CN106284427B - A kind of basement post-pouring zone temporary leaking water earth-retaining construction method - Google Patents

A kind of basement post-pouring zone temporary leaking water earth-retaining construction method Download PDF

Info

Publication number
CN106284427B
CN106284427B CN201610781771.8A CN201610781771A CN106284427B CN 106284427 B CN106284427 B CN 106284427B CN 201610781771 A CN201610781771 A CN 201610781771A CN 106284427 B CN106284427 B CN 106284427B
Authority
CN
China
Prior art keywords
post
formwork
concrete
cast strip
sealing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610781771.8A
Other languages
Chinese (zh)
Other versions
CN106284427A (en
Inventor
邵正东
盛振斌
郭继舟
李少祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201610781771.8A priority Critical patent/CN106284427B/en
Publication of CN106284427A publication Critical patent/CN106284427A/en
Application granted granted Critical
Publication of CN106284427B publication Critical patent/CN106284427B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Hydrology & Water Resources (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention provides a kind of basement post-pouring zone temporary leaking water earth-retaining construction methods, it is mainly included the following steps that:Step 1: sealing construction at the post-cast strip of bottom plate:Arrange mat foundation portion;The formwork for placing of bottom plate is made, and arranges baseplate reinforcing bar in formwork for placing;First non-dismantling formwork and the first steel plate for sealing water are provided;Fix the first non-dismantling formwork;Pour the concrete of bottom plate;Step 2: sealing earth-retaining is constructed at the post-cast strip of exterior wall:It makes and blocks prefabricated section mold and the embedded bar in prefabricated section mold;Pour closure prefabricated section;It is online that post-cast strip steel bar of the embedded bar spot welding of prefabricated section on exterior wall will be blocked;In the upper surface laying water-proof coiled material for blocking prefabricated section;Foundation pit surrounding backfills;Step 3: at floor post-cast strip sealing construction.Beneficial effects of the present invention are:The present invention ensure that water-less environment in basement, working procedure is few, shortens the construction period, has saved construction cost by carrying out temporary enclosed sealing construction to basement bottom board, exterior wall, floor slab back casting band.

Description

A kind of basement post-pouring zone temporary leaking water earth-retaining construction method
Technical field
The present invention relates to basement construction technical fields, and in particular to a kind of basement post-pouring zone temporary leaking water earth-retaining is applied Work method.
Background technology
In construction projects, basement is an extremely important and common part, is mainly used for garage parking or business, Basement post-pouring zone could carry out the backfill of foundation pit surrounding after having constructed.It is applied to basement post-pouring zone since foundation pit support construction Work is complete to need long time, and there are some potential safety problemss, such as underground for pattern foundation pit supporting structure work overlong time before foundation pit backfills When room post-cast strip does not pour, underground water can be seeped into from bottom plate rear pouring tape in basement, and rainwater also can be from exterior wall, floor(Top plate) It is flowed in basement at post-cast strip, to influence basement construction.
Currently, being typically at least two months and main building sedimentation after waiting for main building to bind in the traditional construction of basement post-pouring zone It can just be poured after stabilization, inner and outer basement is entirely connected state.Multiple rainfall can be undergone during this section, foundation pit is due to nothing Method backfills and accelerates deformation;And underground water, rainwater flow into basement from post-cast strip, cause long-term ponding in foundation pit and basement. For water-less environment in deep pit monitor and basement, need to long-term pump drainage water in foundation pit and basement, this not only influences underground The normal construction of room, construction cost increase, claim for eot;If depositing soil, meeting temporarily on the architecture construction place of subsequent construction Postpone the on-stream time of the building of subsequent construction.
Invention content
It is an object of the present invention in view of the deficiencies of the prior art, provide a kind of basement post-pouring zone temporary leaking water earth-retaining Construction method.
The technical solution adopted by the present invention is:A kind of basement post-pouring zone temporary leaking water earth-retaining construction method, it is mainly wrapped Include following steps:
Step 1: sealing construction at the post-cast strip of bottom plate:
(1)Arrange mat foundation portion;
(2)The formwork for placing of bottom plate is made, and arranges baseplate reinforcing bar in formwork for placing;
(3)First non-dismantling formwork and the first steel plate for sealing water are provided;
(4)The first non-dismantling formwork is fixed, the vertical arrangement of the first non-dismantling formwork is simultaneously tight with the outer end end face at bottom plate rear pouring tape Patch, it is affixed with baseplate reinforcing bar and the first steel plate for sealing water spot welding;
(5)Pour the concrete of bottom plate;
Step 2: sealing earth-retaining is constructed at the post-cast strip of exterior wall:
(1)It makes and blocks prefabricated section mold and the embedded bar in prefabricated section mold;
(2)Closure prefabricated section is poured, ensures that the both sides for blocking prefabricated section are wider than post-cast strip, is contacted with exterior wall;
(3)It is online that post-cast strip steel bar of the embedded bar spot welding of prefabricated section on exterior wall will be blocked, on the outside of External Wall after It pours and carries out temporary plugging at band;
(4)In the upper surface laying water-proof coiled material for blocking prefabricated section;
(5)Foundation pit surrounding backfills;
Step 3: at floor post-cast strip sealing construction:
(1)The formwork for placing of floor is made, and arranges floor bar in formwork for placing;
(2)Second non-dismantling formwork is installed at floor slab back casting band, in post-cast strip arranged beneath PVC extrusion molding templates;
(3)Floorslab concrete is poured, after concrete curing, removes the formwork for placing of floor;
(4)It is mixed using the second non-dismantling formwork of fluid sealant pair, floor after floorslab concrete and PVC extrusion moldings template are dry Seam between solidifying soil and PVC extrusion molding templates is sealed.
By said program, in step 1(1)In, concrete cushion is first designed according to soil property situation, binds double-layer double-direction steel Muscle net is placed in the foundation pit of concrete cushion, casting concrete bed course;Again response type is laid in the upper surface of concrete cushion Waterproof roll forms waterproof layer;Finally microlith concrete cover is poured in the upper surface of waterproof layer.
By said program, in step 1(3)In, the first non-dismantling formwork includes bar frame and dense mesh, by close mesh Steel wire is completely layered on bar frame, with tied silk banding fixed.
By said program, in step 1(4)In, the first non-dismantling formwork includes cope plate and lower template, the lower end of cope plate It is connected and fixed with the upper surface of the first steel plate for sealing water, the upper end of cope plate and the gluten of bottom plate are fixedly linked, the upper end of lower template It is connected and fixed with the lower surface of the first steel plate for sealing water;The outer end of the bottom plate is stretched out in the one end of first steel plate for sealing water along its length The external part bending of end face, the first steel plate for sealing water is downward.
By said program, in step 1(5)In, when pouring the concrete of bottom plate, ensure that the slump of concrete is 14cm ~16cm;After pouring, the concrete surface of bottom plate outer end end face is in the male and female face of fine uniform, is handled without dabbing.
By said program, in step 2(2)In, the thickness for blocking prefabricated section can be 100mm, highly according to operation side Space determine.
By said program, in step 3(2)In, post-cast strip, the formwork for placing with floor are stretched out in the both ends of PVC extrusion molding templates Contact;By flitch and steel pipe support, steel pipe is fixed on steel tube frame for the lower part of PVC extrusion molding templates.
By said program, in step 3(4)In, closed-water test, no bright water penetration to basement are carried out after sealing glue solidifying Inside then seal qualification.
Beneficial effects of the present invention are:
1, the present invention ensure that ground by carrying out temporary enclosed sealing construction to basement bottom board, exterior wall, floor slab back casting band Lower interior water-less environment, while foundation pit surrounding can also be backfilled when the construction of exterior wall sealing earth-retaining, this method plays foundation pit Prodigious protective effect, backfill stand-by period greatly shorten, and can deposit soil temporarily at the construction field (site);
2, bar-mat reinforcement in concrete cushion is set, concrete cushion can be effectively prevent because of concrete shrinkage or uneven heavy Drop cracking;Waterproof layer and microlith concrete cover, can play the role of temporary leaking water;
3, the lateral pressure of backfill can be kept out by blocking prefabricated section, at the same time as alter-pouring strips mould plate, blocked and be laid on prefabricated section Waterproof roll also functions to temporary leaking water effect;
4, each form joint at each floor is sealed using fluid sealant, can effectively prevent keeping out floor(Top plate)Table Face rainwater enters in basement;Conventional template is replaced using PVC extrusion molding templates, the service life is longer, and waterproof effect is more preferable.
5, construction method advantages of simple of the present invention can effectively prevent underground water, rainwater to flow into basement, construction from post-cast strip Process is few, shortens the construction period, has saved construction cost.
Description of the drawings
Fig. 1 is midsole board post poured band sealing earth-retaining of the present invention construction schematic diagram.
Fig. 2 is post-pouring belt of outer wall sealing earth-retaining construction schematic diagram in the present invention.
Fig. 3 is floor slab back casting band sealing earth-retaining construction schematic diagram in the present invention.
Wherein:1, bottom plate;2, concrete cushion;3, waterproof layer;4, microlith concrete cover;5, post-cast strip;6, first exempts to tear open Template;7, the first steel plate for sealing water;8, exterior wall;9, waterproof roll;10, foundation pit;11, prefabricated section is blocked;;12, fluid sealant;13,PVC Extrusion molding template;14, steel tube frame;15, steel pipe;16, the second non-dismantling formwork;17, bar-mat reinforcement;18, flitch;19, the second sealing Steel plate;20, floor.
Specific implementation mode
For a better understanding of the present invention, the present invention is further described in the following with reference to the drawings and specific embodiments.
The bottom plate 1 of basement is fixed in the portion of mat foundation, and mat foundation portion is fixedly connected on the ground of basement, ground The upper surface of base is made of each reference plane unit, and each reference plane unit is located in same level, and parallel is set each other It sets.Mat foundation portion includes concrete cushion 2, waterproof layer 3, microlith concrete cover 4 successively according to order from bottom to top.
A kind of basement post-pouring zone temporary leaking water earth-retaining construction method as shown in Fig. 1 ~ 3, it is mainly included the following steps that:
Step 1: sealing earth-retaining is constructed at the post-cast strip 5 of bottom plate 1:
1)Arrange mat foundation portion:Concrete cushion 2,17 juxtaposition of binding double-layer double-direction bar-mat reinforcement are designed according to soil property situation In the foundation pit of concrete cushion 2, casting concrete bed course 2;It is laid with response type waterproof volume in the upper surface of concrete cushion 2 Material forms waterproof layer 3;The microlith concrete cover 4 of 5cm thickness is poured in the upper surface of waterproof layer 3;
2)The formwork for placing of bottom plate 1 is made, and arranges baseplate reinforcing bar in formwork for placing(Including bottom muscle, gluten and distribution Muscle);
(3)First non-dismantling formwork is provided:The reinforcement welding of a diameter of 10~14mm is selected to be fabricated to bar frame, by close mesh Steel wire is completely layered on bar frame, with tied silk banding fixed, forms the first non-dismantling formwork 6 of monolithic;It provides and is fixedly connected First steel plate for sealing water 7;
4)Fix the first non-dismantling formwork 6, the first non-dismantling formwork 6 vertically arrangement and with the outer end end face at 1 post-cast strip 5 of bottom plate It is close to, it is affixed with 1 reinforcing bar of bottom plate and 7 spot welding of the first steel plate for sealing water:First non-dismantling formwork 6 includes cope plate and lower template, upper mold The lower end of plate and the upper surface of the first steel plate for sealing water 7 are connected and fixed(It can spot welding), the upper end of cope plate and the gluten of bottom plate 1 are fixed It is connected(It can spot welding);The upper end of lower template and the lower surface of the first steel plate for sealing water 7 are connected and fixed(It can spot welding);First steel plate for sealing water The outer end end face of the bottom plate 1 is stretched out in 7 one end along its length, and the external part bending of the first steel plate for sealing water 7 is downward;
5)Pour bottom plate 1:The slump of concrete is 14cm~16cm when pouring the concrete of bottom plate 1, and ensureing to pour; After pouring, 1 outer end end face of bottom plate(Namely the outer end end face of post-cast strip 2)Concrete surface be in fine uniform convex-concave Face is handled without dabbing.
Step 2: sealing earth-retaining is constructed at the post-cast strip 5 of exterior wall 8:
1)It makes and blocks prefabricated section mold and the pre-buried double-layer double-direction reinforcing bar in prefabricated section mold(A diameter of 6mm's HRB400 reinforcing bars), the spacing of reinforcing bar double-layer double-direction is 150mm;
2)It pours and blocks prefabricated section 11, ensure that the both sides for blocking prefabricated section 11 are wider than the wide 180mm in post-cast strip, with exterior wall 8 Contact, the thickness for blocking prefabricated section 11 can be 100mm, and height is determined according to the space of operation side, is not preferably less than 300mm;Prefabricated section 11 is blocked with negative and positive angle circular arc;
3)The embedded bar spot welding of prefabricated section 11 will be blocked in exterior wall 8(The second waterproof steel plate 19 is fixed on exterior wall 8)On 5 bar-mat reinforcement of post-cast strip on, carry out temporary plugging at the post-cast strip 5 in the outside of External Wall 6;
4)In the upper surface laying water-proof coiled material 9 for blocking prefabricated section 11(It can be response type waterproof roll);
5)10 surrounding of foundation pit backfills, that is, completes the temporary enclosed sealing construction of post-cast strip 5 at exterior wall 8.
Step 3: at floor 20 post-cast strip 5 sealing construction:
1)Slab form is installed:The formwork for placing of floor is installed, and the second non-dismantling formwork 16 is installed at post-cast strip 5; 5 arranged beneath PVC extrusion moldings template 13 of post-cast strip, the both ends of PVC extrusion moldings template 13 stretch out post-cast strip 5, and mould is poured with floor 20 Plate contacts;The lower part of PVC extrusion moldings template 13 is supported by flitch 18 and steel pipe 15, and steel pipe 15 is fixed on steel tube frame 14;
2)Floor bar is arranged in the formwork for placing of floor 20, and pours floorslab concrete;
3)After floorslab concrete solidification, the formwork for placing of floor 20 is removed(The second non-dismantling formwork 16 at post-cast strip 5 is not torn open It removes);
4)After floorslab concrete and PVC extrusion moldings template 13 are dried, using fluid sealant 12 to the second non-dismantling formwork 16, floor Seam between concrete and PVC extrusion moldings template 13 is sealed, and fluid sealant 12 carries out closed-water test after curing, without bright water penetration Qualification is then sealed in basement, that is, completes the temporary enclosed sealing construction of post-cast strip 5 at floor 20.
After basement post-pouring zone 5 reaches the condition of pouring, the building waste in post-cast strip 5 is cleaned out after can pouring and poured Band concrete.
It these are only the preferred embodiment of the present invention, be not intended to restrict the invention, although with reference to the foregoing embodiments to this Invention is described in detail, for those skilled in the art, still can be to recorded in previous embodiment Technical solution is modified or equivalent replacement of some of the technical features.It is all the spirit and principles in the present invention it Interior, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention.

Claims (7)

1. a kind of basement post-pouring zone temporary leaking water earth-retaining construction method, which is characterized in that it is mainly included the following steps that:
Step 1: sealing construction at the post-cast strip of bottom plate:
(1)Arrange mat foundation portion;Concrete cushion is first designed according to soil property situation, binding double-layer double-direction bar-mat reinforcement is placed in mixed In the foundation pit of solidifying soil padding, casting concrete bed course;It is laid with response type waterproof roll in the upper surface of concrete cushion again, is formed Waterproof layer;Finally microlith concrete cover is poured in the upper surface of waterproof layer;
(2)The formwork for placing of bottom plate is made, and arranges baseplate reinforcing bar in formwork for placing;
(3)First non-dismantling formwork and the first steel plate for sealing water are provided;
(4)The first non-dismantling formwork is fixed, the first non-dismantling formwork is arranged and is close to the outer end end face at bottom plate rear pouring tape vertically, with Baseplate reinforcing bar and the first steel plate for sealing water spot welding are affixed;
(5)Pour the concrete of bottom plate;
Step 2: sealing earth-retaining is constructed at the post-cast strip of exterior wall:
(1)It makes and blocks prefabricated section mold and the embedded bar in prefabricated section mold;
(2)Closure prefabricated section is poured, ensures that the both sides for blocking prefabricated section are wider than post-cast strip, is contacted with exterior wall;
(3)It is online that post-cast strip steel bar of the embedded bar spot welding of prefabricated section on exterior wall will be blocked, the post-cast strip on the outside of External Wall Place carries out temporary plugging;
(4)It is laid with response type waterproof roll in the upper surface for blocking prefabricated section;
(5)Foundation pit surrounding backfills;
Step 3: at floor post-cast strip sealing construction:
(1)The formwork for placing of floor is made, and arranges floor bar in formwork for placing;
(2)Second non-dismantling formwork is installed at floor slab back casting band, in post-cast strip arranged beneath PVC extrusion molding templates;
(3)Floorslab concrete is poured, after concrete curing, removes the formwork for placing of floor;
(4)After floorslab concrete and PVC extrusion moldings template are dry, using the second non-dismantling formwork of fluid sealant pair, floorslab concrete And the seam between PVC extrusion molding templates is sealed.
2. basement post-pouring zone temporary leaking water earth-retaining construction method as described in claim 1, which is characterized in that in step 1 (3)In, the first non-dismantling formwork includes bar frame and dense mesh, and dense mesh is expired and is layered on bar frame, with bundle Silk banding fixed.
3. basement post-pouring zone temporary leaking water earth-retaining construction method as described in claim 1, which is characterized in that in step 1 (4)In, the first non-dismantling formwork includes cope plate and lower template, and the lower end of cope plate connect solid with the upper surface of the first steel plate for sealing water Fixed, the upper end of cope plate and the gluten of bottom plate are fixedly linked, and the upper end of lower template connect solid with the lower surface of the first steel plate for sealing water It is fixed;The outer end end face of the bottom plate is stretched out in the one end of first steel plate for sealing water along its length, and the external part of the first steel plate for sealing water is curved It is bent downward.
4. basement post-pouring zone temporary leaking water earth-retaining construction method as described in claim 1, which is characterized in that in step 1 (5)In, when pouring the concrete of bottom plate, ensure that the slump of concrete is 14cm~16cm;After pouring, bottom plate outer end end The concrete surface in face is in the male and female face of fine uniform, is handled without dabbing.
5. basement post-pouring zone temporary leaking water earth-retaining construction method as described in claim 1, which is characterized in that in step 2 (2)In, the thickness for blocking prefabricated section is 100mm, is highly determined according to the space of operation side;Block prefabricated section band negative and positive angle Circular arc.
6. basement post-pouring zone temporary leaking water earth-retaining construction method as described in claim 1, which is characterized in that in step 3 (2)In, post-cast strip is stretched out at the both ends of PVC extrusion molding templates, is contacted with the formwork for placing of floor;The lower part of PVC extrusion molding templates is by wood Side and steel pipe support, steel pipe are fixed on steel tube frame.
7. basement post-pouring zone temporary leaking water earth-retaining construction method as described in claim 1, which is characterized in that in step 3 (4)In, closed-water test is carried out after sealing glue solidifying, and qualification is then sealed in no bright water penetration to basement.
CN201610781771.8A 2016-08-31 2016-08-31 A kind of basement post-pouring zone temporary leaking water earth-retaining construction method Active CN106284427B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610781771.8A CN106284427B (en) 2016-08-31 2016-08-31 A kind of basement post-pouring zone temporary leaking water earth-retaining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610781771.8A CN106284427B (en) 2016-08-31 2016-08-31 A kind of basement post-pouring zone temporary leaking water earth-retaining construction method

Publications (2)

Publication Number Publication Date
CN106284427A CN106284427A (en) 2017-01-04
CN106284427B true CN106284427B (en) 2018-10-23

Family

ID=57673210

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610781771.8A Active CN106284427B (en) 2016-08-31 2016-08-31 A kind of basement post-pouring zone temporary leaking water earth-retaining construction method

Country Status (1)

Country Link
CN (1) CN106284427B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108457411A (en) * 2018-05-31 2018-08-28 杭州通达集团有限公司 A kind of laminated floor slab and its construction method of assembled architecture
CN108951700B (en) * 2018-07-04 2024-01-16 中铁隧道局集团有限公司 Prefabricated assembled bottom plate connected with piles, assembled structure and installation method thereof
CN108678009A (en) * 2018-07-26 2018-10-19 中建四局第四建筑工程有限公司 A kind of basement post-pouring zone reserved passageway construction method and device
CN109025265B (en) * 2018-07-28 2020-11-06 福建江夏学院 Method for supporting post-cast strip of side mold of thin plate
CN109025293B (en) * 2018-07-28 2020-11-06 福建江夏学院 Thick plate side mold post-cast strip supporting method
CN109736357A (en) * 2019-02-25 2019-05-10 中建四局第一建筑工程有限公司 A kind of basement bottom plate rear pouring tape construction joint optimization processing structure
CN110374214A (en) * 2019-07-29 2019-10-25 江西国金建设集团有限公司 Finished product post-cast strip
CN111395407A (en) * 2020-03-31 2020-07-10 中国二十二冶集团有限公司 Cast-in-place concrete post-cast strip forming construction method
CN111648411B (en) * 2020-05-06 2023-06-09 上海建工二建集团有限公司 Down-turned post-pouring belt support changing structure, construction method and post-pouring belt construction method
CN111997096A (en) * 2020-09-01 2020-11-27 中建八局第四建设有限公司 Raft plate and construction method of basement outer wall post-cast strip
CN115369923B (en) * 2021-05-20 2024-02-02 湖北远大建设集团有限公司 Deformation-preventing slurry leakage post-pouring belt structure of basement bottom plate and construction method thereof
CN114277849B (en) * 2021-11-16 2023-10-27 中国水电建设集团十五工程局有限公司 Construction method of post-cast strip disassembly-free composite water stop template

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101298781A (en) * 2008-06-13 2008-11-05 浙江省一建建设集团有限公司 Basement bottom plate rear pouring tape construction method
CN202530585U (en) * 2012-04-22 2012-11-14 项谱成 Post-cast strip protecting construction for structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101298781A (en) * 2008-06-13 2008-11-05 浙江省一建建设集团有限公司 Basement bottom plate rear pouring tape construction method
CN202530585U (en) * 2012-04-22 2012-11-14 项谱成 Post-cast strip protecting construction for structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
地下室建筑后浇带的施工技术;洪伟民;《福建建材》;20120930(第137期);第2、3节 *
地下室顶板及侧墙后浇带预封闭施工技术;顾福明等;《建筑施工》;20160825;第38卷(第8期);第3节 *

Also Published As

Publication number Publication date
CN106284427A (en) 2017-01-04

Similar Documents

Publication Publication Date Title
CN106284427B (en) A kind of basement post-pouring zone temporary leaking water earth-retaining construction method
CN214061703U (en) Seepage-proofing structure for post-cast strip of bottom plate of underground chamber
CN104404985B (en) The construction method of basement bottom plate rear pouring tape waterproof construction
CN105649113A (en) Structure and construction method of basement post-cast strip
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN105862928B (en) A kind of post-cast strip exterior wall advanced water-stopping processing structure and its construction technology
CN108166531A (en) Basic alter-pouring strips mould plate and the construction method for pouring post-cast strip
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN110388092A (en) A kind of construction method of historical building wall reparation
CN109236322A (en) It a kind of artificial bottom plate preventing soft-rock tunnel pucking and its constructs and method for maintaining
CN108638322B (en) Prefabricated post concreting method in a kind of assembled architecture
CN108360559A (en) The disposable whole pouring construction process method of skyscraper underground garage car ramp
CN102619329B (en) Expansion restraint construction method for post-pouring belt
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN105756100A (en) Basement post-pouring belt system and making method thereof
CN205476487U (en) Dismantled cyclic utilization device of centre form come -up is packed to control light block
CN216340909U (en) Novel advanced water stopping device and system for roof post-cast strip of garage
CN110295630A (en) The late poured band structure of multilayer constraint antiseep
CN208122041U (en) A kind of IPS Cast-in-place concrete shear wall structure of self-heat preservation system system
CN207829011U (en) A kind of contrary sequence method well body retaining wall cover half device
CN109024649A (en) Bottom plate multilayer Large-size rebar installs system and construction method
CN212294760U (en) Advanced waterproof structure of bottom plate post-cast strip
CN211646488U (en) A device that is used for subway lid to dig reverse construction method construction joint water repellent
CN110387908A (en) The rear pouring tape construction method of multilayer constraint antiseep
CN105926437A (en) Hinge joint drainage structure and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant