CN106443339A - Method for selecting wire after single-phase grounding of ungrounded system - Google Patents

Method for selecting wire after single-phase grounding of ungrounded system Download PDF

Info

Publication number
CN106443339A
CN106443339A CN201610860449.4A CN201610860449A CN106443339A CN 106443339 A CN106443339 A CN 106443339A CN 201610860449 A CN201610860449 A CN 201610860449A CN 106443339 A CN106443339 A CN 106443339A
Authority
CN
China
Prior art keywords
phase
circuit
occurs
earthing
voltage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610860449.4A
Other languages
Chinese (zh)
Inventor
许平
王剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Neng Di Electrical Technology Co Ltd
Original Assignee
Nanjing Neng Di Electrical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Neng Di Electrical Technology Co Ltd filed Critical Nanjing Neng Di Electrical Technology Co Ltd
Priority to CN201610860449.4A priority Critical patent/CN106443339A/en
Publication of CN106443339A publication Critical patent/CN106443339A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/08Locating faults in cables, transmission lines, or networks
    • G01R31/081Locating faults in cables, transmission lines, or networks according to type of conductors
    • G01R31/085Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution lines, e.g. overhead

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Emergency Protection Circuit Devices (AREA)

Abstract

The invention discloses a method for selecting a wire after single-phase grounding of an underground system. By adopting the method, after single-phase grounding happens in the ungrounded system, a fault wire can be selected according to the change of zero sequence current after a neutral point of a capacitor bank is instantly grounded. The method comprises the following steps: A, additionally installing a control switch and a medium resistor between the neutral point of a capacitor and the ground, and keeping the control switch on the point position during normal operation; B, judging whether single-phase grounding happens in a circuit or not according to the voltage change of a bus bar, and judging that single-phase grounding failure happens when the criterion is that a zero sequence voltage is more than a certain value, a certain phase voltage in three-phase voltages is reduced, and voltages of other two phases rise; C, immediately closing the control switch and putting in a resistor after single-phase grounding is judged to ensure that the grounding mode of the system is turned into grounding through the resistor and the active component of the zero sequence current of the single-phase grounded circuit is greatly increased; and D, tripping the circuit switch to clear the failure after the single-phase grounded circuit is determined.

Description

The method that isolated neutral system occurs route selection after single-phase earthing
Technical field
The present invention relates to a kind of method that isolated neutral system occurs route selection after single-phase earthing.
Background technology
In China 35kV and 10kV power system, the neutral point of transformator, adopting non_direct ground mode (small current more Earthed system), when there is singlephase earth fault in circuit, often little compared with load current many, the fault phase of the numerical value of fault current Voltage is reduced to zero, and non-faulting phase voltage rises a height of phase voltageTimes, but the line voltage between three-phase is remained in that symmetrically, to supplying Electric load does not affect, and therefore code allows to continue to run with 1~2h.But cause electric power electricity because of overvoltage in actual motion The accidents such as cable blast, TV fuse melting even burn out, busbar short-circuit, rapid determination system earth point eliminates singlephase earth fault pair The safe operation of system has highly important meaning, it is therefore desirable to research and develop a kind of new simple method to solve existing asking Topic.
Content of the invention
Present invention aim to address above-mentioned the deficiencies in the prior art and problem, provide a kind of isolated neutral system and send out The method of route selection after raw single-phase earthing, achievable isolated neutral system is instantaneously connect by capacitor bank neutral point after there is single-phase earthing Behind ground, the change of zero-sequence current is selecting fault wire.When there is singlephase earth fault, by the intervals short time in electricity Container group neutral point switching resistance completes route selection.
Technical scheme is as follows:
The method that the isolated neutral system of the present invention occurs route selection after single-phase earthing, which comprises the following steps:
A), in the transformer substation system of isolated neutral, install a control between the neutral point of capacitor and ground additional and open Close and a middle resistance, when normally running, controlling switch is in a point position;
B), circuit is determined whether according to the change of busbar voltage and single-phase earthing is there occurs, criterion is that residual voltage is big When a certain value, while certain phase voltage declines in three-phase voltage, other two-phase voltages are judged as single-phase earthing event when raising Barrier;
C after), being judged as single-phase earthing, controlling switch of closing immediately, resistance is put into, now the earthing mode of system becomes For resistance grounded, the real component that the zero-sequence current of single-phase earthing circuit occurs can be greatly increased;
D after), determining the circuit that single-phase earthing occurs, by the line switching tripping, fault is cut off.
The method that the isolated neutral system of the present invention occurs route selection after single-phase earthing, its further technical scheme be include with Lower step:
A), in the transformer substation system of isolated neutral, install a control between the neutral point of capacitor and ground additional and open Close and a resistance is 100 ohmages, when normally running, controlling switch is in a point position;
B), circuit is determined whether according to the change of busbar voltage and single-phase earthing is there occurs, criterion is that residual voltage is big In 50V, while certain phase voltage is dropped by less than 30V in three-phase voltage, when other two-phase voltages are raised more than 70V, it is judged as occurring Singlephase earth fault;
C after), being judged as single-phase earthing, controlling switch of closing immediately, resistance is put into, now the earthing mode of system becomes For resistance grounded, the real component that the zero-sequence current of single-phase earthing circuit occurs can be greatly increased;
D after), determining the circuit that single-phase earthing occurs, by the line switching tripping, fault is cut off.
The method that the isolated neutral system of the present invention occurs route selection after single-phase earthing, its further technical scheme is to work as to send out During raw singlephase earth fault, the input of controlling switch/exit for:Put into/exit each 60ms or fixing input, until sentencing Faulty line.
The invention has the advantages that:
The present invention is by being occurred after single-phase earthing zero after the capacitor bank neutral point transient earthing using isolated neutral system The change of sequence electric current is selecting fault wire, and method is simple and convenient, hence it is evident that improve fault detection efficiency, and reducing can in actual motion The fault that can occur.
Description of the drawings
Fig. 1 is system outline figure
Fig. 2 is zero-sequence current loop diagram
Specific embodiment
Embodiment 1
The method that the isolated neutral system of the present invention occurs route selection after single-phase earthing, which comprises the following steps:
A), in the transformer substation system of isolated neutral, install a control between the neutral point of capacitor and ground additional and open Close and one
Individual resistance is 100 ohmages, and when normally running, controlling switch is in a point position;
B), circuit is determined whether according to the change of busbar voltage and single-phase earthing is there occurs, criterion is that residual voltage is big In 50V, while certain phase voltage is dropped by less than 30V in three-phase voltage, when other two-phase voltages are raised more than 70V, it is judged as occurring Singlephase earth fault;
C after), being judged as single-phase earthing, controlling switch of closing immediately, resistance is put into, now the earthing mode of system becomes For resistance grounded, the real component that the zero-sequence current of single-phase earthing circuit occurs can be greatly increased;
D after), determining the circuit that single-phase earthing occurs, by the line switching tripping, fault is cut off.
When there is singlephase earth fault, the input of controlling switch/exit for:Put into/exit each 60ms
Embodiment 2
The method that the isolated neutral system of the present invention occurs route selection after single-phase earthing, which comprises the following steps:
A), in the transformer substation system of isolated neutral, install a control between the neutral point of capacitor and ground additional and open Close and a resistance is 100 ohmages, when normally running, controlling switch is in a point position;
B), circuit is determined whether according to the change of busbar voltage and single-phase earthing is there occurs, criterion is that residual voltage is big In 50V, while certain phase voltage is dropped by less than 30V in three-phase voltage, when other two-phase voltages are raised more than 70V, it is judged as occurring Singlephase earth fault;
C after), being judged as single-phase earthing, controlling switch of closing immediately, resistance is put into, now the earthing mode of system becomes For resistance grounded, the real component that the zero-sequence current of single-phase earthing circuit occurs can be greatly increased;
D after), determining the circuit that single-phase earthing occurs, by the line switching tripping, fault is cut off.
When there is singlephase earth fault, the input of controlling switch/exit for:Fixing input, until sentence the circuit that is out of order.

Claims (3)

1. a kind of method that isolated neutral system occurs route selection after single-phase earthing, it is characterised in that comprise the following steps:
A), in the transformer substation system of isolated neutral, install additional between the neutral point of capacitor and ground a controlling switch and One middle resistance, when normally running, controlling switch is in a point position;
B), circuit is determined whether according to the change of busbar voltage and single-phase earthing is there occurs, criterion is more than certain for residual voltage During one value, while certain phase voltage declines in three-phase voltage, other two-phase voltages are judged as singlephase earth fault when raising;
C after), being judged as single-phase earthing, controlling switch of closing immediately, resistance is put into, now system earthing mode become in order to Resistance grounded, the real component that the zero-sequence current of single-phase earthing circuit occurs can be greatly increased;
D after), determining the circuit that single-phase earthing occurs, by the line switching tripping, fault is cut off.
2. the method that isolated neutral system according to claim 1 occurs route selection after single-phase earthing, it is characterised in that include with Lower step:
A), in the transformer substation system of isolated neutral, install additional between the neutral point of capacitor and ground a controlling switch and When one resistance is 100 ohmages, normally to run, controlling switch is in a point position;
B), circuit is determined whether according to the change of busbar voltage and single-phase earthing is there occurs, criterion is more than for residual voltage 50V, while certain phase voltage is dropped by less than 30V in three-phase voltage, when other two-phase voltages are raised more than 70V, is judged as list Phase earth fault;
C after), being judged as single-phase earthing, controlling switch of closing immediately, resistance is put into, now system earthing mode become in order to Resistance grounded, the real component that the zero-sequence current of single-phase earthing circuit occurs can be greatly increased;
D after), determining the circuit that single-phase earthing occurs, by the line switching tripping, fault is cut off.
3. the method that isolated neutral system according to claim 1 occurs route selection after single-phase earthing, it is characterised in that work as generation During singlephase earth fault, the input of controlling switch/exit for:Put into/exit each 60ms or fixing input, until sentence event Barrier circuit.
CN201610860449.4A 2016-09-28 2016-09-28 Method for selecting wire after single-phase grounding of ungrounded system Pending CN106443339A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610860449.4A CN106443339A (en) 2016-09-28 2016-09-28 Method for selecting wire after single-phase grounding of ungrounded system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610860449.4A CN106443339A (en) 2016-09-28 2016-09-28 Method for selecting wire after single-phase grounding of ungrounded system

Publications (1)

Publication Number Publication Date
CN106443339A true CN106443339A (en) 2017-02-22

Family

ID=58170724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610860449.4A Pending CN106443339A (en) 2016-09-28 2016-09-28 Method for selecting wire after single-phase grounding of ungrounded system

Country Status (1)

Country Link
CN (1) CN106443339A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106771887A (en) * 2017-03-13 2017-05-31 安徽天电气技术股份有限公司 A kind of instantaneous zero sequence voltage drives ground fault line selection device
CN106872857A (en) * 2017-03-13 2017-06-20 安徽天电气技术股份有限公司 A kind of residual voltage drives the ground fault line selection device of zero-sequence current
CN107300656A (en) * 2017-06-17 2017-10-27 李景禄 A kind of earth fault based on power network characteristic parameter incremental starts method
CN107340416A (en) * 2017-08-28 2017-11-10 国网江西省电力公司电力科学研究院 A kind of distribution network failure indicator LC tunings are outer to apply signal source
CN108152683A (en) * 2018-01-10 2018-06-12 济南大学 Based on the earth fault line selection method for helping increasing principle
CN108614180A (en) * 2018-04-12 2018-10-02 山东钢铁股份有限公司 Singlephase earth fault circuit lookup method
CN110568316A (en) * 2019-10-16 2019-12-13 国网四川省电力公司绵阳供电公司 Method for quickly selecting line of ground fault of low-current grounding system
CN110687403A (en) * 2019-11-21 2020-01-14 济南泰景电力技术有限公司 Power distribution network single-phase earth fault detection method and device
CN111308276A (en) * 2020-04-08 2020-06-19 广东电网有限责任公司电力调度控制中心 Power distribution network fault positioning method and device
CN111880110A (en) * 2019-04-15 2020-11-03 山东大学 Single-phase earth fault disappearance judgment method and system for neutral point non-effective earthing system
CN112255573A (en) * 2020-11-20 2021-01-22 国网江苏省电力有限公司盐城供电分公司 Single-phase earth fault processing method for neutral point ungrounded system
CN112909904A (en) * 2021-03-03 2021-06-04 广东电网有限责任公司 Resistance grounding system and control method thereof
CN113725811A (en) * 2020-12-12 2021-11-30 保定钰鑫电气科技有限公司 Method for processing single-phase grounding of non-effective grounding system
CN114089107A (en) * 2021-11-16 2022-02-25 国网福建省电力有限公司南平供电公司 Capacitor line selection method for grounding of central point of transformer substation for single-phase grounding fault disposal
CN115825638A (en) * 2022-09-08 2023-03-21 北京昊创瑞通电气设备股份有限公司 Power distribution network single-phase earth fault comprehensive judgment system and method
CN116482488A (en) * 2023-06-16 2023-07-25 国网山东省电力公司东营供电公司 Power distribution network ground fault distance measurement method and system based on capacitive transient

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103545796A (en) * 2013-09-16 2014-01-29 国家电网公司 Single-phase grounding fault handling device and method for power distribution network with non-effectively grounded neutral points
CN105186470A (en) * 2015-09-10 2015-12-23 国网江西省电力科学研究院 Single-phase ground fault processing method for 10kV ungrounded system
CN105445511A (en) * 2015-12-11 2016-03-30 国家电网公司 Singlephase earth fault signal generating device and method for simulation isolated neutral system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103545796A (en) * 2013-09-16 2014-01-29 国家电网公司 Single-phase grounding fault handling device and method for power distribution network with non-effectively grounded neutral points
CN105186470A (en) * 2015-09-10 2015-12-23 国网江西省电力科学研究院 Single-phase ground fault processing method for 10kV ungrounded system
CN105445511A (en) * 2015-12-11 2016-03-30 国家电网公司 Singlephase earth fault signal generating device and method for simulation isolated neutral system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄荷英: "中性点不接地***发生单相接地故障的处理", 《小水电》 *

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106872857A (en) * 2017-03-13 2017-06-20 安徽天电气技术股份有限公司 A kind of residual voltage drives the ground fault line selection device of zero-sequence current
CN106771887A (en) * 2017-03-13 2017-05-31 安徽天电气技术股份有限公司 A kind of instantaneous zero sequence voltage drives ground fault line selection device
CN107300656A (en) * 2017-06-17 2017-10-27 李景禄 A kind of earth fault based on power network characteristic parameter incremental starts method
CN107340416A (en) * 2017-08-28 2017-11-10 国网江西省电力公司电力科学研究院 A kind of distribution network failure indicator LC tunings are outer to apply signal source
CN108152683A (en) * 2018-01-10 2018-06-12 济南大学 Based on the earth fault line selection method for helping increasing principle
CN108614180B (en) * 2018-04-12 2020-05-29 山东钢铁股份有限公司 Single-phase earth fault line searching method
CN108614180A (en) * 2018-04-12 2018-10-02 山东钢铁股份有限公司 Singlephase earth fault circuit lookup method
CN111880110A (en) * 2019-04-15 2020-11-03 山东大学 Single-phase earth fault disappearance judgment method and system for neutral point non-effective earthing system
CN111880110B (en) * 2019-04-15 2021-08-27 山东大学 Single-phase earth fault disappearance judgment method and system for neutral point non-effective earthing system
CN110568316A (en) * 2019-10-16 2019-12-13 国网四川省电力公司绵阳供电公司 Method for quickly selecting line of ground fault of low-current grounding system
CN110687403A (en) * 2019-11-21 2020-01-14 济南泰景电力技术有限公司 Power distribution network single-phase earth fault detection method and device
CN111308276A (en) * 2020-04-08 2020-06-19 广东电网有限责任公司电力调度控制中心 Power distribution network fault positioning method and device
CN112255573A (en) * 2020-11-20 2021-01-22 国网江苏省电力有限公司盐城供电分公司 Single-phase earth fault processing method for neutral point ungrounded system
CN112255573B (en) * 2020-11-20 2022-12-23 国网江苏省电力有限公司盐城供电分公司 Single-phase earth fault processing method for neutral point ungrounded system
CN113725811A (en) * 2020-12-12 2021-11-30 保定钰鑫电气科技有限公司 Method for processing single-phase grounding of non-effective grounding system
CN113725811B (en) * 2020-12-12 2023-12-05 保定钰鑫电气科技有限公司 Single-phase grounding processing method of non-effective grounding system
CN112909904A (en) * 2021-03-03 2021-06-04 广东电网有限责任公司 Resistance grounding system and control method thereof
CN114089107A (en) * 2021-11-16 2022-02-25 国网福建省电力有限公司南平供电公司 Capacitor line selection method for grounding of central point of transformer substation for single-phase grounding fault disposal
CN114089107B (en) * 2021-11-16 2023-12-22 国网福建省电力有限公司南平供电公司 Capacitor line selection method for single-phase grounding fault handling of transformer substation center point grounding
CN115825638A (en) * 2022-09-08 2023-03-21 北京昊创瑞通电气设备股份有限公司 Power distribution network single-phase earth fault comprehensive judgment system and method
CN116482488A (en) * 2023-06-16 2023-07-25 国网山东省电力公司东营供电公司 Power distribution network ground fault distance measurement method and system based on capacitive transient
CN116482488B (en) * 2023-06-16 2023-09-22 国网山东省电力公司东营供电公司 Power distribution network ground fault distance measurement method and system based on capacitive transient

Similar Documents

Publication Publication Date Title
CN106443339A (en) Method for selecting wire after single-phase grounding of ungrounded system
US10148080B2 (en) Single-phase-to-earth fault processing device and method for neutral non-effectively grounded distribution network
CN102937687B (en) Method for distinguishing disconnection fault and grounding fault during grounding of neutral point through small resistor
CN101701998A (en) Novel faulty line selection method in low current faulty grounding system
CN110912093B (en) Disconnection relay protection method for measuring matching of load side bus line voltage and spare power automatic switching
CN107438929A (en) Method for being protected in combined power transmission line
CN111313379B (en) Disconnection protection method for comparing line voltage on two sides of line and spare power automatic switching
Mardegan et al. Insights into applications of IEEE standards for ground-fault protection in industrial and commercial power systems
CN104122484A (en) Distribution network fault line selection method based on correlation analysis of zero modal current wavelet coefficients
CN203025307U (en) Smart line selector of small-current earthing system
CN205811531U (en) Fault protection system for power distribution system
CN106711987A (en) Quick arc extinguishing system and method for single-phase ground fault of low-current ground system
CN103944151B (en) A kind of guard method of many times parallel circuit different name phase two points ground fault of isolated neutral system
CN102959670A (en) Rush-current limiting apparatus
CN205693353U (en) A kind of power distribution network arc-extinction device
CN109521332A (en) Fault handling method, apparatus and system
CN113765056B (en) Single-phase grounding processing method
Panasetsky et al. On the problem of shunt reactor tripping during single-and three-phase auto-reclosing
CN111224384B (en) Method for comparing line voltage vector difference on two sides of line and protecting line breakage by adopting loop closing and opening operation
JP2023554546A (en) How to handle short circuit between phases
Hartung et al. Limitation of short circuit current by an I S-limiter
CN204012700U (en) Power network neutral point grounding system
CN206806991U (en) A kind of power distribution network busbar protective device of earthing mode self-identifying
CN103018631A (en) System for 10kV fault line detection
CN206960591U (en) A kind of earth fault mutually quick judge module and arc-extinguishing resonance-extinguishing device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170222