternative level and quantity, the engineering of main electrical scheme alternative is calculated Initial cost and annual cost obtain the economy of main electrical scheme alternative;
3) according to the design feature of main electrical scheme alternative, power distribution equipment arrangement, relay protection and control mode, master is connect Line alternative carries out Dexterity analysis;
4) according to reliability, economy and the flexibility of each converter substation scheme's alternative, each converter station is determined The scheme of DC fields electrical main connecting wire;
5) according to the scheme of each converter station DC fields electrical main connecting wire, obtaining flexible direct current power grid DC fields, electrically master is connect The scheme of line.
Above-mentioned steps 1) in, the alternative of each converter station DC fields electrical main connecting wire is the function according to each converter station It can be with the setting of flexible direct current Electric Power Network Planning.
Above-mentioned steps 1) in, to the fail-safe analysis of main electrical scheme alternative, specific step is as follows:
(1.1) according to the structure of main electrical scheme alternative, trouble correlation analytic is carried out, the common mode for obtaining each equipment component is stopped Transport the time;
(1.2) according to the failure rate of equipment each in main electrical scheme alternative, mean repair time, maintenance rate, repair time Equal dependability parameters, obtain system blackout failure rate, System average interruption duration, the availability, power failure of main electrical scheme alternative The fundamental analysis results such as probability, the average time that has a power failure, power failure frequency, loss electric energy, annual operating cost;
(1.3) sensitivity analysis is carried out to equipment previously selected in main electrical scheme alternative, according to preselected equipment Responsive parameter, obtain the sensitivity analysis result of main electrical scheme alternative;
(1.4) according to the fundamental analysis result of main electrical scheme alternative and sensitivity analysis as a result, to obtain main electrical scheme alternative The reliability of scheme.
Above-mentioned steps 3) in, to the Dexterity analysis of main electrical scheme alternative, specific step is as follows:
(3.1) flexibility of main electrical scheme alternative is made of operational flexibility, maintenance flexibility and enlarging flexibility;
(3.2) according to main electrical scheme alternative in management and running, the flexibility ratio of investment and excision generator, load, really Determine the operational flexibility of main electrical scheme alternative;
(3.3) safety inspection is carried out according to the stoppage in transit breaker, bus and relay protection device to main electrical scheme alternative When, the influence to operation of power networks and power supply is caused, determines the maintenance flexibility of main electrical scheme alternative;
(3.4) according to the workload of main electrical scheme alternative later period enlarging and to the influence of system power supply, determine that master connects The enlarging flexibility of line alternative;
(3.5) according to the operational flexibility of main electrical scheme alternative, maintenance flexibility and enlarging flexibility, main electrical scheme is obtained The flexibility of alternative.
Based on the above method, the present invention also provides a kind of system of determining flexible direct current power grid DC fields electrical main connecting wire, It includes memory module, fail-safe analysis module, economy module, Dexterity analysis module and Main Wire Connection Scheme module.
Memory module is used to store the alternative of pre-set each converter station DC fields electrical main connecting wire;
Fail-safe analysis module is used for according in pre-set each converter station DC fields electrical main connecting wire alternative The parameter preset of main electrical scheme topological structure and relevant device carries out fail-safe analysis, economy to the alternative of main electrical scheme Module is used to obtain the economy of main electrical scheme alternative according to the cost level and quantity of equipment each in main electrical scheme alternative, Dexterity analysis module is used for the design feature according to main electrical scheme alternative, power distribution equipment arrangement, relay protection and controlling party Formula carries out Dexterity analysis to main electrical scheme alternative.
Main Wire Connection Scheme module be used for according to the reliability of each converter substation scheme's alternative, economy and flexibly Property, determine the scheme of each converter station DC fields electrical main connecting wire, and according to the side of each converter station DC fields electrical main connecting wire Case obtains the scheme of flexible direct current power grid DC fields electrical main connecting wire.
Embodiment, by taking Zhangbei County station in Zhangbei County's flexible direct current power grid as an example, Zhangbei County stands erectly flow field Main Bus Wiring Scheme Specific step is as follows for selection method:
1) as shown in Figure 1, Zhangbei County's flexible direct current power grid includes 4 converter stations altogether, respectively Zhangbei County station, Kangbao County station, Fengning It stands and Beijing Station;Wherein, Zhangbei County station and Kangbao County station are that sending end new energy collects station, and Fengning station is energy storage regulation station, and Beijing Station is By end station.Zhangbei County stands erectly streaming system using bipolar wiring construction, and rated capacity 3000MW, each pole outlet scale 2 is returned, until Kangbao County It stands and each 1 time of Beijing Station;Zhangbei County's flexible direct current network voltage grade is ± 500kV, presets single bus scheme, double-bus connects 4 line, angle scheme and 3/2 wiring main electrical scheme alternatives, respectively as shown in Fig. 2~Fig. 5;
2) the common mode idle time of main electrical scheme alternative is as shown in table 1:
1 common mode idle time of table
Device name Common mode idle time (h)
DC bus 5
Disconnecting switch 14
Common-mode isolation switch 0.4
Common mode breaker 0.5
The indexs such as failure rate, mean repair time, maintenance rate, repair time, the equipment manufacturing cost of main electrical scheme alternative, such as Shown in table 2;
2 equipment dependability parameter of table
According to common mode idle time and equipment dependability parameter, obtains the power-off fault rate of main electrical scheme alternative, is averaged Interruption duration, availability, power failure probability, the average time that has a power failure, power failure frequency, loss electric energy and operating cost etc. basis point Analysis is as a result, as shown in table 3;Wherein, the electricity price in calculating is 0.5 yuan/kilowatt hour;
The fundamental analysis result of the electrical each main electrical scheme of 3 Zhangbei County's converter station of table
It is new research and development equipment in view of 500kV dc circuit breaker, there is no related operating statistic data, need to dc circuit breaker Failure rate carry out sensitivity analysis, to dc circuit breaker failure rate improve 1 order of magnitude, such as failure rate by 0.0061 time/ It improves in platform year to 0.061 time/platform year;The sensitivity analysis of main electrical scheme alternative is obtained as a result, as shown in table 4;
The electrical each main electrical scheme sensitivity analysis result of 4 Zhangbei County's converter station of table
Main electrical scheme alternative is obtained according to the fundamental analysis result of main electrical scheme alternative and sensitivity analysis result Reliability result: 3/2 wiring > angle scheme > double bus scheme > single bus scheme;Wherein, dc circuit breaker failure rate fluctuates not It will affect the reliability ordering of main electrical scheme alternative.
3) initial cost cost calculation is carried out to main electrical scheme alternative, as shown in table 5, obtains single bus scheme, angular connects Line initial cost level is minimum, 3/2 wiring initial cost highest;Wherein, since 500kV dc circuit breaker involves great expense, about 1.5 hundred million Member/platform, the cost of investment of predominantly breaker when electrical main connecting wire initial cost calculates;
5 main electrical scheme initial cost cost of table
The calculated result of main electrical scheme alternative annual cost is as shown in table 6, single bus scheme and double bus scheme it is reliable Property assessment result is relatively close to;The engineering initial cost of single bus scheme and angle scheme is essentially identical, therefore, connects for single busbar Line and 3/2 wiring carry out annual cost and calculate and compare, wherein engineering economy service life presses 8% by 30 years, earning rate;
6 Zhangbei County's flexible direct current power grid annual cost of table
According to engineering initial cost cost and annual cost, the economy for obtaining single bus scheme scheme is more excellent.
4) flexibility evaluation is carried out to main electrical scheme alternative, as shown in table 7, according to operational flexibility, maintenance flexibility With the comprehensive comparison of enlarging flexibility, obtain that double-bus, 3/2 connection plan flexibility are best, and single bus scheme scheme is taken second place, angle Shape connection plan is relatively poor.
7 Zhangbei County's converter station electrical main connecting wire Dexterity analysis of table
5) it according to the reliability, economy and flexibility of main electrical scheme alternative, determines and Zhangbei County stands erectly electrically master connects in flow field Line is single bus scheme scheme.
The various embodiments described above are merely to illustrate the present invention, and structure and size, setting position and the shape of each component are all can be with It is varied, based on the technical solution of the present invention, the improvement and wait that all principles according to the present invention carry out individual part With transformation, should not exclude except protection scope of the present invention.

Claims (10)

1. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire, which is characterized in that it the following steps are included:
1) it according to main electrical scheme topological structure in pre-set each converter station DC fields electrical main connecting wire alternative and sets Standby parameter preset carries out fail-safe analysis to main electrical scheme alternative;
2) according to the cost of equipment each in main electrical scheme alternative level and quantity, the engineering for calculating main electrical scheme alternative is just thrown Money and annual cost, obtain the economy of main electrical scheme alternative;
3) standby to main electrical scheme according to the design feature of main electrical scheme alternative, power distribution equipment arrangement, relay protection and control mode Scheme is selected to carry out Dexterity analysis;
4) it according to reliability, economy and the flexibility of each converter station DC fields electrical main connecting wire alternative, determines each The scheme of converter station DC fields electrical main connecting wire;
5) according to the scheme of each converter station DC fields electrical main connecting wire, flexible direct current power grid DC fields electrical main connecting wire is obtained Scheme.
2. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as described in claim 1, it is characterised in that: In the step 1), each converter station DC fields electrical main connecting wire alternative is according to the function of each converter station and soft Property DC grid planning setting.
3. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as claimed in claim 2, it is characterised in that: Each converter station DC fields electrical main connecting wire alternative includes single bus scheme, double bus scheme, angle scheme and 3/2 Wiring.
4. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as described in claim 1, it is characterised in that: In the step 1), carrying out fail-safe analysis to main electrical scheme alternative, specific step is as follows:
Trouble correlation analytic is carried out according to the structure of main electrical scheme alternative, obtains the common mode idle time of each equipment component;
According to the dependability parameter of equipment each in main electrical scheme alternative, the fundamental analysis result of main electrical scheme alternative is obtained;
Sensitivity analysis is carried out to equipment previously selected in main electrical scheme alternative, according to the responsive parameter of selected equipment, Obtain the sensitivity analysis result of main electrical scheme alternative;
According to the fundamental analysis result of main electrical scheme alternative and sensitivity analysis as a result, obtaining the reliable of main electrical scheme alternative Property.
5. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as claimed in claim 4, it is characterised in that: The dependability parameter of each equipment includes failure rate, mean repair time, maintenance rate and repair time;The fundamental analysis knot Fruit include system blackout failure rate, System average interruption duration, availability, power failure probability, have a power failure average time, power failure frequency, Lose electric energy and annual operating cost.
6. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as described in claim 1, it is characterised in that: In the step 3), the flexibility of main electrical scheme alternative is made of operational flexibility, maintenance flexibility and enlarging flexibility.
7. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as claimed in claim 6, it is characterised in that: According to main electrical scheme alternative in management and running, the flexibility ratio of investment and excision generator and load determines that main electrical scheme is standby Select the operational flexibility of scheme.
8. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as claimed in claim 6, it is characterised in that: When carrying out safety inspection according to stoppage in transit breaker, bus and the relay protection device to main electrical scheme alternative, cause to power grid The influence of operation and power supply, determines the maintenance flexibility of main electrical scheme alternative.
9. a kind of method of determining flexible direct current power grid DC fields electrical main connecting wire as claimed in claim 6, it is characterised in that: According to the workload of main electrical scheme alternative later period enlarging and to the influence of system power supply, the expansion of main electrical scheme alternative is determined Build flexibility.
10. a kind of system of determining flexible direct current power grid DC fields electrical main connecting wire, it is characterised in that: it include memory module, Fail-safe analysis module, economy module, Dexterity analysis module and Main Wire Connection Scheme module;The memory module is for storing Pre-set each converter station DC fields electrical main connecting wire alternative;The fail-safe analysis module is used for basis and sets in advance Main electrical scheme topological structure and the parameter preset of equipment in each converter station DC fields electrical main connecting wire alternative set, to master Wiring alternative carries out fail-safe analysis, and the economy module is used for the cost according to equipment each in main electrical scheme alternative Horizontal and quantity obtains the economy of main electrical scheme alternative, and the Dexterity analysis module is used for according to main electrical scheme alternative Design feature, power distribution equipment arrangement, relay protection and control mode Dexterity analysis is carried out to main electrical scheme alternative;It is described Main Wire Connection Scheme module is used for reliability, economy and flexibility according to each converter substation scheme's alternative, determines each The scheme of a converter station DC fields electrical main connecting wire, and according to the scheme of each converter station DC fields electrical main connecting wire, it obtains soft The scheme of property DC grid DC fields electrical main connecting wire.
CN201610893959.1A 2016-10-13 2016-10-13 A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire Active CN106451518B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610893959.1A CN106451518B (en) 2016-10-13 2016-10-13 A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610893959.1A CN106451518B (en) 2016-10-13 2016-10-13 A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire

Publications (2)

Publication Number Publication Date
CN106451518A CN106451518A (en) 2017-02-22
CN106451518B true CN106451518B (en) 2019-03-08

Family

ID=58173912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610893959.1A Active CN106451518B (en) 2016-10-13 2016-10-13 A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire

Country Status (1)

Country Link
CN (1) CN106451518B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109347134B (en) * 2018-11-09 2021-10-22 国家电网有限公司 Bipolar flexible direct-current power grid polar line electric main wiring system and online maintenance method
CN113922671B (en) * 2021-10-21 2023-07-21 国网经济技术研究院有限公司 Three-port flexible direct-current transmission DC-DC converter and control method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103227468A (en) * 2013-04-25 2013-07-31 国家电网公司 Main wiring pairing and stringing optimization method for transformer station

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3259839B1 (en) * 2015-04-02 2021-09-29 Siemens Energy Global GmbH & Co. KG Converter arrangement and method for short-circuit protection thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103227468A (en) * 2013-04-25 2013-07-31 国家电网公司 Main wiring pairing and stringing optimization method for transformer station

Also Published As

Publication number Publication date
CN106451518A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
Okba et al. High voltage direct current transmission-A review, part I
US20130015703A1 (en) Microgrid
CN103746404B (en) A kind of honourable fiery bundling direct current delivery system method for estimating stability
Majumder et al. Magic bus: High-voltage DC on the new power transmission highway
CN103997046A (en) Switching control method of energy storage unit of box-type energy storage substation
CN104009452A (en) Protection scheme for direct current distribution system short-circuit fault
WO2021189754A1 (en) Offshore wind power dc transmission system employing two connected transformers, and control method therefor
CN103996986A (en) Box type energy storage transformer substation structure
CN103606107A (en) Wind power-solar power-energy storage combined power generation system equipment state assessment information system
CN111342455B (en) Method for converting 10kV line ring network into power supply
CN106451518B (en) A kind of method and system of determining flexible direct current power grid DC fields electrical main connecting wire
CN104332999A (en) Automatic main grid power supply transferring strategy generation method for regional power grid
CN106356905A (en) Alternating-current and direct-current double-bus controllable power transmission system
CN105743121A (en) Direct grid connected type photovoltaic power station circuit topological structure
CN103532224A (en) Method for configuring UPS (uninterrupted power supply) in offshore wind plant
Zhou et al. An overview on distribution automation system
CN102496075B (en) A kind of online data integration method based on internal memory
CN107508314B (en) Distributed photovoltaic protection system and protection method
Quevedo et al. Smart distribution transformer applied to Smart Grids
CN102185372B (en) Method and device for generating backup automatic switchover control model based on EMS (energy management system)
CN103258301A (en) Power supply reliability evaluating method applicable to county power grid
CN107565521B (en) Method for clearing short-circuit fault on direct current side of flexible direct current power grid
CN108565858A (en) Mixing alternating current-direct current distribution network reliability evaluation method containing flexible substation
CN113659699A (en) Emergency power supply intelligent control method and system for base station
Stein et al. Enel's large scale demonstration project inside GRID4EU: the challenge of RES integration in the MV network

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant