CN106351245A - 塔吊基础座及其施工方法 - Google Patents
塔吊基础座及其施工方法 Download PDFInfo
- Publication number
- CN106351245A CN106351245A CN201610750488.9A CN201610750488A CN106351245A CN 106351245 A CN106351245 A CN 106351245A CN 201610750488 A CN201610750488 A CN 201610750488A CN 106351245 A CN106351245 A CN 106351245A
- Authority
- CN
- China
- Prior art keywords
- section
- heavy
- body frame
- tower crane
- gooseneck
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种塔吊基础座,包括多根主体框架柱、多块钢筋锚固板、大截面钢横梁框架;所述的多块钢筋锚固板分别预埋在多根主体框架柱上,大截面钢横梁框架的外端固定在多块钢筋锚固板上。由于本发明大截面钢横梁框架的外端通过螺栓固定在多块钢筋锚固板上,使得本发明大截面钢横梁框架塔吊基础安拆方便,省时省工又节地,符合绿色施工要求。
Description
技术领域
本发明涉及一种建筑施工设备领域,特别是涉及一种塔吊基础座及其施工方法。
背景技术
随着城市的建设与发展,高层、超高层建筑越来越多,塔吊基础的形式多种多样的,如:独立承台塔吊基础、设置于地下室底板或顶板塔吊基础、核心筒内爬式塔吊等。建筑施工中,各种建筑材料的垂直运输均由塔吊完成,塔吊的稳定性和牢固度直接影响到的施工的安全和进度。尤其是现代高层建筑和深层地下室的施工,塔吊基础往往设置在地下室中间,在地下室施工阶段,基础座平台以下是悬空的,因此对塔吊的要求相当高,一旦塔吊结构出现问题,其导致的后果将不堪设想。影响塔吊整体结构稳定的其中一个主要因素就是塔吊基础座,所有的承重都是由塔吊基础座传递的;除此以外,塔吊基础座还需承受额外的自然风力,所以,塔吊基础座的稳定和牢固是极其重要的。
发明内容
本发明的一个目的在于提供一种结构形式简单、节能环保、可重复使用的塔吊基础座。
本发明的另一个目的在于提供一种安拆方便、省时省工又节地、符合绿色施工要求的塔吊基础座的施工方法。
为实现上述目的,本发明的技术解决方案是:
本发明是一种塔吊基础座,包括多根主体框架柱、多块钢筋锚固板、大截面钢横梁框架;所述的多块钢筋锚固板分别预埋在多根主体框架柱上,大截面钢横梁框架的外端固定在多块钢筋锚固板上。
所述的大截面钢横梁框架由多根大截面H型钢横梁和多根大截面H型钢纵梁构成,多根大截面H型钢横梁分别固定多根大截面H型钢纵梁之间。
所述的大截面钢横梁框架由两根大截面H型钢横梁、两根大截面H型钢纵梁、两根大截面H型钢短纵梁构成;所述的两根大截面H型钢横梁分别平行固定在两根大截面H型钢纵梁之间,两根大截面H型钢短纵梁分别平行固定在两根大截面H型钢横梁之间。
所述的钢筋锚固板由钢筋、锚固板组成; 所述的钢筋为L形钢筋,其L端埋入主体框架柱内,其另一端伸出主体框架柱表面;所述的锚固板为角钢形,其一个侧面与L形钢筋伸出主体框架柱表面的伸出端焊接固定,锚固板的另一个侧面上开设多个通孔且螺栓通过该通孔与大截面钢横梁框架外端固接。
所述的主体框架柱由四根大截面框架柱构成,四根大截面框架柱呈矩形布置,大截面钢横梁框架的四个外端分别固定在四根大截面框架柱上,大截面钢横梁框架距离楼地面100mm-300 mm。
在主体框架柱上预埋钢板,将大截面钢横梁框架固定受力于主体框架柱上。
本发明是一种塔吊基础座的施工方法,包括以下步骤:
(1)测量放线;
(2) 对预埋件预埋位置进行精确定位;
(3)预埋件的制作,主体框架柱钢筋绑扎完成验收合格后,在主体框架柱上预埋钢筋锚固板;
(4)预埋件安装完成,浇捣混凝土,混凝土浇筑合格后及时保温保湿养护,并及时进行预埋件位置的复核测量;
(5)主体框架柱混凝土强度达到70%后安装大截面钢横梁框架,大截面钢横梁框架与预埋件采用高强螺栓连接。
采用上述方案后,由于本发明包括多根主体框架柱、多块钢筋锚固板、大截面钢横梁框架;所述的多块钢筋锚固板分别预埋在多根主体框架柱上,大截面钢横梁框架的外端固定在多块钢筋锚固板上,具有以下优点:
1、由于本发明大截面钢横梁框架的外端通过螺栓固定在多块钢筋锚固板上,使得本发明大截面钢横梁框架塔吊基础安拆方便,省时省工又节地,符合绿色施工要求。
2、与传统塔吊基础相比,本本发明的塔吊基础结构形式简单,节能环保,可重复使用。
3、由于本发明的大截面钢横梁框架塔吊基础设置于主体框架柱上,如,本发明可设置于地下室顶板上,主体结构转换层上等,但受力于主体框架柱上,而不是受力于地下室顶板或主体结构转换层楼地面。
下面结合附图和具体实施例对本发明作进一步的说明。
附图说明
图1是本发明的主视图;
图2是本发明主体框架柱与钢筋锚固板连接的示意图;
图3是本发明钢筋锚固板的正视图。
具体实施方式
如图1、图2所示,本发明是一种塔吊基础座,包括多根主体框架柱1、多块钢筋锚固板2、大截面钢横梁框架3。
所述的多块钢筋锚固板2分别预埋在多根主体框架柱1上,大截面钢横梁框架3的外端固定在多块钢筋锚固板2上。
所述的大截面钢横梁框架3由两根大截面H型钢横梁31、两根大截面H型钢纵梁32、两根大截面H型钢短纵梁33构成;所述的两根大截面H型钢横梁31分别平行固定在两根大截面H型钢纵梁32之间,两根大截面H型钢短纵梁33分别平行固定在两根大截面H型钢横梁31之间。
所述的钢筋锚固板2由钢筋21、锚固板22组成。所述的钢筋21为L形钢筋21,其L端埋入主体框架柱内,其另一端伸出主体框架柱1表面;所述的锚固板2为角钢形,其一个侧面与L形钢筋21伸出主体框架柱1表面的伸出端焊接固定,锚固板2的另一个侧面上开设多个通孔221(如图3所示)且螺栓通过该通孔221与大截面钢横梁框架3外端固接。
所述的主体框架柱1由四根大截面框架柱11构成,四根大截面框架柱11呈矩形布置,大截面钢横梁框架3的四个外端分别固定在四根大截面框架柱11上,大截面钢横梁框架3距离楼地面100mm-300 mm。
本发明是一种塔吊基础座的施工方法,包括以下步骤:
(1)测量放线;
(2) 对预埋件预埋位置进行精确定位;
(3)制作预埋件,主体框架柱1钢筋绑扎完成验收合格后,在主体框架柱1上预埋钢筋锚固板2,锚固长度为500mm。
(4)预埋件安装完成,按设计要求检查验收,合格后方可浇捣混凝土,混凝土为强度不小于C50的商品混凝土,浇捣过程中不得碰撞、移位钢筋预埋件,混凝土浇筑合格后及时保温保湿养护,并及时进行预埋件位置的复核测量,若有偏移应于混凝土初凝之前及时恢复;
(5)主体框架柱1混凝土强度达到70%后安装大截面钢横梁框架3,大截面钢横梁框架3与预埋件采用M20高强螺栓连接;
(6)主体框架柱1混凝土施工完成后,在基础四角预埋件上作好沉降及位移观测点,并作好原始记录;
(7)基础的防雷接地,按现行行业标准《建筑机械使用安全技术规程》JGJ33的规定执行。塔吊接地电阻值不大于4Ω。
(8)塔机底盘安装;
(9)塔吊基础验收;
(10)塔吊的拆除与常规塔吊拆除工序相同,钢结构基础拆除后除高强螺栓以外的其他钢构件可重复使用。
以上所述,仅为本发明较佳实施例而已,大截面钢横梁框架的结构形式有多种,故不能以此限定本发明实施的范围,即依本发明申请专利范围及说明书内容所作的等效变化与修饰,皆应仍属本发明专利涵盖的范围内。
Claims (7)
1.一种塔吊基础座,其特征在于:包括多根主体框架柱、多块钢筋锚固板、大截面钢横梁框架;所述的多块钢筋锚固板分别预埋在多根主体框架柱上,大截面钢横梁框架的外端固定在多块钢筋锚固板上。
2.根据权利要求1所述的塔吊基础座,其特征在于:所述的大截面钢横梁框架由多根大截面H型钢横梁和多根大截面H型钢纵梁构成,多根大截面H型钢横梁分别固定多根大截面H型钢纵梁之间。
3.根据权利要求1或2所述的塔吊基础座,其特征在于:所述的大截面钢横梁框架由两根大截面H型钢横梁、两根大截面H型钢纵梁、两根大截面H型钢短纵梁构成;所述的两根大截面H型钢横梁分别平行固定在两根大截面H型钢纵梁之间,两根大截面H型钢短纵梁分别平行固定在两根大截面H型钢横梁之间。
4.根据权利要求1所述的塔吊基础座,其特征在于:所述的钢筋锚固板由钢筋、锚固板组成; 所述的钢筋为L形钢筋,其L端埋入主体框架柱内,其另一端伸出主体框架柱表面;所述的锚固板为角钢形,其一个侧面与L形钢筋伸出主体框架柱表面的伸出端焊接固定,锚固板的另一个侧面上开设多个通孔且螺栓通过该通孔与大截面钢横梁框架外端固接。
5.根据权利要求1所述的塔吊基础座,其特征在于:所述的主体框架柱由四根大截面框架柱构成,四根大截面框架柱呈矩形布置,大截面钢横梁框架的四个外端分别固定在四根大截面框架柱上,大截面钢横梁框架距离楼地面100mm-300 mm。
6.一种根据权利要求1所述的塔吊基础座的施工方法,其特征在于:在主体框架柱上预埋钢板,将大截面钢横梁框架固定受力于主体框架柱上。
7.根据权利要求6所述的塔吊基础座的施工方法,其特征在于:包括以下步骤:
(1)测量放线;
(2) 对预埋件预埋位置进行精确定位;
(3)预埋件的制作,主体框架柱钢筋绑扎完成验收合格后,在主体框架柱上预埋钢筋锚固板;
(4)预埋件安装完成,浇捣混凝土,混凝土浇筑合格后及时保温保湿养护,并及时进行预埋件位置的复核测量;
(5)主体框架柱混凝土强度达到70%后安装大截面钢横梁框架,大截面钢横梁框架与预埋件采用高强螺栓连接。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610750488.9A CN106351245B (zh) | 2016-08-29 | 2016-08-29 | 塔吊基础座及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610750488.9A CN106351245B (zh) | 2016-08-29 | 2016-08-29 | 塔吊基础座及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106351245A true CN106351245A (zh) | 2017-01-25 |
CN106351245B CN106351245B (zh) | 2018-12-14 |
Family
ID=57855874
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610750488.9A Active CN106351245B (zh) | 2016-08-29 | 2016-08-29 | 塔吊基础座及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106351245B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512639A (zh) * | 2019-07-10 | 2019-11-29 | 中铁二局第一工程有限公司 | 一种无落地式钢结构塔吊基础施工方法及施工结构 |
CN113073677A (zh) * | 2021-03-29 | 2021-07-06 | 四川省建筑科学研究院有限公司 | 用于钢筋混凝土核心筒的塔吊悬空基础装置及其施工方法 |
CN115198786A (zh) * | 2022-07-05 | 2022-10-18 | 广州建筑工程监理有限公司 | 由主体结构承载的h型钢筋混凝土塔吊梁基础及加固方法 |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT522691B1 (de) * | 2019-05-15 | 2021-01-15 | Jak Gewerke Und Maschb Gmbh | Gründung für ein Gebäude |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201581409U (zh) * | 2009-12-25 | 2010-09-15 | 浙江中成建工集团有限公司 | 深基坑钢格构柱支承十字交叉梁的组合式塔吊基础 |
CN103485360A (zh) * | 2013-10-12 | 2014-01-01 | 中建八局第三建设有限公司 | 一种钢平台塔吊基础及其施工方法 |
CN203795458U (zh) * | 2014-03-31 | 2014-08-27 | 上海绿地建设(集团)有限公司 | 一种可以穿越地下室的无承台格构式塔吊基础装置 |
CN203998719U (zh) * | 2014-03-20 | 2014-12-10 | 中国建筑第六工程局有限公司 | 一种高层建筑施工塔吊附着用型钢锚固结构 |
CN105332388A (zh) * | 2015-11-27 | 2016-02-17 | 中国一冶集团有限公司 | 一种拼装钢管混凝土柱帽式塔吊基础结构及施工方法 |
CN206052762U (zh) * | 2016-08-29 | 2017-03-29 | 福建省九龙建设集团有限公司 | 受力于大截面柱的型钢横梁塔吊基础座 |
-
2016
- 2016-08-29 CN CN201610750488.9A patent/CN106351245B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201581409U (zh) * | 2009-12-25 | 2010-09-15 | 浙江中成建工集团有限公司 | 深基坑钢格构柱支承十字交叉梁的组合式塔吊基础 |
CN103485360A (zh) * | 2013-10-12 | 2014-01-01 | 中建八局第三建设有限公司 | 一种钢平台塔吊基础及其施工方法 |
CN203998719U (zh) * | 2014-03-20 | 2014-12-10 | 中国建筑第六工程局有限公司 | 一种高层建筑施工塔吊附着用型钢锚固结构 |
CN203795458U (zh) * | 2014-03-31 | 2014-08-27 | 上海绿地建设(集团)有限公司 | 一种可以穿越地下室的无承台格构式塔吊基础装置 |
CN105332388A (zh) * | 2015-11-27 | 2016-02-17 | 中国一冶集团有限公司 | 一种拼装钢管混凝土柱帽式塔吊基础结构及施工方法 |
CN206052762U (zh) * | 2016-08-29 | 2017-03-29 | 福建省九龙建设集团有限公司 | 受力于大截面柱的型钢横梁塔吊基础座 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512639A (zh) * | 2019-07-10 | 2019-11-29 | 中铁二局第一工程有限公司 | 一种无落地式钢结构塔吊基础施工方法及施工结构 |
CN113073677A (zh) * | 2021-03-29 | 2021-07-06 | 四川省建筑科学研究院有限公司 | 用于钢筋混凝土核心筒的塔吊悬空基础装置及其施工方法 |
CN115198786A (zh) * | 2022-07-05 | 2022-10-18 | 广州建筑工程监理有限公司 | 由主体结构承载的h型钢筋混凝土塔吊梁基础及加固方法 |
CN115198786B (zh) * | 2022-07-05 | 2024-05-07 | 广州建筑工程监理有限公司 | 由主体结构承载的h型钢筋混凝土塔吊梁基础及加固方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106351245B (zh) | 2018-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104141383B (zh) | 一种贝雷梁悬吊模板支撑体系及其施工工法 | |
CN201158933Y (zh) | 一种高层外挑结构维修脚手架装置 | |
CN203947771U (zh) | 一种贝雷梁悬吊模板支撑体系 | |
CN102535845A (zh) | 一种连廊结构承重架的施工方法 | |
CN106351245A (zh) | 塔吊基础座及其施工方法 | |
CN104674665B (zh) | 大空间钢结构连廊桥安装方法 | |
CN206352391U (zh) | 承插型键槽式快拆支撑体系 | |
CN105442839A (zh) | 一种悬挑结构模板排架的搭设方法 | |
CN209585294U (zh) | 一种基于铝模施工的塔吊附着预埋装置 | |
CN106437123A (zh) | 支腿自动翻转式整体提升电梯井操作平台 | |
CN109457814B (zh) | 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法 | |
CN206110635U (zh) | 支腿自动翻转式整体提升电梯井操作平台 | |
CN104499706B (zh) | 电梯井模板平台及其施工方法 | |
CN104961058B (zh) | 一种双z型支撑钢梁和含其的起重机支撑构件及制作方法 | |
CN208534069U (zh) | 钢筋桁架楼承板组合楼盖的装配式支撑装置 | |
CN102605945B (zh) | 木大模板的制作方法 | |
CN114277672B (zh) | 一种大跨度预应力混凝土盖梁构造及其施工方法 | |
CN206052762U (zh) | 受力于大截面柱的型钢横梁塔吊基础座 | |
CN216476335U (zh) | 一种倾斜式框架混凝土圆柱模板加固*** | |
CN106013421B (zh) | 一种钢木复合的装配式纤维混凝土建筑的建造方法 | |
CN108792963A (zh) | 一种用于高层屋面构架的空间钢桁架式塔吊附墙支座方法 | |
CN212176590U (zh) | 装配式建筑免外架安全防护结构 | |
CN204754150U (zh) | 盘型节点式脚手架 | |
CN208347285U (zh) | 一种建筑装修用高空施工支撑结构 | |
CN113958120A (zh) | 一种倾斜式框架混凝土圆柱模板加固*** |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |