CN106251911B - The method of building intelligence system multidigit pre-control electromagnetism Leibo interference - Google Patents

The method of building intelligence system multidigit pre-control electromagnetism Leibo interference Download PDF

Info

Publication number
CN106251911B
CN106251911B CN201610580697.3A CN201610580697A CN106251911B CN 106251911 B CN106251911 B CN 106251911B CN 201610580697 A CN201610580697 A CN 201610580697A CN 106251911 B CN106251911 B CN 106251911B
Authority
CN
China
Prior art keywords
grounding
downlead
metal
cable
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610580697.3A
Other languages
Chinese (zh)
Other versions
CN106251911A (en
Inventor
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Rongchuangda Electronic Technology Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610580697.3A priority Critical patent/CN106251911B/en
Publication of CN106251911A publication Critical patent/CN106251911A/en
Application granted granted Critical
Publication of CN106251911B publication Critical patent/CN106251911B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G12INSTRUMENT DETAILS
    • G12BCONSTRUCTIONAL DETAILS OF INSTRUMENTS, OR COMPARABLE DETAILS OF OTHER APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G12B17/00Screening
    • G12B17/02Screening from electric or magnetic fields, e.g. radio waves

Landscapes

  • Manufacturing Of Electrical Connectors (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention discloses a kind of method of building intelligence system multidigit pre-control electromagnetism Leibo interference, including structure body shielding, spool shielding, device mask construction, equipotential link construction, downlead installation, it is grounded body construction.The present invention is easy for construction, and working performance is excellent.

Description

The method of building intelligence system multidigit pre-control electromagnetism Leibo interference
Technical field
The present invention relates to a kind of methods of building intelligence system multidigit pre-control electromagnetism Leibo interference.
Background technology
Intelligence system is in building field using more and more extensive, it has also become the important component of building, intelligence are The extensive use united in building field brings great convenience to people's life and work, is imitated with work to improve people's quality of life Rate has played great role.But it since intelligence system is extremely sensitive to electromagnetism Leibo, easily goes to pot, brings lives and properties Security threat must implement this building intelligence system electromagnetism Leibo interference pre-control.
Invention content
The purpose of the present invention is to provide a kind of building intelligence system multidigit pre-control electromagnetism thunders easy for construction, effect is good The method of wave interference.
Technical solution of the invention is:
A kind of method of building intelligence system multidigit pre-control electromagnetism Leibo interference, it is characterized in that:Include the following steps:
(1)Structure body shields
Reinforcing bar selects:Select resistivity≤0.97 × 10-7Ω m, the reinforcing bar that phosphorus content is 0.25-0.45%, specification select φ >=3mm reinforcing bars;
Reinforcement welding:It is connected, and welded full using welding;
Reinforcing bar is laid:Selected reinforcing bar is vertically welded on the inherent steel grid at the necessary place of buildings original, And outer lattice tie point, 2-3 internally electrical, electronic intelligence equipment tie points of each layer of setting are set by spacing 2m;
After tie point is formed, internal tie point can be connected in electrical, the electronic intelligence equipment in buildings;
After roofing and wall matrix is formed, in one layer of eyelet 1 × 1cm steel wire cover of ectosome overlying lid, cover with it is outer Lattice tie point connects.And fixed steel wire;
On roofing wall ectosome steel wire cover, a thickness 1-1.5cm electric conduction mortars are painted;
The configuration of the electric conduction mortar:Portland cement 100kg, flyash 50kg, copolymer is selected to be condensed rubber powder 5kg, propyl methocel 5kg, granular polystyrene 1m3, clipped wire 5kg, grade conducting fiber 2kg, by the above amount than into Row is configured and is stirred evenly, and forms electric conduction mortar;
(2)Spool shields
Cable selects:Select metallic shield cable;
Nonmetallic shielded cable disposition:Using the non-metal wire of thickness of pipe wall >=2mm, line is passed through into metal tube;
Cable entries are disposed:Either metal cable or metallic conduit enter at building internal orifice, should be with downlead reinforcing bar It is attached;
Concentric wiring regional processing in buildings:Setting connects up well, and reinforcing bar carries out one week every 50cm spacing in the borehole wall Connection constitutes grid;
Branch line is disposed in buildings:Hardware cloth wire casing is laid, is screwed by 100cm spacing, while hardware cloth Wire casing body should be connected with lower ground wire is drawn;
(3)Device mask is constructed
Metal shell body should be connect with downlead, and connection method uses welding;
The disposition of equipment eyelet uses the close net body of metal;The disposition of shell gap is padded using conductive fiber;
(4)Equipotential link is constructed
Busbar is constructed:In multiple metalwork concentrated areas, one connection busbar, sectional area 25-95mm are set2, this Busbar is made of metallic plate, and is fixed on metope, will be outside multiple metal components, plate, line, pipe, cable shield, equipment metal Shell is attached with conducting wire welding on busbar;
Female ring is constructed:In order to use multiple equipment or system to carry out equipotential link, indoors along wall surrounding setting one Circle connection female ring;This female ring is to be closed, and use metallic plate, the mm of sectional area >=502, it is embedding to be attached on wall, away from ground 5- Multiple components, line equipment are welded on conducting wire in female ring by 10mm, and female ring presses spacing 5m;
(5)Downlead installation
The special downlead of surface should be segmented fixation, and grounding body should be applied to shortest path, lay straight and even straight, nothing Sharp turn;The full exhaustive of weld seam being welded and fixed, bolt fixation should have washer, and the anti-corrosion of welding portion should be complete;
Downlead laying outside building:At the region that personnel can stop or pass through, using following one or more sides Method prevents contact voltage and side lightning pressure from being damaged to personnel:
1)Exposed downlead is in high 2.7m with lower part:Wear the crosslinked polyethylene pipe not less than 3mm thickness, crosslinked polyethylene pipe 100kv surge voltages should be able to be resistant to;
2)The guardrail or warning sign of prevention personnel entrance are set up, guardrail is not less than 3m with downlead horizontal distance;
Reliable electrical connection is done with arrester and earthing or grounding means in downlead both ends respectively;
Other electric wirings without attachment on downlead act the gold for connecing sudden strain of a muscle in communication tower or other towering metal frames When belonging to laying electric wiring on object, circuit uses armored cable of the direct-burried in soil;The metal sheath or metal tube of cable are answered Two-terminal-grounding, the length in placing into the soil are not less than 10m;
Downlead is installed is more than 0.1m with the wall of combustible material or wall thermal insulating interlamellar spacing;
(6)It is grounded body construction
Grounding body selects:Including Grounding Grids, horizontal grounding objects, mixing grounding body;
Grounding material selects:
Grounding Grids material selection section 50mm × 50mm × 4mm, length 2500mm angle steel;
Horizontal grounding objects select length 3000mm, 40 × 4 band steels;
Grounding material progress is zinc-plated, and weld should apply anti-decaying paint;
Grounding body is installed
Paddle type mill can be used in Grounding Grids, and grounding body is hammered underground;
Horizontal grounding objects, should first dig geosyncline, and grounding body is placed in parallel into slot by ground groove depth 1m or more after geosyncline excavates;
Grounding body is mixed, should also dig geosyncline, depth is identical as horizontal grounding objects groove depth;First vertical body and parallel body are welded Connect, then vertical body be driven underground, parallel body it is parallel with slot in;
Downlead is attached with grounding body using welding;Even Soil covering after grafting compacting;
Place mat insulating layer carries out place mat, thickness 50-80mm, width >=grounding body 2m using pitch.
The present invention is easy for construction, and working performance is excellent.
With reference to embodiment, the invention will be further described.
Specific implementation mode
Embodiment 1:
A kind of method of building intelligence system multidigit pre-control electromagnetism Leibo interference, includes the following steps:
(1)Structure body shields
Reinforcing bar selects:Select resistivity≤0.97 × 10-7Ω m, the reinforcing bar that phosphorus content is 0.25-0.45%, specification select φ >=3mm reinforcing bars;
Reinforcement welding:It is connected, and welded full using welding;
Reinforcing bar is laid:Selected reinforcing bar is vertically welded on the inherent steel grid at the necessary place of buildings original, And outer lattice tie point, 2-3 internally electrical, electronic intelligence equipment tie points of each layer of setting are set by spacing 2m;
After tie point is formed, internal tie point can be connected in electrical, the electronic intelligence equipment in buildings;
After roofing and wall matrix is formed, in one layer of eyelet 1 × 1cm steel wire cover of ectosome overlying lid, cover with it is outer Lattice tie point connects.And fixed steel wire;
On roofing wall ectosome steel wire cover, a thickness 1-1.5cm electric conduction mortars are painted;
The configuration of the electric conduction mortar:Portland cement 100kg, flyash 50kg, copolymer is selected to be condensed rubber powder 5kg, propyl methocel 5kg, granular polystyrene 1m3, clipped wire 5kg, grade conducting fiber 2kg, by the above amount than into Row is configured and is stirred evenly, and forms electric conduction mortar;
(2)Spool shields
Cable selects:Select metallic shield cable;
Nonmetallic shielded cable disposition:Using the non-metal wire of thickness of pipe wall >=2mm, line is passed through into metal tube;
Cable entries are disposed:Either metal cable or metallic conduit enter at building internal orifice, should be with downlead reinforcing bar It is attached;
Concentric wiring regional processing in buildings:Setting connects up well, and reinforcing bar carries out one week every 50cm spacing in the borehole wall Connection constitutes grid;
Branch line is disposed in buildings:Hardware cloth wire casing is laid, is screwed by 100cm spacing, while hardware cloth Wire casing body should be connected with lower ground wire is drawn;
(3)Device mask is constructed
Metal shell body should be connect with downlead, and connection method uses welding;
The disposition of equipment eyelet uses the close net body of metal;The disposition of shell gap is padded using conductive fiber;
(4)Equipotential link is constructed
Busbar is constructed:In multiple metalwork concentrated areas, one connection busbar, sectional area 25-95mm are set2, this Busbar is made of metallic plate, and is fixed on metope, will be outside multiple metal components, plate, line, pipe, cable shield, equipment metal Shell is attached with conducting wire welding on busbar;
Female ring is constructed:In order to use multiple equipment or system to carry out equipotential link, indoors along wall surrounding setting one Circle connection female ring;This female ring is to be closed, and use metallic plate, the mm of sectional area >=502, it is embedding to be attached on wall, away from ground 5- Multiple components, line equipment are welded on conducting wire in female ring by 10mm, and female ring presses spacing 5m;
(5)Downlead installation
The special downlead of surface should be segmented fixation, and grounding body should be applied to shortest path, lay straight and even straight, nothing Sharp turn;The full exhaustive of weld seam being welded and fixed, bolt fixation should have washer, and the anti-corrosion of welding portion should be complete;
Downlead laying outside building:At the region that personnel can stop or pass through, using following one or more sides Method prevents contact voltage and side lightning pressure from being damaged to personnel:
1)Exposed downlead is in high 2.7m with lower part:Wear the crosslinked polyethylene pipe not less than 3mm thickness, crosslinked polyethylene pipe 100kv surge voltages should be able to be resistant to;
2)The guardrail or warning sign of prevention personnel entrance are set up, guardrail is not less than 3m with downlead horizontal distance;
Reliable electrical connection is done with arrester and earthing or grounding means in downlead both ends respectively;
Other electric wirings without attachment on downlead act the gold for connecing sudden strain of a muscle in communication tower or other towering metal frames When belonging to laying electric wiring on object, circuit uses armored cable of the direct-burried in soil;The metal sheath or metal tube of cable are answered Two-terminal-grounding, the length in placing into the soil are not less than 10m;
Downlead is installed is more than 0.1m with the wall of combustible material or wall thermal insulating interlamellar spacing;
(6)It is grounded body construction
Grounding body selects:Including Grounding Grids, horizontal grounding objects, mixing grounding body;
Grounding material selects:
Grounding Grids material selection section 50mm × 50mm × 4mm, length 2500mm angle steel;
Horizontal grounding objects select length 3000mm, 40 × 4 band steels;
Grounding material progress is zinc-plated, and weld should apply anti-decaying paint;
Grounding body is installed
Paddle type mill can be used in Grounding Grids, and grounding body is hammered underground;
Horizontal grounding objects, should first dig geosyncline, and grounding body is placed in parallel into slot by ground groove depth 1m or more after geosyncline excavates;
Grounding body is mixed, should also dig geosyncline, depth is identical as horizontal grounding objects groove depth;First vertical body and parallel body are welded Connect, then vertical body be driven underground, parallel body it is parallel with slot in;
Downlead is attached with grounding body using welding;Even Soil covering after grafting compacting;
Place mat insulating layer carries out place mat, thickness 50-80mm, width >=grounding body 2m using pitch.
Embodiment 2:
A kind of method of building intelligence system multidigit pre-control electromagnetism Leibo interference, includes the following steps:
(1)Structure body shields
Reinforcing bar selects:Select resistivity≤0.97 × 10-7Ω m, the reinforcing bar that phosphorus content is 0.25-0.45%, specification select φ >=3mm reinforcing bars;
Reinforcement welding:It is connected, and welded full using welding;
Reinforcing bar is laid:Selected reinforcing bar is vertically welded on the inherent steel grid at the necessary place of buildings original, And outer lattice tie point, 2-3 internally electrical, electronic intelligence equipment tie points of each layer of setting are set by spacing 2m;
After tie point is formed, internal tie point can be connected in electrical, the electronic intelligence equipment in buildings;
After roofing and wall matrix is formed, in one layer of eyelet 1 × 1cm steel wire cover of ectosome overlying lid, cover with it is outer Lattice tie point connects.And fixed steel wire;
On roofing wall ectosome steel wire cover, a thickness 1-1.5cm electric conduction mortars are painted;
The configuration of the electric conduction mortar:Portland cement 100kg, flyash 50kg, copolymer is selected to be condensed rubber powder 5kg, propyl methocel 5kg, granular polystyrene 1m3, clipped wire 5kg, grade conducting fiber 2kg, by the above amount than into Row is configured and is stirred evenly, and forms electric conduction mortar;
(2)Spool shields
Cable selects:Select metallic shield cable;
Nonmetallic shielded cable disposition:Using the non-metal wire of thickness of pipe wall >=2mm, line is passed through into metal tube;
Cable entries are disposed:Either metal cable or metallic conduit enter at building internal orifice, should be with downlead reinforcing bar It is attached;
Concentric wiring regional processing in buildings:Setting connects up well, and reinforcing bar carries out one week every 50cm spacing in the borehole wall Connection constitutes grid;
Branch line is disposed in buildings:Hardware cloth wire casing is laid, is screwed by 100cm spacing, while hardware cloth Wire casing body should be connected with lower ground wire is drawn;
(3)Device mask is constructed
Metal shell body should be connect with downlead, and connection method uses welding;
The disposition of equipment eyelet uses the close net body of metal;The disposition of shell gap is padded using conductive fiber;
(4)Equipotential link is constructed
Busbar is constructed:In multiple metalwork concentrated areas, one connection busbar, sectional area 25-95mm are set2, this Busbar is made of metallic plate, and is fixed on metope, will be outside multiple metal components, plate, line, pipe, cable shield, equipment metal Shell is attached with conducting wire welding on busbar;
Female ring is constructed:In order to use multiple equipment or system to carry out equipotential link, indoors along wall surrounding setting one Circle connection female ring;This female ring is to be closed, and use metallic plate, the mm of sectional area >=502, it is embedding to be attached on wall, away from ground 5- Multiple components, line equipment are welded on conducting wire in female ring by 10mm, and female ring presses spacing 5m;
(5)Downlead installation
The special downlead of surface should be segmented fixation, and grounding body should be applied to shortest path, lay straight and even straight, nothing Sharp turn;The full exhaustive of weld seam being welded and fixed, bolt fixation should have washer, and the anti-corrosion of welding portion should be complete;
Downlead laying outside building:At the region that personnel can stop or pass through, using following one or more sides Method prevents contact voltage and side lightning pressure from being damaged to personnel:
1)Exposed downlead is in high 2.7m with lower part:Wear the crosslinked polyethylene pipe not less than 3mm thickness, crosslinked polyethylene pipe 100kv surge voltages should be able to be resistant to;
2)The guardrail or warning sign of prevention personnel entrance are set up, guardrail is not less than 3m with downlead horizontal distance;
Reliable electrical connection is done with arrester and earthing or grounding means in downlead both ends respectively;
Other electric wirings without attachment on downlead act the gold for connecing sudden strain of a muscle in communication tower or other towering metal frames When belonging to laying electric wiring on object, circuit is using the conducting wire for wearing metal tube laying;The metal sheath or metal tube of cable answer both ends Ground connection, the length in placing into the soil are not less than 10m;
Downlead is installed is more than 0.1m with the wall of combustible material or wall thermal insulating interlamellar spacing;
(6)It is grounded body construction
Grounding body selects:Including Grounding Grids, horizontal grounding objects, mixing grounding body;
Grounding material selects:
Grounding Grids material selection section 50mm × 50mm × 4mm, length 2500mm angle steel;
Horizontal grounding objects select length 3000mm, 40 × 4 band steels;
Grounding material progress is zinc-plated, and weld should apply anti-decaying paint;
Grounding body is installed
Paddle type mill can be used in Grounding Grids, and grounding body is hammered underground;
Horizontal grounding objects, should first dig geosyncline, and grounding body is placed in parallel into slot by ground groove depth 1m or more after geosyncline excavates;
Grounding body is mixed, should also dig geosyncline, depth is identical as horizontal grounding objects groove depth;First vertical body and parallel body are welded Connect, then vertical body be driven underground, parallel body it is parallel with slot in;
Downlead is attached with grounding body using welding;Even Soil covering after grafting compacting;
Place mat insulating layer carries out place mat, thickness 50-80mm, width >=grounding body 2m using pitch;
High electric resistance of soil disposition:Using one or more of following method:
1)Grounding body length of embedment is increased, grounding body passes through high electric resistance of soil layer
2)Fill friction reducer
3)Draw sewage drop resistance.

Claims (1)

1. a kind of method of building intelligence system multidigit pre-control electromagnetism Leibo interference, it is characterized in that:Include the following steps:
(1)Structure body shields
Reinforcing bar selects:Select resistivity≤0.97 × 10-7Ω m, the reinforcing bar that phosphorus content is 0.25-0.45%, specification selection φ >= 3mm reinforcing bars;
Reinforcement welding:It is connected, and welded full using welding;
Reinforcing bar is laid:Selected reinforcing bar is vertically welded on the inherent steel grid at the necessary place of buildings original, and pressed Outer lattice tie point, 2-3 internally electrical, electronic intelligence equipment tie points of each layer of setting are arranged in spacing 2m;
After tie point is formed, internal tie point can be connected in electrical, the electronic intelligence equipment in buildings;
After roofing and wall matrix is formed, in one layer of eyelet 1 × 1cm steel wire cover of ectosome overlying lid, cover connects with outer lattice Contact connects;And fixed steel wire;
On roofing wall ectosome steel wire cover, a thickness 1-1.5cm electric conduction mortars are painted;
The configuration of the electric conduction mortar:Select Portland cement 100kg, flyash 50kg, copolymer condensation rubber powder 5kg, Propyl methocel 5kg, granular polystyrene 1m3, clipped wire 5kg, grade conducting fiber 2kg are matched by the above amount ratio It sets and stirs evenly, form electric conduction mortar;
(2)Spool shields
Cable selects:Select metallic shield cable;
Nonmetallic shielded cable disposition:Using the non-metal wire of thickness of pipe wall >=2mm, line is passed through into metal tube;
Cable entries are disposed:Either metal cable or metallic conduit enter at building internal orifice, should be carried out with downlead reinforcing bar Connection;
Concentric wiring regional processing in buildings:Setting connects up well, and reinforcing bar every 50cm spacing connect within one week in the borehole wall, Constitute grid;
Branch line is disposed in buildings:Hardware cloth wire casing is laid, is screwed by 100cm spacing, while hardware cloth wire casing Body should be connected with lower ground wire is drawn;
(3)Device mask is constructed
Metal shell body should be connect with downlead, and connection method uses welding;
The disposition of equipment eyelet uses the close net body of metal;The disposition of shell gap is padded using conductive fiber;
(4)Equipotential link is constructed
Busbar is constructed:In multiple metalwork concentrated areas, one connection busbar, sectional area 25-95mm are set2, this busbar It is made of metallic plate, and is fixed on metope, by multiple metal components, plate, line, pipe, cable shield, equipment metal shell, It is attached on busbar with conducting wire welding;
Female ring is constructed:In order to use multiple equipment or system to carry out equipotential link, connect indoors along one circle of wall surrounding setting Connect female ring;This female ring is to be closed, and use metallic plate, the mm of sectional area >=502, it is embedding to be attached on wall, away from ground 5- Multiple components, line equipment are welded on conducting wire in female ring by 10mm, and female ring is by spacing 5m settings;
(5)Downlead installation
The special downlead of surface should be segmented fixation, and grounding body should be applied to shortest path, laying it is straight and even it is straight, without urgency It is curved;The full exhaustive of weld seam being welded and fixed, bolt fixation should have washer, and the anti-corrosion of welding portion should be complete;
Downlead laying outside building:At the region that personnel can stop or pass through, using following one or more methods, prevent Only contact voltage and side lightning pressure damage personnel:
1)Exposed downlead is in high 2.7m with lower part:The crosslinked polyethylene pipe not less than 3mm thickness is worn, crosslinked polyethylene pipe should be able to It is resistant to 100kv surge voltages;
2)The guardrail or warning sign of prevention personnel entrance are set up, guardrail is not less than 3m with downlead horizontal distance;
Reliable electrical connection is done with arrester and earthing or grounding means in downlead both ends respectively;
Other electric wirings without attachment on downlead act the metal object for connecing sudden strain of a muscle in communication tower or other towering metal frames When upper laying electric wiring, circuit uses armored cable of the direct-burried in soil;The metal sheath or metal tube of cable answer both ends Ground connection, the length in placing into the soil are not less than 10m;
Downlead is installed is more than 0.1m with the wall of combustible material or wall thermal insulating interlamellar spacing;
(6)It is grounded body construction
Grounding body selects:Including Grounding Grids, horizontal grounding objects, mixing grounding body;
Grounding material selects:
Grounding Grids material selection section 50mm × 50mm × 4mm, length 2500mm angle steel;
Horizontal grounding objects select the band steel of length 3000mm, width 40mm, thickness 4mm;
Grounding material progress is zinc-plated, and weld should apply anti-decaying paint;
Grounding body is installed;
Grounding Grids use paddle type mill, and Grounding Grids are hammered underground;
Horizontal grounding objects, should first dig geosyncline, and horizontal grounding objects are placed in parallel into slot by ground groove depth 1m or more after geosyncline excavates;
Grounding body is mixed, should also dig geosyncline, depth is identical as horizontal grounding objects groove depth;First by Grounding Grids and horizontal grounding Body welds, and then Grounding Grids is driven underground, horizontal grounding objects are parallel in slot;
Downlead is attached with grounding body using welding;Even Soil covering after grafting compacting;
Place mat insulating layer, using pitch progress place mat, thickness 50-80mm, width is wider 2m or more than grounding body.
CN201610580697.3A 2016-07-22 2016-07-22 The method of building intelligence system multidigit pre-control electromagnetism Leibo interference Active CN106251911B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610580697.3A CN106251911B (en) 2016-07-22 2016-07-22 The method of building intelligence system multidigit pre-control electromagnetism Leibo interference

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610580697.3A CN106251911B (en) 2016-07-22 2016-07-22 The method of building intelligence system multidigit pre-control electromagnetism Leibo interference

Publications (2)

Publication Number Publication Date
CN106251911A CN106251911A (en) 2016-12-21
CN106251911B true CN106251911B (en) 2018-07-27

Family

ID=57603325

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610580697.3A Active CN106251911B (en) 2016-07-22 2016-07-22 The method of building intelligence system multidigit pre-control electromagnetism Leibo interference

Country Status (1)

Country Link
CN (1) CN106251911B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107949263B (en) * 2017-12-19 2020-03-20 中国科学院新疆天文台 Electromagnetic shielding method for building

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144970A (en) * 1998-11-18 2000-05-26 Shimizu Corp Electromagnetic wave-shielding acoustic equipment
JP2011032718A (en) * 2009-07-31 2011-02-17 Taisei Corp Equipotentiality of important room in building and structure grounding mechanism
CN102943534A (en) * 2012-11-08 2013-02-27 中国水电顾问集团华东勘测设计研究院 Electromagnetic radiation integral shielding structure for large space
KR101314951B1 (en) * 2012-09-07 2013-10-04 한신공영 주식회사 Method of excuting building for shielding hemp intruded through spinning and conduction
CN103723975A (en) * 2013-12-31 2014-04-16 宝钢建筑***集成有限公司 Rapid-hardening steel slag mortar capable of being constructed by spraying
CN103774766A (en) * 2014-01-10 2014-05-07 葛加君 Thunder and lightning pro-control construction method for intelligent building
CN103779824A (en) * 2014-01-10 2014-05-07 葛加君 Photovoltaic solar building lightning protection facility construction method
WO2014210007A1 (en) * 2013-06-24 2014-12-31 The Board Of Regents Of The University Of Nebraska Structural concrete mix for construction for electromagnetic wave/pulse shielding
CN105332438A (en) * 2015-11-30 2016-02-17 成都市工业设备安装公司 Welding-type high-performance electromagnetic shielding chamber construction technology
CN105735591A (en) * 2016-02-29 2016-07-06 邱炎新 Building external wall with good anti-electromagnetic radiation performance

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5749178A (en) * 1996-08-06 1998-05-12 Garmong; Victor H. Shielded enclosure
JPH10331290A (en) * 1997-05-29 1998-12-15 Kumagai Gumi Co Ltd Radio-wave absorbing wall
CN101030454B (en) * 2006-03-03 2010-12-22 西南科技大学 Production and usage for electromagnetic shielding functional metaprimitive
CN104674977A (en) * 2013-11-27 2015-06-03 贵阳铝镁设计研究院有限公司 Electromagnetic shielding wall and construction method thereof

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144970A (en) * 1998-11-18 2000-05-26 Shimizu Corp Electromagnetic wave-shielding acoustic equipment
JP2011032718A (en) * 2009-07-31 2011-02-17 Taisei Corp Equipotentiality of important room in building and structure grounding mechanism
KR101314951B1 (en) * 2012-09-07 2013-10-04 한신공영 주식회사 Method of excuting building for shielding hemp intruded through spinning and conduction
CN102943534A (en) * 2012-11-08 2013-02-27 中国水电顾问集团华东勘测设计研究院 Electromagnetic radiation integral shielding structure for large space
WO2014210007A1 (en) * 2013-06-24 2014-12-31 The Board Of Regents Of The University Of Nebraska Structural concrete mix for construction for electromagnetic wave/pulse shielding
CN103723975A (en) * 2013-12-31 2014-04-16 宝钢建筑***集成有限公司 Rapid-hardening steel slag mortar capable of being constructed by spraying
CN103774766A (en) * 2014-01-10 2014-05-07 葛加君 Thunder and lightning pro-control construction method for intelligent building
CN103779824A (en) * 2014-01-10 2014-05-07 葛加君 Photovoltaic solar building lightning protection facility construction method
CN105332438A (en) * 2015-11-30 2016-02-17 成都市工业设备安装公司 Welding-type high-performance electromagnetic shielding chamber construction technology
CN105735591A (en) * 2016-02-29 2016-07-06 邱炎新 Building external wall with good anti-electromagnetic radiation performance

Also Published As

Publication number Publication date
CN106251911A (en) 2016-12-21

Similar Documents

Publication Publication Date Title
CN111244629B (en) Lightning protection grounding method of shared iron tower
CN103457044B (en) The earthing device of 10kV distribution network overhead line tower pole and laying method thereof
CN211556167U (en) Earthing device suitable for rock area
CN106251911B (en) The method of building intelligence system multidigit pre-control electromagnetism Leibo interference
CN103779824B (en) Photovoltaic solar building lightning protection facility construction method
CN211182560U (en) Novel tower lightning grounding device
KR101255118B1 (en) Sheet type ground plate
CN107134660A (en) Underground pipe gallery electrical grounding net
CN109818300A (en) Cable laying construction system
CN106785511A (en) Horizontal grounding composite resistance reduction groove of power transmission line tower and construction method
CN105429034A (en) Grounding device of transformer substation containing inlet and outlet cables and mounting method thereof
CN105305106A (en) Anti-theft grounding electrode for ground wire, and telegraph pole
US6866770B2 (en) Protective ground mat for induced potentials and method therefor
CN205790429U (en) Lightning protection grounding component
CN212908136U (en) Combined grounding system of sewage treatment plant
CN104184015A (en) Installation construction process for grounding device
CN210838137U (en) Grounding device for movable steam injection boiler of oil field
CN107337099A (en) A kind of lightning protection day net laid for power station cable crane
CN208908260U (en) The independent compound earthed system of antistatic
CN102610934B (en) Construction method for reducing ground resistance of wind driven generator
CN105977661A (en) Installation and construction technology of grounding copper cables
CN115441215A (en) Grounding grid system
CN207530308U (en) A kind of lightning protection system of side slope anchor cable monitoring system
CN216488552U (en) Earthing electrode device in arid gobi area
CN111641096B (en) Construction process of conductive polymer material grounding grid

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191205

Address after: Room c506a-18, University Business Park, No. 99, University Road, Xuzhou hi tech Industrial Development Zone, Xuzhou City, Jiangsu Province

Patentee after: Xuzhou rongchuangda Electronic Technology Co., Ltd

Address before: 226400, Development Building, east side of Taishan Road, digging Town, Rudong County, Jiangsu, Nantong 1002

Patentee before: Ge Jiajun

TR01 Transfer of patent right