CN106351128B - The construction method of cable-stayed bridge end bay girder - Google Patents

The construction method of cable-stayed bridge end bay girder Download PDF

Info

Publication number
CN106351128B
CN106351128B CN201611070272.4A CN201611070272A CN106351128B CN 106351128 B CN106351128 B CN 106351128B CN 201611070272 A CN201611070272 A CN 201611070272A CN 106351128 B CN106351128 B CN 106351128B
Authority
CN
China
Prior art keywords
construction
girder
pier
end bay
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611070272.4A
Other languages
Chinese (zh)
Other versions
CN106351128A (en
Inventor
刘怀刚
高世强
安邦
庄值政
孙战赢
张凤凰
费永忠
肖向荣
赵升辉
檀兴华
张铮
葛纪平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge South China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201611070272.4A priority Critical patent/CN106351128B/en
Publication of CN106351128A publication Critical patent/CN106351128A/en
Application granted granted Critical
Publication of CN106351128B publication Critical patent/CN106351128B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of construction methods of cable-stayed bridge end bay girder, and this method comprises the following steps, carry out the construction of cable-stayed bridge main-beam support pier stud, and the support pier stud includes at least king-tower and auxiliary pier;Pier top beam section is poured in the support pier top end;Hanging Basket is installed in the pier top beam section;Using the Hanging Basket and centered on the auxiliary pier along bridge to extending end bay girder;The end bay girder and mounted transition beam section preparatory on the king-tower are joined the two sections of a bridge, etc, to complete the construction of end bay girder.Disclosed technical solution of the invention constructs to bridge end bay using Hanging Basket after the completion of pier stud construction, the end bay of bridge is made to construct not by topographic constraints, save the installation of a large amount of brackets, and working procedure is simple, convenient, can accelerate speed of application, saves the duration of a project.

Description

The construction method of cable-stayed bridge end bay girder
[technical field]
The present invention relates to field of bridge construction, the in particular to working procedure of cable-stayed bridge end bay girder and construction method neck Domain.
[background technique]
The end bay of bridge is in the spanning between abutment and bridge pier, and the construction of bridge end bay girder is frequently with full hall at present Support Method carries out.Raft support method is to take at regular intervals, gathers and sets up, the construction method of the scaffold to play a supportive role; Construction with brackets is that bracket is set up at bridge location, and pontic concrete is poured on bracket, removes mould after concrete reaches intensity Plate and bracket.Construction with brackets has shortcomings, and it is big, long in time limit to show as working rack template consumption, to mountain area Bridge and Gao Dun have significant limitation;These disadvantages use it should not in the higher bridge construction of pier stud, also be not suitable for In the end bay work progress of relatively large cable-stayed bridge.Cradle construction is applied to cable-stayed bridge by arrangement and method for construction provided by the present invention The construction of end bay girder so that the construction of end bay girder be made to be no longer influenced by the limitation of landform, and can be realized and accelerate end bay girder Construction speed, the purpose shortened the construction period.
For support pier stud of the support edge across girder compared to main pier, diameter or width is generally smaller, this is also just meaned , the ability that the support pier stud of the end bay girder resists end bay girder generation unbalanced load in casting process is lower, and by During cradle construction, the unbalanced load generated during end bay girder pouring construction is required to the branch of the end bay girder Support pier stud is come when carrying, therefore being constructed using Hanging Basket to end bay girder, this is also increased in work progress due to described Unbalanced load on end bay girder and end bay girder beam body capsizing case hair risk occurs.Therefore end bay girder beam body uses extension Basket method applies the design that man-hour requirement carries out additional structure to the support pier stud of end bay girder, resists end bay girder beam body to improve it The ability toppled.
[summary of the invention]
The purpose of the present invention is to provide do not limited by landform when cable-stayed bridge end bay main girder construction, the construction party of quick construction Method.
To realize the purpose, the present invention adopts the following technical scheme:
The construction method of cable-stayed bridge end bay girder comprising following steps:
The construction of cable-stayed bridge main-beam support pier stud is carried out, the support pier stud includes at least king-tower and auxiliary pier;
Pier top beam section is poured in the support pier top end;
Hanging Basket is installed in the pier top beam section;
Using the Hanging Basket and centered on the auxiliary pier along bridge to extending end bay girder;
The end bay girder and mounted transition beam section preparatory on the king-tower are joined the two sections of a bridge, etc, to complete end bay master The construction of beam.
Further, the support pier stud is equipped with the temporary anchoring structure for preventing girder from toppling comprising is set to institute It states the support construction for being used to resist the vertical pressure from the continuous beam between support pier and the pier top beam section and is used for The antidumping structure of the unbalanced moments generated in girder casting process is resisted, the antidumping structure includes being set to the support The fastening reinforcing bar of steel-pipe pile and the connection steel-pipe pile and the pier top beam section around pier.
Specifically, setting up the bracket or bracket for pouring the pier top beam section on its periphery after the completion of support pier construction And formwork for placing;
Preferably, the Hanging Basket is equipped with the anchor being anchored on girder and anchors simultaneously with Hanging Basket and the girder Flexible protective rope, with for preventing the Hanging Basket from toppling.
Further, by the end bay girder and preparatory mounted transition beam section is joined the two sections of a bridge, etc on the king-tower step Suddenly, comprising the following steps:
The hanger for installing closure section is set up using the Hanging Basket;Closure section concreting is set up using the hanger Template;Pour closure section girder;After concrete strength reaches construction requirement, tensioning closure section girder along bridge to prestressed strand, Complete closure section construction.
Specifically, the construction requirement is that concrete strength reaches 90% design strength and the age of concrete was not less than 7 days.
Preferably, the position for carrying out closure step further includes pair of the end bay girder with the access bridge that bank is arranged in Connect position.
Further, the position for carrying out closure step further includes based on two adjacent extended end bay masters of auxiliary pier institute The docking location of beam.
Optionally, after the hanger for installing closure section is set up using the Hanging Basket, the Hanging Basket is removed.
Compared with prior art, the present invention has following advantage:
The technical solution adopted in the present invention, by installing Hanging Basket in pier top beam section, and based on the Hanging Basket to end bay Girder section construction, be based on cradle construction the advantages of, influence the construction of end bay girder by landform, relative to full hall Support Method can also accelerate speed of application, save the construction period.
In addition, technical solution provided by the present invention, is provided with temporary anchoring structure on the support pier stud of end bay girder, The temporary anchoring structure can increase the ability that the support pier stud resists unbalanced load, can make the side using construction cradle There is higher working security in the construction process across girder, to reduce the risk of construction safety accident.Further, this hair Hanging Basket used by technical solution provided by bright is also equipped with the anchor structure for enhancing its resistance to capsizing, is further ensured that and applies Work safety.
[Detailed description of the invention]
Fig. 1 is the distribution schematic diagram of the construction method bridge pier of cable-stayed bridge end bay girder of the present invention.
Fig. 2 is the structural schematic diagram of the construction method pier top beam section of cable-stayed bridge end bay girder of the present invention.
Fig. 3 is the structural schematic diagram before the construction method end bay continuous beam beam body closure of cable-stayed bridge end bay girder of the present invention.
Fig. 4 is the construction method of cable-stayed bridge end bay girder of the present invention with the structural representation of the auxiliary pier of temporary anchoring structure Figure.
[specific embodiment]
The present invention is further described with exemplary embodiment with reference to the accompanying drawing, wherein identical label in attached drawing All refer to identical component.In addition, if the detailed description of known technology is for showing the invention is characterized in that unnecessary , then it omits it.
Embodiment one
Fig. 1-Fig. 3 is please referred to, it illustrates the construction procedures of cable-stayed bridge end bay girder provided by the present invention, specific to wrap It includes:
S1, carries out the construction of cable-stayed bridge main-beam support pier stud, and the support pier stud includes at least king-tower and auxiliary pier;
Such as Fig. 1, the support pier stud of cable-stayed bridge end bay girder includes king-tower 5, auxiliary pier 1 and abutment 6, and wherein auxiliary pier uses Thin-wall Hollow Pier, half range bridge pier is as box-shaped cross-section.It further include each before the construction of the king-tower 5, auxiliary pier 1 and abutment 6 The bearing platform construction step of pier stud is supportted, the mode that the cushion cap and support pier stud of each support pier stud are all made of cast-in-place construction is completed.
S2 pours pier top beam section in the support pier top end;
As shown in Fig. 2, the mode that the support pier top end is all made of concrete cast-in-situ has pier top beam section.Wherein, bridge Platform 6 and king-tower 5 are constructed using raft support method, main pylon pier side stand 52, abutment pier side stand 61, the specific steps are as follows:
Bracket is set up, sets up scaffold stand in the pier side of abutment and king-tower respectively;
Installation template sets up the formwork for placing of pier top beam section using the scaffold stand;
It pours, using concrete cast-in-situ construction casting concrete in the formwork for placing;
Maintenance, to the concrete poured carry out maintenance up to concrete strength reach 90% design strength grade point and When the age of concrete is not less than 7 days, the tensioning beam section direction across bridge and along bridge to prestressed strand, complete pier top beam section and apply Work.
Wherein, the pier top beam section that abutment pier side is poured is access bridge 62, and the pier top beam section that main pylon pier side is poured is transition Bridge section 53.
The construction of auxiliary pier pier top beam section is constructed using bracket, the specific steps are as follows:
Set up bracket, along bridge to utilize auxiliary pier pier shaft and pier shaft accessory structure (steel-pipe pile of such as temporary anchoring structure) Bracket is set up, construction bracket uses the form of shelf bracket on the outside of direction across bridge, and inside diaphragm plate uses the form of bearing support, top Plate uses the form of full framing;
Installation template sets up the formwork for placing of pier top beam section using the bracket;
It pours, using concrete cast-in-situ construction casting concrete in the formwork for placing;
Maintenance, to the concrete poured carry out maintenance up to concrete strength reach 90% design strength grade point and When the age of concrete is not less than 7 days, the tensioning beam section direction across bridge and along bridge to prestressed strand, complete pier top beam section and apply Work.
S3 installs Hanging Basket in the pier top beam section;
Hanging Basket 3 is mounted in auxiliary pier pier top beam section, the primary structure of the Hanging Basket include: upper front beam, upper middle cross beam, Bottom basket system, suspension system, main truss, rear anchor system, running gear, template system etc..Hanging Basket is applied to applying for end bay girder Working hour needs the anchor measure enhanced it, prevents Hanging Basket from capsizing case occurring in the construction process.The anchoring of enhancing is arranged Applying, which may is that increase in the rear anchor system of the Hanging Basket, promotes anchor, described to promote erecting in anchor and girder It is anchored to presstressed reinforcing steel to provide the prestressing force of enhancing Hanging Basket resistance to capsizing;Or to be connected to main truss cradle two sides another for one end Hold the flexible protective rope being connected in girder beam body;And the or combination for both the above structure.The assembled step of the Hanging Basket are as follows: Surveying and locating-laying track bearing beam and track-installation main truss-installation harness system-installation bottom basket system.
S4, using the Hanging Basket and centered on the auxiliary pier along bridge to extending end bay girder;
Using the Hanging Basket, segmentation pours girder beam body, and the concrete strength that each section of beam body is poured reaches 90% design When strength grade value and the age of concrete are not less than 7 days, the prestressed strand of the tensioning beam section repeats above-mentioned operational procedure, directly It constructs and completes to the beam section adjacent with closure section beam section.
S5 joins the two sections of a bridge, etc the end bay girder and mounted transition beam section preparatory on the king-tower, to complete side Construction across girder.
The closure of closure section can be used Hanging Basket method and construct, and also can set up hanger above closure section by Hanging Basket, adopt It is carried out with hanger method.When using hanging frame method construction, needing to carry out setting up for hanger using Hanging Basket, hanging the specific steps of frame method construction Are as follows:
Hanger is set up, sets up the hanger for installing closure section using the Hanging Basket;
Template is set up, sets up closure section concrete-pouring template using the hanger;
It pours, pours closure section girder;
Curing concrete and stretch-draw prestressing force steel beam, after concrete strength reaches construction requirement, tensioning closure section girder is suitable Bridge completes closure section construction to the prestressed strand with direction across bridge.
Wherein, using hanger method carry out closing construction before, for convenient for construction, can be after setting up foot prop, by the extension Basket is removed.The hanger method closing construction can be used for the closing construction of end bay girder between auxiliary pier, also can be used for auxiliary pier and bridge Girder closing construction between platform also can be used for the girder closing construction between auxiliary pier and king-tower.
Embodiment two
Fig. 4 is that part A has additional the auxiliary pier of temporary anchoring structure and the enlarged drawing of pier top beam section in Fig. 2.Such as Fig. 4 institute Show, the step of one auxiliary pier pier construction of embodiment in, further include that setting prevents main girder construction process middle girder from toppling The step of temporary anchoring structure 12, wherein the temporary anchoring structure 12 includes: set on the support pier and the pier top beam section Between for resist the vertical pressure from the continuous beam support construction and generated for resisting in girder casting process Unbalanced moments antidumping structure, the antidumping structure includes the steel-pipe pile and connection institute around the support pier State the fastening reinforcing bar of steel-pipe pile and the pier top beam section.
The temporary anchoring structure is to prevent from generating imbalance to box beam center by continuous beam unbalanced load in construction Moment of flexure makes the risk that beam body is toppled.Temporary anchoring structure is made of steel-pipe pile, fastening reinforcing bar and temporary support, form and principle Are as follows: auxiliary pier and the anchoring temporarily of beam body are to anchor the form combined in vitro in vivo using " soft outside but hard inside ", " soft outside " mainly Refer to " pier side steel pipe+fastening reinforcing bar ", " interior rigid " refers mainly to the temporary support of auxiliary pier pier top;The pier top temporary support master of " interior rigid " It is used to resist the pressure of continuous beam vertical direction;" the pier side steel pipe+fastening reinforcing bar " of " outer soft " is mainly used for resisting continuous beam The unbalanced moment that casting process generates.When continuous beam beam body is by unbalanced load, it may appear that corresponding unbalanced moment, The steel-pipe pile for being now in toppling direction is pressurized and generates counter-force, to form the moment of flexure for stopping beam body to be toppled, the steel of opposite side Tubular pole also can produce the moment of flexure for stopping beam body to be toppled, the two is antidumping moment of flexure, can be used for resisting the continuous beam by pulling force The unbalanced moment generated in beam body casting process.To prevent auxiliary pier master when cable-stayed bridge end bay girder is using cradle construction Beam topples.
Although having been illustrated with some exemplary embodiments of the invention above, those skilled in the art will be managed Solution, in the case where not departing from the principle of the present invention or spirit, can make a change these exemplary embodiments, of the invention Range is defined by the claims and their equivalents.

Claims (9)

1. the construction method of cable-stayed bridge end bay girder, which is characterized in that itself the following steps are included:
The construction of cable-stayed bridge main-beam support pier stud is carried out, the support pier stud includes at least king-tower and auxiliary pier;
Pier top beam section is poured on the top of the king-tower and the top of auxiliary pier;
Hanging Basket is installed in the pier top beam section;
Using the Hanging Basket and centered on the auxiliary pier along bridge to extending end bay girder;
The end bay girder and mounted transition beam section preparatory on the king-tower are joined the two sections of a bridge, etc, to complete end bay girder Construction.
2. construction method according to claim 1, which is characterized in that the support pier stud is equipped with for preventing girder from inclining The temporary anchoring structure covered comprising come from the company for resisting between the support pier stud and the pier top beam section Continue the support construction of the vertical pressure of beam and the antidumping structure for resisting the unbalanced moments generated in girder casting process, The antidumping structure includes the steel-pipe pile and the connection steel-pipe pile and the pier top beam section around the support pier stud Fastening reinforcing bar.
3. construction method according to claim 1, which is characterized in that after the completion of support pier stud construction, set up on its periphery For pouring the bracket or bracket and formwork for placing of the pier top beam section.
4. construction method according to claim 1, which is characterized in that the Hanging Basket is equipped with the anchoring dress being anchored on girder The flexible protective rope set and anchored simultaneously with Hanging Basket and the girder, for preventing the Hanging Basket from toppling.
5. construction method according to claim 1, which is characterized in that by the end bay girder on the king-tower in advance The step of mounted transition beam section is joined the two sections of a bridge, etc, comprising the following steps:
The hanger for installing closure section is set up using the Hanging Basket;Closure section concreting mould is set up using the hanger Plate;Pour closure section girder;After concrete strength reaches construction requirement, tensioning closure section girder along bridge to prestressed strand, it is complete At closure section construction.
6. construction method according to claim 5, which is characterized in that the construction requirement is that concrete strength reaches 90% Design strength and the age of concrete are not less than 7 days.
7. construction method according to claim 5, which is characterized in that it further includes described for carrying out the position of closure step The docking location of end bay girder and the access bridge that bank is set.
8. construction method according to claim 5, which is characterized in that the position for carrying out closure step further includes being based on Two adjacent auxiliary piers extended end bay girder docking location.
9. construction method according to claim 5, which is characterized in that set up using the Hanging Basket for installing closure section After hanger, the Hanging Basket is removed.
CN201611070272.4A 2016-11-28 2016-11-28 The construction method of cable-stayed bridge end bay girder Active CN106351128B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611070272.4A CN106351128B (en) 2016-11-28 2016-11-28 The construction method of cable-stayed bridge end bay girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611070272.4A CN106351128B (en) 2016-11-28 2016-11-28 The construction method of cable-stayed bridge end bay girder

Publications (2)

Publication Number Publication Date
CN106351128A CN106351128A (en) 2017-01-25
CN106351128B true CN106351128B (en) 2019-04-09

Family

ID=57862406

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611070272.4A Active CN106351128B (en) 2016-11-28 2016-11-28 The construction method of cable-stayed bridge end bay girder

Country Status (1)

Country Link
CN (1) CN106351128B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207452739U (en) * 2017-10-01 2018-06-05 中国路桥工程有限责任公司 A kind of cable-stayed bridge beams of concrete mid-span closure segment pre-stress system
CN114293414A (en) * 2021-12-03 2022-04-08 中铁第四勘察设计院集团有限公司 Viaduct transition section structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003253620A (en) * 2002-03-06 2003-09-10 Kurosawa Construction Co Ltd Cable stayed bridge and its construction method
CN101424072A (en) * 2008-11-18 2009-05-06 中铁一局集团有限公司 Counter weight control construction method for large span un-symmetric segment stayed-cable bridge
CN101619562A (en) * 2009-07-21 2010-01-06 中交第二公路勘察设计研究院有限公司 Open web type continuous steel bridge structure and buckling, hanging and pouring method of cantilever
CN102296525A (en) * 2011-05-31 2011-12-28 中铁大桥勘测设计院有限公司 Support system mixed combined beam cable-stayed bridge and construction method thereof
CN104264592A (en) * 2014-10-14 2015-01-07 中国水利水电第四工程局有限公司 Construction method of continuous beam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003253620A (en) * 2002-03-06 2003-09-10 Kurosawa Construction Co Ltd Cable stayed bridge and its construction method
CN101424072A (en) * 2008-11-18 2009-05-06 中铁一局集团有限公司 Counter weight control construction method for large span un-symmetric segment stayed-cable bridge
CN101619562A (en) * 2009-07-21 2010-01-06 中交第二公路勘察设计研究院有限公司 Open web type continuous steel bridge structure and buckling, hanging and pouring method of cantilever
CN102296525A (en) * 2011-05-31 2011-12-28 中铁大桥勘测设计院有限公司 Support system mixed combined beam cable-stayed bridge and construction method thereof
CN104264592A (en) * 2014-10-14 2015-01-07 中国水利水电第四工程局有限公司 Construction method of continuous beam

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
泉州晋江大桥斜拉桥主梁施工;杨奉举;《桥梁建设》;20101030(第5期);第84页
连续箱梁体外临时固结技术;刘先涛;《交通世界》;20150630(第18期);第66页
韩国突山二桥的设计与施工;黄清;《世界桥梁》;20140330(第3期);第7-8页及图1

Also Published As

Publication number Publication date
CN106351128A (en) 2017-01-25

Similar Documents

Publication Publication Date Title
CN109944170A (en) Continuous beam with high-pier end bay Cast-in-Situ Segment and closure section integrated construction system and construction method
CN105839536B (en) A kind of construction method of Cable-stayed Bridge Pylon
CN105648926B (en) Large-Span Continuous girder span building up station rotation swivel construction method
CN108004928B (en) A kind of asymmetric rigid frame-continuous girder construction technology
CN104631333B (en) Arch bridge needle beam, stringer and floorings cast-in-place construction travelling bridge and method
CN110331668A (en) A kind of back-cable-free cable-stayed bridge inclined in two-way V-shaped bridge tower construction method
CN107905114B (en) A kind of construction method of large span Successive interference cancellation
CN105178200B (en) The oblique pull sectional shelf-unit construction method of number segmental construction of suspension pouring arch-type bridge
CN106436583B (en) A kind of interim stretch-draw anchor suspension device of great cantilever bent cap and its construction method
CN103938552B (en) Steel truss arched bridge self-balancing cantilever construction method and the spacing bearing of main pier
CN106087777B (en) The construction method of high pier long cantilever Cast-in-place Bent Cap combined type formwork system
CN102561191A (en) Integral lifting system and construction method for arch bridge ribs
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN107905111B (en) A kind of rigid frame-continuous girder end bay construction technology
CN105568870B (en) For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction
CN102953337B (en) Bridge construction method
CN108842597A (en) A kind of municipal construction temporary concrete steel structure bridge and its installation method
CN205975387U (en) Cast -in -place bent cap combined type formwork system of long cantilever of high mound
CN106351128B (en) The construction method of cable-stayed bridge end bay girder
CN102268858B (en) Cradle for suspension pouring of arch-type bridge
CN106012851A (en) Synchronous construction method of steel box girder and concrete pier studs
CN102277836B (en) Construction method of tilting concrete tower base
CN108643206A (en) Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method
CN108487080B (en) Super-span T-type rigid structure beam side earnestly supports pinner reversed construction method
CN202380403U (en) Integral hoisting system of arch rib of arch bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant