CN106368645B - SAGD well temperature measuring cable is with pressure to be mentioned, under construction method - Google Patents

SAGD well temperature measuring cable is with pressure to be mentioned, under construction method Download PDF

Info

Publication number
CN106368645B
CN106368645B CN201610911934.XA CN201610911934A CN106368645B CN 106368645 B CN106368645 B CN 106368645B CN 201610911934 A CN201610911934 A CN 201610911934A CN 106368645 B CN106368645 B CN 106368645B
Authority
CN
China
Prior art keywords
temperature measuring
pressure
measuring cable
packing
greasing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610911934.XA
Other languages
Chinese (zh)
Other versions
CN106368645A (en
Inventor
桑林翔
周晓义
万宏宾
禄红新
刘崇勇
曲方舟
颜伟
朱德纯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KARAMAY TIANXINGTAI PETROLEUM SCIENCE & TECHNOLOGY Co Ltd
Original Assignee
KARAMAY TIANXINGTAI PETROLEUM SCIENCE & TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KARAMAY TIANXINGTAI PETROLEUM SCIENCE & TECHNOLOGY Co Ltd filed Critical KARAMAY TIANXINGTAI PETROLEUM SCIENCE & TECHNOLOGY Co Ltd
Priority to CN201610911934.XA priority Critical patent/CN106368645B/en
Publication of CN106368645A publication Critical patent/CN106368645A/en
Application granted granted Critical
Publication of CN106368645B publication Critical patent/CN106368645B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/02Surface sealing or packing
    • E21B33/03Well heads; Setting-up thereof
    • E21B33/068Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells
    • E21B33/072Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells for cable-operated tools

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses SAGD well temperature measuring cable it is with pressure mention, under construction method.It goes into the well the following steps are included: temperature measuring cable is with pressure: being fastened being installed behind fan-shaped one end of I-shaped flange and well head cooperation;By temperature measuring cable it is with pressure mention, lower sealing device is all installed and is fastened and stops;It is put into packing into packing box, and compresses packing with gland for packing box, whether observation packing is sealed temperature measuring cable, then opens thermal recovery gate valve, and temperature measuring cable is mentioned, introduced at the top of lower sealing device up to reaching design thermometric depth from temperature measuring cable is with pressure by injection device;After temperature measuring cable is lowered into design position, by grease filling machine to temperature measuring cable it is with pressure mention, the grease pouring valve greasing of the greasing sealer of lower sealing device, realize the sealing of temperature measuring cable;After being bled off pressure by relief valve, remove packing, it mentions by beating elevator again, remove packing gland, packing box, pressure relief flange and the sealer that surges lower sealing device upper end respectively since temperature measuring cable is with pressure, well head static seal device is finally installed and seals well head and temperature measuring cable;The present invention efficiently reduces pollution, protects environment.

Description

SAGD well temperature measuring cable is with pressure to be mentioned, under construction method
Technical field
The present invention relates to a kind of construction method, more particularly, to a kind of SAGD well temperature measuring cable it is with pressure mention, under construction method.
Background technique
At present SAGD well mention, lower temperature measuring equipment when, need first to stop taking out by producing well, stop infusing, wait the temperature of production well Degree declines with pressure, then carries out kill-job operation with pump truck and waterwheel, after well head is without pressure, opens well head test line and carries out thermometric The mentioning of cable, lower construction.The test of SAGD downhole temperature is conventional to be mentioned, lower operation can to operation oil well using high density well control fluids kill-job or Open flow means will carry out operation after oil well pressure reduction.High density well control fluids kill-job is not only at high cost, the time is long, Er Qiehui Blocking underground fluid swivels, influence oil recovery amount and steam injection efficiency.If be depressured using open flow, stratum energy not only can be largely reduced Amount, brings immeasurable loss to subsequent production, while will also result in environmental pollution.No pressure mentions, existing for lower temperature measuring equipment Problem:
1, the normal production cycle of production well is influenced, yield is reduced.
2, kill-job liquid measure is once excessive in Well Killing Process, will affect the fluctuation of oil recovery liquid level, makes producing well can not when serious Production needs operation again.
3, waste of resource, each kill-job at least need the water or strong brine of two to three vehicles;Strong brine has metal under high temperature Corrosion.
Summary of the invention
It provides a kind of structurally reasonable the present invention be directed to the above problem, does not need to stop well to bleed off pressure, cool down, realize that dynamic is close Envelope shortens construction period;Well killing fluid and its ground construction equipment and expense needed for reducing routine work, and pollution is reduced, protection The SAGD well temperature measuring cable of environment is with pressure to be mentioned, under construction method.
The technical solution that the present invention solves technical problem is: SAGD well temperature measuring cable is with pressure to be mentioned, under construction method, including with Lower step:
One, temperature measuring cable is with pressure goes into the well:
Step 1) by temperature measuring cable it is with pressure mention, in lower sealing device fan-shaped one end of I-shaped flange and well head cooperation after install It fastens;
Step 2 installs thermal recovery gate valve again, and sequentially installs greasing sealer on thermal recovery gate valve, hydraulic blowout preventer, lets out Pressure flange, packing box and packing gland, until by temperature measuring cable it is with pressure mention, lower sealing device is all installed and is fastened and stops;
Step 3) is put into packing into packing box, and compresses packing with gland for packing box, and whether observation packing is sealed survey Then warm cable opens thermal recovery gate valve 2, temperature measuring cable is mentioned, introduced at the top of lower sealing device from temperature measuring cable is with pressure by injection device Until reaching design thermometric depth;
After step 4) temperature measuring cable is lowered into design position, by grease filling machine to temperature measuring cable it is with pressure mention, the note of lower sealing device The grease pouring valve greasing of rouge sealer, realizes the sealing of temperature measuring cable;
After step 5) is bled off pressure by relief valve, remove packing, then by beat elevator from temperature measuring cable it is with pressure mention, lower sealing dress It sets upper end to start to remove packing gland, packing box, pressure relief flange and the sealer that surges respectively, well head standstill seal dress is finally installed It sets and seals well head and temperature measuring cable;
Two, temperature measuring cable proposition well head with pressure:
Step 1) realizes the sealing of temperature measuring cable by grease pouring valve greasing of the grease filling machine to greasing sealer;
Step 2 removes well head static seal device by way of beating elevator with crane cooperation, and seals in greasing Surge sealer, pressure relief flange, packing box and packing gland are sequentially installed on device, and fastened;
Step 3) proposes that device proposes temperature measuring cable into greasing sealer by temperature measuring cable, closes thermal recovery gate valve;
After step 4) is bled off pressure by relief valve, the packing in packing box is taken out, temperature measuring cable is all proposed;
Step 5) sequentially removes packing box, pressure relief flange, hydraulic blowout preventer and greasing sealer, finally installs well head again Static seal device is by wellhead sealing.
Need first to confirm well head pressure before the step 1) not higher than 5MPa, temperature is not higher than 300 DEG C, 100 meters of surrounding Interior steam injection well requires to stop infusing, and guarantees that the pressure and temp of construction well is stablized.
The other end for the I-shaped flange that the temperature measuring cable is with pressure to be mentioned, lower sealing device is one end flanges and well head matches The end flange of flange and thermal recovery gate valve is connected, and another end flanges of thermal recovery gate valve and the end flange of greasing sealer are connected, Another end flanges of greasing sealer and the end flange of hydraulic blowout preventer are connected, another end flanges of hydraulic blowout preventer with connect Pressure relief flange and packing box end flange be connected, the other end of packing box is threadedly coupled with packing gland, I-shaped flange and Thermal recovery gate valve, thermal recovery gate valve and greasing sealer, greasing sealer and hydraulic blowout preventer and hydraulic blowout preventer and pressure relief flange Ring gasket is equipped between pressure relief flange and packing box.
Pipe sleeve, greasing pressing sleeve and greasing positioning are respectively equipped at axial centre in the greasing sealer from top to down Nut, and the axial centre of three is equipped with the through-hole being adapted to temperature measuring cable diameter.
The transverse center line position of the pipe sleeve is at least provided with a grease pouring valve, and grease pouring valve is fixed on greasing sealer On.
The pressure relief flange lateral middle is equipped with relief valve.
At axial centre in the packing box to it is lower and on be respectively equipped with centralizer positioning screw cap, washer, centralizer, Tower packing and packing fixed stop.
It is additionally provided with centralizer at axial centre in the packing gland, and is contacted with packing.
The centralizer is two arc rings equipped with ectonexine, and the middle part dislocation lap joint of two arc rings is at circle It constitutes.
Hydraulic power unit of the hydraulic blowout preventer by distance greater than 10 meters controls.
The present invention has following advantages and effect compared with prior art:
The present invention does not need to stop well to bleed off pressure cooling, can shorten construction period;Reduce routine work needed for well killing fluid and its The expense of ground construction equipment.Using tower packing_seal, realize depressed in band mention, lower temperature measuring cable when dynamic sealing.Thermometric After cable tie depresses oil well, using grease injection method, realize with the wellhead sealing construction under pressure condition.It is with pressure mention, lower temperature measuring cable When, once dynamic sealing fail, hydraulic power unit with 15 meters of hydraulic blowout preventer distance, can in case of emergency start in time at a distance Hydraulic blowout preventer is sealed temperature measuring equipment, realizes blowout preventer.
In addition, the present invention does not have outside fluid invasion, oil-gas Layer is just without the injury of external solid phase, the gas phase of liquid phase, no New interlayer contradiction can be generated, formation pressure system not will receive destruction, does not need to re-establish balance, is conducive to oil well reparation Stable and high yields afterwards;Relative to it is traditional mention, lower temperature testing device operation, it is with pressure in the case where not open flow, not draining overflow Operation, does not need release for individual well, and the operation such as kill-job reduces costs, efficiently reduces pollution, protect environment, protects It has held the formation pressure system that entire note adopts network not to be damaged, has not needed to resettle pressing weighing apparatus, guaranteeing oil well output, improving Gas injection timeliness etc. has huge effect.The configuration of the present invention is simple, it is versatile, there is good economic benefit and society's effect Benefit.
Operating Pressure of the present invention can generate following significant comprehensive benefit:
1, payzone is protected, is improved reserves utilization rate (recovery ratio);
2, it realizes no pollution, extends the production cycle of oil/gas well;
3, environment is protected, zero-emission is realized in energy-saving and emission-reduction;
4, production capacity restoration costs have been saved;
5, well killing fluid cost has been saved;
6, do not stop production operation;
7, shorten the synthetic job duration.
Detailed description of the invention
Fig. 1 is schematic view of the front view of the invention;
Fig. 2 is the schematic view of the front view of centralizer of the present invention;
Fig. 3 is the overlooking structure diagram of centralizer of the present invention;
Major part in figure: I-shaped flange 1, thermal recovery gate valve 2, greasing positioning screw cap 3, hydraulic blowout preventer 4, grease pouring valve 5, note Rouge sealer 6, ring gasket 7, hydraulic blowout preventer 8, pressure relief flange 9, centralizer positioning screw cap 10, washer 11, centralizer 12 are surveyed Warm cable 13, packing gland 14, packing 15, packing box 16, relief valve 17, pipe sleeve 18.
Specific embodiment
The present invention will be described in further detail combined with specific embodiments below, but protection scope of the present invention is not had The embodiment of body is limited, and is subject to claims.In addition, with without prejudice under the premise of technical solution of the present invention, to this hair Any modifications or changes easy to accomplish of those of ordinary skill in the art made by bright fall within claim model of the invention Within enclosing.
Embodiment 1:
As shown in Figure 1, 2, 3, SAGD well temperature measuring cable it is with pressure mention, under construction method, comprising the following steps:
One, temperature measuring cable 13 is with pressure goes into the well:
Step 1) by temperature measuring cable it is with pressure mention, in lower sealing device fan-shaped one end of I-shaped flange 1 and well head cooperation after install It fastens;
Step 2 installs thermal recovery gate valve 2 again, and greasing sealer 6, hydraulic blowout preventer are sequentially installed on thermal recovery gate valve 2 8, pressure relief flange 9, packing box 16 and packing gland 14, until by temperature measuring cable it is with pressure mention, lower sealing device is all installed and is fastened It is good to stop;
Step 3) is put into packing into packing box, and compresses packing with gland for packing box, and whether observation packing is sealed survey Then warm cable opens thermal recovery gate valve 2, temperature measuring cable 13 is mentioned, drawn at the top of lower sealing device from temperature measuring cable is with pressure by injection device Enter until reaching design thermometric depth, tripping in controls lowering velocity in the process, and preventing from being hampered fractures, and one is first slowly above mentioned after being hampered Section distance is transferred again;
After step 4) temperature measuring cable 13 is lowered into design position, by grease filling machine to temperature measuring cable it is with pressure mention, lower sealing device Greasing sealer 65 greasing of grease pouring valve, realize temperature measuring cable 13 sealing;
After step 5) is bled off pressure by relief valve 17, remove packing, then by beat elevator from temperature measuring cable it is with pressure mention, lower sealing Device upper end starts to remove packing gland 14, packing box 16, pressure relief flange 9 and the sealer 8 that surges respectively, and it is quiet finally to install well head Only sealing device seals well head and temperature measuring cable 13;
Two, temperature measuring cable proposition well head with pressure:
Step 1) realizes the sealing of temperature measuring cable 13 by grease pouring valve 5 greasing of the grease filling machine to greasing sealer 6;
Step 2 removes well head static seal device, and on greasing sealer 6 by beating elevator mode with crane cooperation Surge sealer 8, pressure relief flange 9, packing box 16 and packing gland 14 are sequentially installed, and fastened;
Step 3) proposes that device proposes temperature measuring cable 13 into greasing sealer 6 by temperature measuring cable, closes thermal recovery gate valve 2;
After step 4) is bled off pressure by relief valve 17, the packing 15 in packing box 16 is taken out, temperature measuring cable 13 is all proposed;
Step 5) sequentially removes packing box 16, pressure relief flange 9, hydraulic blowout preventer 8 and greasing sealer 6, finally pacifies again Well head static seal device is filled by wellhead sealing.
Need first to confirm well head pressure before above-mentioned step 1) not higher than 5MPa, temperature is not higher than 300 DEG C, 100 meters of surrounding Interior steam injection well requires to stop infusing, and guarantees that the pressure and temp of construction well is stablized.
The I-shaped flange 1 that above-mentioned temperature measuring cable is with pressure to be mentioned, lower sealing device, which is one end flanges, to match with well head it is another End flanges and the end flange of thermal recovery gate valve 2 are connected, another end flanges of thermal recovery gate valve 2 and the end flange of greasing sealer 6 It is connected, another end flanges of greasing sealer 6 and the end flange of hydraulic blowout preventer 8 are connected, another hold-carrying of hydraulic blowout preventer 8 It is blue to be connected with the end flange of concatenated pressure relief flange 9 and packing box 16, the other end and 14 screw thread of packing gland of packing box 16 Connection, I-shaped flange 1 and thermal recovery gate valve 2, thermal recovery gate valve 2 and greasing sealer 6, greasing sealer 6 and hydraulic blowout preventer 8 and Ring gasket 7 is equipped between hydraulic blowout preventer 4 and pressure relief flange 9 and pressure relief flange 9 and packing box 16.
Pipe sleeve 18, greasing pressing sleeve 4 and greasing are respectively equipped at axial centre in above-mentioned greasing sealer 6 from top to down Positioning screw cap 3, and the axial centre of three is equipped with the through-hole being adapted to 13 diameter of temperature measuring cable.
The transverse center line position of above-mentioned pipe sleeve 18 is at least provided with a grease pouring valve 5, and to be fixed on greasing close for grease pouring valve 5 It seals on device 6.
Above-mentioned 9 lateral middle of pressure relief flange is equipped with relief valve 17.
At axial centre in above-mentioned packing box 15 to it is lower and on be respectively equipped with centralizer positioning screw cap 10, washer 11, Centralizer 12, tower packing 15 and packing fixed stop.
It is additionally provided with centralizer 12 at axial centre in above-mentioned packing gland 14, and is contacted with packing 15.
Above-mentioned centralizer 12 is two arc rings equipped with ectonexine, the middle part dislocation lap joint Cheng Yuan of two arc rings Shape is constituted.
Hydraulic power unit control of the above-mentioned hydraulic blowout preventer 8 by distance less than 10 meters.
Above-mentioned I-shaped flange 1, thermal recovery gate valve 2, hydraulic blowout preventer 8 and pressure relief flange 9 axial centre at be equipped with The through-hole of 35 ~ 60mm.
The through-hole being adapted to 13 diameter of temperature measuring cable is equipped at the axial centre of above-mentioned packing gland 14.

Claims (9)

1.SAGD well temperature measuring cable is with pressure to be mentioned, under construction method, it is characterised in that the following steps are included:
It goes into the well Step 1: temperature measuring cable (13) is with pressure:
1) it mentions temperature measuring cable is with pressure, installs and fasten after fan-shaped one end of I-shaped flange (1) and well head cooperation in lower sealing device;
2) it installs again thermal recovery gate valve (2), and greasing sealer (6), hydraulic blowout preventer is sequentially installed on thermal recovery gate valve (2) (8), pressure relief flange (9), packing box (16) and packing gland (14), until by temperature measuring cable it is with pressure mention, lower sealing device all pacify It fills and fastens and stop;
3) ajust temperature measuring cable it is with pressure mention, under, observation packing temperature measuring cable whether is sealed, then open thermal recovery gate valve (2), pass through note Enter device and temperature measuring cable (13) is mentioned, introduced up to reaching design thermometric depth at the top of lower sealing device from temperature measuring cable is with pressure;
4) after temperature measuring cable (13) is lowered into design position, by grease filling machine to temperature measuring cable it is with pressure mention, the greasing of lower sealing device it is close Grease pouring valve (5) greasing of device (6) is sealed, realizes the sealing of temperature measuring cable (13);
5) after bleeding off pressure by relief valve (17), packing is removed, then mention, on lower sealing device from temperature measuring cable is with pressure by beating elevator End starts to remove packing gland (14), packing box (16), pressure relief flange (9) and the sealer that surges (8) respectively, finally installs well head Static seal device seals well head and temperature measuring cable (13);
Step 2: temperature measuring cable proposition well head with pressure:
1) by grease pouring valve (5) greasing of grease filling machine to greasing sealer (6), the sealing of temperature measuring cable (13) is realized;
2) by beating elevator mode with crane cooperation, it is packed into packing, removes well head static seal device, and in greasing sealer (6) surge sealer (8), pressure relief flange (9), packing box (16) and packing gland (14) are sequentially installed on, and fastened;
3) it proposes that device proposes temperature measuring cable (13) into greasing sealer (6) by temperature measuring cable, closes thermal recovery gate valve (2);
4) after being bled off pressure by relief valve (17), the packing (15) in packing box (16) is taken out, temperature measuring cable (13) is all proposed;
5) packing box (16), pressure relief flange (9), hydraulic blowout preventer (8) and greasing sealer (6) are sequentially removed, is finally pacified again Well head static seal device is filled by wellhead sealing,
Pressure relief flange (9) lateral middle is equipped with relief valve (17).
2. SAGD well temperature measuring cable according to claim 1 is with pressure to be mentioned, under construction method, it is characterised in that the step Need first to confirm well head pressure before one not higher than 2MPa, temperature is not higher than 200 DEG C, and steam injection well requires to stop infusing in 100 meters of surrounding, protects The pressure and temp of card construction well is stablized.
3. SAGD well temperature measuring cable according to claim 1 is with pressure to be mentioned, under construction method, it is characterised in that the thermometric Another end flanges and thermal recovery gate valve for the I-shaped flange (1) that cable tie pressure mentions, lower sealing device is one end flanges and well head matching (2) end flange is connected, and another end flanges of thermal recovery gate valve (2) and the end flange of greasing sealer (6) are connected, and greasing is close Seal device (6) another end flanges and hydraulic blowout preventer (8) end flange be connected, another end flanges of hydraulic blowout preventer (8) with The end flange of concatenated pressure relief flange (9) and packing box (16) is connected, the other end of packing box (16) and packing gland (14) Be threadedly coupled, I-shaped flange (1) and thermal recovery gate valve (2), thermal recovery gate valve (2) and greasing sealer (6), greasing sealer (6) with It is all provided between hydraulic blowout preventer (8) and hydraulic blowout preventer (8) and pressure relief flange (9) and pressure relief flange (9) and packing box (16) There are ring gasket (7).
4. SAGD well temperature measuring cable according to claim 3 is with pressure to be mentioned, under construction method, it is characterised in that the greasing Pipe sleeve (18), greasing pressing sleeve (4) and greasing positioning screw cap (3) are respectively equipped at axial centre in sealer (6) from top to down, And the axial centre of three is equipped with the through-hole being adapted to temperature measuring cable (13) diameter.
5. SAGD well temperature measuring cable according to claim 4 is with pressure to be mentioned, under construction method, it is characterised in that the pipe sleeve (18) transverse center line position is at least provided with a grease pouring valve (5), and grease pouring valve (5) is fixed on greasing sealer (6).
6. SAGD well temperature measuring cable according to claim 3 is with pressure to be mentioned, under construction method, it is characterised in that the packing At axial centre in box (15) to it is lower and on be respectively equipped with centralizer positioning screw cap (10), washer (11), centralizer (12), tower The packing (15) and packing fixed stop of formula.
7. SAGD well temperature measuring cable according to claim 3 is with pressure to be mentioned, under construction method, it is characterised in that the packing It is additionally provided at axial centre in gland (14) centralizer (12), and is contacted with packing (15).
8. SAGD well temperature measuring cable according to claim 7 is with pressure to be mentioned, under construction method, it is characterised in that the righting Device (12) is two arc rings equipped with ectonexine, and the middle part dislocation lap joint of two arc rings is constituted at circle.
9. SAGD well temperature measuring cable according to claim 3 is with pressure to be mentioned, under construction method, it is characterised in that described surges Hydraulic power unit control of the preventer (8) by distance less than 10 meters.
CN201610911934.XA 2016-10-19 2016-10-19 SAGD well temperature measuring cable is with pressure to be mentioned, under construction method Active CN106368645B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610911934.XA CN106368645B (en) 2016-10-19 2016-10-19 SAGD well temperature measuring cable is with pressure to be mentioned, under construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610911934.XA CN106368645B (en) 2016-10-19 2016-10-19 SAGD well temperature measuring cable is with pressure to be mentioned, under construction method

Publications (2)

Publication Number Publication Date
CN106368645A CN106368645A (en) 2017-02-01
CN106368645B true CN106368645B (en) 2019-09-03

Family

ID=57895911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610911934.XA Active CN106368645B (en) 2016-10-19 2016-10-19 SAGD well temperature measuring cable is with pressure to be mentioned, under construction method

Country Status (1)

Country Link
CN (1) CN106368645B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086952B (en) * 2018-01-12 2024-06-14 科莱斯(天津)电热科技有限公司 High-pressure wellhead T-cable hanging and releasing integrated device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2135642Y (en) * 1992-09-01 1993-06-09 辽河石油勘探局茨榆坨采油厂 Changeable rod sealing device
CN2286239Y (en) * 1997-04-02 1998-07-15 中国石油天然气总公司石油勘探开发科学研究院廊坊分院完井工艺研究所 Low-voltage electric cable test wellhead blowout preventor
WO2013163607A1 (en) * 2012-04-27 2013-10-31 Rohrback Cosasco Systems, Inc. Magnetic retrieval tool
CN204040979U (en) * 2014-08-11 2014-12-24 中国石油化工股份有限公司 Hi-pot test well low frictional resistance logging cable sealer
CN104675357A (en) * 2013-12-02 2015-06-03 中国石油化工股份有限公司 Simple wellhead device and application method thereof
CN204804750U (en) * 2015-07-16 2015-11-25 任丘市博鑫石油机械制造有限公司 Cable blowout preventer
CN204804739U (en) * 2015-06-01 2015-11-25 中国石油化工股份有限公司 Oil pipe prevents gusher mouth pressure relief device
CN205172507U (en) * 2015-12-10 2016-04-20 盘锦鸿海钻采技术发展有限公司 Natural gas is annotated, is adopted well cable logging high pressure and prevents system of spouting

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8047295B2 (en) * 2007-04-24 2011-11-01 Fmc Technologies, Inc. Lightweight device for remote subsea wireline intervention

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2135642Y (en) * 1992-09-01 1993-06-09 辽河石油勘探局茨榆坨采油厂 Changeable rod sealing device
CN2286239Y (en) * 1997-04-02 1998-07-15 中国石油天然气总公司石油勘探开发科学研究院廊坊分院完井工艺研究所 Low-voltage electric cable test wellhead blowout preventor
WO2013163607A1 (en) * 2012-04-27 2013-10-31 Rohrback Cosasco Systems, Inc. Magnetic retrieval tool
CN104675357A (en) * 2013-12-02 2015-06-03 中国石油化工股份有限公司 Simple wellhead device and application method thereof
CN204040979U (en) * 2014-08-11 2014-12-24 中国石油化工股份有限公司 Hi-pot test well low frictional resistance logging cable sealer
CN204804739U (en) * 2015-06-01 2015-11-25 中国石油化工股份有限公司 Oil pipe prevents gusher mouth pressure relief device
CN204804750U (en) * 2015-07-16 2015-11-25 任丘市博鑫石油机械制造有限公司 Cable blowout preventer
CN205172507U (en) * 2015-12-10 2016-04-20 盘锦鸿海钻采技术发展有限公司 Natural gas is annotated, is adopted well cable logging high pressure and prevents system of spouting

Also Published As

Publication number Publication date
CN106368645A (en) 2017-02-01

Similar Documents

Publication Publication Date Title
CN204679347U (en) A kind of drilling fluid pressurization sealing crushing test device
CN102434135B (en) Multi-layer discharge and mining device for multiple seam developed area
CN108999597A (en) A kind of center completion tubular column and gaslift construction method for gaslift production
CN112012706A (en) Offshore thickened oil steam huff-puff injection-production integrated device
CN106368645B (en) SAGD well temperature measuring cable is with pressure to be mentioned, under construction method
CN106198933A (en) A kind of device of the gradient layer simulation for deep water weak consolidated formation well cementation intensity
CN104213888A (en) Down-hole steam injection string of thick-oil thermal production well
CN205605156U (en) Workover device is pressed in oil gas field area
CN206319854U (en) Colliery drilling and sealing device
CN106285547B (en) For SAGD well temperature measuring cable it is with pressure mention, under sealing device
CN205714137U (en) Compensation separate injection tubing string
CN206091928U (en) A sealing device that is used for SAGD well surveying temperature cable area pressure to carry, descend
CN104806211B (en) One kind takes over calm the anger extracting device of oil and method
CN103806878B (en) Not kill-job of sea electric pump lifting technology tubing string
CN203835374U (en) Wellhead ascension monitoring device for offshore heavy oil thermal recovery
CN204082070U (en) A kind of casing head of well head automatic compensation, annular space pressure relief device
CN207144900U (en) A kind of oil jacket annular pressure automatic protecting control device
CN203626689U (en) Shaft mouth protection, seal and connection device
CN206487435U (en) The totally-enclosed brill plug device of high pressure shallow-layer
CN105275422A (en) Thermal recovery casing head
CN201620887U (en) Machine-acquiring testing pipe-string for floating drilling rig
CN204212732U (en) A kind of reducing formula dual tubing oil recovery casing head of well head
CN203347704U (en) Well washing and oil draining device for pumping well
CN207212312U (en) A kind of multi-functional pressure obtaning device
CN202228039U (en) Ground hydraulic-control cable packer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant