CN106425316A - Double-lug plate for hinging work-pieces and manufacturing technology thereof - Google Patents

Double-lug plate for hinging work-pieces and manufacturing technology thereof Download PDF

Info

Publication number
CN106425316A
CN106425316A CN201611025839.6A CN201611025839A CN106425316A CN 106425316 A CN106425316 A CN 106425316A CN 201611025839 A CN201611025839 A CN 201611025839A CN 106425316 A CN106425316 A CN 106425316A
Authority
CN
China
Prior art keywords
otic placode
connection otic
plate
welding
workpiece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611025839.6A
Other languages
Chinese (zh)
Inventor
李洋
邵长军
吴义成
吴新明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaibei Huai Chi Technology Co Ltd
Original Assignee
Huaibei Huai Chi Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaibei Huai Chi Technology Co Ltd filed Critical Huaibei Huai Chi Technology Co Ltd
Priority to CN201611025839.6A priority Critical patent/CN106425316A/en
Publication of CN106425316A publication Critical patent/CN106425316A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Arc Welding In General (AREA)

Abstract

The invention discloses a double-lug plate for hinging work-pieces. The double-lug plate comprises a welding plate and two connecting lug plates, wherein the connecting lug plates are located on the top of the welding plate, the connecting lug plates are provided with pin holes and are symmetrically arranged relative to the welding plate, and the welding plate and the connecting lug plates are fixedly connected. Compared with the prior art, the double-lug plate for hinging the work-pieces and the manufacturing technology thereof have the advantages that the structure is simple, use is convenient, the mechanical property of low-carbon steel is greatly improved after heat treatment, welding grooves are formed in welding parts so that the welding strength can be improved, the manufacturing technology is simple, the design is reasonable, the consumed materials are few, the cost is low, installation and use are convenient, and the production cost of enterprises is lowered.

Description

A kind of hinged use bi-lug plate of workpiece and its processing technology
Technical field
The present invention relates to the hinged use bi-lug plate of vehicle technology field, more particularly to a kind of workpiece and its processing technology.
Background technology
With the development of China's economic, plant equipment manufacturing has obtained developing faster, manufactures in plant equipment etc. In industry, machining refers to the process of be changed the overall dimensions of workpiece or performance by a kind of plant equipment, machine Production process refers to make all processes of product from raw material.The transport including raw material and preservation for production of machinery, The preparation of production, the manufacture of blank, the processing of part and heat treatment, the assembling of product and debugging, the content such as paint and packaging. The content of production process is quite varied, and the principle of modern enterprise system analysis engineering and method tissue are produced and Instructing manufacture, will Production process regards a production system with input and output as.The method using traditional mechanical processing is referred to, according to figure The pattern of paper and size, make shape, size, relative position and the property of blank become the overall process of qualified parts, processing technique It is the work that does required for before workman is processed, it is to avoid processing error occurs in process, causes economic loss.Machinery The step of processing process is workpiece or part manufacture processing, using the method for machining, directly changes the shape of blank Shape, size and surface quality etc. so as to which the process for becoming part is referred to as mechanical processing technique flow process.Such as common parts Processing process is roughing-polish-assembling-inspection-packaging, is exactly the general flow process of individual processing.Machining work Skill is exactly on the basis of flow process, changes the production shape of object, size, relative position and property etc. so as to become finished product or Semi-finished product, are each steps, and the detailed description of each flow process is such as, above said, and roughing potentially includes blank manufacture, beats Mill etc., polish may be divided into car, pincers worker, milling machine, etc., each step will have detailed data, such as roughness Reach how many, tolerance will reach how many.
Commonly use hinged in machining and workpiece assembling, it is common one that hinged monaural plate and hinged bi-lug plate coordinate Kind hinged cooperation, as which has the performances such as simple structure, easy to operate, use intensity be high, this hinge method is extensively applied In all trades and professions.For the hinged use bi-lug plate of workpiece, complex manufacturing technology of the prior art, the product structure that produces is strong The difficult effective control of degree, is not suitable for promoting the use of.
Content of the invention
The invention aims to shortcoming present in prior art is solved, and a kind of workpiece for proposing hinged uses ears Plate.
To achieve these goals, following technical scheme present invention employs:A kind of hinged use bi-lug plate of workpiece, including weldering Fishplate bar and connection otic placode, the connection otic placode is located at welded plate top, and the number of the connection otic placode is individual, the connection otic placode On offer pin hole, and the connection otic placode is symmetrical arranged with regard to welded plate, and the welded plate is fixedly connected with connection otic placode.
Preferably, the material of the welded plate and connection otic placode is mild steel.
Preferably, the welded plate and connection otic placode are connected by way of welding, and the company of welded plate and connection otic placode The place of connecing offers bevel for welding.
The invention allows for a kind of processing technology of the hinged use bi-lug plate of workpiece, comprises the steps:
S1, raw material prepare, and choose mild steel steel plate raw material, buy the rule of the steel plate for making welded plate on material market Lattice thickness is 20mm, and the gauge thickness for making the steel plate of connection otic placode is 15mm, and pickup is standby;
S2, the blanking of welded plate and process, the specification for obtaining in S1 is transferred to blanking workshop for the steel plate of 20mm to be carried out Processing, according to layout design size, is programmed in numerical control chamber, carries out blanking using plasma digital control cutting machine, and blanking is completed Afterwards, the welded plate of acquisition is delivered to finishing department after workpiece cooling, is existed using abrasive machine by standing cooling 20min-30min Bevel for welding is outputed in the junction of welded plate and connection otic placode, controls machining accuracy in ± 0.5mm, the workpiece that then will obtain Being transferred to polishing workshop carries out grinding process, will be clean to the burr at welding plate surface and edge, waste scrap, and pickup is standby;
S3, the blanking of connection otic placode and process, the specification for obtaining are transferred to blanking workshop for the steel plate of 15mm enter in S1 Row processing, according to layout design size, is programmed in numerical control chamber, carries out blanking using plasma digital control cutting machine, and blanking is complete Cheng Hou, standing cooling 20min-30min, after workpiece cooling, the connection otic placode of acquisition being delivered to polishing workshop carries out burnishing part Reason, will be clean to the burr at welding plate surface and edge, waste scrap, and pickup is standby;
S4, normalized treatment, the connection otic placode for obtaining in the welded plate that S2 is obtained and S3 is transferred to normalizing workshop just to be carried out Fire is processed, and control normalizing temperature is between 750 DEG C -800 DEG C, and the normalizing time, between 40min-50min, improves the mechanicalness of steel Energy;
S5, annealing, the welded plate crossed by normalized treatment in S4 and connection otic placode make annealing treatment, using air-cooled Heat on workpiece is taken away rapidly by the type of cooling using aerator, realizes fast cooling, and cool time is 50min-60min, After workpiece cooling, the welded plate of acquisition and connection otic placode are transferred to rivet welding workshop and are assembled, pickup is standby;
The welding assembly of S6, welded plate and connection otic placode, the welded plate for obtaining in S5 and connection otic placode are carried out welding group Dress, is positioned at connection otic placode on welded plate by the method for spot welding first, carries out full weld then along bevel for welding, during cooling Between be 50min-60min, after workpiece cooling after, by the Workpiece transfer of acquisition to polish workshop carry out grinding process, by workpiece table The burr at face and edge, waste scrap are clean, and pickup is standby;
S7, straightening processing, the Workpiece transfer for obtaining are processed to workshop is aligned, control the flatness of workpiece in S6 In ± 0.02mm, pickup is standby;
S8, blasting treatment, the Workpiece transfer for obtaining in S7 to sand-blast shop is carried out blasting treatment, by the ferrum of surface of the work Rust, dust etc. are cleaned out, and pickup is standby;
S9, zinc-plated process, the Workpiece transfer for obtaining after blasting treatment in S8 is carried out zinc-plated process, coating to zinc-plated workshop In process, make conducting salt, boric acid by the use of salt zinc oxide, potassium chloride and make pH value buffer agent as zinc-plated formula, using DC source With numerical control Double-pulse Plating Power Source, under the conditions of magnetic agitation, in the electrolysis bath of the two poles of the earth, electrogalvanizing is carried out, thickness of coating is in 4um-7um Between, in coating Passivation Treatment, 30 DEG C of light-emitting solution being made up of 35ml/L nitric acid and 10ml/L hydrochloric acid goes out light 2s, after passivation Rinse in hot water, then drying 20min under the conditions of 80 DEG C carries out aging, after the zinc coat of surface of the work dries, takes Part is standby;
S10, packaging.
Preferably, welding current is controlled in step S6, and prime coat is using 100~120A or so, the welding electricity of packed layer Stream scope is between 150~250A, and welding current is suitably reduced by capping layer, between 150~160A.
A kind of hinged use bi-lug plate of workpiece and its processing technology that the present invention is provided, compared with prior art, the present invention is tied Structure is simple, and easy to use, after heat treatment, the mechanical performance of mild steel is greatly reinforced, by opening up bevel for welding in weld, plus Strong weld intensity, processing technology is simple, reasonable in design, and which is with material is few, low cost, easy to install, reduces enterprise and produces into This.
Description of the drawings
Fig. 1 is the main structure diagram of the present invention;
Fig. 2 is the left view structural representation of the present invention;
Fig. 3 is the overlooking the structure diagram of the present invention.
In figure:1 welded plate, 2 connection otic placodes, 3 pin holes.
Specific embodiment
In order that the objects, technical solutions and advantages of the present invention become more apparent, below in conjunction with specific embodiment, to this Invention is further elaborated.Specific embodiment described herein is not used to limit only in order to explain the present invention The present invention.
Embodiment 1
A kind of hinged use bi-lug plate of workpiece, including welded plate 1 and connection otic placode 2, the connection otic placode 2 is located at welded plate 1 Top, the number of the connection otic placode 2 is 2, offers pin hole 3, and the connection otic placode 2 is closed in the connection otic placode 2 It is symmetrical arranged in welded plate 1, the welded plate 1 is fixedly connected with connection otic placode 2, the material of the welded plate 1 and connection otic placode 2 Mild steel is, the welded plate 1 and connection otic placode 2 are connected by way of welding, and the company of welded plate 1 and connection otic placode 2 The place of connecing offers bevel for welding.
The invention allows for a kind of processing technology of the hinged use bi-lug plate of workpiece, comprises the steps:
S1, raw material prepare, and choose mild steel steel plate raw material, buy the rule of the steel plate for making welded plate on material market Lattice thickness is 20mm, and the gauge thickness for making the steel plate of connection otic placode is 15mm, and pickup is standby;
S2, the blanking of welded plate and process, the specification for obtaining in S1 is transferred to blanking workshop for the steel plate of 20mm to be carried out Processing, according to layout design size, is programmed in numerical control chamber, carries out blanking using plasma digital control cutting machine, and blanking is completed Afterwards, the welded plate of acquisition is delivered to finishing department after workpiece cooling, is existed using abrasive machine by standing cooling 20min-30min Bevel for welding is outputed in the junction of welded plate and connection otic placode, controls machining accuracy in ± 0.5mm, the workpiece that then will obtain Being transferred to polishing workshop carries out grinding process, will be clean to the burr at welding plate surface and edge, waste scrap, and pickup is standby;
S3, the blanking of connection otic placode and process, the specification for obtaining are transferred to blanking workshop for the steel plate of 15mm enter in S1 Row processing, according to layout design size, is programmed in numerical control chamber, carries out blanking using plasma digital control cutting machine, and blanking is complete Cheng Hou, standing cooling 20min-30min, after workpiece cooling, the connection otic placode of acquisition being delivered to polishing workshop carries out burnishing part Reason, will be clean to the burr at welding plate surface and edge, waste scrap, and pickup is standby;
S4, normalized treatment, the connection otic placode for obtaining in the welded plate that S2 is obtained and S3 is transferred to normalizing workshop just to be carried out Fire is processed, and control normalizing temperature is between 750 DEG C -800 DEG C, and the normalizing time, between 40min-50min, improves the mechanicalness of steel Energy;
S5, annealing, the welded plate crossed by normalized treatment in S4 and connection otic placode make annealing treatment, using air-cooled Heat on workpiece is taken away rapidly by the type of cooling using aerator, realizes fast cooling, and cool time is 50min-60min, After workpiece cooling, the welded plate of acquisition and connection otic placode are transferred to rivet welding workshop and are assembled, pickup is standby;
The welding assembly of S6, welded plate and connection otic placode, the welded plate for obtaining in S5 and connection otic placode are carried out welding group Dress, is positioned at connection otic placode on welded plate by the method for spot welding first, carries out full weld then along bevel for welding, during cooling Between be 50min-60min, after workpiece cooling after, by the Workpiece transfer of acquisition to polish workshop carry out grinding process, by workpiece table The burr at face and edge, waste scrap are clean, and pickup is standby;
S7, straightening processing, the Workpiece transfer for obtaining are processed to workshop is aligned, control the flatness of workpiece in S6 In ± 0.02mm, pickup is standby;
S8, blasting treatment, the Workpiece transfer for obtaining in S7 to sand-blast shop is carried out blasting treatment, by the ferrum of surface of the work Rust, dust etc. are cleaned out, and pickup is standby;
S9, zinc-plated process, the Workpiece transfer for obtaining after blasting treatment in S8 is carried out zinc-plated process, coating to zinc-plated workshop In process, make conducting salt, boric acid by the use of salt zinc oxide, potassium chloride and make pH value buffer agent as zinc-plated formula, using DC source With numerical control Double-pulse Plating Power Source, under the conditions of magnetic agitation, in the electrolysis bath of the two poles of the earth, electrogalvanizing is carried out, thickness of coating is in 4um-7um Between, in coating Passivation Treatment, 30 DEG C of light-emitting solution being made up of 35ml/L nitric acid and 10ml/L hydrochloric acid goes out light 2s, after passivation Rinse in hot water, then drying 20min under the conditions of 80 DEG C carries out aging, after the zinc coat of surface of the work dries, takes Part is standby;
S10, packaging.
Welding current is controlled in step S6, and prime coat is using 100~120A or so, and the welding current scope of packed layer exists Between 150~250A, welding current is suitably reduced by capping layer, between 150~160A.
In sum:Compared with prior art, present configuration is simple, easy to use, after heat treatment, the machinery of mild steel Performance is greatly reinforced, and by opening up bevel for welding in weld, strengthens weld strength, and processing technology is simple, reasonable in design, its use Material is few, low cost, easy to install, reduces enterprise's production capacity.
The above, the only present invention preferably specific embodiment, but protection scope of the present invention is not limited thereto, Any those familiar with the art the invention discloses technical scope in, technology according to the present invention scheme and its Inventive concept equivalent or change in addition, should all be included within the scope of the present invention.

Claims (5)

1. the hinged use bi-lug plate of a kind of workpiece, including welded plate (1) and connection otic placode (2), it is characterised in that:The connection otic placode (2) welded plate (1) top is located at, and the number of connection otic placode (2) is 2, offers pin hole on connection otic placode (2) (3), and the connection otic placode (2) is symmetrical arranged with regard to welded plate (1), welded plate (1) and connection otic placode (2) are fixing even Connect.
2. the hinged use bi-lug plate of a kind of workpiece according to claim 1, it is characterised in that:Welded plate (1) and connection The material of otic placode (2) is mild steel.
3. the hinged use bi-lug plate of a kind of workpiece according to claim 1, it is characterised in that:Welded plate (1) and connection Otic placode (2) is connected by way of welding, and the junction of welded plate (1) and connection otic placode (2) offers bevel for welding.
4. the processing technology of the hinged use bi-lug plate of workpiece described in a kind of claim 1, it is characterised in that:Comprise the steps:
S1, raw material prepare, and choose mild steel steel plate raw material on material market, buy the specification thickness of the steel plate for making welded plate Spend for 20mm, the gauge thickness for making the steel plate of connection otic placode is 15mm, pickup is standby;
S2, the blanking of welded plate and process, the specification for obtaining are transferred to blanking workshop for the steel plate of 20mm are processed in S1, According to layout design size, being programmed in numerical control chamber, blanking is carried out using plasma digital control cutting machine, after the completion of blanking, quiet Cooling 20min-30min is put, after workpiece cooling, the welded plate of acquisition is delivered to finishing department, using abrasive machine in welded plate Bevel for welding is outputed with the junction of connection otic placode, control machining accuracy in ± 0.5mm, then by the Workpiece transfer for obtaining extremely Polishing workshop carries out grinding process, will be clean to the burr at welding plate surface and edge, waste scrap, and pickup is standby;
S3, the blanking of connection otic placode and process, by the specification for obtaining in S1 for 15mm steel plate be transferred to blanking workshop carry out plus Work, according to layout design size, is programmed in numerical control chamber, carries out blanking using plasma digital control cutting machine, after the completion of blanking, Standing cooling 20min-30min, after workpiece cooling, the connection otic placode of acquisition being delivered to polishing workshop carries out grinding process, will weldering The burr at fishplate bar surface and edge, waste scrap are clean, and pickup is standby;
S4, normalized treatment, the connection otic placode for obtaining in the welded plate that S2 is obtained and S3 is transferred to normalizing workshop to be carried out at normalizing Reason, control normalizing temperature is between 750 DEG C -800 DEG C, and the normalizing time, between 40min-50min, improves the mechanical performance of steel;
S5, annealing, the welded plate crossed by normalized treatment in S4 and connection otic placode make annealing treatment, using air-cooled cooling Heat on workpiece is taken away rapidly by mode using aerator, realizes fast cooling, and cool time is 50min-60min, to treat work After part cooling, the welded plate of acquisition and connection otic placode are transferred to rivet welding workshop and are assembled, pickup is standby;
The welding assembly of S6, welded plate and connection otic placode, the welded plate for obtaining in S5 and connection otic placode are carried out welding assembly, first The method for first passing through spot welding is positioned at connection otic placode on welded plate, carries out full weld then along bevel for welding, and cool time is 50min-60min, after workpiece cooling, the Workpiece transfer of acquisition is carried out grinding process to workshop of polishing, by surface of the work and The burr at edge, waste scrap are clean, and pickup is standby;
S7, straightening processing, by the Workpiece transfer for obtaining in S6 to align workshop processed, make workpiece flatness control ± 0.02mm, pickup is standby;
S8, blasting treatment, the Workpiece transfer for obtaining in S7 to sand-blast shop is carried out blasting treatment, by the rust of surface of the work, Dust etc. is cleaned out, and pickup is standby;
S9, zinc-plated process, Workpiece transfer to the zinc-plated workshop for obtaining after blasting treatment in S8 is carried out zinc-plated process, and coating is processed In, make conducting salt, boric acid by the use of salt zinc oxide, potassium chloride and make pH value buffer agent as zinc-plated formula, using DC source sum Control Double-pulse Plating Power Source, carry out electrogalvanizing under the conditions of magnetic agitation in the electrolysis bath of the two poles of the earth, thickness of coating 4um-7um it Between, in coating Passivation Treatment, 30 DEG C of light-emitting solution being made up of 35ml/L nitric acid and 10ml/L hydrochloric acid goes out light 2s, in heat after passivation Rinse in water, then dry under the conditions of 80 DEG C 20min carry out aging, after the zinc coat of surface of the work dries, pickup Standby;
S10, packaging.
5. the processing technology of the hinged use bi-lug plate of a kind of workpiece according to claim 4, it is characterised in that:Control in step S6 Make welding current, prime coat is using 100~120A or so, the welding current scope of packed layer between 150~250A, capping Welding current is suitably reduced by layer, between 150~160A.
CN201611025839.6A 2016-11-18 2016-11-18 Double-lug plate for hinging work-pieces and manufacturing technology thereof Pending CN106425316A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611025839.6A CN106425316A (en) 2016-11-18 2016-11-18 Double-lug plate for hinging work-pieces and manufacturing technology thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611025839.6A CN106425316A (en) 2016-11-18 2016-11-18 Double-lug plate for hinging work-pieces and manufacturing technology thereof

Publications (1)

Publication Number Publication Date
CN106425316A true CN106425316A (en) 2017-02-22

Family

ID=58221706

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611025839.6A Pending CN106425316A (en) 2016-11-18 2016-11-18 Double-lug plate for hinging work-pieces and manufacturing technology thereof

Country Status (1)

Country Link
CN (1) CN106425316A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107962349A (en) * 2017-11-13 2018-04-27 昆山市福玛精密钣金有限公司 Pre-determined bit formula is to ear connecting plate preparation process
CN108436090A (en) * 2018-04-04 2018-08-24 广东鸿图南通压铸有限公司 A kind of zincincation of powder metallurgy holder
CN108747210A (en) * 2018-05-10 2018-11-06 来安县隆华摩擦材料有限公司 A kind of clutch disc hole opening technology
CN108942085A (en) * 2017-05-17 2018-12-07 中科智远信息科技有限公司 Radar fixing frame hole forming process
CN113102950A (en) * 2021-04-15 2021-07-13 浙江精工钢结构集团有限公司 Special-shaped section hot galvanizing stiffening plate and manufacturing process thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06339819A (en) * 1992-10-17 1994-12-13 Hoesch Platinen Gmbh Method for manufacturing welded steel plate-made intermediate article
CN104646934A (en) * 2013-11-25 2015-05-27 大连康赛谱科技发展有限公司 Method for manufacturing high-speed steel and low-carbon steel compounded metal plate
CN204454343U (en) * 2014-12-31 2015-07-08 山东大汉建设机械有限公司 A kind of otic placode connection device
CN204586423U (en) * 2015-02-09 2015-08-26 上海金翅鹏实业有限公司 A kind of transition wheel support and transition wheel bracket assembly
CN105644452A (en) * 2014-11-12 2016-06-08 上海海拉电子有限公司 Vehicle radar installation support
CN105966552A (en) * 2016-07-11 2016-09-28 江苏工力重机有限公司 Adjustable windproof mooring seat structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06339819A (en) * 1992-10-17 1994-12-13 Hoesch Platinen Gmbh Method for manufacturing welded steel plate-made intermediate article
CN104646934A (en) * 2013-11-25 2015-05-27 大连康赛谱科技发展有限公司 Method for manufacturing high-speed steel and low-carbon steel compounded metal plate
CN105644452A (en) * 2014-11-12 2016-06-08 上海海拉电子有限公司 Vehicle radar installation support
CN204454343U (en) * 2014-12-31 2015-07-08 山东大汉建设机械有限公司 A kind of otic placode connection device
CN204586423U (en) * 2015-02-09 2015-08-26 上海金翅鹏实业有限公司 A kind of transition wheel support and transition wheel bracket assembly
CN105966552A (en) * 2016-07-11 2016-09-28 江苏工力重机有限公司 Adjustable windproof mooring seat structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108942085A (en) * 2017-05-17 2018-12-07 中科智远信息科技有限公司 Radar fixing frame hole forming process
CN107962349A (en) * 2017-11-13 2018-04-27 昆山市福玛精密钣金有限公司 Pre-determined bit formula is to ear connecting plate preparation process
CN108436090A (en) * 2018-04-04 2018-08-24 广东鸿图南通压铸有限公司 A kind of zincincation of powder metallurgy holder
CN108747210A (en) * 2018-05-10 2018-11-06 来安县隆华摩擦材料有限公司 A kind of clutch disc hole opening technology
CN113102950A (en) * 2021-04-15 2021-07-13 浙江精工钢结构集团有限公司 Special-shaped section hot galvanizing stiffening plate and manufacturing process thereof

Similar Documents

Publication Publication Date Title
CN106425316A (en) Double-lug plate for hinging work-pieces and manufacturing technology thereof
CN104786003B (en) The restorative procedure of housing main bearing dead eye
CN111805247B (en) Automatic milling, grinding and polishing combined machining system and method for large workpiece
CN103273280B (en) A kind of processing method of special type inspection template
CN103143897B (en) Elongated fillet long purlin anti-deformation processing method
CN103692172A (en) Method for manufacturing titanium alloy straightener blade
CN105108346A (en) Stainless steel weld joint and surrounding impurity treatment process
CN110253231B (en) Machining method for removing burrs of solid retainer
CN103433684A (en) Online repairing method for bearing position abrasion of main shaft of fan
CN109290920A (en) A kind of ironcasting blank automatic finishing device and method
CN107263027A (en) A kind of titanium alloy single frame class method of processing parts
CN104759717A (en) Finishing machining method for metal rotation surface based on dual-peak pulse current and electrochemical machinery
CN106378592A (en) Machining technology for metal container with riveting nut
CN105328399A (en) Machining method for split casing type parts of aero-engines
CN202910298U (en) Numerically controlled lathe with double cross sliding tables and double systems
CN103600213A (en) Method for manufacturing cutting edges of cutting boards of hot shearing machines for bars
CN102059591A (en) Combined machine tool capable of simultaneously performing machining at stations
CN108044438B (en) Automobile forge piece overlap removal device and method based on robot speed Control
CN102848152A (en) Processing method of manipulators
CN109465677A (en) A kind of robot constant force polishing method
CN103862236A (en) Processing method of mechanical parts
CN106378586B (en) A kind of processing excircles cambered surface process and rotary support used
CN209304295U (en) A kind of ironcasting blank automatic finishing device
CN114102069A (en) FOD antenna processing technology
CN104087980B (en) The method improving the precision of Dual-head chamfering machining shock absorber working cylinder end

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170222