CN106283955A - Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction - Google Patents

Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction Download PDF

Info

Publication number
CN106283955A
CN106283955A CN201610826229.XA CN201610826229A CN106283955A CN 106283955 A CN106283955 A CN 106283955A CN 201610826229 A CN201610826229 A CN 201610826229A CN 106283955 A CN106283955 A CN 106283955A
Authority
CN
China
Prior art keywords
support rail
rail beam
pile foundation
base plate
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610826229.XA
Other languages
Chinese (zh)
Other versions
CN106283955B (en
Inventor
郭建湖
李小和
赵新益
姜鹰
姚洪锡
李巍
王勇刚
杨辉建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201610826229.XA priority Critical patent/CN106283955B/en
Publication of CN106283955A publication Critical patent/CN106283955A/en
Application granted granted Critical
Publication of CN106283955B publication Critical patent/CN106283955B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • E01B2/006Deep foundation of tracks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/08Deep or vertical foundation

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Railway Tracks (AREA)
  • Foundations (AREA)

Abstract

The invention belongs to that middle low speed magnetic suspension traffic engineering is low puts Line technology field, and disclose medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction, including roadbed filling under pile foundation carrying structure, reinforced concrete supporting beam, armored concrete support rail beam base plate, reinforced concrete beam type structure, support rail beam and support rail beam both sides backfill filler, pile foundation carrying structure is provided with many;Described reinforced concrete beam type structure is accepted at the top of armored concrete support rail beam base plate;Support rail beam both sides backfill filler is accepted by roadbed filling under described support rail beam.The present invention can avoid the low defect putting circuit support rail girder construction of tradition, long-time stability are more preferable, and support rail girder construction is deformed and the high request of settlement after construction by low speed magnetic suspension traffic engineering track structure during it both meets, meet again the requirement of the controllability of bedding long-time stability, durability and construction quality, and economy is more preferably.

Description

Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
Technical field
The invention belongs to that middle low speed magnetic suspension traffic engineering is low puts Line technology field, more particularly, to middle low speed magnetic Floating traffic engineering single line embankment location support rail girder construction pattern.
Background technology
Middle low speed magnetic suspension track traffic belongs to a kind of novel traffic mode, and achievement in research both domestic and external is less, the whole world Open the circuit minority especially of operation.The middle low speed magnetic suspension railway business fortune that the most only in March, 2005, Japan's construction was opened The middle low speed magnetic suspension railway business operating line that line-the East Hillside Line and in June, 2014, Korea S opened.And the middle low speed of China Magnetic suspension traffic only National University of Defense technology's test wire, Green City Mountain test wire, Tangshan experiment line at present, but do not put into effect Formal circuit, and all based on elevated structure, rarely seen about the low research put in terms of circuit support rail girder construction and application.
Middle low speed magnetic suspension hangs traffic civil engineering part and mainly comprises bridge, low circuit, station and the rolling stock section of putting, and low puts circuit Being made up of with roadbed under support rail beam the section of track, support rail beam, the support rail beam of supporting track is arranged on the roadbed being made up of earth structure On, the operation of middle low speed magnetic suspension train includes suspending, guide, drive and brake and is required for completing on support rail beam.Magnetic Aerotrain is the highest to line construction deformation requirements, because the least the deforming it is possible to affect comfortableness even prestige by bus of structure Side of body traffic safety, so the design of support rail beam is particularly significant.
Existing support rail girder construction is applied and be there is problems in that on circuit middle low speed magnetic suspension traffic low putting
(1) existing low circuit support rail girder construction of putting is arranged on embankment earth structure, embankment earth structure by Filler fills compacting and forms, and compaction quality is wayward, and the later stage is susceptible to deformation, and settlement after construction is difficult to control to.
(2) low circuit support rail girder construction of putting requires height to the settlement after construction of roadbed and ground, and is routed through the ground in region Matter condition is typically all complicated and changeable, therefore also needs to ground be carried out consolidation process simultaneously, and roadbed filling puts slope groundwork Reinforcing area increases, and cost is high, long in time limit;And basement process belongs to disguised engineering, conventional reinforced soft soil ground is used to arrange Executing and reinforce, construction quality is wayward.
(3) owing to filler fills the low circuit earth structure of putting being compacted, there is vulnerability, and construction quality is difficult to Control, relatively easily produce differential settlement, cause bedding vertical and horizontal bad stability under support rail beam, so that support rail beam The stability in the large of structure is impaired.
Magnetic suspension is low, and to put circuit support rail beam higher to post-construction settlement of subgrade, bedding long-time stability and life requirement, when When circuit is positioned at foundation stabilization location, taking traditional support rail girder construction pattern to there is the construction period long, construction quality is the most easily-controllable The defects such as system, whole structural stability are poor and less economical.
Summary of the invention
For disadvantages described above or the Improvement requirement of prior art, the invention provides medium-and low-speed maglev traffic engineering single line and fill out Side's location pile foundation joist type support rail girder construction, can avoid the low defect putting circuit support rail girder construction of tradition, and construction quality is easier to During controlling, long-time stability are more preferable, and it both meets, support rail girder construction is deformed by low speed magnetic suspension traffic engineering track structure With the high request of settlement after construction, meet again the requirement of the controllability of bedding long-time stability, durability and construction quality, and economical Property is more preferably.
For achieving the above object, the invention provides medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type to hold Beam-and-rail structure, it is characterised in that include that pile foundation carries structure, reinforced concrete supporting beam, armored concrete support rail beam base plate, reinforcing bar Roadbed filling and support rail beam both sides backfill filler under concrete beam-type structure, support rail beam, wherein,
Described pile foundation carrying structure is provided with many, and every described pile foundation carrying structure is all vertically arranged, and every institute Described reinforced concrete supporting beam is all accepted on the top stating pile foundation carrying structure;
Described reinforced concrete supporting beam accepts described armored concrete support rail beam base plate;
Described reinforced concrete beam type structure is accepted at the top of described armored concrete support rail beam base plate;
The top of described pile foundation carrying structure embeds described reinforced concrete supporting beam and just connects with it, described armored concrete torr Beam has just connect with described armored concrete support rail beam base plate or has overlapped, described armored concrete support rail beam base plate and described reinforced concrete Soil girder structure formed by integrally casting molding thus collectively form armored concrete support rail beam;
Described reinforced concrete supporting beam both sides are provided with for limiting described armored concrete support rail beam base plate lateral displacement Convex gear platform;
Under described support rail beam, roadbed filling is arranged between shallow layer reinforcement district and described armored concrete support rail beam base plate, with For providing construction flat for described armored concrete support rail beam base plate, reinforced concrete supporting beam and support rail beam both sides backfill filler Platform, and provide lateral support for described pile foundation carrying structure;Wherein, described shallow layer reinforcement district is arranged on the shallow table of soft stratum Layer, and roadbed filling and the vertical consistency of described reinforced concrete beam type structure under described shallow layer reinforcement district, described support rail beam;
Described support rail beam both sides backfill filler is accepted by roadbed filling under described support rail beam, and described support rail beam both sides Backfill filler props up the both sides of described armored concrete support rail beam base plate, so that described armored concrete support rail beam base plate is risen protection Act on and retrain the transverse shifting of described armored concrete support rail beam base plate, and maintenance passage is provided;
Under described support rail beam roadbed filling and described support rail beam both sides backfill filler collectively form filler filling body, described in fill out Material filling body both sides are provided with weathering;
The lower end of every described pile foundation carrying structure sequentially passes through roadbed filling under described support rail beam, described shallow layer reinforcement district Stretching in supporting course with after described soft stratum, with when soft stratum produces sedimentation, described pile foundation carrying structure can be born negative Frictional resistance, thus provide stable bearing capacity to armored concrete support rail beam base plate and reinforced concrete beam type structure, to reduce The adverse effect vertical, the vertical and horizontal rigidity of armored concrete support rail beam produced because of the sedimentation of filler filling body.
Preferably, described pile foundation carrying structure is cast-in-situ bored pile, reinforced concrete supporting beam and support rail beam base plate just connect or Overlap joint, just connects with pile foundation carrying structure.Using pin overlap joint in the position of support rail beam internode seam, remaining position uses and just connects.
Preferably, described support rail beam both sides backfill the height of filler and the height phase of described armored concrete support rail beam base plate Deng.
Preferably, pile foundation carrying structure described in all these is ranks arrangements.
In general, by the contemplated above technical scheme of the present invention compared with prior art, it is possible to show under acquirement Benefit effect:
(1) the armored concrete support rail beam base plate of the present invention, reinforced concrete beam type structure all use armored concrete existing Field one-piece casting, the two composition integral reinforced concrete structure is in order to directly take on track load and the magnetic-levitation train of track transmission Load, then deadweight and upper load are passed to pile foundation rigidly connected with it carrying structure, structural reliability is high.
(2) the pile foundation carrying structure of the present invention is goed deep in supporting course, and embankment produces when necessarily settling, and pile foundation carrying structure depends on So can bear negative friction and stronger bearing capacity is provided, it is to avoid because of filling compaction with foundation stabilization quality is wayward causes Differential settlement is vertical on support rail beam, the impact of vertical and horizontal rigidity, structure vertical cross stiffness and structural reliability are more excellent.
(3) put circuit soft soil zone low, according to embankment stability need the shallow top layer of soft stratum is carried out necessity Reinforcing, its reinforcement depth is by embankment stability control, compared to by settling and stablizing tradition when Two indices controls solely For base reinforcing mode, shallow layer reinforcement district reinforcement depth is little, can effectively control roadbed reclamation and roadbed in conjunction with pile foundation carrying structure Settlement after construction.Non-soft soil zone more can avoid embankment to put the stiffening basic ground of the wide area produced behind slope, and Pile foundation carrying structure construction quality is more easy to control, can effectively control construction quality, investment reduction, reduction of erection time, has significantly Technology and economic advantages.
(4) reinforced concrete supporting beam that pile foundation carrying structure and reinforced concrete floor are arranged, can be greatly reduced pile foundation The stress concentration phenomenon of armored concrete support rail beam base plate at carrying structure;Further, since laterally the connecting of reinforced concrete supporting beam Connect effect, too increase lateral stiffness and the ability of opposing differential settlement deformation of structure, the quantity of transverse pile foundation can be reduced, Reduce investment.
Accompanying drawing explanation
Fig. 1 is the schematic cross-sectional view of the present invention;
Fig. 2 is the schematic longitudinal section of the present invention;
Fig. 3 is the distribution schematic diagram of pile foundation of the present invention carrying structure;
Fig. 4 is that pile foundation reinforced concrete supporting beam of the present invention has just connect connection diagram with armored concrete support rail beam base plate.
Fig. 5 is that pile foundation reinforced concrete supporting beam of the present invention overlaps connection diagram with armored concrete support rail beam base plate.
Fig. 6 is the cross sectional representation of pin in the present invention.
Detailed description of the invention
In order to make the purpose of the present invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, right The present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, and It is not used in the restriction present invention.If additionally, technical characteristic involved in each embodiment of invention described below The conflict of not constituting each other just can be mutually combined.
Reference Fig. 1~Fig. 6, medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction, including Pile foundation carrying structure 3, reinforced concrete supporting beam 90, armored concrete support rail beam base plate 2, reinforced concrete beam type structure 1, support rail Roadbed filling 5 and support rail beam both sides backfill filler 4 under beam, wherein,
Described pile foundation carrying structure 3 is provided with many, and every described pile foundation carrying structure 3 is all vertically arranged, and every Described reinforced concrete supporting beam 90 is all accepted on the top of described pile foundation carrying structure 3;
Described reinforced concrete supporting beam 90 accepts described armored concrete support rail beam base plate 2;
Described reinforced concrete beam type structure 1 is accepted on the top of described armored concrete support rail beam base plate 2;
The top of described pile foundation carrying structure 3 embeds described reinforced concrete supporting beam 90 and just connects with it, described reinforced concrete Soil joist 90 has just connect with described armored concrete support rail beam base plate 2 or has overlapped, and described armored concrete support rail beam base plate 2 is with described Reinforced concrete beam type structure 1 is one-body molded thus collectively forms armored concrete support rail beam 9;
It is provided with on described reinforced concrete supporting beam 90 for limiting described armored concrete support rail beam base plate 2 lateral displacement Convex gear platform 91;
Under described support rail beam roadbed filling 5 be arranged on shallow layer reinforcement district 6 and described armored concrete support rail beam base plate 2 it Between, carry for for described armored concrete support rail beam base plate 2, reinforced concrete supporting beam 90 and support rail beam both sides backfill filler 4 For operation platform, and provide lateral support for described pile foundation carrying structure 3;Wherein, described shallow layer reinforcement district 6 is arranged on flabbily The shallow top layer of layer 7, and roadbed filling 5 and described reinforced concrete beam type structure under described shallow layer reinforcement district 6, described support rail beam The vertical consistency of 1;
Described support rail beam both sides backfill filler 4 is accepted by roadbed filling 5 under described support rail beam, and described support rail beam two Side backfill filler 4 props up the both sides of described armored concrete support rail beam base plate 2, with to described armored concrete support rail beam base plate 2 Shield and retrain the transverse shifting of described armored concrete support rail beam base plate 2, and maintenance passage is provided;
Under described support rail beam, roadbed filling 5 and described support rail beam side backfill filler 4 collectively form filler filling body 10, described Filler filling body 10 both sides are provided with weathering 11;
The lower end of every described pile foundation carrying structure 3 sequentially passes through roadbed filling 5, described shallow layer reinforcement under described support rail beam Stretching into behind district 6 and described soft stratum 7 in supporting course 8, with when soft stratum 7 produces sedimentation, described pile foundation carrying structure 3 can Bear negative friction, thus provide stable carrying to armored concrete support rail beam base plate 2 and reinforced concrete beam type structure 1 Power, to reduce because vertical, the vertical and horizontal rigidity of armored concrete support rail beam 9 are produced not by the sedimentation of backfill packing section 10 Profit impact.
Further, described pile foundation carrying structure 3 be cast-in-situ bored pile, reinforced concrete supporting beam and support rail beam base plate just connect or Overlap joint, just connects with pile foundation carrying structure.Position reinforced concrete supporting beam at support rail beam internode seam uses pin with support rail beam base plate Nail overlap joint, remaining position uses and just connects.
Described pin 10 includes pre-buried connection reinforcing bar 10.1, Colophonium hemp cut 10.2 and rustless steel sleeve pipe 10.3, described pre-buried Connect reinforcing bar 10.1 be positioned at described rustless steel sleeve pipe 10.3 and arrange described Colophonium hemp cut 10.2 between the two.
The height of described support rail beam both sides backfill filler 4 is equal with the height of described armored concrete support rail beam base plate 2, institute These the described pile foundations carrying structure 3 having is arranged in ranks.
This structural shape can effectively solve in low speed magnetic suspension traffic engineering low to put circuit tight to post-construction settlement of subgrade requirement Lattice, the engineering taking traditional foundation stabilization measure to cause is huge, it is big, long in time limit to invest, and basement process and embankment Construction quality is wayward, bedding long-time stability and the problem of poor durability, thus improves low circuit support rail girder construction of putting Reliability, reduces the engineering risk of traditional structure pattern.
The armored concrete support rail beam 9 of the present invention uses reinforced concrete soil scene one-piece casting, to directly take on track lotus Carry and the magnetic-levitation train load of track transmission, then deadweight and upper load are passed to pile foundation rigidly connected with it carrying structure 3, structural reliability is high, can save the large area stiffening basic ground produced after traditional embankment puts slope.
Pile foundation carrying structure 3 uses cast-in-situ bored pile, transverse direction and longitudinal direction to have and is arranged with many reinforced concrete drillings fillings Note stake, vertical and horizontal rigidity is big;And pile foundation carries structure 3 and gos deep into supporting course 8, when soft stratum 7 produces sedimentation, pile foundation carries Structure 3 still can be born negative friction and be provided stronger bearing capacity to armored concrete support rail beam base plate 2.
The reinforced concrete supporting beam 90 that pile foundation carrying structure 3 and reinforced concrete floor 2 are arranged, can be greatly reduced pile foundation The stress concentration phenomenon of armored concrete support rail beam base plate 2 at carrying structure 3;Further, since the horizontal stroke of reinforced concrete supporting beam 90 To interconnection function, too increase lateral stiffness and the ability of opposing differential settlement deformation of structure, transverse pile foundation can be reduced Quantity, reduces investment.
Low when putting circuit by soft soil zone, top layer shallow to ground should be needed to carry out necessity add according to embankment stability Gu, form shallow layer reinforcement district 6.The reinforcement depth in shallow layer reinforcement district 6 is by embankment stability control, and its reinforcement depth should be according to embankment Raising, foundation condition are determined by stability calculation.Compared to by settling and stablizing the single ground of tradition when Two indices controls For reinforcing mode, shallow layer reinforcement district 6 reinforcement depth is little, can effectively control roadbed reclamation and roadbed in conjunction with pile foundation carrying structure 3 Settlement after construction.By contrast, this new structure foundation stabilization quantity is little, invests little, and more conducively construction quality and settlement after construction Control, and save cost and reduction of erection time.
The making step that the present invention is concrete is as follows:
(1) smooth construction site, requires to carry out the shallow layer foundation consolidation process of necessity, forms shallow layer reinforcement district according to design 6, then require placement in layers according to embankment and be densified to reinforced concrete floor bottom surface absolute altitude;
(2) it is in embankment subgrade cross section, the perfusion of vertical section direction construction drill at reinforced concrete floor bottom surface absolute altitude Stake, i.e. pile foundation carrying structure 3, drilled pile construction should use the construction technology little to railway embankment disturbance, if desired at embankment Steel pile casting is set in the range of filled height or draws hole;After cast-in-situ bored pile reaches desired strength, amputate pile crown by code requirement, Assembling reinforcement concrete joist and the connection reinforcing bar with stake;
(3) according to design attitude to reinforced concrete supporting beam 90, convex gear platform 91 formwork erection, one-time-concreting molding, before pouring Carry out all kinds of built-in fitting such as pin 10 and with pile foundation connect the location of reinforcing bar and installation, concrete is removed after reaching design strength Template;
It is (4) long to armored concrete support rail beam base plate 2 and reinforced concrete beam type structure 1 merogenesis formwork erection according to design joint, One-time-concreting molding, carries out all kinds of built-in fitting such as sleeper pedestal and connects reinforcing bar, water conservancy diversion rail bearing built-in fitting, pile foundation connection before pouring The location of reinforcing bar etc. and installation;
(5) difference form removal after each parts concrete reaches design strength, then by armored concrete support rail beam base plate 2 Bedding filler backfill in thickness range, outward-dipping weathering is made in backfill face and to carry out top layer by design requirement waterproof i.e. Can.
As it will be easily appreciated by one skilled in the art that and the foregoing is only presently preferred embodiments of the present invention, not in order to Limit the present invention, all any amendment, equivalent and improvement etc. made within the spirit and principles in the present invention, all should comprise Within protection scope of the present invention.

Claims (6)

1. medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction, it is characterised in that include pile foundation Carrying structure (3), reinforced concrete supporting beam (90), armored concrete support rail beam base plate (2), reinforced concrete beam type structure (1), Roadbed filling (5) and support rail beam both sides backfill filler (4) under support rail beam, wherein,
Described pile foundation carrying structure (3) is provided with many, and every described pile foundation carrying structure (3) is all vertically arranged, and every Described reinforced concrete supporting beam (90) is all accepted on the top of described pile foundation carrying structure (3);
Described reinforced concrete supporting beam (90) accepts described armored concrete support rail beam base plate (2);
Described reinforced concrete beam type structure (1) is accepted on the top of described armored concrete support rail beam base plate (2);
The top of described pile foundation carrying structure (3) embeds described reinforced concrete supporting beam (90) and just connects with it, described reinforced concrete Soil joist (90) has just connect with described armored concrete support rail beam base plate (2) or has overlapped, described armored concrete support rail beam base plate (2) With the formed by integrally casting molding of described reinforced concrete beam type structure (1) thus collectively form armored concrete support rail beam (9);
Described reinforced concrete supporting beam (90) both sides are provided with for limiting described armored concrete support rail beam base plate (2) laterally position Convex gear platform (91) moved;
Under described support rail beam roadbed filling (5) be arranged on shallow layer reinforcement district (6) and described armored concrete support rail beam base plate (2) it Between, backfill filler for for described armored concrete support rail beam base plate (2), reinforced concrete supporting beam (90) and support rail beam both sides (4) provide operation platform, and be that described pile foundation carrying structure (3) provides lateral support;Wherein, described shallow layer reinforcement district (6) sets Put roadbed filling (5) and described steel under the shallow top layer at soft stratum (7), and described shallow layer reinforcement district (6), described support rail beam Reinforced concrete beam type structure (1) vertical consistency;
Described support rail beam both sides backfill filler (4) are accepted by roadbed filling (5) under described support rail beam, and described support rail beam two Side backfill filler (4) props up the both sides of described armored concrete support rail beam base plate (2), with at the bottom of described armored concrete support rail beam Plate (2) shields and retrains the transverse shifting of described armored concrete support rail beam base plate (2), and provides maintenance to lead to Road;
Under described support rail beam, roadbed filling (5) and described support rail beam both sides backfill filler (4) collectively form filler filling body (10), Described filler filling body (10) both sides are provided with weathering (11);
The lower end of every described pile foundation carrying structure (3) sequentially passes through roadbed filling (5), described shallow layer reinforcement under described support rail beam Stretching in supporting course (8) behind district (6) and described soft stratum (7), with when soft stratum (7) produces sedimentation, described pile foundation is held Carry structure (3) and negative friction can be born, thus be armored concrete support rail beam base plate (2) and reinforced concrete beam type structure (1) There is provided stable bearing capacity, to reduce vertical, longitudinally to armored concrete support rail beam (9) of the sedimentation because of filler filling body (10) The adverse effect produced with lateral stiffness.
Medium-and low-speed maglev traffic engineering single line embankment location the most according to claim 1 pile foundation joist type support rail girder construction, It is characterized in that, described pile foundation carrying structure (3) is cast-in-situ bored pile, and reinforced concrete supporting beam has just connect with support rail beam base plate or taken Connect, just connect with pile foundation carrying structure.
Medium-and low-speed maglev traffic engineering single line embankment location the most according to claim 1 pile foundation joist type support rail girder construction, It is characterized in that, position reinforced concrete supporting beam and support rail beam base plate at support rail beam internode seam use pin overlap joint, remaining position Put employing just to connect.
Medium-and low-speed maglev traffic engineering single line embankment location the most according to claim 1 pile foundation joist type support rail girder construction, It is characterized in that, the height of described support rail beam both sides backfill filler (4) and the height of described armored concrete support rail beam base plate (2) Equal.
Medium-and low-speed maglev traffic engineering single line embankment location the most according to claim 1 pile foundation joist type support rail girder construction, It is characterized in that, described in all these, pile foundation carrying structure (3) is arranged in ranks.
Medium-and low-speed maglev traffic engineering single line embankment location the most according to claim 1 pile foundation joist type support rail girder construction, It is characterized in that, described pin includes that pre-buried connection reinforcing bar, Colophonium hemp cut and rustless steel sleeve pipe, described pre-buried connection reinforcing bar are positioned at Described rustless steel sleeve pipe is interior and arranges described Colophonium hemp cut between the two.
CN201610826229.XA 2016-09-15 2016-09-15 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction Active CN106283955B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610826229.XA CN106283955B (en) 2016-09-15 2016-09-15 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610826229.XA CN106283955B (en) 2016-09-15 2016-09-15 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction

Publications (2)

Publication Number Publication Date
CN106283955A true CN106283955A (en) 2017-01-04
CN106283955B CN106283955B (en) 2017-12-12

Family

ID=57711425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610826229.XA Active CN106283955B (en) 2016-09-15 2016-09-15 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction

Country Status (1)

Country Link
CN (1) CN106283955B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111235969A (en) * 2020-03-16 2020-06-05 中铁二院工程集团有限责任公司 Overhead roadbed structure, roadbed assembly, roadbed system and construction method
CN113502847A (en) * 2021-07-15 2021-10-15 天津城建大学 Assembly type rigid support protection foundation structure for buried pipeline

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005057380A1 (en) * 2005-11-30 2007-06-06 Walter Sobolewski Tubular, hollow, solid roadway
CN201473871U (en) * 2009-08-26 2010-05-19 铁道第三勘察设计院集团有限公司 Rail track of maglev train with middle and low-speed
CN203546524U (en) * 2013-09-29 2014-04-16 中铁二院工程集团有限责任公司 Medium-and-low-speed magnetically-suspended traffic integral-type road-bed track structure
CN104480803A (en) * 2014-12-11 2015-04-01 中铁第四勘察设计院集团有限公司 Medium-and-low speed magnetic levitation railway low route continuous arched supporting rail beam structure and construction method
CN105887587A (en) * 2016-04-29 2016-08-24 中铁第四勘察设计院集团有限公司 Turnout zone and non-turnout zone transition section structure for medium and low-speed magnetic levitation low implantation line
CN206157484U (en) * 2016-09-15 2017-05-10 中铁第四勘察设计院集团有限公司 Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005057380A1 (en) * 2005-11-30 2007-06-06 Walter Sobolewski Tubular, hollow, solid roadway
CN201473871U (en) * 2009-08-26 2010-05-19 铁道第三勘察设计院集团有限公司 Rail track of maglev train with middle and low-speed
CN203546524U (en) * 2013-09-29 2014-04-16 中铁二院工程集团有限责任公司 Medium-and-low-speed magnetically-suspended traffic integral-type road-bed track structure
CN104480803A (en) * 2014-12-11 2015-04-01 中铁第四勘察设计院集团有限公司 Medium-and-low speed magnetic levitation railway low route continuous arched supporting rail beam structure and construction method
CN105887587A (en) * 2016-04-29 2016-08-24 中铁第四勘察设计院集团有限公司 Turnout zone and non-turnout zone transition section structure for medium and low-speed magnetic levitation low implantation line
CN206157484U (en) * 2016-09-15 2017-05-10 中铁第四勘察设计院集团有限公司 Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111235969A (en) * 2020-03-16 2020-06-05 中铁二院工程集团有限责任公司 Overhead roadbed structure, roadbed assembly, roadbed system and construction method
CN113502847A (en) * 2021-07-15 2021-10-15 天津城建大学 Assembly type rigid support protection foundation structure for buried pipeline

Also Published As

Publication number Publication date
CN106283955B (en) 2017-12-12

Similar Documents

Publication Publication Date Title
CN206157496U (en) Moderate -low speed magnetic levitation traffic engineering single line location pile foundation combined type support rail girder construction of filling
CN106283948B (en) Medium-and low-speed maglev traffic engineering two-wire embankment location pile foundation joist type support rail girder construction
CN206157484U (en) Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling
CN106283955B (en) Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN206157483U (en) Moderate -low speed magnetic levitation traffic engineering double -line location supporting beam of pile foundation formula support rail girder construction of filling
CN106283949B (en) Medium-and low-speed maglev traffic engineering single line embankment location independence pier stud type support rail girder construction
CN206157495U (en) Moderate -low speed magnetic levitation double -line compound framing type support rail girder construction of location pile foundation of filling
CN206127736U (en) Moderate -low speed magnetic levitation double -line compound framing formula support rail roof beam transition section structure of location pile foundation that fills
CN106283952B (en) Medium-and low-speed maglev two-wire excavation location pile foundation joist framing type support rail girder construction
CN106283938A (en) Medium-and low-speed maglev two-wire excavation location pile foundation is combined framing type support rail girder construction
CN206157490U (en) Moderate -low speed magnetic levitation double -line location supporting beam of pile foundation framing type support rail girder construction of filling
CN106283968B (en) Medium-and low-speed maglev two-wire embankment location pile foundation is combined framing type support rail girder construction
CN106436497B (en) Medium-and low-speed maglev traffic engineering two-wire embankment location independence pier stud type support rail girder construction
CN206127742U (en) Moderate -low speed magnetic levitation traffic engineering double -line location detached pier column type support rail girder construction of filling
CN206157477U (en) Moderate -low speed magnetic levitation traffic engineering double -line location pile foundation combined type support rail girder construction of filling
CN206127745U (en) Moderate -low speed magnetic levitation traffic engineering single line location detached pier column type support rail girder construction of filling
CN106283971B (en) Medium-and low-speed maglev traffic engineering single line excavation location pile foundation joist type support rail girder construction
CN106283967B (en) Medium-and low-speed maglev two-wire embankment location pile foundation joist framing type support rail beam transition section structure
CN206157487U (en) Moderate -low speed magnetic levitation single line location pile foundation combined type support rail roof beam transition section structure that fills
CN206219912U (en) Medium-and low-speed maglev two-wire embankment location pile foundation joist framing type support rail beam transition section structure
CN106436496B (en) Medium-and low-speed maglev single line embankment location pile foundation combined type support rail beam transition section structure
CN206157486U (en) Moderate -low speed magnetic levitation traffic engineering single line excavation location pile foundation combined type support rail girder construction
CN206219896U (en) Medium-and low-speed maglev traffic engineering two-wire excavation location pile foundation joist type support rail girder construction
CN206157494U (en) Moderate -low speed magnetic levitation traffic engineering single line excavation location supporting beam of pile foundation formula support rail girder construction
CN106283972B (en) Medium-and low-speed maglev traffic engineering single line embankment location pile foundation combined type support rail girder construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant