CN106436746A - Prefabricated box-type substation cement foundation - Google Patents
Prefabricated box-type substation cement foundation Download PDFInfo
- Publication number
- CN106436746A CN106436746A CN201610956740.1A CN201610956740A CN106436746A CN 106436746 A CN106436746 A CN 106436746A CN 201610956740 A CN201610956740 A CN 201610956740A CN 106436746 A CN106436746 A CN 106436746A
- Authority
- CN
- China
- Prior art keywords
- foundation
- embedded
- iron
- basic
- box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The invention discloses a prefabricated box-type substation cement foundation which comprises two semi-structure members with symmetric structures and matched with each other, wherein the semi-structure member comprises a concrete casting part, a ventilation louver, an embedded bar hoisting part, foundation embedded connection soldering iron and foundation embedded iron. Compared with the prior art, by adopting off-site production and split mounting, the on-site foundation production time is saved, the construction time is greatly shortened, and the processes such as transportation and mounting are more convenient; the mechanical strength and service life of the produced box-type substation foundation are greatly improved; to move the equipment, the foundation can move along as a whole or in a split manner for repeated use, thus the cost is saved, an effect of environmental protection can be realized, and powerful guarantee is provided for the increase of production and consumption and safe operation of equipment and the like of power supply enterprises; and moreover, the production and mounting of the foundation promote industrial promotion and application, and the market competitiveness of the enterprise is enhanced.
Description
Technical field
The present invention relates to casing installation foundation manufacture technology field, more particularly to a kind of Prefabricated box-type power substation cement based
Plinth.
Background technology
Box-type substation, is prepackage type electric substation or preassembled transformer station again, is a kind of high-tension switch gear, distribution transformer
Device and low-voltage distribution equipment, by certain connection plan row, all-in-one-piece prefabrication is indoor, outdoor close-coupled controller switching equipment, will
The functions such as transformer pressure-reducing, low-voltage distribution are organically combined, installed in a protection against the tide, antirust, dust-proof, protection against rodents, fire prevention,
Antitheft, heat-insulated, totally-enclosed, moveable steel-structure box, is particularly well-suited to urban network construction and upgradation, be after civil engineering transformer station
A kind of brand-new transformer station for emerging.Box-type substation is applied to mine, factory and enterprise, oil gas field and wind power station, and it replaces
For original civil engineering power distribution room, power distribution station, become new complete change power distribution equipment.Box-type substation is installed when installing
On concrete pedestal, therefore, box type transformer substation base should meet economy, and convenient and environmental protection of construction and installation etc. will
Ask.
The installation of general box-type substation is all to build basis by laying bricks or stones by installation unit scene, needs to expend substantial amounts of manpower thing
Power, and concrete curing time.Box type transformer substation base is built at scene by laying bricks or stones, needs to build by laying bricks or stones by basic drawing, engineering time and coagulation
Native curing time is longer, is unfavorable for the reduction of erection time, and as installation unit and device fabrication unit are frequently not same enterprise
Industry, after basis is made, can usually occur basis and the unmatched situation of box-type substation, cause to return in a large number during in-site installation
Work, wastes a large amount of manpower and materials and time.And scene is built box type transformer substation base by laying bricks or stones and is used only once, the machinery on basis is strong
Degree and service life are short, and can produce building waste, and the wasting of resources does not meet the construction requirement of environmental protection.
Content of the invention
It is an object of the invention to provide a kind of Prefabricated box-type power substation concrete pedestal, with solve above-mentioned scene build by laying bricks or stones box
The necessary field fabrication of transformer substation foundation, long construction period, it is used only once, when under basis with box-type substation mismatch case
Do over again in a large number, the mechanical strength on basis and service life are short, and can produce the problems such as building waste, wasting of resources.
For realizing the purpose of the present invention, the invention provides a kind of Prefabricated box-type power substation concrete pedestal, its feature exists
In including two symmetrical configuration and the half hitch component that is used in combination, the half hitch component includes concreting part, ventilation hundred
Leaf window, embedded bar lifting part, the pre-buried connection soldering iron in basis, basic embedded iron;The concreting part includes to be arranged at
Operating board that end face stretches out, the side plate of two corresponding settings and the intermediate plate of biside plate middle part is arranged at, institute
The bottom for stating intermediate plate is provided with cable incoming-outgoing string holes;The upper surface of two side plates is respectively arranged with two embedded bar lifting parts
With a basic embedded iron and position is corresponding two-by-two, basic embedded iron is arranged between two embedded bar lifting parts, both sides
The described basic pre-buried connection soldering iron being provided with the side of plate for the connection of half hitch component;The top of two side plates is respectively provided with
There is an air vent, the air vent is shutter.
Wherein, the cable incoming-outgoing string holes is two, in the bottom of intermediate plate or so interval setting.
Wherein, the pre-buried connection soldering iron in spaced two bases up and down is respectively arranged with the side of arbitrary side plate.
Compared with prior art, the invention has the beneficial effects as follows:Due to taking making, partial installation formula outside the venue, not only
The time of field basic making is saved, the duration is substantially reduced, and makes the operations such as transport, installation more convenient, so make
Box type transformer substation base out substantially increases the mechanical strength on basis and service life, if equipment needs displacement, Ben Ji
Plinth can also entirety or split displacement therewith, reused, not only saved cost but also the effect of environmental protection can be reached, be power supply
The volume increase of enterprise is extended sales, and the aspect such as equipment safety operation provides powerful guarantee, and the making on this basis and installation are easy in industry
Upper promotion and application, improve the market competitiveness of enterprise.
Description of the drawings
Fig. 1 show the structural representation of half hitch framework of the present invention;
Fig. 2 show the structural representation of the present invention;
In figure:1- concreting part, 2- ventilation shutter, 3- embedded bar lifting part, the pre-buried connection soldering iron in 4- basis,
5- basis embedded iron, 6- operating board, 7- cable incoming-outgoing string holes.
Specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail.It should be appreciated that described herein
Specific embodiment only in order to explain the present invention, be not intended to limit the present invention.
It should be noted that " connection " described herein and the word for expressing " connection ", such as " being connected ",
" being connected " etc., which both may refer to a certain part and had been directly connected to another part, it is also possible to refer to a certain part by other portions
Part is connected with another part.
As shown in Figure 1 and Figure 2, embodiments of the invention, Prefabricated box-type power substation concrete pedestal, including two structures pair
The half hitch component for claiming and being used in combination, the half hitch component includes that concreting part 1, ventilation shutter 2, embedded bar hang
Piece installing 3, the pre-buried connection soldering iron 4 in basis, basic embedded iron 5;The concreting part 1 includes that being arranged at upper end extends outwardly
The side plate of 6, two corresponding settings of operating board and be arranged at the intermediate plate of biside plate middle part, under the intermediate plate
Portion is provided with cable incoming-outgoing string holes 7;The upper surface of two side plates is respectively arranged with two embedded bar lifting parts 3 and a basis
Embedded iron 5 and position is corresponding two-by-two, basic embedded iron 5 is arranged between two embedded bar lifting parts 3, the side of biside plate
On be provided with for half hitch component connection the basis pre-buried connect soldering iron 4;The top of two side plates is respectively arranged with one
Air vent, the air vent is shutter 2.
It should be noted that as box-type substation volume weight is larger, also there is larger weight on case station basis, pours on basis
The safety of the lifting for considering when building and convenient, embedded bar lifting part 3 in the concreting part, wait lift in place after by reinforcing bar
Cut and flush with concrete foundation face, box-type substation can be installed.Case station concreting part 1 is in bottom of intermediate plate or so
Cable incoming-outgoing string holes 7 is arranged at intervals with, and cable incoming-outgoing string holes 7 is, after the fixation of two, case station is finished, can to pass through manhole in case station
Enter inside cartonning station, complete the volume line connection of cable.There is the operating platform 6 of outside extension basic upper surface, and basis is installed
After good, operator may stand on operating platform 6 and carry out repair and maintenance to case station.The basic left and right sides is provided with ventilating blind
Window 2, it is ensured that well-ventilated when operator enter basic internal connection cable by manhole.On the basis of embedded iron 5 be used for and case
The feet channel steel welding of formula transformer station.
It should be noted that this Prefabricated box-type power substation basis is made up of two half hitch components, two half hitch components are
Symmetrical structure, is respectively arranged with the pre-buried company in spaced two bases up and down on the side of the arbitrary side plate of concreting part 1
Soldering iron 4 is connect, the pre-buried soldering iron 4 that connects in the basic basis by centre is welded to connect as an entirety.
Installation process:
When box-type substation is installed, bed course is being carried out after floor leveling in the foundation ditch for digging in advance, 2 bases are being poured
Part 1 is lifted on bed course in place, after adjusting relative position, two parts basis is poured part electric welding connection, while reinforcing bar will be lifted
Cut with concrete foundation face and as shown in the figure 2 are flushed, form a complete case station basis.Then earth filling tamping, you can install
Box-type substation, by the feet channel steel of box-type substation with the basis of embedded iron parts 5 weld, case station i.e. fixation finishes.
The above is only the preferred embodiment of the present invention, it is noted that for the common skill of the art
For art personnel, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications
Also protection scope of the present invention should be regarded as.
Claims (3)
1. a kind of Prefabricated box-type power substation concrete pedestal, it is characterised in that including two symmetrical configuration and be used in combination
Half hitch component, the half hitch component includes concreting part, ventilation shutter, embedded bar lifting part, basic pre-buried connection
Soldering iron, basic embedded iron;The concreting part includes to be arranged at that operating board, two that upper end extends outwardly are corresponding sets
The side plate that puts and the intermediate plate for being arranged at biside plate middle part, the bottom of the intermediate plate is provided with cable incoming-outgoing string holes;
The upper surface of two side plates is respectively arranged with two embedded bar lifting parts and a basic embedded iron and position is corresponding two-by-two,
Basic embedded iron is arranged between two embedded bar lifting parts, is provided with for the connection of half hitch component on the side of biside plate
The basic pre-buried connection soldering iron;The top of two side plates is respectively arranged with an air vent, and the air vent is shutter.
2. a kind of Prefabricated box-type power substation concrete pedestal according to claim 1, it is characterised in that the cable incoming-outgoing
String holes is two, in the bottom of intermediate plate or so interval setting.
3. a kind of Prefabricated box-type power substation concrete pedestal according to claim 1, it is characterised in that the side of arbitrary side plate
The pre-buried connection soldering iron in spaced two bases up and down is respectively arranged with face.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610956740.1A CN106436746A (en) | 2016-10-26 | 2016-10-26 | Prefabricated box-type substation cement foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610956740.1A CN106436746A (en) | 2016-10-26 | 2016-10-26 | Prefabricated box-type substation cement foundation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106436746A true CN106436746A (en) | 2017-02-22 |
Family
ID=58180772
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610956740.1A Pending CN106436746A (en) | 2016-10-26 | 2016-10-26 | Prefabricated box-type substation cement foundation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106436746A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109004567A (en) * | 2018-10-17 | 2018-12-14 | 上海南桥变压器有限责任公司 | Integrated container-type substation |
CN109252613A (en) * | 2017-07-12 | 2019-01-22 | 保时捷股份公司 | For fixing the concrete pedestal of metal shell |
CN109653231A (en) * | 2019-01-24 | 2019-04-19 | 西安西微电力设备有限公司 | A kind of prefabrication type outdoor power equipment basis and preparation method thereof and installation method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2697381B1 (en) * | 1992-10-22 | 1994-12-02 | Simplex Appareils | Station for electrical networks. |
DE102007016364A1 (en) * | 2007-04-03 | 2008-10-16 | Rittal Gmbh & Co. Kg | Cover plate arrangement for switchgear cabinet, has cover plates with recesses formed for feeding through cables or wires, where recesses are coverable by selected number of module plates with masses adapted to recesses |
CN103296591A (en) * | 2013-06-18 | 2013-09-11 | 国家电网公司 | Combined box type substation foundation |
CN204441754U (en) * | 2015-03-17 | 2015-07-01 | 陈勤亚 | A kind of box for box-type transformer substation with stealthy aeration structure |
CN206143802U (en) * | 2016-10-26 | 2017-05-03 | 天津市华旺电力水泥制品有限公司 | Prefabricated formula box -type substation cement foundation |
-
2016
- 2016-10-26 CN CN201610956740.1A patent/CN106436746A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2697381B1 (en) * | 1992-10-22 | 1994-12-02 | Simplex Appareils | Station for electrical networks. |
DE102007016364A1 (en) * | 2007-04-03 | 2008-10-16 | Rittal Gmbh & Co. Kg | Cover plate arrangement for switchgear cabinet, has cover plates with recesses formed for feeding through cables or wires, where recesses are coverable by selected number of module plates with masses adapted to recesses |
CN103296591A (en) * | 2013-06-18 | 2013-09-11 | 国家电网公司 | Combined box type substation foundation |
CN204441754U (en) * | 2015-03-17 | 2015-07-01 | 陈勤亚 | A kind of box for box-type transformer substation with stealthy aeration structure |
CN206143802U (en) * | 2016-10-26 | 2017-05-03 | 天津市华旺电力水泥制品有限公司 | Prefabricated formula box -type substation cement foundation |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109252613A (en) * | 2017-07-12 | 2019-01-22 | 保时捷股份公司 | For fixing the concrete pedestal of metal shell |
CN109004567A (en) * | 2018-10-17 | 2018-12-14 | 上海南桥变压器有限责任公司 | Integrated container-type substation |
CN109004567B (en) * | 2018-10-17 | 2023-12-22 | 上海电气集团(张家港)变压器有限公司 | Integral box-type substation |
CN109653231A (en) * | 2019-01-24 | 2019-04-19 | 西安西微电力设备有限公司 | A kind of prefabrication type outdoor power equipment basis and preparation method thereof and installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11655641B2 (en) | Construction building equipment and construction method thereof | |
CN104805866B (en) | Prefabricated pipe gallery and construction method | |
US7467910B2 (en) | Prefabricated structure made of reinforced concrete with an integrated removable handling system | |
CN205444446U (en) | Assembled industrialization steel construction house | |
CN204826308U (en) | Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall | |
CN203924471U (en) | Precast concrete external wall panel | |
CN109680938A (en) | A kind of nonstandard layer aluminum wood steel combination template and its construction method, building | |
CN106436746A (en) | Prefabricated box-type substation cement foundation | |
CN113338508A (en) | PC component installation construction method for fabricated building | |
CN107060152B (en) | Attachment device and method between a kind of prefabricated internal partition wall of substation and floor | |
CN203821454U (en) | Reinforcing type inspection-well cover plate with stainless steel plate on upper portion | |
CN111733873A (en) | Construction method of assembled subway station | |
CN105064391A (en) | Assembled equipment foundation | |
CN114541632A (en) | Construction method for using laminated slab for prefabricated building roof layer floor slab | |
CN206143802U (en) | Prefabricated formula box -type substation cement foundation | |
CN210562276U (en) | Integrated foundation structure of assembled transformer substation | |
CN209854577U (en) | Assembled thin-wall box-shaped channel | |
CN111236603B (en) | Comprehensive construction method for steel plate mesh overhanging scaffold | |
CN108396781B (en) | Assembled shaft fore shaft circle beam member structure | |
CN105386447A (en) | Construction method for replacement support of post-cast strip in construction site | |
CN206158255U (en) | Prefabricated assembled communication machinery room | |
CN106436745A (en) | Prefabricated switching station foundation | |
CN204940328U (en) | Assembled equipment foundation | |
CN209853563U (en) | Assembled muck block wall's hoist | |
CN106193685A (en) | Prefabricated assembled communications equipment room structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170222 |
|
WD01 | Invention patent application deemed withdrawn after publication |