CN106436734A - Power transmission line assembly-type arch base and construction method - Google Patents

Power transmission line assembly-type arch base and construction method Download PDF

Info

Publication number
CN106436734A
CN106436734A CN201610503568.4A CN201610503568A CN106436734A CN 106436734 A CN106436734 A CN 106436734A CN 201610503568 A CN201610503568 A CN 201610503568A CN 106436734 A CN106436734 A CN 106436734A
Authority
CN
China
Prior art keywords
unidirectional
steel strand
strand wires
cambered
pieces
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610503568.4A
Other languages
Chinese (zh)
Other versions
CN106436734B (en
Inventor
张盈哲
刘燕平
龚坚刚
孙永军
王淑红
章李刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610503568.4A priority Critical patent/CN106436734B/en
Publication of CN106436734A publication Critical patent/CN106436734A/en
Application granted granted Critical
Publication of CN106436734B publication Critical patent/CN106436734B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/08Reinforcements for flat foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

A power transmission line assembly-type arch base and a construction method are provided. The arch base is consisted of a rigid upper plate housing and a lower flexible stay cable which are installed inside the foundation; the rigid upper plate housing is consisted of a quadrangle inner arch housing which is enclosed by four lower prefabricated unidirectional bow-shaped splints and an upper base columns; two of the four unidirectional bow-shaped splints are symmetrically arranged and are successively spliced to form an inner arch housing with a quadrangle peripheral at the bottom, a hollow inside and a quadrangle hole in the middle of the upper part.

Description

A kind of transmission line of electricity assembled arch basis and construction method
Technical field
The present invention relates to a kind of transmission line of electricity assembled arch basis and construction method, especially one kind is applied to non-rock Soil property tower position push basis, belong to transmission line tower foundation formal technique field.
Background technology
Flexible mat foundation is the base form being used widely in the transmission line of electricity of various electric pressures.In design When, reduce the additional stress of substrate by increasing base areas, so that basis is met and push requirement for bearing capacity, utilize basis simultaneously And its deadweight of the overlying soil body come to undertake basis uplift force.
It is not enough to there is both sides in flexible board-like foundation main:(1) when basic role power is larger, sole plate area meeting Larger, simultaneously because the thickness of slab of the requirement mat foundation of self-strength also can be larger, so that base concrete large usage quantity, And now the stock utilization of basic abdominal part concrete is relatively low in fact;(2)Casting concrete wire-tie from excavating to again To maintenance, the duration of foundation construction is longer for transmission line of electricity.
Content of the invention
It is an object of the invention to overcoming the shortcomings of that prior art exists, and provide a kind of structure simple, uniform force, jail Gu reliable, transmission line of electricity assembled arch basis and the construction method of efficiency of construction can be improved.
The purpose of the present invention to complete by following technical solution, a kind of transmission line of electricity assembled arch basis, it Mainly it is made up of the flexible cable that the armored concrete rigid top plate shell being arranged in ground and bottom steel strand wires are constituted, described In the square that rigid top plate shell is enclosed by following four pieces prefabricated unidirectional cambered plates, shell is bent in bow housing and interlocking in square In hole in the middle of body top and assemble all-in-one-piece basic stand column and constitute, described four pieces of unidirectional cambered plates are arranged symmetrically and phase two-by-two Mutually it is spliced to form a bottom successively to be in square periphery, inner hollow and have in a square hole in top intermediate formation Bow housing, makes the outer side wall of surrounding of interior bow housing form tapered slope wall;
Between the described unidirectional cambered plate being arranged symmetrically two-by-two, at least after steel strand wires tensioning is used respectively in upper and lower, anchor is tight simultaneously Constitute described flexible cable, wherein top steel strand wires also extend through interlocking basic stand column bottom in middle hole.
As preferred:Described basic stand column includes a column body, and the bottom of this column body is provided with coordinating The connection pylon of hole in the middle of bow housing upper;Described unidirectional cambered plate includes the bar blocks that bottom is placed on ground basal plane, It is connected to surface plate obliquely above this bar blocks, and make two pieces of unidirectional cambered plates being arranged symmetrically form bosoms, outer The interior bow housing on the tapered inclined-plane in portion;Four pieces of described unidirectional cambered plates and a basic stand column by armored concrete prefabricated and Become;
Tight with anchor after row's steel strand wires tensioning in bottom between the described unidirectional cambered plate being arranged symmetrically, and on top with upper and lower two After row's steel strand wires tensioning, anchor is tight.
A kind of construction method on transmission line of electricity assembled arch basis as described above, described construction method includes walking as follows Suddenly:
Step one:First, excavate foundation according to key dimension, after finishing, squeeze in the bottom surface of ground and can play support work Timber;
Step 2:Lift four pieces of prefabricated unidirectional cambered plates successively, be simultaneously connected with the two-way steel strand wires in tight bottom, but steel strand wires are temporary transient Do not apply prestressing force, form bow housing in square;
Step 3:By the use of four pieces of unidirectional cambered plates as template, backfill, to the inner space of interior bow housing, tamps soil simultaneously Body;
Step 4:Hoisting prefabricated basic stand column, the two-way steel strand wires in tensioning upper and lower part anchor are tight successively, and two ends prefabricated Cement plaster is used outside anchorage in unidirectional cambered plate;
Step 5:The outside soil body of back filled foundation, only stays the top of basic stand column to expose on ground.
The present invention mainly changes the structural form of flexible mat foundation:Using by rigid top plate shell(Armored concrete) With lower flexible drag-line(Steel strand wires)" arch basis " structural system of composition, adopts assembled pattern simultaneously;Consequently, it is possible to Under load action, upper plate shell(Similar " arch " structure)The deformation tendency of horizontal direction is resisted by the tension member of lower edge, on the one hand Significantly reduce the stress on upper plate shell top, on the other hand can mitigate the support burden of the upper plate shell both sides soil body, give full play to The strong tensile property of steel strand wires improves overall structure stress performance, so that top bending component and bottom tension member is learnt from other's strong points to offset one's weaknesses, Collaborative work, reaches self-balancing, and system is simple, stress is clear and definite, has given full play to the effect of two kinds of structural materials.
Push bearing capacity in order to ensure to meet basis simultaneously, during construction, the soil body of abdominal part is tamped, be processed into close The real, foundation soil close to undisturbed soil attribute, thus basis can utilize the lower pressure of soil body transmission of abdominal part.
The invention belongs to one kind improvement to prior art, it is simple that it has a structure, uniform force, solid and reliable, can carry The features such as high efficiency of construction.
Brief description
Fig. 1 is the overall structure diagram of the present invention.
Fig. 2 is the overlooking the structure diagram of the present invention.
Fig. 3 is the basic stand column generalized section of the present invention.
Fig. 4 is the unidirectional cambered plate generalized section of the present invention.
Fig. 5 is step one schematic diagram of the present invention.
Fig. 6 is the step 2 schematic diagram of the present invention.
Fig. 7 is the step 3 schematic diagram of the present invention.
Fig. 8 is the step 4 schematic diagram of the present invention.
Fig. 9 is the step 5 schematic diagram of the present invention.
Specific embodiment
The present invention will be described in detail below in conjunction with the accompanying drawings and the specific embodiments:Fig. 1, shown in 2, of the present invention A kind of transmission line of electricity assembled arch basis, it is mainly by the armored concrete rigid top plate shell being arranged in ground and bottom steel The flexible cable composition that twisted wire is constituted, the four directions that described rigid top plate shell is enclosed by following four pieces prefabricated unidirectional cambered plates 1 In shape, bow housing bends in hole in the middle of housing upper and assembles all-in-one-piece basic stand column 2 in square with interlocking and constitutes, institute Stating four pieces of unidirectional cambered plates 1 and being arranged symmetrically two-by-two and be mutually spliced to form a bottom successively is in square periphery, inner hollow And have the interior bow housing of a square hole in top intermediate formation, make the outer side wall of surrounding of interior bow housing form tapered slope wall 11;
At least in upper and lower respectively with anchor after steel strand wires 3,4 tensionings between the described unidirectional cambered plate 1 being arranged symmetrically two-by-two Tight and constitute described flexible cable, wherein top steel strand wires 3 also extend through interlocking basic stand column 2 bottom in middle hole.
Shown in Fig. 3, described basic stand column 2 includes a column body 21, and the bottom of this column body 21 is provided with for joining The connection pylon 22 of hole in the middle of bow housing upper in closing;
Shown in Fig. 4, described unidirectional cambered plate 1 includes the bar blocks 12 that bottom is placed on ground basal plane, on this bar blocks 12 It is connected to surface plate 13 obliquely, and make two pieces of unidirectional cambered plates 1 formation bosoms being arranged symmetrically, outsides tapered tiltedly The interior bow housing in face;Four pieces of described unidirectional cambered plates 1 and a basic stand column 2 are formed by armored concrete is prefabricated;
Tight with anchor after row's steel strand wires 4 tensioning in bottom between the described unidirectional cambered plate 1 being arranged symmetrically, and on top with up and down After two row's steel strand wires 3 tensioning, anchor is tight.
A kind of construction method on described transmission line of electricity assembled arch basis, described construction method comprises the steps:
Step one:First, excavate foundation according to key dimension, after finishing, squeeze in the bottom surface of ground and can play support work Timber, as shown in Figure 5;
Step 2:Lift four pieces of prefabricated unidirectional cambered plates successively, be simultaneously connected with the two-way steel strand wires in tight bottom, but steel strand wires are temporary transient Do not apply prestressing force, form bow housing in square, as shown in Figure 6;
Step 3:By the use of four pieces of unidirectional cambered plates as template, backfill, to the inner space of interior bow housing, tamps soil simultaneously Body, as shown in Figure 7;
Step 4:Hoisting prefabricated basic stand column, the two-way steel strand wires in tensioning upper and lower part anchor are tight successively, and two ends prefabricated Cement plaster is used, as shown in Figure 8 outside anchorage in unidirectional cambered plate.
Step 5:The outside soil body of back filled foundation, only stays the top of basic stand column to expose on ground, as shown in Figure 9.
" assembled arch basis " of the present invention is by rigid top plate shell(Armored concrete)With lower flexible drag-line(Steel Twisted wire)Composition, wherein rigid top plate case member is made up of five pre-constructed units, and each part is connected by top drag-line each other;
Described rigid top plate shell is by five precast concrete part composing plate shells, Main Function be under the foundation pressure after will The compressive stress that load passes to foundation soil and undertakes basic top.
Described lower flexible drag-line be rigid top plate shell bottom connect steel strand wires, bidirectional arrangements, its act as to The tension of anti-basic infrastructure.
Described pre-constructed unit, respectively prefabricated foundation pillar partses, i.e. basic stand column and precoated plate case member, i.e. unidirectional Cambered plate, it is concrete prefabricated element, and has reserved anchorage at drag-line position when prefabricated.
Described top flexible cable is the steel strand wires connecting on rigid top plate shell top, bidirectional arrangements.
Embodiment:The composition form on assembled arch of the present invention basis is:
Assembled arch basis is made up of six parts, respectively pillar partses(Basic stand column), four plate case members(Unidirectional bow Shape plate)And drag-line part.
(1)Pillar partses(Basic stand column):Pillar partses are column body and lower panel support(Connect pylon)Pre-manufactured steel Reinforced concrete component, simultaneously foundation bolt also prefabricated wherein, as shown in Figure 3.
(2)Plate case member(Unidirectional cambered plate):This plate case member is four pieces of inclined plane parts, i.e. of arch basis upper board shell Unidirectional cambered plate, the anchorage also prefabricated bottom thereon of drag-line, as shown in Figure 4.
(3)Drag-line part(Steel strand wires)It is contemplated that subsoil water etching problem, drag-line is using epoxy coating steel strand wires, steel strand Line one end is first anchored by pre-buried anchorage, and it is tight that other end carries out after tensioning anchor again using jack after passing through anchorage.
(4)Each unit construction:This arch assembling type base connects combination part and is predominantly located at two positions:(1)Top Use prestressed cable anchor tight between pillar partses and plate case member;(2)The two of lower panel case member symmetrically unidirectional cambered plate difference Tight with prestressed cable anchor.Concrete combination is as shown in Figure 2.
2. construction process:The construction main flow on assembled arch basis is as described below:
Step one:First, after finishing according to key dimension excavation, squeeze into timber in ground.The effect of timber is, basic components Play a supporting role, as shown in Figure 5 during assembly.
Step 2:Lifting part is unidirectional cambered plate successively, is simultaneously connected with tight bottom bidirectional cable(Steel strand wires), but drag-line Temporarily do not apply prestressing force, as shown in Figure 6.
Step 3:By the use of four pieces of unidirectional cambered plates as template, backfill to inner space, tamp the soil body, timber simultaneously Do not need to extract, timber can indirectly strengthen and pushes bearing capacity, but do not consider, as shown in Figure 7 when calculating.
Step 4:Lifting basic stand column, tensioning upper and lower part bidirectional cable anchor are tight successively, and use outside the anchorage of two ends Cement plaster, as shown in Figure 8.
Step 5:The outside soil body of back filled foundation, as shown in Figure 9.

Claims (3)

1. a kind of transmission line of electricity assembled arch basis, it mainly by the armored concrete rigid top plate shell being arranged in ground and The flexible cable that bottom steel strand wires are constituted forms it is characterised in that described rigid top plate shell is by following four pieces prefabricated unidirectional arch In the square that plate encloses, bow housing and interlocking are bent in hole in the middle of housing upper in square and are assembled all-in-one-piece base Plinth column is constituted, and described four pieces of unidirectional cambered plates are arranged symmetrically two-by-two and are mutually spliced to form a bottom successively is in outside square Enclose, inner hollow have the interior bow housing of a square hole in top intermediate formation, make the outer side wall shape of surrounding of interior bow housing Tapered beveled walls;
Between the described unidirectional cambered plate being arranged symmetrically two-by-two, at least after steel strand wires tensioning is used respectively in upper and lower, anchor is tight simultaneously Constitute described flexible cable, wherein top steel strand wires also extend through interlocking basic stand column bottom in middle hole.
2. transmission line of electricity assembled arch basis according to claim 1 is it is characterised in that described basic stand column includes One column body, the bottom of this column body is provided with the connection pylon for coordinating hole in the middle of interior bow housing upper;Described Unidirectional cambered plate includes the bar blocks that bottom is placed on ground basal plane, is connected to surface plate obliquely on this bar blocks, and Two pieces of unidirectional cambered plates being arranged symmetrically are made to form bosom, the interior bow housing on outside tapered inclined-plane;Four pieces of described lists Form to cambered plate and a basic stand column by armored concrete is prefabricated;
Tight with anchor after row's steel strand wires tensioning in bottom between the described unidirectional cambered plate being arranged symmetrically, and on top with upper and lower two After row's steel strand wires tensioning, anchor is tight.
3. a kind of construction method on transmission line of electricity assembled arch as claimed in claim 1 or 2 basis is it is characterised in that described Construction method comprises the steps:
Step one:First, excavate foundation according to key dimension, after finishing, squeeze in the bottom surface of ground and can play support work Timber;
Step 2:Lift four pieces of prefabricated unidirectional cambered plates successively, be simultaneously connected with the two-way steel strand wires in tight bottom, but steel strand wires are temporary transient Do not apply prestressing force, form bow housing in square;
Step 3:By the use of four pieces of unidirectional cambered plates as template, backfill, to the inner space of interior bow housing, tamps soil simultaneously Body;
Step 4:Hoisting prefabricated basic stand column, the two-way steel strand wires in tensioning upper and lower part anchor are tight successively, and two ends prefabricated Cement plaster is used outside anchorage in unidirectional cambered plate;
Step 5:The outside soil body of back filled foundation, only stays the top of basic stand column to expose on ground.
CN201610503568.4A 2016-07-01 2016-07-01 A kind of transmission line of electricity assembled arch basis and construction method Active CN106436734B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610503568.4A CN106436734B (en) 2016-07-01 2016-07-01 A kind of transmission line of electricity assembled arch basis and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610503568.4A CN106436734B (en) 2016-07-01 2016-07-01 A kind of transmission line of electricity assembled arch basis and construction method

Publications (2)

Publication Number Publication Date
CN106436734A true CN106436734A (en) 2017-02-22
CN106436734B CN106436734B (en) 2018-11-20

Family

ID=58183298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610503568.4A Active CN106436734B (en) 2016-07-01 2016-07-01 A kind of transmission line of electricity assembled arch basis and construction method

Country Status (1)

Country Link
CN (1) CN106436734B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241840A (en) * 2019-06-06 2019-09-17 浙江华云电力工程设计咨询有限公司 A kind of premade shells Screw Anchor composite foundation and construction method
CN112482345A (en) * 2020-11-30 2021-03-12 上海宝冶冶金工程有限公司 Method and structure for improving bearing capacity of natural foundation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241840A (en) * 2019-06-06 2019-09-17 浙江华云电力工程设计咨询有限公司 A kind of premade shells Screw Anchor composite foundation and construction method
CN112482345A (en) * 2020-11-30 2021-03-12 上海宝冶冶金工程有限公司 Method and structure for improving bearing capacity of natural foundation

Also Published As

Publication number Publication date
CN106436734B (en) 2018-11-20

Similar Documents

Publication Publication Date Title
CN207160039U (en) A kind of Tenon prefabricated PC open caisson
CN207194006U (en) A kind of prefabricated concrete retaining wall
CN109944250B (en) Foundation pit forward and backward combined construction method of non-permanent vertical supporting system
CN101939492B (en) Precast temporary facility structure and construction method for the same
CN101629408A (en) Composite anchoring structure on guyed tower end of cable-stayed bridge
CN201288328Y (en) Beam-plate integrated prefabricated split mounting type tower crane fixed foundation
CN208899527U (en) A kind of supporting and the integrated system of Pipe rack
KR100968259B1 (en) Slab bridge and this construction technique
CN106436734B (en) A kind of transmission line of electricity assembled arch basis and construction method
CN205934954U (en) Bow -shaped basis of transmission line assembled
CN112227353A (en) Assembled integral static pressure pile
CN208219689U (en) Prefabricated components concrete tower fan foundation structure
US20190186166A1 (en) Wind turbine tower with reinforcing elements
CN215977351U (en) Reinforced framework foundation structure and supporting mechanism
CN201794215U (en) Pretensioning method prestress reinforced concrete prefabricated beam
CN204590336U (en) A kind of overlapped shear wall based on half prefabricated ultra-tough steel concrete
KR101131631B1 (en) Assembling bridge construction method using Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
CN114991142B (en) Assembled plate-rock anchor rod composite foundation and construction method
CN201526048U (en) Anchor-type metal foundation
CN101230667A (en) Force-bearing type superposed component
CN111255074A (en) Prefabricated column-steel beam hybrid frame structure and construction method thereof
CN101230664A (en) Force-bearing type underplate component
CN221218875U (en) Assembled bearing platform anchor rod foundation for power transmission line
CN109235444A (en) A kind of prismatic prestressing force support pile, piling wall and its construction method
CN217000063U (en) Modular drainage inspection shaft

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant