CN106339490A - System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model - Google Patents
System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model Download PDFInfo
- Publication number
- CN106339490A CN106339490A CN201610788265.1A CN201610788265A CN106339490A CN 106339490 A CN106339490 A CN 106339490A CN 201610788265 A CN201610788265 A CN 201610788265A CN 106339490 A CN106339490 A CN 106339490A
- Authority
- CN
- China
- Prior art keywords
- data
- progress
- dimensional
- module
- work point
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 59
- 238000000034 method Methods 0.000 title claims abstract description 13
- 238000007726 management method Methods 0.000 claims abstract description 56
- 238000004458 analytical method Methods 0.000 claims abstract description 11
- 238000012550 audit Methods 0.000 claims abstract description 11
- 238000012795 verification Methods 0.000 claims description 19
- 230000008676 import Effects 0.000 claims description 15
- 238000007619 statistical method Methods 0.000 claims description 15
- 230000003111 delayed effect Effects 0.000 claims description 13
- 238000013461 design Methods 0.000 claims description 13
- 239000000284 extract Substances 0.000 claims description 10
- 238000004364 calculation method Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 claims description 3
- 238000012986 modification Methods 0.000 claims description 3
- 230000004048 modification Effects 0.000 claims description 3
- 230000008569 process Effects 0.000 claims description 3
- 238000013480 data collection Methods 0.000 claims description 2
- 238000009472 formulation Methods 0.000 claims description 2
- 239000000203 mixture Substances 0.000 claims description 2
- 238000012545 processing Methods 0.000 claims description 2
- 238000004321 preservation Methods 0.000 claims 1
- 230000000007 visual effect Effects 0.000 abstract description 5
- 230000008520 organization Effects 0.000 abstract 3
- 230000008859 change Effects 0.000 description 5
- 241000222065 Lycoperdon Species 0.000 description 2
- 241000768494 Polymorphum Species 0.000 description 2
- 238000009430 construction management Methods 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000012512 characterization method Methods 0.000 description 1
- 235000014510 cooky Nutrition 0.000 description 1
- 238000000354 decomposition reaction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000003607 modifier Substances 0.000 description 1
- 238000010606 normalization Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000011800 void material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/29—Geographical information databases
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
- G06T17/05—Geographic models
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Software Systems (AREA)
- Databases & Information Systems (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Entrepreneurship & Innovation (AREA)
- Remote Sensing (AREA)
- Geometry (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Computer Graphics (AREA)
- Data Mining & Analysis (AREA)
- General Engineering & Computer Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a system and a method for managing railway bridge construction progress based on a 3DGIS (Three-dimensional Geographic Information System) and an engineering three-dimensional model. The system comprises a user management module, an actual progress data collecting module, a construction and organization plan module, a three-dimensional image progress display module, a statistic analysis module, a progress early-warning module and a log record module, wherein the actual progress data collecting module has the functions of data filling and reporting, data auditing and storing; the construction and organization plan module is used for making and inputting a work point construction and organization plan; the three-dimensional image display module has the functions of three-dimensional image leading-in, bridge work point model leading-in, three-dimensional navigating and progress display; the statistic analysis module is used for carrying out statistic analysis on progress data and outputting a statistical form; the progress early-warning module has the functions of early-warning personnel allocation and short message reminding; the log record module is capable of recording user login information, progress filling and reporting information and audit information in real time. According to the system and the method, disclosed by the invention, refined and three-dimensional visual management of railway bridge construction progress can be realized.
Description
Technical field
The invention belongs to the informationization technology field of railway and Construction of Urban Rail Traffic is and in particular to one kind is based on
The railroad bridge construction project time management systems and management method of 3dgis and engineering threedimensional model.
Background technology
The fast development built with railway infrastructure, substantial amounts of large-scale and extra-large bridge constantly putting into operation,
It is contemplated that the factor such as environment, soil, maintenance particularly in high speed railway construction, the proportion shared by bridge is increasing.Mesh
The displaying of front Bridges in Our Country construction speed and management mainly adopt form and X-Y scheme mode, carry out data with this mode and adopt
The standardization of collection and automaticity is low, Up-to-date state is poor, data granularity is thick, have that data acquisition is difficult, data statistic analysis not
The problems such as convenient, progress shows visual in image.The complexity being continuously increased with information in work progress of bridge construction quantity
And instantaneity, bring very big pressure to construction management, need the management means of modernization badly.
Content of the invention
It is an object of the present invention to provide a kind of standardization and high degree of automation, Up-to-date state are good, be easy to data acquisition
Data statistical analysiss, progress show the visual in image railroad bridge construction speed pipe based on 3dgis and engineering threedimensional model
Reason system.
It is a further object of the present invention to provide a kind of carry out railroad bridge construction project time management using above-mentioned management system
Method.
For this reason, technical scheme is as follows:
A kind of railroad bridge construction project time management system based on 3dgis and engineering threedimensional model, including user management mould
Block, actual progress data acquisition module, to apply group schedule module, three-dimensional image progress display module, statistical analysis module, progress pre-
Alert module and logger module, described user management module is used for carrying out User logs in, cancellation, personal management and authority joining
Put;Described actual progress data acquisition module be used for carrying out data make a report on, data examination & verification and data loading;Described apply group plan mould
Block is used for carrying out plan and plan typing;Described three-dimensional image progress display module is used for three-dimensional scenic loading, bridge work
Point model imports, three-dimensional range and progress show;Described statistical analysis module is used for carrying out statistics analysis and report output;
Described progress warning module is used for carrying out early warning personnel depaly and note is reminded;Described logger module is used for real time record and uses
Family log-on message, progress make a report on information and msu message.
Described User logs in is user input username and password login system, and illegal account is unable to login system;Described
Nullify the user account information preserving for user log off, system-kill;Described personal management is that system user is added
Plus, delete and change;Described authority configuration is that system user authority is managed, and described system user authority includes manager
Authority, data make a report on authority, data examination & verification authority, plan authority, statistical analysiss authority and three dimensional navigation authority.
Described data is made a report on and is made a report on the user of authority for having data and make a report on system using the construction data of X-Y scheme
Make a report on progress data;Described data audits the construction data examination & verification using X-Y scheme for the user auditing authority for having data
The progress data that system audit user makes a report on;Described data loading is that the user with data examination & verification authority will audit the number passing through
According to input database.
Described plan is target advance, the plan on-stream time including work point component and the plan formulating bridge work point
Deadline;Described plan typing is in the work point target advance input database that will formulate.
The three-dimensional geographic scenes that described three-dimensional scenic is loaded as real scene around rail track is rendered generation enter
Row loads;
It is that science of bridge building threedimensional model is loaded in described three-dimensional scenic that described bridge work point model imports;Described three-dimensional
Roaming is to carry out multi-angle to bridge work point display effect to browse;Described progress is shown as dragging time shafts, in three-dimensional scenic
The progress of display bridge work point random time point.
It is in data base, work point actual progress data and target advance data to be inquired about that described statistics are analyzed
And statistical analysiss, extract work point day, week, month, year, Kai Lei branch, subdivisional work data;Described report output is by statistics
The result of analysis is output as form.
Described early warning personnel depaly is that configuration needs to send the personnel that short message warning is reminded;It is according to meter that described note is reminded
The advanced or delayed work sky that the progress of drawing is gone out with actual progress comparing calculation, formulates advanced warning grade, and exceeding definition grade will send out automatically
Note, to related personnel, carries out progress warning.
A kind of railroad bridge construction project time management method based on 3dgis and engineering threedimensional model, using claim 1-7
Any one of bridge construction carried out based on the railroad bridge construction project time management system of 3dgis and engineering threedimensional model enter
Degree management, described management method includes: three-dimensional scenic is set up;Bridge work point model decomposes and imports;The adopting of actual progress data
Collection;Target advance data loading;Three-dimensional image progress shows;Generate progress report and carry out progress early warning.
Described three-dimensional scenic is set up to include processing the digital image data in rail track region and is generated orthography, by number
Word altitude data processes and generates digital elevation model, is then superimposed described orthography with digital elevation model and renders generation void
Intend three-dimensional scenic.
Described bridge work point model decomposition is comprised the following steps with importing:
1) adopt parametric modeling mode, automatically extract work point design parameter from two-dimensional design in figure;
2) bridge work point model is decomposed, be classified as pile foundation, cushion cap, pier shaft, beam section and beam block;
3) interface that 3ds max provides is utilized to generate threedimensional model;
4) make the three-dimensional of bridge work point part and import table, including definition component numbering, calculate its geographical coordinate and attitude
Parameter;
5) according to the geographical coordinate in described three-dimensional importing table and attitude parameter, work point model importing 3dgis platform is carried out
Display and management.
The collection of described actual progress data comprises the following steps:
1) work extracted point design parameter is stored in underlying parameter data base;
2) obtain work point design parameter from data base, generate pile foundation, cushion cap, pier shaft, beam section, the two dimensional surface of beam block
Figure, using openlayers provide assembly and interface realize work point vector figure Fast Drawing, render, Pan and Zoom;
3) vector element is clicked on from two-dimensional vector figure to carry out progress and make a report on, described pile foundation, cushion cap, beam section, the entering of beam block
Degree is represented with completing and not completing two states, and pier shaft progress actually accomplishes highly to represent by input, carries after the completion of making a report on
Give auditor;
4) auditor audits to the progress data made a report on, and underproof data is marked, and returns modification, such as
Fruit all qualified then by data inputting actual progress data base.
Described target advance data loading is by the target advance input database of work point, specially adopts gunter drawing
Method is formulated work point and is applied group plan input database.
Described three-dimensional image progress shows, is the actual progress data using described input database and target advance number
According to, according to progress data calculate and change described bridge work point model each component color, realize bridge construction three-dimensional shaped
As progress shows.
Described generation progress report, be described actual progress data and target advance data are carried out count, relative analyses,
Extract work point day, week, month, year, open tired (having totaled since going into operation) branch, subdivisional work data, generate progress report.
Described carry out progress early warning, be that described actual progress data and target advance data are analyzed, calculate
Before excess of export or the delayed duration, formulate advanced warning grade, to exceeding definition grade, automatically send short messages to related personnel, carry out progress report
Alert.
The invention has the beneficial effects as follows,
1st, the present invention makes a report on system by patterned construction data, construction data collecting efficiency is greatly improved, significantly
Decrease the input service amount of user, data normalization degree is high;
2nd, the present invention passes through patterned construction data auditing system, the progress data made a report on is audited, makes progress
Examination & verification is very visual in image, easy to operate, reduces the labor intensity of auditor, has ensured the accuracy of data;
3rd, the progress data of present invention collection can drive science of bridge building threedimensional model, carries out three-dimensional shaped in 3dgis platform
As progress display, the space-time characterisation of work progress can be shown comprehensive, visual in imagely, contribute to construction management person to project progress
Grasp macroscopical;
4th, the present invention can carry out statistical analysiss to progress data, automatically generate various statistical report forms, drastically reduce the area use
Family statistic analysis amount, improves bridge construction progress control level and efficiency;
5th, the present invention is analyzed to target advance and actual progress by progress warning module, calculates delayed or super
Front work sky, sends an SMS to management personnel automatically according to advanced warning grade, ensures project progress.
Brief description
Fig. 1 is the functional block diagram group of the railroad bridge construction project time management system based on 3dgis and engineering threedimensional model
Cheng Tu;
Fig. 2 is the flow chart of the railroad bridge construction project time management method based on 3dgis and engineering threedimensional model;
Fig. 3 is that the management method Bridge work point model of the present invention decomposes and guiding flow figure;
Fig. 4 be the present invention management method in actual progress collecting method flow chart.
Specific embodiment
Below in conjunction with the accompanying drawings the management system and management method of the present invention is described in detail.
As shown in figure 1, the railroad bridge construction project time management system bag based on 3dgis and engineering threedimensional model of the present invention
Include: user management module, actual progress data acquisition module, apply group schedule module, three-dimensional image progress display module, statistical
Analysis module and logger module.
Described user management module is used for carrying out User logs in, cancellation, personal management and authority configuration.Wherein:
User logs in refers to user input username and password login system, and illegal account is unable to login system, system root
According to the username and password of user input, search from database user table, then login system that the match is successful;
Cancellation refers to user log off, the user account letter preserving in system-kill browser cookies and session
Breath, needs after cancellation again to log in and could use system;
Personal management refers to that system manager user is added to system user, deletes, changing etc. operating, and data base uses
The information such as user name, password, department are preserved, password is stored with the mode that md5 encrypts in the table of family;
Authority configuration refers to that system manager user is managed to system user authority, and described system user authority includes
Administrator right, data make a report on authority, data examination & verification authority, plan authority, statistical analysiss authority and three dimensional navigation authority.
Each user has the authority of oneself, has data and makes a report on the user of authority and can be made a report on using the construction data of X-Y scheme
System makes a report on progress data;The user having data examination & verification authority can be filled out using the construction data examination & verification user of X-Y scheme
The progress data of report;The user having plan authority can be made a plan using applying group schedule module;Have statistical analysiss
The user of authority can carry out report output using statistical analysis module;The user having three dimensional navigation authority can log in
Work point three-dimensional image progress checked by 3dgis platform.
Described actual progress data acquisition module be used for carrying out data make a report on, data examination & verification and putting in storage.Wherein:
Data is made a report on to refer to have data and make a report on the user of authority and is filled out using the construction data system of making a report on of X-Y scheme
Report progress data, specially selects work point, obtains work point parameter, provided using openlayers from underlying parameter data base
Assembly and interface are realized the Fast Drawing of bridge work point vector figure, are rendered, translate, scaling, and click vector element carries out progress and fills out
Report, submits to auditor and is audited after the completion of making a report on;
Data examination & verification refers to that the user with data examination & verification authority utilizes the construction data auditing system of X-Y scheme to examine
The progress data that core user makes a report on, specially on two-dimentional work point vector figure, needs the highlighted expression of key element of examination & verification, clicks on key element
Check progress msg, underproof data is marked, returns modification, if all qualified, enter next step, by data
In typing actual progress data base;
Data loading refers to that the user with data examination & verification authority will audit the data inputting data base passing through, the number of warehouse-in
Can not change again according to locked.
Described applying organizes formulation and the typing that schedule module applies group plan for work point, and the method using gunter drawing formulates work point
Apply group plan, record in initial and the deadline, and input database of each task, work point part.
Described three-dimensional image progress display module is used for carrying out three-dimensional scenic loading, bridge work point model imports, three-dimensional unrestrained
Trip and progress show.Wherein:
Three-dimensional scenic loads the three-dimensional geographical environment referring to for real scene around rail track render generation and loads
Shown in 3dgis platform;
Bridge work point model imports and refers to science of bridge building threedimensional model is loaded in three-dimensional scenic, by making bridge work
Point part is three-dimensional to import table, and including unit number definition, geographical coordinate calculates, attitude parameter calculates, and imports in table according to three-dimensional
Geographical coordinate and attitude parameter, attitude parameter includes the angle of pitch, yaw angle and roll angle, realizes the seamless of bridge work point part
Splicing and assembling;
Three-dimensional range refers in three-dimensional scenic, bridge work point display effect to be carried out comprehensive, multi-angle and browses;
Progress shows and refers to drag time shafts, obtain from data base the actual progress of current time work point and plan into
Degree, calculates the completion statuses of each component of point model of going to work, and represents progress status by changing model color in three-dimensional scenic,
As completed use blueness represents, do not start represents with Lycoperdon polymorphum Vitt, actual progress exceedes target advance redness and represents, actual enter
Spend delayed target advance yellow to represent.
Described statistical analysis module is used for carrying out the statistical analysiss of progress data, from data base, progress data is united
Meter inquiry, can extract day, week, month, year, open tired (having totaled since going into operation) branch and subdivisional work data, output statistics
Form;
Described progress warning module is used for carrying out early warning personnel depaly and note is reminded.Wherein:
Early warning personnel depaly refers to configure to be needed to send the personnel that short message warning is reminded, the surname of record keeping personnel in data base
Name and cell-phone number;
Note reminds the advanced or delayed work sky referring to go out according to target advance and actual progress comparing calculation, formulates early warning
Grade, exceedes definition grade and is automatically sent short messages to related personnel, carry out progress warning.
Described logger module is used for real time record user login information, progress makes a report on information, msu message, these letters
Breath is saved in data base it is ensured that each database manipulation has record can follow, and ensures data safety.
Referring to Fig. 2-Fig. 4, the railroad bridge construction project time management side based on 3dgis and engineering threedimensional model of the present invention
Method, comprises the following steps: three-dimensional scenic is set up, bridge work point model decomposes and the construction data importing, setting up X-Y scheme
Make a report on system, set up the construction data auditing system of X-Y scheme, set up actual progress data base, set up target advance data
Storehouse, carry out three-dimensional image progress based on progress data driving model and show, generate progress report and carry out progress early warning.Concrete step
Suddenly as follows:
1st, three-dimensional scenic is set up: the digital image data in rail track region is processed and generates orthography dom, by numeral
Altitude data process generate digital elevation model dem, then orthography is superimposed with digital elevation model render generate virtual
Three-dimensional scenic.
2nd, bridge work point model decomposes and imports: by engineering control decomposing, by bridge work point model be divided into pile foundation, cushion cap,
Pier shaft, beam section and beam block, import and are shown in 3dgis platform and manage, bridge work point model adopts parametric modeling mode,
Automatically extract parameter from two-dimensional design drawing, generate threedimensional model using the interface that 3ds max provides;From two-dimensional design drawing
In automatically extract parameter, carry out secondary development under autocad platform, according to professionally-designed chart lateral model, set up interpreting blueprints rule,
Interpreting blueprints rule according to definition is interpreted, with figure layer, color, line style as foundation, to annotation, component multistage in design drawing
Line, cross section structure parameter are refined, and extract design parameter.In order to show pier shaft progress, pier shaft needs by highly dividing further
Solution, typically can be decomposed by 3 meters one section, pile foundation, cushion cap, beam section, beam block etc. do not need to decompose further.Make bridge work
Point part is three-dimensional to import table, and including unit number definition, geographical coordinate calculates and attitude parameter calculates, and imports in table according to three-dimensional
Geographical coordinate and attitude parameter, realize the seamless spliced of bridge work point part and assembling.Unit number defines: its pile foundation,
Cushion cap, the numbering of pier shaft are made up of work vertex type, work point numbering, unit type, bridge pier numbering, element type, unit number, beam
Section, beam block number are made up of work vertex type, work point numbering, unit type, beam numbering, unit number, and such as numbering is 1-21-p-0-
Z-0, wherein 1 expression bridge, 21 represent work point numbering, and p represents bridge pier, and 0 represents bridge pier numbering, and z represents drilled pile, 0 expression stake
Numbering.
3rd, the construction data carrying out X-Y scheme is made a report on: the parameter automatically extracting in two-dimensional design drawing is stored in data
Storehouse, obtains work point parameter, the assembly providing and interface realize the quick of work point vector figure using openlayers from data base
Draw, render, roam and scale, click vector element carries out progress and makes a report on, and pile foundation, cushion cap, beam section and beam block progress are with completing
Represent with undone two states, pier shaft progress actually accomplishes height by input and represents.In order to ensure the verity of data, use
The progress data that family is made a report on need to audit ability input database by auditor, and usually unit in charge of construction's surveyor enters line number
According to making a report on, supervisor auditor is audited.
4th, carry out the construction data examination & verification of X-Y scheme: the progress data that user makes a report on is audited, needs to audit
Data be highlighted on vectogram, by click on check the progress msg made a report on, underproof data is marked, moves back
Return something for repairs and change, if all qualified, enter next step, by data inputting actual progress data base.
5th, set up actual progress data base: in the progress data input database that examination & verification is passed through, it is right to need before warehouse-in
Data carries out logical consistency inspection, and such as pier shaft does not complete, above beam section can not possibly complete.Data after warehouse-in can not be more
Change.
6th, set up target advance data base: by the target advance input database of work point, particularly as follows: using gunter drawing
Method is formulated work point and is applied group plan input database, when the plan initial time including each task and component and plan complete
Between, the planned start time of such as No. 19 pier pier shafts is August in 2016 20, and Projected completion time is September in 2016 20.
7th, carry out three-dimensional image progress based on progress data driving model to show: lookup acquisition work point one day from data base
Phase actual progress data and target advance data, calculate the completion statuses of work each component of point model according to progress data, according to
The color of each component of status modifier, realizes bridge construction three-dimensional image progress and shows.As completed use blueness represents, do not open
Begin represents with Lycoperdon polymorphum Vitt, actual progress exceedes target advance redness and represents, actual progress delayed target advance yellow represents.
8th, generate progress report: statistical query is carried out to progress data, day, week, month, year, Kai Lei branch can be extracted, divide
Item project data, generates progress report.As can be with statistical query currently all bridge work point drilled piles, cushion cap, pier shaft, beam etc.
Day, week, month, year, open tired quantity performed, volume residual etc..
9th, progress early warning: actual progress data and target advance data are analyzed, calculate advanced or delayed
Duration, formulate advanced warning grade, when exceeding definition grade, automatically send short messages to related personnel, carry out progress warning.As red in defined
Color, orange, yellow, blue level Four advanced warning grade, red delayed 60 days, orange delayed 40 days, delayed 20 days of yellow, blue delayed
10 days, when exceeding yellow advanced warning grade, automatically send short messages to related management personnel and reminded.
Claims (15)
1. a kind of railroad bridge construction project time management system based on 3dgis and engineering threedimensional model it is characterised in that: include use
Family management module, actual progress data acquisition module, apply group schedule module, three-dimensional image progress display module, statistical analysiss mould
Block, progress warning module and logger module,
Described user management module is used for carrying out User logs in, cancellation, personal management and authority configuration;
Described actual progress data acquisition module be used for carrying out data make a report on, data examination & verification and data loading;
Described group schedule module of applying is used for carrying out plan and plan typing.
Described three-dimensional image progress display module is used for three-dimensional scenic loading, the importing of bridge work point model, three-dimensional range and progress
Display;
Described statistical analysis module is used for carrying out statistics analysis and report output;
Described progress warning module is used for carrying out early warning personnel depaly and note is reminded;
Described logger module is used for real time record user login information, progress makes a report on information and msu message.
2. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described User logs in is user input username and password login system, and illegal account is unable to login system;
The described user account information nullified as user log off, system-kill preservation;
Described personal management is system user to be added, delete and changes;
Described authority configuration is that system user authority is managed, and described system user authority includes administrator right, data
Make a report on authority, data examination & verification authority, plan authority, statistical analysiss authority and three dimensional navigation authority.
3. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described data is made a report on and is made a report on the user of authority for having data and made a report on using the construction data system of making a report on of X-Y scheme
Progress data;
Described data audits the construction data auditing system examination & verification using X-Y scheme for the user auditing authority for having data
The progress data that user makes a report on;
Described data loading is that the user with data examination & verification authority will audit the data inputting data base passing through.
4. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described plan is the target advance formulating bridge work point, and plan on-stream time and plan including work point component complete
Time;
Described plan typing is in the work point target advance input database that will formulate.
5. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
The three-dimensional geographic scenes that described three-dimensional scenic is loaded as real scene around rail track is rendered generation carry out adding
Carry;
It is that science of bridge building threedimensional model is loaded in described three-dimensional scenic that described bridge work point model imports;
Described three-dimensional range is to carry out multi-angle to bridge work point display effect to browse;
Described progress is shown as dragging time shafts, shows the progress of bridge work point random time point in three-dimensional scenic.
6. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
It is in data base, work point actual progress data and target advance data to be inquired about and unite that described statistics are analyzed
Meter analysis, extracts work point day, week, month, year, Kai Lei branch, subdivisional work data;
Described report output is that the result analyzing statistics is output as form.
7. railroad bridge construction project time management system as claimed in claim 1 it is characterised in that:
Described early warning personnel depaly is that configuration needs to send the personnel that short message warning is reminded;
Described note reminds the advanced or delayed work sky being to go out according to target advance and actual progress comparing calculation, formulates early warning etc.
Level, exceedes definition grade and is automatically sent short messages to related personnel, carry out progress warning.
8. a kind of railroad bridge construction project time management method based on 3dgis and engineering threedimensional model it is characterised in that: using power
Profit requires carrying out based on the railroad bridge construction project time management system of 3dgis and engineering threedimensional model any one of 1-7
Bridge construction progress control, described management method includes: three-dimensional scenic is set up;Bridge work point model decomposes and imports;Actual enter
The collection of degrees of data;Target advance data loading;Three-dimensional image progress shows;Generate progress report and carry out progress early warning.
9. railroad bridge construction project time management method as claimed in claim 8 it is characterised in that: described three-dimensional scenic sets up bag
Include to process the digital image data in rail track region and generate orthography, digital elevation data processing is generated digital elevation
Then described orthography is superimposed with digital elevation model and renders generation virtual three-dimensional scene by model.
10. railroad bridge construction project time management method as claimed in claim 8 it is characterised in that: described bridge work point model
Decompose and comprise the following steps with importing:
1) adopt parametric modeling mode, automatically extract work point design parameter from two-dimensional design in figure;
2) bridge work point model is decomposed, be classified as pile foundation, cushion cap, pier shaft, beam section and beam block;
3) interface that 3ds max provides is utilized to generate threedimensional model;
4) make the three-dimensional of bridge work point part and import table, including definition component numbering, calculate its geographical coordinate and attitude parameter;
5) according to the geographical coordinate in described three-dimensional importing table and attitude parameter, work point model importing 3dgis platform is shown
And management.
11. railroad bridge construction project time management methods as claimed in claim 10 are it is characterised in that described actual progress data
Collection comprise the following steps:
1) work extracted point design parameter is stored in underlying parameter data base;
2) obtain work point design parameter from data base, generate pile foundation, cushion cap, pier shaft, beam section, the 2 d plane picture of beam block, profit
With openlayers provide assembly and interface realize work point vector figure Fast Drawing, render, Pan and Zoom;
3) vector element is clicked on from two-dimensional vector figure to carry out progress and make a report on, described pile foundation, cushion cap, beam section, the progress of beam block are used
Complete and do not complete two states to represent, pier shaft progress actually accomplishes highly to represent by input, submits to after the completion of making a report on
Auditor;
4) auditor audits to the progress data made a report on, and underproof data is marked, returns modification, if entirely
Portion qualified then by data inputting actual progress data base.
12. railroad bridge construction project time management methods as claimed in claim 11 are it is characterised in that described target advance data
Warehouse-in is by the target advance input database of work point, specially applies group using the method formulation work point of gunter drawing and plans and record
Enter data base.
13. railroad bridge construction project time management methods as claimed in claim 12 are it is characterised in that described three-dimensional image progress
Display, is the actual progress data using described input database and target advance data, is calculated according to progress data and changes
The color of each component of described bridge work point model, realizes bridge construction three-dimensional image progress and shows.
14. railroad bridge construction project time management methods as claimed in claim 12 are it is characterised in that described generation progress report
Table, be described actual progress data and target advance data are carried out count, relative analyses, extract work point day, week, month, year, open
Tired branch, subdivisional work data, generate progress report.
15. railroad bridge construction project time management methods as claimed in claim 12 are it is characterised in that described to carry out progress pre-
Alert, it is that described actual progress data and target advance data are analyzed, calculates the advanced or delayed duration, formulate pre-
Alert grade, to exceeding definition grade, automatically sends short messages to related personnel, carries out progress warning.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610788265.1A CN106339490A (en) | 2016-08-31 | 2016-08-31 | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610788265.1A CN106339490A (en) | 2016-08-31 | 2016-08-31 | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106339490A true CN106339490A (en) | 2017-01-18 |
Family
ID=57822369
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610788265.1A Pending CN106339490A (en) | 2016-08-31 | 2016-08-31 | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106339490A (en) |
Cited By (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106875159A (en) * | 2017-02-17 | 2017-06-20 | 中国十七冶集团有限公司 | The city integrated piping lane construction total management system of cast-in-place structural |
CN106997511A (en) * | 2017-04-05 | 2017-08-01 | 中铁四局集团有限公司 | Railway beam yard management system and railway beam yard management method based on BIM technology |
CN107133787A (en) * | 2017-06-26 | 2017-09-05 | 山东奥联信息科技有限公司 | Highway project management method and system |
CN107590597A (en) * | 2017-09-08 | 2018-01-16 | 太仓贝岭思拓软件科技有限公司 | A kind of architectural engineering progress becomes more meticulous and various dimensions management method |
CN107705100A (en) * | 2017-11-02 | 2018-02-16 | 港珠澳大桥管理局 | A kind of management system of Traffic Engineering Construction progress |
CN107797824A (en) * | 2017-11-08 | 2018-03-13 | 北京恒华伟业科技股份有限公司 | A kind of project progress methods of exhibiting and device |
CN109359125A (en) * | 2018-08-27 | 2019-02-19 | 中铁建工集团有限公司 | A kind of progress fine-grained management method and its system for construction project |
CN109523182A (en) * | 2018-11-27 | 2019-03-26 | 华规软件(上海)有限公司 | A kind of beam field production management method, platform, computer equipment and storage medium |
CN109558412A (en) * | 2018-09-20 | 2019-04-02 | 中建科技有限公司深圳分公司 | The data growing method and device of assembled architecture construct platform |
CN109583852A (en) * | 2018-12-29 | 2019-04-05 | 中铁局集团有限公司第三工程分公司 | A kind of goods and materials for bridge cantilever pouring construction and progress msg management system |
CN109903008A (en) * | 2019-01-25 | 2019-06-18 | 国电南瑞科技股份有限公司 | A kind of subway work construction project progress visualization managing and control system and management-control method |
CN109949001A (en) * | 2019-02-22 | 2019-06-28 | 上海市建设工程监理咨询有限公司 | A kind of Project Supervision organization management system |
CN110070284A (en) * | 2019-04-17 | 2019-07-30 | 江苏开通建设工程有限公司 | A kind of wisdom beam course management system based on BIM technology |
CN110163509A (en) * | 2019-05-23 | 2019-08-23 | 重庆渝高科技产业(集团)股份有限公司 | A kind of big data platform project management system based on architectural engineering |
CN110443480A (en) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110766790A (en) * | 2019-10-21 | 2020-02-07 | 中国铁路设计集团有限公司 | Parameter-driven self-adaptive multi-level three-dimensional visualization method for high-speed railway bridge |
CN111021265A (en) * | 2020-01-16 | 2020-04-17 | 中铁十九局集团第一工程有限公司 | BIM technology-based railway large-span continuous beam swivel construction control method |
CN111160852A (en) * | 2019-12-16 | 2020-05-15 | 温州电力建设有限公司 | Intelligent engineering data writing system and method based on big data |
CN111611204A (en) * | 2020-04-30 | 2020-09-01 | 中国舰船研究设计中心 | Distributed task progress data acquisition and analysis method |
CN112365222A (en) * | 2020-10-21 | 2021-02-12 | 中交第二航务工程局有限公司 | Intelligent construction informatization system for cast-in-situ bored pile |
CN112818455A (en) * | 2021-02-22 | 2021-05-18 | 深圳市市政设计研究院有限公司 | Bridge structure response monitoring method and system |
CN113012288A (en) * | 2021-04-02 | 2021-06-22 | 长江空间信息技术工程有限公司(武汉) | Three-dimensional dynamic visualization method for long-distance engineering construction progress |
CN113673899A (en) * | 2021-08-28 | 2021-11-19 | 江苏苏科建设项目管理有限公司 | Road engineering progress management method based on supervision cloud system |
CN113988820A (en) * | 2021-11-23 | 2022-01-28 | 中国铁路通信信号上海工程局集团有限公司 | Engineering project scheduling management system |
WO2022040919A1 (en) * | 2020-08-25 | 2022-03-03 | 南京翱翔信息物理融合创新研究院有限公司 | Internet-based method for displaying three-dimensional road bridge progress |
CN114399260A (en) * | 2021-11-30 | 2022-04-26 | 北京全路通信信号研究设计院集团有限公司 | Data vectorization method and system for construction management information system |
CN115798137A (en) * | 2022-08-02 | 2023-03-14 | 中建铁路投资建设集团有限公司 | Three-dimensional visual big data monitoring and early warning system based on Internet of things |
CN116205411A (en) * | 2023-04-27 | 2023-06-02 | 山东铁路投资控股集团有限公司 | Material consumption checking method, device, equipment and medium based on big data |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101418542A (en) * | 2008-11-21 | 2009-04-29 | 上海市政工程设计研究总院 | Cable system construction method of spatial self-anchored rope-suspension bridge |
CN101476291A (en) * | 2009-01-21 | 2009-07-08 | 中铁一局集团有限公司 | Segment-assembling simply supported box girder movable falsework construction method |
DE102013005891A1 (en) * | 2013-03-11 | 2014-09-11 | Universität Kassel | Generative method for producing a component having at least one cavity, in particular by 3D printing technology with a sand and a binder |
CN105652830A (en) * | 2015-12-25 | 2016-06-08 | 中国铁道科学研究院铁道建筑研究所 | Bridge monitoring system based on BIM |
-
2016
- 2016-08-31 CN CN201610788265.1A patent/CN106339490A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101418542A (en) * | 2008-11-21 | 2009-04-29 | 上海市政工程设计研究总院 | Cable system construction method of spatial self-anchored rope-suspension bridge |
CN101476291A (en) * | 2009-01-21 | 2009-07-08 | 中铁一局集团有限公司 | Segment-assembling simply supported box girder movable falsework construction method |
DE102013005891A1 (en) * | 2013-03-11 | 2014-09-11 | Universität Kassel | Generative method for producing a component having at least one cavity, in particular by 3D printing technology with a sand and a binder |
CN105652830A (en) * | 2015-12-25 | 2016-06-08 | 中国铁道科学研究院铁道建筑研究所 | Bridge monitoring system based on BIM |
Non-Patent Citations (2)
Title |
---|
唐文波: "基于4D信息模型的大型桥梁施工进度仿真研究", 《中南大学》 * |
王华 等: "高速铁路桥梁三维施工进度管理***研发", 《铁路计算机应用》 * |
Cited By (36)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106875159A (en) * | 2017-02-17 | 2017-06-20 | 中国十七冶集团有限公司 | The city integrated piping lane construction total management system of cast-in-place structural |
CN106997511A (en) * | 2017-04-05 | 2017-08-01 | 中铁四局集团有限公司 | Railway beam yard management system and railway beam yard management method based on BIM technology |
CN107133787A (en) * | 2017-06-26 | 2017-09-05 | 山东奥联信息科技有限公司 | Highway project management method and system |
CN107133787B (en) * | 2017-06-26 | 2023-10-27 | 山东奥联信息科技有限公司 | Highway engineering management method and system |
CN107590597A (en) * | 2017-09-08 | 2018-01-16 | 太仓贝岭思拓软件科技有限公司 | A kind of architectural engineering progress becomes more meticulous and various dimensions management method |
CN107705100B (en) * | 2017-11-02 | 2022-04-26 | 港珠澳大桥管理局 | Management system for traffic engineering construction progress |
CN107705100A (en) * | 2017-11-02 | 2018-02-16 | 港珠澳大桥管理局 | A kind of management system of Traffic Engineering Construction progress |
CN107797824A (en) * | 2017-11-08 | 2018-03-13 | 北京恒华伟业科技股份有限公司 | A kind of project progress methods of exhibiting and device |
CN109359125A (en) * | 2018-08-27 | 2019-02-19 | 中铁建工集团有限公司 | A kind of progress fine-grained management method and its system for construction project |
CN109558412A (en) * | 2018-09-20 | 2019-04-02 | 中建科技有限公司深圳分公司 | The data growing method and device of assembled architecture construct platform |
CN109523182A (en) * | 2018-11-27 | 2019-03-26 | 华规软件(上海)有限公司 | A kind of beam field production management method, platform, computer equipment and storage medium |
CN109583852A (en) * | 2018-12-29 | 2019-04-05 | 中铁局集团有限公司第三工程分公司 | A kind of goods and materials for bridge cantilever pouring construction and progress msg management system |
CN109903008B (en) * | 2019-01-25 | 2022-09-09 | 国电南瑞科技股份有限公司 | Visual management and control system and method for subway construction project progress |
CN109903008A (en) * | 2019-01-25 | 2019-06-18 | 国电南瑞科技股份有限公司 | A kind of subway work construction project progress visualization managing and control system and management-control method |
CN109949001A (en) * | 2019-02-22 | 2019-06-28 | 上海市建设工程监理咨询有限公司 | A kind of Project Supervision organization management system |
CN110070284A (en) * | 2019-04-17 | 2019-07-30 | 江苏开通建设工程有限公司 | A kind of wisdom beam course management system based on BIM technology |
CN110163509A (en) * | 2019-05-23 | 2019-08-23 | 重庆渝高科技产业(集团)股份有限公司 | A kind of big data platform project management system based on architectural engineering |
CN110443480B (en) * | 2019-07-26 | 2023-10-27 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110443480A (en) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110766790A (en) * | 2019-10-21 | 2020-02-07 | 中国铁路设计集团有限公司 | Parameter-driven self-adaptive multi-level three-dimensional visualization method for high-speed railway bridge |
CN110766790B (en) * | 2019-10-21 | 2023-06-23 | 中国铁路设计集团有限公司 | Parameter-driven high-speed railway bridge self-adaptive multi-level three-dimensional visualization method |
CN111160852A (en) * | 2019-12-16 | 2020-05-15 | 温州电力建设有限公司 | Intelligent engineering data writing system and method based on big data |
CN111021265A (en) * | 2020-01-16 | 2020-04-17 | 中铁十九局集团第一工程有限公司 | BIM technology-based railway large-span continuous beam swivel construction control method |
CN111611204B (en) * | 2020-04-30 | 2024-03-01 | 中国舰船研究设计中心 | Distributed task progress data acquisition and analysis method |
CN111611204A (en) * | 2020-04-30 | 2020-09-01 | 中国舰船研究设计中心 | Distributed task progress data acquisition and analysis method |
WO2022040919A1 (en) * | 2020-08-25 | 2022-03-03 | 南京翱翔信息物理融合创新研究院有限公司 | Internet-based method for displaying three-dimensional road bridge progress |
CN112365222A (en) * | 2020-10-21 | 2021-02-12 | 中交第二航务工程局有限公司 | Intelligent construction informatization system for cast-in-situ bored pile |
CN112818455A (en) * | 2021-02-22 | 2021-05-18 | 深圳市市政设计研究院有限公司 | Bridge structure response monitoring method and system |
CN113012288B (en) * | 2021-04-02 | 2022-04-22 | 长江空间信息技术工程有限公司(武汉) | Three-dimensional dynamic visualization method for long-distance engineering construction progress |
CN113012288A (en) * | 2021-04-02 | 2021-06-22 | 长江空间信息技术工程有限公司(武汉) | Three-dimensional dynamic visualization method for long-distance engineering construction progress |
CN113673899A (en) * | 2021-08-28 | 2021-11-19 | 江苏苏科建设项目管理有限公司 | Road engineering progress management method based on supervision cloud system |
CN113988820A (en) * | 2021-11-23 | 2022-01-28 | 中国铁路通信信号上海工程局集团有限公司 | Engineering project scheduling management system |
CN114399260A (en) * | 2021-11-30 | 2022-04-26 | 北京全路通信信号研究设计院集团有限公司 | Data vectorization method and system for construction management information system |
CN115798137A (en) * | 2022-08-02 | 2023-03-14 | 中建铁路投资建设集团有限公司 | Three-dimensional visual big data monitoring and early warning system based on Internet of things |
CN115798137B (en) * | 2022-08-02 | 2023-12-22 | 中建铁路投资建设集团有限公司 | Three-dimensional visual big data monitoring and early warning system based on Internet of things |
CN116205411A (en) * | 2023-04-27 | 2023-06-02 | 山东铁路投资控股集团有限公司 | Material consumption checking method, device, equipment and medium based on big data |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106339490A (en) | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model | |
CN106384191A (en) | Railway tunnel construction progress management system and method based on 3DGIS and engineering 3D model | |
CN106384190A (en) | Railway roadbed construction progress management system and method based on 3DGIS and engineering 3D model | |
LU501999A1 (en) | Pumped storage power station comprehensive management method, platform and system, device and medium | |
CN111369158A (en) | BIM-based informatization quality management method and system | |
CN109671150B (en) | Airport earthwork calculation method based on digital earth | |
WO2011072467A1 (en) | Method and system for monitoring of wetlands resource and ecological environment | |
Liapi | 4D visualization of highway construction projects | |
CN111401726A (en) | Building design method, device, system and storage medium | |
CN104217384A (en) | A nuclear accident emergency processing and auxiliary decision support system | |
CN111782712A (en) | Natural resource asset audit comprehensive space analysis system and method | |
Pietsch | GIS in landscape planning | |
CN105354882A (en) | Method for constructing big data architecture based three-dimensional panoramic display platform for large-spatial-range electricity transmission | |
Huang et al. | The city management based on smart information system using digital technologies in China | |
CN117371233A (en) | Reservoir flood control system based on UE technique | |
CN114781827A (en) | Environment sample investigation cloud management method based on geographic spatial information | |
Shaw et al. | High resolution LiDAR specifically for archaeology: Are we fully exploiting this valuable resource | |
Tiwari et al. | 3D city model enabled e-governance for sustainable urbanization | |
Kevany | GIS in the World Trade Center response: 10 years after | |
Duque et al. | Building a digital twin of the Italian coasts | |
Galmarini et al. | Real-time monitoring data for real-time multi-model validation: coupling ENSEMBLE and EURDEP | |
Li et al. | Application of three-dimensional GIS to water resources | |
Zhang et al. | Research on GIM-based 3D Digital Construction Management Scheme for Power Grid Engineering | |
Asha Kiran et al. | Statistical Anatomizing and Visualization of Data for Planning and Decision Making using POSTGRES and GIS Tools | |
Gorreja et al. | 3D GIS for a Smart Management System Applied to Historical Villages Damaged by Earthquake |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination |