CN106400837A - Horizontal sliding and transporting method for pipelines in pipe corridor - Google Patents
Horizontal sliding and transporting method for pipelines in pipe corridor Download PDFInfo
- Publication number
- CN106400837A CN106400837A CN201611076354.XA CN201611076354A CN106400837A CN 106400837 A CN106400837 A CN 106400837A CN 201611076354 A CN201611076354 A CN 201611076354A CN 106400837 A CN106400837 A CN 106400837A
- Authority
- CN
- China
- Prior art keywords
- screw sleeve
- monorail crane
- straight screw
- pipelines
- transporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Electric Cable Installation (AREA)
Abstract
The invention relates to a horizontal sliding and transporting method for pipelines in a pipe corridor. The method includes the steps of installing a roof formwork of a utility tunnel; paying off embedding position lines of straight threaded sleeves according to a predesigned position plan of embedded parts of a monorail crane; embedding the straight threaded sleeves into a bottom plate according to the embedding position lines of the straight threaded sleeves; blocking the lower ends of the straight threaded sleeves; attaching the outer ends of the straight threaded sleeves to the upper surface of the roof formwork; pouring concrete and disassembling the roof formwork after the concrete reaches the form stripping strength; installing a monorail crane rail through bolts; and installing the monorail crane on the monorail crane rail. According to the horizontal sliding and transporting method for the pipelines in the pipe corridor, a detachable sliding rail is manufactured by embedding bolt sleeves for transporting the pipelines, the bolt sleeves are embedded into a slab, then the rail are installed on a roof through the bolts, the electric monorail crane is adopted for transporting the pipelines, and therefore the manpower is greatly saved, the health of workers is guaranteed, the transporting and installing efficiency of the pipelines is improved, and the construction cost is lowered.
Description
Technical field
The present invention relates to a kind of construction techniques, specifically, it is to be related to a kind of piping lane pipe level slip transporter
Method.
Background technology
Underground pipe gallery system not only solves Urban Traffic Jam Based, also greatly facilitate electric power, communication, combustion gas,
The maintenance of the urban operating mechanisms such as water supply and sewage and maintenance.Additionally, this system also has certain protection against and mitigation of earthquake disasters effect.
Underground pipe gallery plays an important role with the city integrated bearing capacity of raising to meeting people's livelihood primary demand.
Common trench construction avoids frequently excavating road and traffic and resident trip being made due to laying and keeping in repair underground utilities
Become impact and disturb, keep the appearance of a street complete and attractive in appearance.
Reduce the expense repeatedly overhauled on road surface and the maintenance cost of utilities pipeline.Maintain the integrity on road surface and all kinds of
The durability of pipeline, is easy to laying, increase and decrease, keeping in repair and daily management of various pipelines.
Due to common trench gut line compact and reasonable arrangement, it is effectively utilized the space under road, has saved urban land;By
In the inspection shaft of the roofbolt decreasing road and various pipeline, room etc., the graceful landscape in city;Because aerial pipeline enters together
Ground, reduces the contradiction of aerial line and greening.
In underground pipe gallery system construction, various pipeline transportation are installed traditional construction and are constructed using ground monorail crane,
Because in piping lane, space is less, pipe level transport expends a large amount of manpower and materials, there is many potential safety hazards.
Content of the invention
For above-mentioned deficiency of the prior art, the present invention provides a kind of safe and reliable, raising efficiency of construction, reduces construction
The piping lane pipe level slip way of transportation of cost.
The technical solution used in the present invention is:
A kind of piping lane pipe level slip way of transportation,
Underground pipe gallery roof plate template is installed;
The monorail crane embedded part location drawing designing on the estimation releases the pre-buried position line of straight screw sleeve;
Colligation roof steel bar;
According to the pre-buried position line of straight screw sleeve on base plate pre-buried straight screw sleeve;
Fixation tightened by the reinforcing bar of straight screw sleeve upper end mantle fiber;
Straight screw sleeve lower end is blocked;
Straight screw sleeve is perpendicular to roof plate template;
Fitted with roof plate template upper surface in the end of straight screw sleeve outer end;
Casting concrete, reaches dismounting roof plate template after strength of mould stripping after concrete;
Find out straight screw sleeve and pluck out closure;
Monorail crane rail is installed by bolt;
Monorail crane is installed on monorail crane rail.
Described monorail crane adopts two electric block transport pipelines;One electric hoist configures forward drive power, and another auxiliary
Help.
The beneficial effect of hinge structure of the present invention:
Piping lane pipe level slip way of transportation of the present invention, makes detachable sliding rail come delivery tube by built-in bolt sleeve
Road, built-in bolt sleeve on floor, then track bolt is arranged on top board, afterwards line pipe is lifted up into using electric monorail
Road transports, thus a large amount of manpowers saved, it is ensured that personnel health, improve the efficiency of pipeline transportation installation, thus improving engineering
Integral construction progress.Pipeline transportation finishes and associated components and device can be disassembled reuse, reduces construction cost.
Brief description
Fig. 1 is the construction process schematic diagram of piping lane pipe level slip way of transportation of the present invention;
Fig. 2 is the construction present invention looks up structural representation of piping lane pipe level slip way of transportation of the present invention;
Fig. 3 is the 1-1 cross section structure diagram of Fig. 2;
Fig. 4 is the anchor bar main structure diagram of piping lane pipe level slip way of transportation of the present invention;
Fig. 5 is the anchor bar left view structural representation of piping lane pipe level slip way of transportation of the present invention.
Critical piece symbol description in accompanying drawing:
In figure:
1st, straight screw sleeve is pre- 2, anchor bar
3rd, top board 4, roof plate template
5th, connect reinforcing bar.
Specific embodiment
Referring to the drawings and embodiment the present invention will be described in detail:
Accompanying drawing 1-5 understands, a kind of piping lane pipe level slip way of transportation,
Underground pipe gallery roof plate template 4 is installed;
The monorail crane embedded part location drawing designing on the estimation releases the pre-buried position line of straight screw sleeve 1;
Colligation roof steel bar;
According to the pre-buried position line of straight screw sleeve 1 on base plate 3 pre-buried straight screw sleeve 1;
Fixation tightened by the reinforcing bar of straight screw sleeve 1 upper end mantle fiber;
Straight screw sleeve 1 lower end is blocked;
Straight screw sleeve 1 is perpendicular to roof plate template 4;
Fitted with roof plate template 4 upper surface in the end of straight screw sleeve 1 outer end;
Casting concrete, reaches dismounting roof plate template 4 after strength of mould stripping after concrete;
Find out straight screw sleeve 1 and pluck out closure;
Monorail crane rail is installed by bolt;
Monorail crane is installed on monorail crane rail.
Described monorail crane adopts two electric block transport pipelines;One electric hoist configures forward drive power, and another auxiliary
Help.Synchronously carried out with guarantee lifting safety, treat that monorail crane debugging, examination and test run finish, pipeline transportation can be carried out.
A kind of piping lane pipe level slip conveying arrangement,
The pre-buried straight screw sleeve 1 being arranged in piping lane top board 4 and the monorail crane rail being connected with straight screw sleeve 1;
Described straight screw sleeve 1 outboard end surface and piping lane top board surface are in same horizontal plane;
The inner of described straight screw sleeve 1 is connected with the outboard end of anchor bar 2;
The outboard end of described anchor bar 2 is provided with external screw thread;
The outboard end of described anchor bar 2 is connected with straight screw sleeve 1 by screw thread;
Described monorail crane rail is connected with straight screw sleeve 1 by bolt.
Anchor bar is L-shaped.
Anchor bar is in rice font away from one end of straight screw sleeve.
Adjacent anchor bar passes through connection reinforcing bar 5 and is connected.
The above, be only presently preferred embodiments of the present invention, not the structure of the present invention is made any pro forma
Limit.Any simple modification, equivalent variations and modification that every technical spirit according to the present invention is made to above example, all
Belong in the range of technical scheme.
Claims (2)
1. a kind of piping lane pipe level slip way of transportation it is characterised in that
Underground pipe gallery roof plate template is installed;
The monorail crane embedded part location drawing designing on the estimation releases the pre-buried position line of straight screw sleeve;
Colligation roof steel bar;
According to the pre-buried position line of straight screw sleeve on base plate pre-buried straight screw sleeve;
Fixation tightened by the reinforcing bar of straight screw sleeve upper end mantle fiber;
Straight screw sleeve lower end is blocked;
Straight screw sleeve is perpendicular to roof plate template;
Fitted with roof plate template upper surface in the end of straight screw sleeve outer end;
Casting concrete, reaches dismounting roof plate template after strength of mould stripping after concrete;
Find out straight screw sleeve and pluck out closure;
Monorail crane rail is installed by bolt;
Monorail crane is installed on monorail crane rail.
2. according to claim 1 piping lane pipe level slip way of transportation it is characterised in that:Described monorail crane adopts two
Electric block transport pipeline;One electric hoist configures forward drive power, another auxiliary.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611076354.XA CN106400837A (en) | 2016-11-30 | 2016-11-30 | Horizontal sliding and transporting method for pipelines in pipe corridor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611076354.XA CN106400837A (en) | 2016-11-30 | 2016-11-30 | Horizontal sliding and transporting method for pipelines in pipe corridor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106400837A true CN106400837A (en) | 2017-02-15 |
Family
ID=58084661
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611076354.XA Pending CN106400837A (en) | 2016-11-30 | 2016-11-30 | Horizontal sliding and transporting method for pipelines in pipe corridor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106400837A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101183779A (en) * | 2007-12-14 | 2008-05-21 | 李作河 | Overhead rail type integral moving monorail crane |
CN202790904U (en) * | 2012-08-17 | 2013-03-13 | 陕西化建工程有限责任公司 | Monorail trolley transportation device for construction of pipeline corridor frame of process pipeline |
CN103255840A (en) * | 2013-04-28 | 2013-08-21 | 江苏省华建建设股份有限公司 | Combined built-in fitting for concrete walls and column tie bars and installation construction method thereof |
CN105398953A (en) * | 2015-12-01 | 2016-03-16 | 中国二十二冶集团有限公司 | Horizontal conveying construction method for underground pipe gallery and pipeline |
CN205151546U (en) * | 2015-09-29 | 2016-04-13 | 中建安装工程有限公司 | Quick assembly disassembly formula multilayer piping lane poling device |
-
2016
- 2016-11-30 CN CN201611076354.XA patent/CN106400837A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101183779A (en) * | 2007-12-14 | 2008-05-21 | 李作河 | Overhead rail type integral moving monorail crane |
CN202790904U (en) * | 2012-08-17 | 2013-03-13 | 陕西化建工程有限责任公司 | Monorail trolley transportation device for construction of pipeline corridor frame of process pipeline |
CN103255840A (en) * | 2013-04-28 | 2013-08-21 | 江苏省华建建设股份有限公司 | Combined built-in fitting for concrete walls and column tie bars and installation construction method thereof |
CN205151546U (en) * | 2015-09-29 | 2016-04-13 | 中建安装工程有限公司 | Quick assembly disassembly formula multilayer piping lane poling device |
CN105398953A (en) * | 2015-12-01 | 2016-03-16 | 中国二十二冶集团有限公司 | Horizontal conveying construction method for underground pipe gallery and pipeline |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205276316U (en) | Modular prefabricated piping lane | |
CN104631349B (en) | A kind of dismounting of urban viaduct steel box-girder and deposit method | |
CN205296342U (en) | Run by gravity sewage system in utility tunnel | |
CN208074267U (en) | A kind of hanging bracing means of Urban Underground pipe gallery excavation pit gut line | |
CN205479706U (en) | Push pipe work jing ding advances structure | |
CN110410099A (en) | It is a kind of using corrugated plating come the construction method of Strengthening Tunnel | |
CN106320370A (en) | Underground comprehensive pipe rack system | |
CN204040021U (en) | Large diameter pile construction equipment system in city underground engineering tunneling pilot tunnel | |
CN106996483B (en) | A kind of city integrated piping lane pipe sedimentation automatic control support | |
CN206396792U (en) | A kind of three-way sewage pipe crosses pipe gallery crossover node structure | |
CN206538685U (en) | Twin shaft pier and middle binder truss move integrally system | |
CN106400837A (en) | Horizontal sliding and transporting method for pipelines in pipe corridor | |
CN206308706U (en) | Piping lane pipe level slides conveying arrangement | |
CN205954680U (en) | Novel utility tunnel | |
CN206396789U (en) | A kind of comprehensive pipe gallery structure for being easy to sewage collecting to discharge | |
CN205475320U (en) | Semi -underground formula utility tunnel | |
CN205742273U (en) | A kind of fiberglass pipe gallery | |
CN107268680A (en) | Prefabricated double-bin underground comprehensive pipe gallery | |
CN107747321A (en) | Assembled steel system utility tunnel sewage conduit overhauls structure | |
CN113482046A (en) | Pipe gallery segment installation construction system and method | |
CN209637775U (en) | Prevent the two lining trolleys that vault comes to nothing | |
CN106351259A (en) | Pipe gallery assembly type bridge frame installing method | |
CN105604089A (en) | Semi-underground comprehensive pipe gallery | |
CN207176735U (en) | A kind of pipe gallery formwork for placing fixes device | |
CN205857240U (en) | A kind of prefabricated pipe gallery |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170215 |