CN106451146A - Installation method of shock isolation device for electrical equipment - Google Patents

Installation method of shock isolation device for electrical equipment Download PDF

Info

Publication number
CN106451146A
CN106451146A CN201610862736.9A CN201610862736A CN106451146A CN 106451146 A CN106451146 A CN 106451146A CN 201610862736 A CN201610862736 A CN 201610862736A CN 106451146 A CN106451146 A CN 106451146A
Authority
CN
China
Prior art keywords
shock insulation
built
isolator
fitting
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610862736.9A
Other languages
Chinese (zh)
Inventor
张谦
程永锋
王晓宁
孙宇晗
卢智成
林森
刘振林
朱祝兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI filed Critical State Grid Corp of China SGCC
Priority to CN201610862736.9A priority Critical patent/CN106451146A/en
Publication of CN106451146A publication Critical patent/CN106451146A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B3/00Apparatus specially adapted for the manufacture, assembly, or maintenance of boards or switchgear
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/54Anti-seismic devices or installations

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention provides an installation method of a shock isolation device for electrical equipment. The method comprises the following steps: an installation step of shock isolators: connecting a plurality of shock isolators with a plurality of embedded parts; embedding the embedded parts in a prefabricated foundation, and enabling the parameters of each embedded part to meet preset requirements; and an installation step of a shock isolation support: installing the shock isolation support above each shock isolator. According to the installation method provided by the invention, the installation steps of the shock isolators and the shock isolation support are provided, the shock resistance effect of the electrical equipment is improved, the technical blank of installing the shock isolation device for the electrical equipment is filled, and the installation method plays important roles for carrying out shock-resistant field operation and guaranteeing construction safety quality in site.

Description

Power equipment earthquake isolating equipment installation method
Technical field
The present invention relates to electrical network mitigation technical field, in particular to a kind of power equipment earthquake isolating equipment installation side Method.
Background technology
Within 2015, rising, extra-high-voltage alternating current engineering has been enter into the new normality that scale is built, the inevitable warp of part engineering Cross the higher region of magnitude, such as Xi Meng~east, engineering Beijing, Shandong newly-built transformer station of 1000kV, Meng Xi~Tianjin Nan work The Cheng Jin north newly-built transformer station of 1000kV, elm horizontal stroke~newly-built transformer station of engineering Jinzhong City, Weifang 1000kV and the newly-built power transformation of Weifang 1000kV Standing, these transformer stations all propose very high requirement, wherein Weifang 1000kV newly-built substation equipment antidetonation to providing fortification against earthquakes Fortification intensity is more up to 9 degree, is the highest extra-high-voltage alternating current transformer station of antidetonation earthquake intensity up to now.
Extra-high-voltage alternating current Substation Electric Equipment height is high, interconnects, interacts, cause earthquake shadow between each equipment Ringing more complicated, the difficulty of antidetonation is bigger, it is higher to require, and currently without the installation method of power equipment earthquake isolating equipment, causes Make the anti seismic efficiency difference of power equipment.
Content of the invention
In consideration of it, the present invention proposes a kind of power equipment earthquake isolating equipment installation method, it is intended to solve there is presently no The problem of the power equipment anti seismic efficiency difference that the installation method of earthquake isolating equipment causes.
One aspect, the present invention proposes a kind of power equipment earthquake isolating equipment installation method, and the method includes walking as follows Suddenly:Multiple isolators are connected by isolator installation steps with built-in fitting;Prefabricated foundation is embedded with multiple built-in fitting, and, The parameter of each built-in fitting is satisfied by preset requirement;Shock insulation support installation steps, at the shock insulation support installed above of each isolator.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, it is characterised in that in isolator installation steps Also include before:Prefabricated foundation detecting step, whether the flatness on detection prefabricated foundation surface meets preset requirement, if discontented Foot, then process prefabricated foundation surface to reaching preset requirement.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, in isolator installation steps, each built-in fitting Parameter includes flatness, axis and absolute altitude.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, isolator installation steps farther include:The One detection sub-step, detects whether the difference in height between each isolator meets preset requirement;First sandwiched sub-step, if discontented Foot preset requirement, then sandwiched clamp between isolator and built-in fitting.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, shock insulation support installation steps farther include: Weld sub-cloth rapid, multiple shock insulation unit are carried out welding and forms shock insulation support;Coating sub-step, at the weld of each shock insulation unit Coating corrosion-inhibiting coating;Be sticked sub-step, and the weld between each shock insulation unit is sticked reinforcement steel plate.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, also include:Support member installation steps, will be every The outer rim of shake support is connected with the built-in fitting in prefabricated foundation by multiple support members.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, also include:Strengthen step, at each support member Outside is sticked reinforcement steel plate.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, also wrapped before shock insulation support installation steps Include:Stopping means installation steps, arrangement stopping means around each isolator, and, by each stopping means and prefabricated foundation In pre-buried built-in fitting be connected.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, stopping means installation steps farther include: Second detection sub-step, detects whether the difference in height between each stopping means meets preset requirement;Second sandwiched sub-step, if It is unsatisfactory for preset requirement, then sandwiched clamp between stopping means and built-in fitting.
Further, in above-mentioned power equipment earthquake isolating equipment installation method, also include:Ground connection step, by shock insulation support Ground connection.
The power equipment that the present invention provides is with in earthquake isolating equipment installation method, in the present embodiment, it is proposed that earthquake isolating equipment and The installation steps of shock insulation support, improve the anti seismic efficiency of power equipment, have filled up the skill that power equipment earthquake isolating equipment is installed Art is blank, carries out antidetonation construction operation to guide field, ensures that construction safety quality has important function.
Brief description
By reading the detailed description of hereafter preferred embodiment, various other advantage and benefit common for this area Technical staff will be clear from understanding.Accompanying drawing is only used for illustrating the purpose of preferred embodiment, and is not considered as to the present invention Restriction.And it in whole accompanying drawing, is denoted by the same reference numerals identical parts.In the accompanying drawings:
The flow chart of the power equipment earthquake isolating equipment installation method that Fig. 1 provides for the embodiment of the present invention;
In the power equipment earthquake isolating equipment installation method that Fig. 2 provides for the embodiment of the present invention, the structure of earthquake isolating equipment is shown It is intended to;
In the power equipment earthquake isolating equipment installation method that Fig. 3 provides for the embodiment of the present invention, earthquake isolating equipment and shock insulation prop up The structural representation of frame;
The another flow chart of the power equipment earthquake isolating equipment installation method that Fig. 4 provides for the embodiment of the present invention;
The another flow chart of the power equipment earthquake isolating equipment installation method that Fig. 5 provides for the embodiment of the present invention;
In the power equipment earthquake isolating equipment installation method that Fig. 6 provides for the embodiment of the present invention, earthquake isolating equipment, shock insulation support Structural representation with support member;
The another flow chart of the power equipment earthquake isolating equipment installation method that Fig. 7 provides for the embodiment of the present invention;
The another flow chart of the power equipment earthquake isolating equipment installation method that Fig. 8 provides for the embodiment of the present invention;
The another flow chart of the power equipment earthquake isolating equipment installation method that Fig. 9 provides for the embodiment of the present invention.
Detailed description of the invention
It is more fully described the exemplary embodiment of the disclosure below with reference to accompanying drawings.Although accompanying drawing shows the disclosure Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure and should be by embodiments set forth here Limited.On the contrary, these embodiments are provided to be able to be best understood from the disclosure, and can be by the scope of the present disclosure Complete conveys to those skilled in the art.It should be noted that in the case of not conflicting, embodiment in the present invention and Feature in embodiment can be mutually combined.Describe the present invention below with reference to the accompanying drawings and in conjunction with the embodiments in detail.
See Fig. 1, the flow chart of the power equipment earthquake isolating equipment installation method that Fig. 1 provides for the embodiment of the present invention.As Shown in figure, the method comprises the steps:
Multiple isolators are connected by isolator installation steps S1 with built-in fitting.Prefabricated foundation is embedded with multiple pre-buried Part, and, the parameter of each built-in fitting is satisfied by preset requirement.
Specifically, see Fig. 2, prefabricated foundation 1 is embedded with multiple built-in fitting, and, before pouring basis, need inspection Survey the parameter of each built-in fitting, if parameter is unsatisfactory for preset requirement, need to process built-in fitting.Answer when isolator 2 is installed Make corresponding hoisting platform or formulate corresponding measure, it is to avoid direct mobile friction and the collision on built-in fitting of isolator 2.Isolator 2 bodies (containing annular disk, bearing, upper junction plate, lower connecting plate) and maintenance regulation metallic magnetism machined one-tenth one in the factory Overall, i.e. isolator 2, integral installation in installation process.Each isolator 2 weight is about 100kg, and hanging method uses crane 2 are lifted by crane or use removable tripod and coordinate chain block lifting isolator 2.When being embodied as, each isolator 2 with relative Built-in fitting can be connected by bolt.During installation, first take out the connecting bolt on built-in fitting, then by under isolator 2 Connecting plate is bolted on built-in fitting by take out before, and fastening torque of bolt value should meet products instruction and want Ask, operating process ensures the integral level of isolator 2.During installation, it is also noted that isolator 2 should take interim covering protection Measure, avoiding sharppointed article to stab, and, should there is fixation, to avoid isolator 2 tension.Additionally, installation process is adjusted Whole skin should be used to hammer into shape, to avoid using hard thing to impact and then to damage isolator 2.
Shock insulation support installation steps S2, at the shock insulation support installed above of each isolator.
Specifically, seeing Fig. 3, shock insulation support 3 is tackled quantity, the length of each component of composition shock insulation support 3, is hung down before installing At straight degree and erection joint, bolt orifice spacing etc. check comprehensively, check that result should meet design and require.To make in or The deformation producing in person's transport, should complete to correct in a pre-installation.The mode using lifting is positioned over shock insulation support 3 at each shock insulation Then the upper junction plate of each isolator 2 is connected by the top of device 2 with shock insulation support 3.When being embodied as, the upper company of isolator 2 Fishplate bar can be bolted with shock insulation support 3.
In the present embodiment, it is proposed that the installation steps of earthquake isolating equipment and shock insulation support, improve the antidetonation effect of power equipment Really, fill up the technological gap that power equipment earthquake isolating equipment is installed, carry out antidetonation construction operation, guarantee to guide field Construction safety quality has important function.
See Fig. 4, the another flow process of the power equipment earthquake isolating equipment installation method that Fig. 4 provides for the embodiment of the present invention Figure.As it can be seen, the method comprises the steps:
Multiple isolators are connected by isolator installation steps S1 with built-in fitting.Prefabricated foundation is embedded with multiple pre-buried Part, and, the parameter of each built-in fitting is satisfied by preset requirement.
Shock insulation support installation steps S2, at the shock insulation support installed above of each isolator.
Wherein, the specific implementation process of isolator installation steps S1 and shock insulation support installation steps S2 sees above-described embodiment , the present embodiment repeats no more again.
Before isolator installation steps S1, can also include:Prefabricated foundation detecting step S3, detects prefabricated foundation surface Flatness whether meet preset requirement, if be unsatisfactory for, then process prefabricated foundation surface to reaching preset requirement.
Specifically, owing to the seismic fortification intensity of power equipment is high, accordingly, it would be desirable to according to drawing requirement, use horizon rule, Whether the error of the surface smoothness of the detection prefabricated foundation 1 such as level meter meets preset requirement, for example, and the prefabricated foundation 1 of detection The error of preset requirement of surface smoothness be ± 1mm.If being unsatisfactory for preset requirement, then should process the table of prefabricated foundation 1 Face, for example, polish, until it reaches preset requirement.During it should be noted that be embodied as, the surface smoothness of prefabricated foundation 1 Preset requirement can determine according to actual conditions, and it is not done any restriction by the present embodiment.
In the present embodiment, by detecting the precision of fundamentals of forecasting, it is ensured that the installation accuracy of earthquake isolating equipment, and then improve The anti seismic efficiency of power equipment.It should be noted that in one embodiment of the invention, in isolator installation steps S1, The parameter of each built-in fitting can include flatness, axis and absolute altitude.
Specifically, the parameter of each built-in fitting includes flatness, axis and absolute altitude.Before prefabricated foundation 1 pours, should detect Whether the parameter of each built-in fitting meets preset requirement.When being embodied as, level meter and Sopwith staff can be used to detect each built-in fitting Whether flatness meets deviation range, and for example, the deviation range of flatness is ± 1mm, if the deviation range of being unsatisfactory for, then tackles Polish in the surface of each built-in fitting, till meeting preset requirement.Use the built-in fitting of each row of theodolite testing, each row Whether axis meets deviation range, and for example, the deviation range of axis, for less than or equal to 2mm, if the deviation range of being unsatisfactory for, then should The position of each built-in fitting is adjusted.Whether the absolute altitude using level meter and Sopwith staff to detect each built-in fitting meets deviation range, For example, the deviation range of absolute altitude is ± 1mm, if the deviation range of being unsatisfactory for, then the absolute altitude tackling each built-in fitting is adjusted, directly Meet error range to the elevation difference of each built-in fitting.During it should be noted that be embodied as, the surface smoothness of each built-in fitting, The preset requirement of axis and absolute altitude can determine according to actual conditions, and it is not done any restriction by the present embodiment.
In the present embodiment, by the parameter of each built-in fitting of detection, i.e. detect flatness, axis and the absolute altitude of each built-in fitting, Ensure that the installation accuracy of each isolator 2.
In one embodiment of the invention, isolator installation steps S1 may further include:
First detection sub-step S11, detects whether the difference in height between each isolator meets preset requirement.
Specifically, after the installation of each isolator 2, should detect whether the difference in height between each isolator 2 meets default wanting Asking, for example, the preset requirement of the difference in height between each isolator 2 is for less than or equal to 3mm.During it should be noted that be embodied as, Between each isolator 2, the preset requirement of difference in height can determine according to actual conditions, and it is not done any restriction by the present embodiment.
First sandwiched sub-step S12, if being unsatisfactory for preset requirement, then sandwiched sandwiched between isolator and built-in fitting Body.
Specifically, if the difference in height between each isolator 2 is unsatisfactory for preset requirement, then can be in the lower company of isolator 2 Sandwiched clamp between fishplate bar and built-in fitting, so that the difference in height between each isolator 2 meets preset requirement.When being embodied as, Clamp can be steel plate.
In the present embodiment, whether meet preset requirement by the difference in height between each isolator 2 of detection, and pre-to being unsatisfactory for If require isolator 2 and built-in fitting between sandwiched clamp, it is ensured that the installation accuracy of each isolator 2, so ensure that every Shake effect.
In one embodiment of the invention, shock insulation support installation steps S2 may further include:
Weld the rapid S21 of sub-cloth, multiple shock insulation unit are carried out welding and forms shock insulation support.
Specifically, see Fig. 3, owing to shock insulation support 3 volume is bigger, it has not been convenient to transport, therefore, can first make multiple shock insulation Unit.For example, each shock insulation support 3 can be divided into four shock insulation unit, and each shock insulation unit all first completes in factory.
After each shock insulation shipped to erecting bed, crane is used to lift each shock insulation unit successively, then will be each Be fastened by bolts between shock insulation unit, finally again by between each shock insulation unit docking part weld, and then formed every Shake support 3.When being embodied as, each shock insulation unit can use multiple Plate Welding to form, and each steel plate all uses Welder's font Cross section, the two-sided full weld of the elongated weld seam in the edge of a wing and web junction.During welding, face of weld all should linearly type spill, should avoid Sting the defect such as meat and arc crater, welding deformation should be prevented in addition, note rational welding sequence, it is to avoid one-shot forming, weldquality 2 grades of weld seam requirements can be met.After welding completes, crank detection test detection can be carried out with butt welded seam welding quality, so that welding Outward appearance technique reaches code requirement.
In hoisting process, first should select crane model, if shock insulation unit the heaviest in each shock insulation unit is heavily M1, Suspender weight is M2, lifting maximum distance is the mounting distance that regulating compensation becomes shock insulation unit, and operating radius is R, then crane Load is K × (M1+M2), wherein, K is safety coefficient, and when being embodied as, K can take 1.2.For example, the heaviest in each shock insulation unit Shock insulation unit heavily be 10t, suspender weight is 1t, lifting maximum distance be regulating compensation become shock insulation unit mounting distance, make Industry radius is 19.7m, then the load of crane is 13.2t.According to 130t crane performance table, 130t crane performance table may refer to table 1, farthest operating radius is 20m, and lifting weight during brachium 25.42m is 16t, and 16t is more than 13.2t, meets lifting requirements.
Table 1
After crane model selects to complete, the lifting to each shock insulation unit can use 4 colligation liftings, lifting force F1= G/4/cos60 °, wherein, G is the gravity of each shock insulation unit.Additionally, the erect-position of crane can be with the on-the-spot actual feelings of incorporation engineering Condition.
Coating sub-step S22, at the weld coating corrosion-inhibiting coating of each shock insulation unit.
Specifically, first the face of weld of shock insulation unit is processed, remove overlap.Then, between each shock insulation unit Weld and each each shock insulation unit weld anticorrosive coating of self.When being embodied as, anticorrosive coating can be first The zinc rich primer of coating preset thickness, such as 40um, it is then coated with the epoxy micaceous iron floating coating of preset thickness, such as 100um, Rear coating polyurethane enamels, such as 60um.The gross thickness of anticorrosive coat is more than or equal to presetting gross thickness, and for example presetting gross thickness is 200um.During it should be noted that be embodied as, the default gross thickness of anticorrosive coat can determine according to actual conditions, this enforcement It is not done any restriction by example.
Be sticked sub-step S23, and the weld between each shock insulation unit is sticked reinforcement steel plate.
Specifically, after the welding between each shock insulation unit completes, can be sticked reinforcement steel plate at weld.
In the present embodiment, shock insulation support 3 is divided into multiple shock insulation unit, convenient transport and lifting.Each shock insulation unit it Between weld be sticked and strengthen steel plate and strengthen the bonding strength of each shock insulation unit, meanwhile, also strengthen the rigidity of shock insulation support 3. At the weld coating corrosion-inhibiting coating of each shock insulation unit, avoiding each shock insulation unit to receive corrosion, and then ensure that shock insulation support 3 Integrality.
See Fig. 5, the another flow process of the power equipment earthquake isolating equipment installation method that Fig. 5 provides for the embodiment of the present invention Figure.As it can be seen, the method comprises the steps:
Prefabricated foundation detecting step S3, whether the flatness on detection prefabricated foundation surface meets preset requirement, if discontented Foot, then process prefabricated foundation surface to reaching preset requirement.
Multiple isolators are connected by isolator installation steps S1 with built-in fitting.Prefabricated foundation is embedded with multiple pre-buried Part, and, the parameter of each built-in fitting is satisfied by preset requirement.
Shock insulation support installation steps S2, at the shock insulation support installed above of each isolator.
Support member installation steps S4, by the outer rim of shock insulation support by multiple support members 4 and the built-in fitting in prefabricated foundation 1 It is connected.
Specifically, see Fig. 6, in order to make shock insulation support 3 position more be fixed, the outer rim of shock insulation support 3 can be passed through Multiple support members 4 are connected with the built-in fitting in prefabricated foundation 1.When being embodied as, each support member 4 can be c shaped steel.Need Bright, the specific implementation process of prefabricated foundation detecting step S3, isolator installation steps S1 and shock insulation support installation steps S2 Seeing above-described embodiment, the present embodiment repeats no more again.
In the present embodiment, by installing multiple support member 4 between the outer rim of shock insulation support 3 and built-in fitting additional so that shock insulation The position of support 3 is more fixed, and then improves isolating affection.
See Fig. 7, the another flow process of the power equipment earthquake isolating equipment installation method that Fig. 7 provides for the embodiment of the present invention Figure.As it can be seen, the method comprises the steps:
Prefabricated foundation detecting step S3, whether the flatness on detection prefabricated foundation surface meets preset requirement, if discontented Foot, then process prefabricated foundation surface to reaching preset requirement.
Multiple isolators are connected by isolator installation steps S1 with built-in fitting.Prefabricated foundation is embedded with multiple pre-buried Part, and, the parameter of each built-in fitting is satisfied by preset requirement.
Shock insulation support installation steps S2, at the shock insulation support installed above of each isolator.
Support member installation steps S4, by the outer rim of shock insulation support by multiple support members 4 and the built-in fitting in prefabricated foundation 1 It is connected.
Strengthening step S5, be sticked outside each described support member reinforcement steel plate.
Specifically, can be sticked outside each support member 4 certain thickness reinforcement steel plate, for example, the thick steel of the 1.2mm that is sticked Plate.When being embodied as, strengthen the top of steel plate and support member 4 and be sticked bolt can be used to be fixed, reinforcement steel plate and support The side of part 4 is sticked place, and at least two bolt can be used from top to bottom to be fixed.It should be noted that prefabricated foundation inspection Survey the specific implementation process of step S3, isolator installation steps S1, shock insulation support installation steps S2 and support member installation steps S4 Seeing above-described embodiment, the present embodiment repeats no more again.
In the present embodiment, be sticked outside each support member 4 strengthens the rigidity that steel plate improves each support member 4, further The position making shock insulation support 3 is more fixed, and then improves isolating affection.
See Fig. 8, the another flow process of the power equipment earthquake isolating equipment installation method that Fig. 8 provides for the embodiment of the present invention Figure.As it can be seen, the method comprises the steps:
Prefabricated foundation detecting step S3, whether the flatness on detection prefabricated foundation surface meets preset requirement, if discontented Foot, then process prefabricated foundation surface to reaching preset requirement.
Multiple isolators are connected by isolator installation steps S1 with built-in fitting.Prefabricated foundation is embedded with multiple pre-buried Part, and, the parameter of each built-in fitting is satisfied by preset requirement.
Shock insulation support installation steps S2, at the shock insulation support installed above of each isolator.
Support member installation steps S4, by the outer rim of shock insulation support by multiple support members 4 and the built-in fitting in prefabricated foundation 1 It is connected.
Strengthening step S5, be sticked outside each described support member reinforcement steel plate.
Wherein, prefabricated foundation detecting step S3, isolator installation steps S1, shock insulation support installation steps S2, support member peace The specific implementation process of dress step S4 and reinforcement step S5 sees above-described embodiment, and the present embodiment repeats no more again.
Before shock insulation support installation steps S2, can also include:Stopping means installation steps S6, in the week of each isolator Cloth puts stopping means, and, the built-in fitting that each stopping means is pre-buried with prefabricated foundation is connected.
Specifically, arrangement stopping means 5 around each isolator 2, first takes out the connecting bolt on built-in fitting, then will Each stopping means 5 is separately fixed on corresponding built-in fitting by the bolt taking out before.In installation process, it is ensured that each spacing The integral level of device 5, and avoid rubber cushion pressurized, deformation and the breakage of stopping means 5.When being embodied as, isolator installs step Rapid S1 and stopping means installation steps S6 do not have sequencing.
In the present embodiment, installation stopping means 5 around each isolator 2, also limit while to power equipment shock insulation Make the larger displacement of power equipment, it is to avoid power equipment produces larger displacement because of earthquake, further ensures electric power and sets Standby safety.
In above-described embodiment, stopping means installation steps S6 may further include:
Second detection sub-step S61, detects whether the difference in height between each stopping means meets preset requirement.
Specifically, after the installation of each stopping means 5, should detect whether the difference in height between each stopping means 5 meets pre- If requiring, for example, the difference in height between each stopping means 5 is less than or equal to 3mm.During it should be noted that be embodied as, each spacing Between device 5, the preset requirement of difference in height can determine according to actual conditions, and it is not done any restriction by the present embodiment.
Second sandwiched sub-step S62, if being unsatisfactory for preset requirement, then sandwiched between stopping means and described built-in fitting Clamp.
Specifically, if the difference in height between each stopping means 5 is unsatisfactory for preset requirement, then can be stopping means 5 He Sandwiched clamp between built-in fitting, so that the difference in height between each stopping means 5 meets preset requirement.When being embodied as, sandwiched Body can be steel plate.
In the present embodiment, whether meet preset requirement by the difference in height between each stopping means 5 of detection, and to being unsatisfactory for Sandwiched clamp between the stopping means 5 of preset requirement and built-in fitting, it is ensured that the installation accuracy of each stopping means 5, Jin Erbao Demonstrate,prove isolating affection.
See Fig. 9, the another flow process of the power equipment earthquake isolating equipment installation method that Fig. 9 provides for the embodiment of the present invention Figure.As it can be seen, the method comprises the steps:
Prefabricated foundation detecting step S3, whether the flatness on detection prefabricated foundation surface meets preset requirement, if discontented Foot, then process prefabricated foundation surface to reaching preset requirement.
Multiple isolators are connected by isolator installation steps S1 with built-in fitting.Prefabricated foundation is embedded with multiple pre-buried Part, and, the parameter of each built-in fitting is satisfied by preset requirement.
Stopping means installation steps S6, arrangement stopping means around each isolator, and, by each stopping means with pre- In system basis, pre-buried built-in fitting is connected.
Shock insulation support installation steps S2, at the shock insulation support installed above of each isolator.
Support member installation steps S4, by the outer rim of shock insulation support by multiple support members 4 and the built-in fitting in prefabricated foundation 1 It is connected.
Strengthening step S5, be sticked outside each described support member reinforcement steel plate.
Shock insulation support is grounded by ground connection step S7.
It should be noted that prefabricated foundation detecting step S3, isolator installation steps S1, stopping means installation steps S6, The specific implementation process of shock insulation support installation steps S2, support member installation steps S4 and reinforcement step S5 sees above-described embodiment and is Can, the present embodiment repeats no more again.
It in the present embodiment, is possible to prevent equipment to jeopardize personal safety because insulation damages is charged shock insulation support 3 ground connection.
In sum, in the present embodiment, it is proposed that the installation steps of earthquake isolating equipment and shock insulation support, improve power equipment Anti seismic efficiency, filled up power equipment earthquake isolating equipment install technological gap, guide field is carried out antidetonation construction Operation, guarantee construction safety quality have important function.
Obviously, those skilled in the art can carry out various change and the modification essence without deviating from the present invention to the present invention God and scope.So, if these modifications of the present invention and modification belong to the scope of the claims in the present invention and equivalent technologies thereof Within, then the present invention is also intended to comprise these changes and modification.

Claims (10)

1. a power equipment earthquake isolating equipment installation method, it is characterised in that comprise the steps:
Multiple described isolators are connected by isolator installation steps with built-in fitting;Prefabricated foundation is embedded with multiple built-in fitting, Further, the parameter of each described built-in fitting is satisfied by preset requirement;
Shock insulation support installation steps, at the shock insulation support installed above of each described isolator.
2. power equipment earthquake isolating equipment installation method according to claim 1, it is characterised in that in described isolator peace Also include before dress step:
Prefabricated foundation detecting step, whether the flatness on detection prefabricated foundation surface meeting preset requirement, if be unsatisfactory for, then locating Manage described prefabricated foundation surface to reaching preset requirement.
3. power equipment earthquake isolating equipment installation method according to claim 1, it is characterised in that described isolator is installed In step, the parameter of each described built-in fitting includes flatness, axis and absolute altitude.
4. power equipment earthquake isolating equipment installation method according to claim 1, it is characterised in that described isolator is installed Step farther includes:
First detection sub-step, whether the difference in height detecting between each described isolator meets preset requirement;
First sandwiched sub-step, if being unsatisfactory for preset requirement, then sandwiched sandwiched between described isolator and described built-in fitting Body.
5. power equipment earthquake isolating equipment installation method according to claim 1, it is characterised in that described shock insulation support is pacified Dress step farther includes:
Weld sub-cloth rapid, multiple shock insulation unit are carried out welding and forms described shock insulation support;
Coating sub-step, at the weld coating corrosion-inhibiting coating of each described shock insulation unit;
Be sticked sub-step, and the weld between each described shock insulation unit is sticked reinforcement steel plate.
6. power equipment earthquake isolating equipment installation method according to claim 1, it is characterised in that also include:
Support member installation steps, by the outer rim of described shock insulation support by multiple support members and the built-in fitting in described prefabricated foundation It is connected.
7. power equipment earthquake isolating equipment installation method according to claim 6, it is characterised in that also include:
Strengthening step, be sticked outside each described support member reinforcement steel plate.
8. power equipment earthquake isolating equipment installation method according to claim 1, it is characterised in that at described shock insulation support Also include before installation steps:
Stopping means installation steps, arrangement stopping means around each described isolator, and, by each stopping means with prefabricated Built-in fitting pre-buried in Ji Chu is connected.
9. power equipment earthquake isolating equipment installation method according to claim 8, it is characterised in that described stopping means is pacified Dress step farther includes:
Second detection sub-step, whether the difference in height detecting between each described stopping means meets preset requirement;
Second sandwiched sub-step, if being unsatisfactory for preset requirement, then sandwiched folder between described stopping means and described built-in fitting If body.
10. power equipment earthquake isolating equipment installation method according to claim 1, it is characterised in that also include:
Described shock insulation support is grounded by ground connection step.
CN201610862736.9A 2016-09-28 2016-09-28 Installation method of shock isolation device for electrical equipment Pending CN106451146A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610862736.9A CN106451146A (en) 2016-09-28 2016-09-28 Installation method of shock isolation device for electrical equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610862736.9A CN106451146A (en) 2016-09-28 2016-09-28 Installation method of shock isolation device for electrical equipment

Publications (1)

Publication Number Publication Date
CN106451146A true CN106451146A (en) 2017-02-22

Family

ID=58170114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610862736.9A Pending CN106451146A (en) 2016-09-28 2016-09-28 Installation method of shock isolation device for electrical equipment

Country Status (1)

Country Link
CN (1) CN106451146A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201146335Y (en) * 2007-11-30 2008-11-05 国网北京电力建设研究院 Shock insulation apparatus for high voltage electric installation
CN102162305A (en) * 2011-05-16 2011-08-24 江苏兴邦建工集团有限公司 Construction process for installing elastic slippage shock isolation support
CN102808518A (en) * 2011-06-01 2012-12-05 永升建设集团有限公司 Method for mounting main body vibration isolating support base
CN104376972A (en) * 2014-11-24 2015-02-25 中国电力工程顾问集团西南电力设计院 500kV transformer shock insulation structure and installation method
CN105544762A (en) * 2015-12-21 2016-05-04 广州机施建设集团有限公司 Method for installing seismic isolation layer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201146335Y (en) * 2007-11-30 2008-11-05 国网北京电力建设研究院 Shock insulation apparatus for high voltage electric installation
CN102162305A (en) * 2011-05-16 2011-08-24 江苏兴邦建工集团有限公司 Construction process for installing elastic slippage shock isolation support
CN102808518A (en) * 2011-06-01 2012-12-05 永升建设集团有限公司 Method for mounting main body vibration isolating support base
CN104376972A (en) * 2014-11-24 2015-02-25 中国电力工程顾问集团西南电力设计院 500kV transformer shock insulation structure and installation method
CN105544762A (en) * 2015-12-21 2016-05-04 广州机施建设集团有限公司 Method for installing seismic isolation layer

Similar Documents

Publication Publication Date Title
CN107012949B (en) Lifting method of large-span steel corridor
CN101967886B (en) Assembly and installation methods of steel containment vessel of nuclear power station
CN105383642B (en) A kind of vertical guide rail erecting and welding method
CN103883129B (en) A kind of steel structural roof beam installation method
CA2915584C (en) Method for constructing cylindrical tank
CN102080417B (en) Construction method for split burying of large T-shaped sleeve bolt
CN106401198A (en) Large-span steel gallery lifting equipment and construction method
CN110528891A (en) Large-span Spherical rack integral hoisting method
CN112554345A (en) Ground splicing and integral lifting construction method for large-span welding ball net rack
CN107100309A (en) A kind of construction method for the large-scale multi-angular cantilever frame of integral hoisting
CN103816983A (en) Installation construction method of large coal pulverizer
CN104420694B (en) The general installation method of benzene hydrogenation engineering tower
CN104712083A (en) Dragline tensioning method for long-span dragline glass curtain wall
CN101769076B (en) Method for lifting, hanging and installing frames of anti-vibration device for buildings
CN108775188A (en) A kind of prestressing force communication king-post and its construction method
CN207525886U (en) A kind of steel building assembles damping device
CN103953052A (en) Pile-beam-arch steel pipe column construction method
CN106451146A (en) Installation method of shock isolation device for electrical equipment
CN102767289A (en) Asymmetric and integrated lifting construction method for large scale grid structure
CN102720386A (en) Inversing method of inner side clustering hoop of vertical storage tank
CN107303941A (en) The derrick and its centering installation method of offshore drilling ship
CN206737145U (en) For installing the node of multi-storied garage steel construction
CN113323404A (en) Installation method of integrated steel truss
CN101344005B (en) Method for simultaneously mounting internal barrel and internals of deep well high pressure aeration reactor
CN206673517U (en) A kind of New type through-wall sleeve mounting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170222

RJ01 Rejection of invention patent application after publication