CN106451424B - The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic - Google Patents

The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic Download PDF

Info

Publication number
CN106451424B
CN106451424B CN201610882429.7A CN201610882429A CN106451424B CN 106451424 B CN106451424 B CN 106451424B CN 201610882429 A CN201610882429 A CN 201610882429A CN 106451424 B CN106451424 B CN 106451424B
Authority
CN
China
Prior art keywords
photovoltaic
power
cost
curve
transmission network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610882429.7A
Other languages
Chinese (zh)
Other versions
CN106451424A (en
Inventor
范宏
左路浩
高绘彦
马莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai University of Electric Power
Original Assignee
Shanghai University of Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai University of Electric Power filed Critical Shanghai University of Electric Power
Priority to CN201610882429.7A priority Critical patent/CN106451424B/en
Publication of CN106451424A publication Critical patent/CN106451424A/en
Application granted granted Critical
Publication of CN106451424B publication Critical patent/CN106451424B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/30Circuit design
    • G06F30/36Circuit design at the analogue level
    • G06F30/367Design verification, e.g. using simulation, simulation program with integrated circuit emphasis [SPICE], direct methods or relaxation methods
    • H02J3/385
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/10Photovoltaic [PV]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Power Engineering (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of power transmission network stochastic programming methods of electricity generation grid-connecting containing large-scale photovoltaic, according to real-time lighting intensity and ambient temperature data, simulate the power curve in large-sized photovoltaic power station, consider the randomness of photovoltaic power output, fluctuation, it is theoretical based on equivalent energy function method and stochastic programming, construct the mathematical model of the power transmission network random expected value bi-level programming of the electricity generation grid-connecting containing large-scale photovoltaic, reasonable hybrid algorithm is designed according to self-adapted genetic algorithm and primal-dual interior method, plan model is effectively solved, obtain optimum programming scheme, meet the demand of the power grid stochastic programming to generate electricity containing large-scale photovoltaic, it is clear with logical construction, practical reasonable advantage.This method is agreed at this stage and the development trend of the following large-scale photovoltaic can be widely applied in the electric system stochastic programming simulation calculating of large-scale photovoltaic power generation with very strong theoretical property and practicability.

Description

The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic
Technical field
The present invention relates to a kind of transmission of electricity network technology, in particular to the power transmission network of a kind of electricity generation grid-connecting containing large-scale photovoltaic is random Planing method.
Background technique
With rapid economic development, energy and environmental problem has become world today's focus of interest.Coal, petroleum, The demand of the energy such as natural gas is growing day by day, but these energy are non-renewable, and can cause to environment sternly during utilization Heavily contaminated, also increasing for influencing caused by social sound development and stabilization, solar energy is a kind of clean renewable Severe situation and the environmental pollution of energy shortages can be effectively relieved in the energy, the photovoltaic power generation technology converted solar energy into electrical energy Pressure.
Under the support of national governments' policy, by years of researches, nowadays photovoltaic power generation have become one more at Ripe new energy power generation technology, photovoltaic electric energy is gradually from the supplement energy to alternative energy source transition, and wherein photovoltaic plant is big Type scale is even more the developing direction and research emphasis become from now on.With shared by photovoltaic power generation in the power system installed capacity Than increasing, the extensive concentration exploitation of photovoltaic power generation can generate electric system certain influence.Photovoltaic is contributed not Certainty also influences whether Electric Power Network Planning.
Using stochastic programming theory power planning research field latest development, to grid type centralized photovoltaic on a large scale Electricity generation system and power network expansion planning method are studied, and the uncertain factor of analyzing influence photovoltaic power output is established extensive Centralized photovoltaic power output model simulates the electric power containing photovoltaic plant using suitable method then in conjunction with Operation of Electric Systems feature System random walk establishes the power grid random expected value plan model to generate electricity containing large-scale photovoltaic in conjunction with stochastic programming theory Electric Power Network Planning is carried out, is fully considered since the uncertain bring of photovoltaic power output influences, to obtain suitable Electric Power Network Planning side Case.
Summary of the invention
Influence problem the present invention be directed to Solar use to Electric Power Network Planning from now on proposes a kind of containing large-scale photovoltaic The power transmission network stochastic programming method of electricity generation grid-connecting considers randomness, the wave of photovoltaic power output by simulating the power output of large-scale photovoltaic Dynamic property, theoretical based on equivalent energy function method and stochastic programming, the power transmission network of building electricity generation grid-connecting containing large-scale photovoltaic is advised at random The mathematical model drawn effectively solves plan model by the reasonable hybrid algorithm of modern optimization Theoretical Design.
The technical solution of the present invention is as follows: a kind of power transmission network stochastic programming method of electricity generation grid-connecting containing large-scale photovoltaic, specifically Include the following steps:
1) according to real-time lighting intensity and ambient temperature data, the timing power curve in large-sized photovoltaic power station is simulated:
2) it on the basis of the timing power curve of the photovoltaic plant obtained by step 1), in conjunction with the supplemental characteristic of actual electric network, obtains To the net load curve for removing photovoltaic power output, initial equivalent electric quantity function is formed, is calculated based on equivalent energy function method and determines light The maximum size of volt power generation in the power system;
3) the upper layer model of power transmission network random expected value bilevel programming model is with the minimum target of total cost desired value, packet Include newly-increased route, electric generation investment construction cost, operation and maintenance cost, supply interruption cost and cutting load rejection penalty desired value;Lower layer Model is with the minimum target of cutting load rejection penalty under N safe operating conditions, N-1 safe operating conditions;According to random expectation It is worth Two-Hierarchical Programming Theory and Transmission Expansion Planning in Electric constraint condition, establishes the power transmission network random expected value bi-level programming containing large-scale photovoltaic Model;
4) upper layer carries out global optimizing using self-adapted genetic algorithm, generates optimization rack, obtains construction cost, then pass through Dry run obtain operation and maintenance cost, environmental costs, short of electricity amount expense desired value, lower layer utilize primal-dual interior method Cutting load rejection penalty is calculated, upper layer is fed back to and obtains the total cost of optimization aim, optimal rack knot is obtained by iteration convergence Structure.
According to real-time lighting intensity and ambient temperature data in the step 1), the timing for simulating large-sized photovoltaic power station goes out Force curve, wherein the power output model in large-sized photovoltaic power station are as follows:
PPV=η Pmaxηmpptηinv
η=ηref[1-ε(Ta-Tref)]
In formula, PPVFor photovoltaic plant real output, PmaxFor photovoltaic plant MPPT maximum power point tracking control under most Big output power, η are the efficiency of photovoltaic module, ηmpptFor the efficiency of MPPT control assembly, ηinvFor the efficiency of inverter, ηrefFor Photovoltaic module efficiency under reference temperature, ε are photovoltaic module temperature coefficient, are taken as 0.003~0.005, TaFor real time environment temperature Degree, TrefFor reference temperature, 25 DEG C are taken.
Specific step is as follows for the step 2):
A, it is added the timing power curve of resulting photovoltaic power generation as negative load with timing load curve, by photovoltaic Timing power curve separated from timing load curve, obtain net load curve;
B, it being formed according to net load curve using load as horizontal axis, load duration is the equivalent load curve of the longitudinal axis, Step-length is chosen according to conventional power unit capacity, is ranked up conventional power unit according to cost of electricity-generating, by equivalent load curve and combination Conventional power unit capacity and corresponding forced outage rate combine, and form initial equivalent electric quantity function, and each unit is successively arranged to run, Calculate its generated energy;
C, according to equivalent energy function method, new equivalent load curve is formed in the case where having arranged previous unit, Equivalent electric quantity function is corrected according to the capacity of remaining conventional power unit and corresponding forced outage rate, and checks whether all units arrange It finishes, if not provided, going to step B, if all arranging to finish, according to the sequence arranged properly, calculates overall running cost;
D, the specific gravity of photovoltaic capacity in systems is adjusted, the system production cost and each index in a variety of situations are calculated, Obtain the theoretical upper limit of photovoltaic capacity accounting.
The beneficial effects of the present invention are: the power transmission network stochastic programming method of present invention electricity generation grid-connecting containing large-scale photovoltaic, Randomness, the fluctuation for considering photovoltaic power output, theoretical based on equivalent energy function method and stochastic programming, building contains large-scale photovoltaic The mathematical model of the power transmission network random expected value bi-level programming of electricity generation grid-connecting, according in self-adapted genetic algorithm and original-antithesis Point method designs reasonable hybrid algorithm, is effectively solved to plan model, obtains optimum programming scheme, meets and contains extensive light The demand for lying prostrate the power grid stochastic programming of power generation, has the advantages that logical construction is clear, practical reasonable.
Detailed description of the invention
Fig. 1 is the power transmission network stochastic programming method flow diagram of the electricity generation grid-connecting of the invention containing large-scale photovoltaic;
Fig. 2 is the electric diagram of the embodiment of the present invention;
Fig. 3 is one figure of production graph of simulation results of the embodiment of the present invention;
Fig. 4 is two figure of production graph of simulation results of the embodiment of the present invention;
Fig. 5 is the process of hybrid algorithm in the power transmission network stochastic programming method of the electricity generation grid-connecting of the invention containing large-scale photovoltaic Figure;
Fig. 6 is the optimum programming result electric diagram of the embodiment of the present invention.
Specific embodiment
The power transmission network stochastic programming method flow diagram of the electricity generation grid-connecting containing large-scale photovoltaic as shown in Figure 1, specifically includes following Step:
S1 simulates the power curve in large-sized photovoltaic power station according to real-time lighting intensity and ambient temperature data;
The supplemental characteristic of S2 combination actual electric network is calculated based on equivalent energy function method and determines photovoltaic power generation in electric system In maximum size;
S3 is established according to random expected value Two-Hierarchical Programming Theory and Transmission Expansion Planning in Electric constraint condition containing the defeated of large-scale photovoltaic Power grid random expected value bilevel programming model;
S4 is obtained according to model feature using the hybrid algorithm solving model of improved adaptive GA-IAGA and primal-dual interior method Optimum programming scheme.
According to real-time lighting intensity and ambient temperature data in step S1, the timing power output for simulating large-sized photovoltaic power station is bent Line, wherein the power output model in large-sized photovoltaic power station are as follows:
PPV=η Pmaxηmpptηinv
η=ηref[1-ε(Ta-Tref)]
In formula, PPVFor photovoltaic plant real output, PmaxIt is controlled for photovoltaic plant in MPPT (MPPT maximum power point tracking) Under peak power output, η be photovoltaic module efficiency, ηmpptFor the efficiency of MPPT control assembly, ηinvFor the effect of inverter Rate, ηrefFor the photovoltaic module efficiency under reference temperature, ε is photovoltaic module temperature coefficient, is generally taken as 0.003~0.005, Ta For real time environment temperature, TrefFor reference temperature, 25 DEG C are taken.
PmaxValue it is related with the U-I characteristic of photovoltaic, mathematical model is shown below:
In formula, I, U are respectively the output electric current and voltage of single photovoltaic cell;C1、C2For intermediate variable, need according to light Variation according to intensity and environment temperature is constantly modified;IscFor short circuit current, UocFor open-circuit voltage.Because solar irradiation is strong It is continually changing for spending with environment temperature, therefore C in U-I mathematical model1、C2Update equation be shown below:
In formula, ImFor maximum power point electric current, UmFor maximum power point voltage.Isc、Uoc、Im、UmFor photovoltaic cell technology ginseng Numerical value, it is related with illumination variation and variation of ambient temperature.The present embodiment takes respectively referring to the technical parameter of monocrystalline Silicon photrouics Optimum operating voltage Um=17.1V, open-circuit voltage Uoc=22V, recommended current Im=3.5A, open-circuit current Isc=3.8V. The update equation of photovoltaic cell technical parameter is shown below in the present embodiment:
X=R/60 × 697.33
K=X/Xref
Tc(t)=Ta(t)+gR
Δ T=Tc(t)-Tref
I'm=Imk(1+aΔT+bX)
I′sc=Isck(1+aΔT+bX)
U'm=Um(k+c)(1-dΔT-eX)
U'oc=Uoc(k+c)(1-dΔT-eX)
In formula, R is any intensity of solar radiation, unit mWcm2, XrefFor standard intensity of illumination 1000W/m2, X is monthly The real-time lighting intensity of typical day, k are the ratio of real-time lighting intensity and standard intensity of illumination;TrefFor reference temperature, it is taken as 25 DEG C, TcFor the temperature of photovoltaic module, TaFor the environment temperature in photovoltaic module location, Tmax、TminFor the temperature maximum value of typical day And minimum value, tpAt the time of for one day, the highest temperature occurred, it is considered that be 14:00, g is illumination temperature coefficient, takes 0.03 DEG C m2/W;Isc’、Uoc’、Im’、Um' it is Isc、Uoc、Im、UmDifferent illumination intensity and at a temperature of correction value, a, b, c, d, e are normal Number, representative value are a=0.0025/ DEG C, b=7.5e-5m2/ W, c=0.5, d=0.0028/ DEG C, e=8.4e-5m2/W。
The supplemental characteristic that actual electric network is combined in step S2 is calculated based on equivalent energy function method and determines photovoltaic power generation in electricity Maximum size in Force system, specific steps are as follows:
1, using the timing power curve of photovoltaic power generation obtained in step S1 as negative load and timing load curve phase Add, the timing power curve of photovoltaic is separated from timing load curve, obtains net load curve;Timing load curve is same Loads all in electric system are added the curve changed over time to the characterization load generated by one time point;
2, it being formed according to net load curve using load as horizontal axis, load duration is the equivalent load curve of the longitudinal axis, Suitable step-length is chosen according to conventional power unit capacity, is ranked up conventional power unit according to cost of electricity-generating, by equivalent load curve It is combined with combination conventional power unit capacity and corresponding forced outage rate, forms initial equivalent electric quantity function, successively arrange each machine Group operation, calculates its generated energy;
3, according to equivalent energy function method (equivalent energy function method in calculating can according to calculate step correct automatically, this A is the core methed of equivalent energy function method), new equivalent load curve is formed in the case where having arranged previous unit, Equivalent electric quantity function is corrected according to the capacity of remaining conventional power unit and corresponding forced outage rate, and checks whether all units arrange It finishes, if not provided, going to step 2, if all arranging to finish, according to the sequence arranged properly, calculates overall running cost;
4, the specific gravity of photovoltaic capacity in systems is adjusted, the system production cost and each index in a variety of situations are calculated, Obtain the theoretical upper limit of photovoltaic capacity accounting.
Fig. 2 is the electric diagram of the present embodiment, and G indicates that conventional power unit, Bus indicate node bus, Synch.Cond. in figure (synchronous condenser) indicates phase modifier, the total producing cost C of the electric systemtotalIncluding fuel cost Cfuel、 Operation and maintenance cost CO&M, average short of electricity making up price CUEC, environmental costs Cenvi, it may be assumed that
Ctotal=Cfuel+CO&M+CUEC+Cenvi
In formula: Cfuel,iFor the fuel cost of i-th unit unit generated energy;CO&M, iFor i-th unit unit generated energy Operation and maintenance cost;EENS is system loss of energy expectation;Cenvi,iFor the environmental costs of i-th unit unit generated energy, it is Altogether there is n platform unit generation.For photovoltaic plant, fuel is not consumed, does not discharge exhaust gas, therefore its fuel cost, ring Border expense is all 0.
In embodiment, original installed capacity is constant in system, and photovoltaic capacity accounts for the ratio point of system total installation of generating capacity It Wei 0,5%, 10%, 15%, 20%, 30%, 40%, 50%, 60%, 70%, 80%.Analog result is as shown in Figure 3,4, figure 3 indicate the situation of change with increase the two indexs of EENS and LOLP of photovoltaic plant capacity in system, wherein LOLP is indicated The loss of load probability (electric system proper noun) of system, Fig. 4 indicate the increase with photovoltaic plant capacity in system, system The middle relationship for abandoning light rate and total cost, complex chart 3 and Fig. 4 are reduced to dissolve photovoltaic power generation as far as possible and are abandoned light rate, and protect The operational reliability of card system, photovoltaic capacity should be no more than the 50% of total capacity in system.
According to random expected value Two-Hierarchical Programming Theory and Transmission Expansion Planning in Electric constraint condition in step S3, establishes and contain extensive light The power transmission network random expected value bilevel programming model of volt, wherein power transmission network random expected value bilevel programming model in the present embodiment Upper layer model be including newly-increased route, electric generation investment construction cost, operation and maintenance expense with the minimum target of total cost desired value With, supply interruption cost and cutting load rejection penalty desired value;Underlying model is under N safe operating conditions, N-1 safe operating conditions The minimum target of cutting load rejection penalty.
Upper layer model are as follows:
Min E [S]=E [Sinv]+E[Soper]
In formula, S is system total cost, SinvTo increase route, electric generation investment construction cost, S newlyoperThe fortune returned for lower layer Row, maintenance and load-shedding cost;ClFor transmission line of electricity specific investment cost expense, 1,300,000 yuan/km is taken;Nl-ijFor the planning of node i to j The number of lines,Nl-ij Respectively its maximin, Pl-ijFor the rated capacity of route, PijFor route Real-time Power Flow;Cpv For the specific investment cost expense of photovoltaic plant, 6,500,000 yuan/MW, P are takenN.pviFor the planned capacity value of node i photovoltaic plant;OCGiFor The unit operating cost of node i thermal power generation unit, PGiFor the power output of node i thermal power generation unit,PGi For node i firepower hair The power output lower limit of motor group,For the power output upper limit of node i thermal power generation unit;OCpviIt is transported for the unit of node i photovoltaic plant Row expense, PpviFor the power output of node i photovoltaic plant,PPVi For the power output lower limit of node i photovoltaic plant,For node i photovoltaic electric The power output upper limit stood;F is lower layer's cutting load rejection penalty,For cutting load desired value, PCiFor the cutting load amount in node i, PDi For the load in node i, B is the admittance matrix of system rack, and θ is node voltage phase angle matrix, UOC (Unit Outage Cost it is) unit outage cost cost, takes 19.5 yuan/kWh, EENSiEach node expected loss of energy during for research,For its upper limit.
Underlying model are as follows:
Min F=fN+fN-1
s.t.
hN(x, y)=0
hN-1(x, y)=0
In formula, F is lower layer's cutting load rejection penalty, fNFor the cutting load rejection penalty under N safe operating conditions, fN-1For Cutting load rejection penalty under N-1 safe operating conditions;hN(x, y)=0 is the equality constraint under N safe operating conditions, hN-1 (x, y)=0 is the equality constraint under N-1 safe operating conditions;For differing under N safe operating conditions Formula constraint,gN For gNThe minimum value and maximum value of (x, y),For under N-1 safe operating conditions Inequality constraints,gN-1 For gN-1The minimum value and maximum value of (x, y);X is state variable, including admittance matrix, node Injecting power, generator output bound, route rated capacity, y are decision variable, including cutting load amount, node voltage phase angle, Line Flow.
Mould is solved using the hybrid algorithm of improved adaptive GA-IAGA and primal-dual interior method according to model feature in step S4 Type obtains optimum programming scheme, wherein upper layer carries out global optimizing using improved adaptive GA-IAGA, generates optimization rack, is built If expense, then by dry run obtain operation and maintenance cost, environmental costs, short of electricity amount expense desired value, lower layer is using former Beginning-dual interior point calculates cutting load rejection penalty, feeds back to upper layer and obtains the total cost of optimization aim, is obtained by iteration convergence To optimal grid structure.
The constraint of lower layer's cutting load uses primal-dual interior method in the present embodiment, and upper layer uses improved adaptive GA-IAGA, Fig. 5 For the flow chart of the present embodiment hybrid algorithm, specific steps are as follows:
Step 1: input parameter, generates initial population, which includes M sample, and sample is initial individuals, and individual exists The Transmission Expansion Planning in Electric scheme generated is specifically indicated in system, each sample carries out under N safe operation, N-1 safe operating conditions Cutting load amount desired value calculates, line construction expense calculates and production simulation expense calculates, and acquires the total cost of each individual Desired value;
Step 2: being arranged from big to small according to total cost desired value, m individual before memory, and carries out network connectivty and repair Just and total cost desired value calculates, and re-starts sequence;
Step 3: carrying out crossover operation to randomly selected 2 Different Individuals, if 2 individuals are identical, individual is carried out inverse Turn operation;
Step 4: network connectivty amendment and the calculating of total cost desired value are carried out to new individual, if the new individual total cost phase Prestige value is then replaced former individual, otherwise, is not replaced better than former individual;
Step 5: random picking individual carries out mutation operation;
Step 6: network connectivty amendment and the calculating of total cost desired value are carried out to new individual, if the new individual total cost phase Prestige value then replaces former individual better than former individual, is otherwise again carried out benefit to the individual and calculates operation;
Step 7: network connectivty amendment and the calculating of total cost desired value are carried out to new individual, if the new individual total cost phase Prestige value is then replaced former individual, otherwise, is not replaced better than former individual;
Step 8: checking whether that satisfaction terminates the number of iterations condition, if not satisfied, continuing third step operation;If satisfied, eventually Only iteration exports result sample.
Step 9: being arranged from small to large respectively according to load-shedding cost desired value, line construction expense and total cost desired value Sequence exports the optimal case of each result.
Wherein, the improved adaptive GA-IAGA of the present embodiment uses self-adapted genetic algorithm, crossover probability and mutation probability energy It is enough to be changed automatically according to fitness.The algorithm and upper layer models coupling, firstly generate a certain number of initial plan schemes, i.e., and the Sample described in one step calculates the fitness of these samples then in conjunction with underlying model, then counts compared with average fitness The crossover probability and mutation probability for intersecting individual and variation individual (i.e. Transmission Expansion Planning in Electric scheme) are calculated, is finally meeting the number of iterations Optimum individual, i.e. optimum programming scheme are exported after condition.Crossover probability P in self-adapted genetic algorithmcWith mutation probability PmMeter It is as follows to calculate formula:
In formula, fmaxFor fitness value maximum in group, favgFor the average fitness value of per generation group, f ' is to intersect Two individuals in biggish fitness value, f is the fitness value for wanting variation individual, k1、k2、k3And k4For constant.Wherein, group Body refers to all Transmission Expansion Planning in Electric schemes that made a variation and be intersected, and individual refers to single Transmission Expansion Planning in Electric scheme.
In the present embodiment, the newly-increased photovoltaic capacity of node 1,9,13,24 is 40,100,100,60MW, node 9,13,23, 24 load increases to 255,345,50,40MW, is obtained according to above-mentioned random expected value bilevel programming model and hybrid algorithm process The optimum programming scheme arrived is as shown in Figure 6.

Claims (2)

1. a kind of power transmission network stochastic programming method of electricity generation grid-connecting containing large-scale photovoltaic, specifically comprises the following steps:
1) according to real-time lighting intensity and ambient temperature data, the timing power curve in large-sized photovoltaic power station is simulated:
2) it on the basis of the timing power curve of the photovoltaic plant obtained by step 1), in conjunction with the supplemental characteristic of actual electric network, is removed The net load curve for going photovoltaic to contribute, forms initial equivalent electric quantity function, is calculated based on equivalent energy function method and determines photovoltaic hair The maximum size of electricity in the power system;
3) the upper layer model of power transmission network random expected value bilevel programming model be with the minimum target of total cost desired value, including it is new Increase route, electric generation investment construction cost, operation and maintenance cost, supply interruption cost and cutting load rejection penalty desired value;Underlying model It is with the minimum target of cutting load rejection penalty under N safe operating conditions, N-1 safe operating conditions;According to random expected value two Layer planning theory and Transmission Expansion Planning in Electric constraint condition establish the power transmission network random expected value bi-level programming mould containing large-scale photovoltaic Type;
4) upper layer carries out global optimizing using self-adapted genetic algorithm, generates optimization rack, obtains construction cost, then pass through simulation Operation obtain operation and maintenance cost, environmental costs, short of electricity amount expense desired value, lower layer using primal-dual interior method calculating Cutting load rejection penalty, feeds back to upper layer and obtains the total cost of optimization aim, obtains optimal grid structure by iteration convergence;
It is characterized in that, simulating large-sized photovoltaic power station according to real-time lighting intensity and ambient temperature data in the step 1) Timing power curve, the wherein power output model in large-sized photovoltaic power station are as follows:
PPV=η Pmaxηmpptηinv
η=ηref[1-ε(Ta-Tref)]
In formula, PPVFor photovoltaic plant real output, PmaxIt is defeated for maximum of the photovoltaic plant under MPPT maximum power point tracking control Power out, η are the efficiency of photovoltaic module, ηmpptFor the efficiency of MPPT control assembly, ηinvFor the efficiency of inverter, ηrefFor reference At a temperature of photovoltaic module efficiency, ε be photovoltaic module temperature coefficient, be taken as 0.003~0.005, TaFor real time environment temperature, TrefFor reference temperature, 25 DEG C are taken.
2. the power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic according to claim 1, which is characterized in that institute Stating step 2), specific step is as follows:
A, the timing power curve of resulting photovoltaic power generation is subtracted each other with timing load curve, by the timing power curve of photovoltaic from It is separated in timing load curve, obtains net load curve;
B, it being formed according to net load curve using load as horizontal axis, load duration is the equivalent load curve of the longitudinal axis, according to Conventional power unit capacity chooses step-length, is ranked up conventional power unit according to cost of electricity-generating, by equivalent load curve and combines conventional Unit capacity and corresponding forced outage rate combine, and form initial equivalent electric quantity function, and each unit is successively arranged to run, and calculate Its generated energy;
C, according to equivalent energy function method, new equivalent load curve is formed in the case where having arranged previous unit, according to The capacity of remaining conventional power unit and corresponding forced outage rate correct equivalent electric quantity function, and check whether all units have arranged Finish, if not provided, going to step B, if all arranging to finish, according to the sequence arranged properly, calculates overall running cost;
D, the specific gravity of photovoltaic capacity in systems is adjusted, the system production cost and each index in a variety of situations is calculated, obtains The theoretical upper limit of photovoltaic capacity accounting.
CN201610882429.7A 2016-10-09 2016-10-09 The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic Active CN106451424B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610882429.7A CN106451424B (en) 2016-10-09 2016-10-09 The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610882429.7A CN106451424B (en) 2016-10-09 2016-10-09 The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic

Publications (2)

Publication Number Publication Date
CN106451424A CN106451424A (en) 2017-02-22
CN106451424B true CN106451424B (en) 2018-12-14

Family

ID=58172016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610882429.7A Active CN106451424B (en) 2016-10-09 2016-10-09 The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic

Country Status (1)

Country Link
CN (1) CN106451424B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107169607B (en) * 2017-05-27 2020-12-22 上海电力学院 Energy efficiency power plant optimization configuration and plant network coordination planning method based on cost
CN107147152B (en) * 2017-06-15 2019-12-10 广东工业大学 new energy power distribution network multi-type active and reactive power source collaborative optimization configuration method and system
CN109325608B (en) * 2018-06-01 2022-04-01 国网上海市电力公司 Distributed power supply optimal configuration method considering energy storage and considering photovoltaic randomness
CN109586279B (en) * 2018-11-20 2022-03-25 国网新疆电力有限公司经济技术研究院 Interconnected power grid planning method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103530473A (en) * 2013-10-25 2014-01-22 国家电网公司 Random production analog method of electric system with large-scale photovoltaic power station

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103530473A (en) * 2013-10-25 2014-01-22 国家电网公司 Random production analog method of electric system with large-scale photovoltaic power station

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
基于虚拟分区调度和二层规划的城市配电网光伏-储能优化配置;白牧可 等;《电力自动化设备》;20160531;第36卷(第5期);141-148 *
基于随机期望值规划的输电网规划方法;范宏 等;《华东电力》;20071231;第35卷(第12期);16-21 *
考虑经济型可靠性的输电网二层规划模型及混合算法;范宏 等;《中国电机工程学报》;20080605;第28卷(第16期);第1-7页 *
计入光伏发电的电力***分时段随机生产模拟;郭旭阳 等;《电网技术》;20130630;第37卷(第6期);第1499-1505页 *

Also Published As

Publication number Publication date
CN106451424A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
Jamshidi et al. Techno-economic analysis and size optimization of an off-grid hybrid photovoltaic, fuel cell and diesel generator system
Mahmoudi et al. Optimization of a hybrid energy system with/without considering back-up system by a new technique based on fuzzy logic controller
CN102623989B (en) Method for optimization and configuration of intermittent distributed generation (DG)
CN106451424B (en) The power transmission network stochastic programming method of the electricity generation grid-connecting containing large-scale photovoltaic
CN103903073A (en) Planning method and system for optimizing micro-grid containing distributed power sources and stored energy
Castañeda et al. Sizing methods for stand-alone hybrid systems based on renewable energies and hydrogen
Song et al. Multi-objective configuration optimization for isolated microgrid with shiftable loads and mobile energy storage
CN114595868A (en) Source network and storage collaborative planning method and system for comprehensive energy system
Zhai et al. Optimal Design Method of a Hybrid CSP‐PV Plant Based on Genetic Algorithm Considering the Operation Strategy
CN112561273B (en) Active power distribution network renewable DG planning method based on improved PSO
Rouhani et al. A comprehensive method for optimum sizing of hybrid energy systems using intelligence evolutionary algorithms
CN116402210A (en) Multi-objective optimization method, system, equipment and medium for comprehensive energy system
CN115204562B (en) Multi-energy sharing-based distributed collaborative optimization scheduling method and system for interconnected micro energy networks
Коровкин Optimal reactive power dispatch in power system comprising renewable energy sources by means of a multi-objective particle swarm algorithm
CN110098623B (en) Prosumer unit control method based on intelligent load
jing Hu et al. Capacity optimization of wind/PV/storage power system based on simulated annealing-particle swarm optimization
Bao et al. Genetic algorithm based optimal capacity allocation for an independent wind/pv/diesel/battery power generation system
Zhang et al. A novel coordinated control for NZEB clusters to minimize their connected grid overvoltage risks
Amouzad Mahdiraji et al. Optimal in smart grids considering interruptible loads and photo-voltaic sources using genetic optimization
Zhao et al. Research on Multiobjective Optimal Operation Strategy for Wind‐Photovoltaic‐Hydro Complementary Power System
Abdallh et al. Efficient modeling, control and optimization of hybrid renewable-conventional energy systems
Cai et al. Two-tier coordinated optimal scheduling of wind/PV/hydropower and storage systems based on generative adversarial network scene generation
Alkano et al. Distributed MPC for Power-to-Gas facilities embedded in the energy grids
Cordero et al. Energy Control and sizing optimization of an off grid Hybrid System (Wind-Hydrokinetic-Diesel)
Mou et al. An Optimal Allocation Strategy for Multienergy Networks Based on Double‐Layer Nondominated Sorting Genetic Algorithms

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant