CN106245925A - In communication base station signal tower transformation reinforcement means and reinforce signal tower - Google Patents
In communication base station signal tower transformation reinforcement means and reinforce signal tower Download PDFInfo
- Publication number
- CN106245925A CN106245925A CN201610603384.5A CN201610603384A CN106245925A CN 106245925 A CN106245925 A CN 106245925A CN 201610603384 A CN201610603384 A CN 201610603384A CN 106245925 A CN106245925 A CN 106245925A
- Authority
- CN
- China
- Prior art keywords
- pipe fitting
- described part
- stator
- rod member
- signal tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
- E04H12/10—Truss-like structures
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
This application discloses the transformation reinforcement means of signal tower in a kind of communication base station and reinforce signal tower, method includes: make Part I pipe fitting and Part II pipe fitting, use structure glue the described Part I pipe fitting after correction polishing and described Part II pipe fitting to be bonded in signal tower on rod member to be reinforced, and by stator, described Part I pipe fitting and described Part II pipe fitting are fixed.So mode, by selecting bonding increasing section and the method for stability, by structure glue, Part I pipe fitting and Part II pipe fitting are bonded in outside rod member to be fixed, then Part I pipe fitting and Part II pipe fitting bolt are fixed, make Part I pipe fitting and Part II pipe fitting tightly be wrapped in outside rod member to be fixed, rod member pressure experienced is transmitted by the frictional force between bonding force and the steel pipe of structure glue, make its common stress, both add the cross-sectional area of rod member, again rod member is carried out reliable reinforcement.
Description
Technical field
The application relates to signal tower renovation technique field, specifically, relating to the transformation of signal tower in a kind of communication base station
Reinforcement means and reinforcing signal tower.
Background technology
Along with the raising of scientific and technological level, communication technology produces and people's daily life breath with the modernization of industry as a kind of
The science and technology that manner of breathing closes, its development is also with rapid changepl. never-ending changes and improvements, and the most in the last few years, the development speed of communication technology is prominent especially to fly
Push ahead vigorously, it may be said that the every aspect that communication technology is lived each production technical field, various industry and people at present is all played the part of
Drill very important role.
It is known that current You Duojia operator unity of possession market, home communications field, such as China Mobile, middle League of Nations
Logical, China Telecom etc., Ge Jia operator is respectively provided with feature and the advantage of self, thus can be that society provides more multiselect
Select, more perfect service.Meanwhile, the situation that Duo Jia operator coexists also can stimulate the strong of telecommunications service by benign competition
Health and benign development.
But, Duo Jia operator coexists and also has certain defect, and distinct issues are exactly that Duo Jia operator is each
From investing construction infrastructure and hardware device respectively, and each it is used alone so that the overall resource utilization of country is low.
How the communication base station of multiple operators is incorporated on an existing base station, shares same signal tower, and signal tower
Bearing capacity meet carrying many operators communication equipment demand become problem demanding prompt solution.
Summary of the invention
In view of this, during technical problems to be solved in this application there is provided a kind of communication base station, the transformation of signal tower adds
Solid method and reinforcing signal tower, by selecting bonding increasing section and the method for stability, by structure glue by Part I pipe
Part and Part II pipe fitting are bonded in outside rod member to be fixed, then by solid with bolt to Part I pipe fitting and Part II pipe fitting
Fixed, make Part I pipe fitting and Part II pipe fitting tightly be wrapped in outside rod member to be fixed, by the bonding force of structure glue
With the frictional force between steel pipe transmits rod member pressure experienced so that it is common stress, both added the cross-sectional area of rod member, again
Rod member has been carried out reliable reinforcement.
In order to solve above-mentioned technical problem, the application has a following technical scheme:
The present invention provides the transformation reinforcement means of signal tower in a kind of communication base station, it is characterised in that including:
Steel pipe is processed into the length that rod member to be reinforced with signal tower is identical;
The most repeatedly being cut by steel pipe, the part cut open forms Part I pipe fitting and second respectively
Partial tube;
It is welded and fixed sheet respectively on the described Part I pipe fitting and described Part II pipe fitting of cutting formation, described solid
Stator positional symmetry on described Part I pipe fitting and described Part II pipe fitting, close described Part I pipe fitting and institute
When stating Part II pipe fitting, symmetrical described stator overlaps;
Perform pipe cutting successively and be welded and fixed the operation of sheet, until a described steel pipe is fully cut into separation
Two parts, and on the Part I pipe fitting separated and described Part II pipe fitting, complete the welding of stator;
The described Part I pipe fitting and described Part II pipe fitting being welded with described stator is carried out the most overall
Polishing;
Described Part I pipe fitting after the most overall polishing and described Part II pipe fitting are carried out zinc-plated place
Reason;
Described Part I pipe fitting after zinc-plated and described Part II pipe fitting are corrected and the overall polishing of second time
Process;
Use structure glue that the described Part I pipe fitting after correction polishing and described Part II pipe fitting are bonded to signal
In tower on rod member to be reinforced, and by stator, described Part I pipe fitting and described Part II pipe fitting are fixed.
Preferably, wherein:
Farther include:
Cross is used to hand over the rod member on (n+1)th layer and (n-1)th layer respectively the rod member in signal tower n-th layer with fixture
The mode of fork is fixed,
Wherein, n > 1, described fixture is that screw is connected with the fixed form of described rod member, and described fixture is metal tube
Shape structure or metallic rod shaped structure.
Preferably, wherein:
The most repeatedly being cut by steel pipe, the part cut open forms Part I pipe fitting and second respectively
Partial tube, be further:
The method using plasma segmentation cutting, the most repeatedly cuts steel pipe, the part cut open
Form Part I pipe fitting and Part II pipe fitting respectively.
Preferably, wherein:
Described Part I pipe fitting after polishing for the first time and described Part II pipe fitting are carried out zinc-plated process, further
For:
Use the parallel zinc-plated mode risen and fallen, to the described Part I pipe fitting after polishing for the first time and described Part II
Pipe fitting carries out zinc-plated process.
Preferably, wherein:
Band female through hole is distributed on described stator,
Described by stator, described Part I pipe fitting and described Part II pipe fitting are fixed, are further:
Described Part I pipe fitting and Part II pipe fitting penetrate bolt in the through hole of each stator overlapped, uses
The stator that each is overlapped by bolt is fixed so that described Part I pipe fitting and described Part II pipe fitting will rod members be reinforced
Tight.
A kind of reinforcing signal tower, it is characterised in that including: rod member to be reinforced, Part I pipe fitting and Part II pipe fitting,
It is symmetrically distributed with stator on described Part I pipe fitting and described Part II pipe fitting,
Described Part I pipe fitting and described Part II pipe fitting by structure glue be bonded in described on rod member to be reinforced, institute
State Part I pipe fitting and described Part II pipe fitting is fixed by stator;
Described Part I pipe fitting and described Part II pipe fitting are by being cut into several times along diameter of steel tube direction, often
In the part cut out, described stator is welded after secondary cutting;
Described stator is fixed on described Part I pipe fitting and described Part II pipe fitting by the way of welding, institute
Stating stator positional symmetry on described Part I pipe fitting and described Part II pipe fitting, close described Part I pipe fitting
During with described Part II pipe fitting, symmetrical described stator overlaps;
Described Part I pipe fitting and described Part II pipe fitting sequentially pass through for the first time overall polishing, zinc-plated respectively
Process, correct and the overall polishing of second time.
Preferably, wherein:
Farther include: some fixtures,
Described fixture, for adopting the rod member in signal tower n-th layer with the rod member on (n+1)th layer and (n-1)th layer respectively
It is fixed by the mode of decussation,
Wherein, n > 1, described fixture is that screw is connected with the fixed form of described rod member, and described fixture is metal tube
Shape structure or metallic rod shaped structure.
Preferably, wherein:
Described steel pipe uses the method for plasma segmentation cutting to cut.
Preferably, wherein:
The mode of zinc-plated process be parallel rise and fall zinc-plated.
Preferably, wherein:
Farther include: bolt,
Band female through hole is distributed on described stator,
Described bolt passes on described Part I pipe fitting and Part II pipe fitting in the through hole of each stator overlapped,
The stator each overlapped is fixed so that described Part I pipe fitting and described Part II pipe fitting will treat described reinforcing rod member
Tight.
Compared with prior art, in communication base station described herein signal tower transformation reinforcement means and reinforce signal
Tower, has reached following effect:
1) in communication base station provided by the present invention signal tower transformation reinforcement means and reinforce signal tower, pass through structure glue
Existing rod member and newly-increased part are combined into one, and newly-increased part uses steel pipe, first uses structure glue after being cut by steel pipe
Will after cutting the Part I pipe fitting of steel pipe and Part II pipe fitting bonding with former rod member, then by the Part I pipe fitting of steel pipe with
Part II pipe fitting is fixed by stator, so that be made up of steel pipe Part I pipe fitting and Part II pipe fitting tightly
It is wrapped in outside former rod member, transmits, by the frictional force between bonding force and the steel pipe of structure glue, the pressure that rod member is subject to,
Make its newly-increased part and common stress of original rod member, both added the cross-sectional area of rod member after reinforcing, and too increased rod member simultaneously
Stability so that signal tower has obtained strong reinforcing, it is possible to bear bigger load.
2) by the signal tower after the transformation reinforcement means of signal tower is reinforced in communication base station provided by the present invention, load-carrying
Ability is higher, it is possible to bear platform and the support arm of Duo Jia operator, so that the signal tower of multiple operators is integrated,
Share a signal tower to be possibly realized, therefore and then beneficially Economization on land usable floor area, reduce the wasting of resources.
3) in communication base station provided by the present invention signal tower transformation reinforcement means and reinforce signal tower, use structure
Glue, bonds to the transformation Part I pipe fitting of tower section, Part II pipe fitting on rod member to be reinforced, and by bolt through stator
Through hole in, by bolt, Part I pipe fitting and Part II pipe fitting are fastened, make Part I pipe fitting and Part II pipe
It is peripheral that part is tightly wrapped in pipe fitting to be reinforced, it is possible to strengthens the globality of structure, and retrofit scheme risk is little for this, it is low to invest, can be real
Shi Xingqiang.
Accompanying drawing explanation
Accompanying drawing described herein is used for providing further understanding of the present application, constitutes the part of the application, this Shen
Schematic description and description please is used for explaining the application, is not intended that the improper restriction to the application.In the accompanying drawings:
Fig. 1 is the flow chart of the transformation reinforcement means of signal tower in communication base station of the present invention;
Fig. 2 is to form Part I pipe fitting and the structural representation of Part II pipe fitting after steel pipe is cut by the present invention;
Fig. 3 is the flow chart of the transformation reinforcement means of signal tower in communication base station in the embodiment of the present invention;
Fig. 4 is the connection diagram of fixture of the present invention and signal tower rod member.
Detailed description of the invention
As employed some vocabulary in the middle of description and claim to censure specific components.Those skilled in the art should
It is understood that hardware manufacturer may call same assembly with different nouns.This specification and claims are not with name
The difference claimed is used as distinguishing the mode of assembly, but is used as the criterion distinguished with assembly difference functionally.As logical
" comprising " mentioned in the middle of piece description and claim is an open language, therefore should be construed to " comprise but do not limit
In "." substantially " referring in receivable range of error, those skilled in the art can solve described in the range of certain error
Technical problem, basically reaches described technique effect.Additionally, " coupling " word comprises any directly and indirectly electric property coupling at this
Means.Therefore, if a first device is coupled to one second device described in literary composition, then representing described first device can direct electrical coupling
It is connected to described second device, or is indirectly electrically coupled to described second device by other devices or the means that couple.Description
Subsequent descriptions is to implement the better embodiment of the application, for the purpose of right described description is the rule so that the application to be described,
It is not limited to scope of the present application.The protection domain of the application is when being as the criterion depending on the defined person of claims.
Embodiment 1
Shown in Figure 1 in herein described communication base station signal tower transformation reinforcement means a kind of embodiment, should
Transformation reinforcement means includes:
Step 101, steel pipe is processed into the length that rod member to be reinforced with signal tower is identical;
Step 102, the most repeatedly being cut by steel pipe, the part cut open forms Part I pipe respectively
Part and Part II pipe fitting;
Step 103, respectively cutting formed described Part I pipe fitting and described Part II pipe fitting on be welded and fixed
Sheet, described stator positional symmetry on described Part I pipe fitting and described Part II pipe fitting, closes described first
When being in charge of part and described Part II pipe fitting, symmetrical described stator overlaps;
Step 104, perform pipe cutting and be welded and fixed the operation of sheet, until being cut completely by a described steel pipe successively
Composition from two parts, and on the Part I pipe fitting separated and described Part II pipe fitting, complete the welding of stator;
Step 105, the described Part I pipe fitting and described Part II pipe fitting being welded with described stator is carried out
Once overall polishing;
Step 106, the described Part I pipe fitting after for the first time polishing and described Part II pipe fitting are carried out zinc-plated place
Reason;
Step 107, to the described Part I pipe fitting after zinc-plated with described Part II pipe fitting is corrected and second time
Overall polishing;
Step 108, use structure glue will correction polishing after described Part I pipe fitting and described Part II pipe fitting glue
Receive in signal tower on rod member to be reinforced, and by stator, described Part I pipe fitting and described Part II pipe fitting are carried out
Fixing.
In the application, in communication base station, the transformation reinforcement means of signal tower farther includes:
Cross is used to hand over the rod member on (n+1)th layer and (n-1)th layer respectively the rod member in signal tower n-th layer with fixture
The mode of fork is fixed, and sees Fig. 4,
Wherein, n > 1, described fixture is that screw is connected with the fixed form of described rod member, and described fixture is metal tube
Shape structure or metallic rod shaped structure.
It is situation during three pipe towers that Fig. 4 gives signal tower, and for three pipe towers, when fixing, each layer uses downwards up time
The interconnection of pin direction is reinforced, such as when reinforcing downwards, with fixture by the A pipe of n-th layer to (n-1)th layer of B pipe interconnection
Reinforce, with fixture, the B pipe of n-th layer is reinforced to (n-1)th layer of C pipe interconnection, with fixture by the C pipe of n-th layer to (n-1)th
Layer A pipe interconnection is reinforced;Each layer upwards uses counterclockwise interconnection to reinforce, such as when upwards reinforcing, with fixing
N-th layer A pipe is reinforced by part to (n+1)th layer of C pipe interconnection, is added to (n+1)th layer of B pipe interconnection by n-th layer C pipe with fixture
Gu, with fixture, n-th layer B pipe is reinforced to (n+1)th layer of A pipe interconnection.
When signal tower is four pipe tower, the mode that interconnection is reinforced uses diagonally opposed reinforces up or down.
In above-mentioned steps 102, the most repeatedly being cut by steel pipe, the part cut open forms first respectively
Partial tube and Part II pipe fitting, be further:
The method using plasma segmentation cutting, diametrically cuts steel pipe, and the part cut open is respectively
Form Part I pipe fitting and Part II pipe fitting.
Steel beam column adds man-hour, and steel pipe needs cutting, in order to reduce the deformation produced in cutting process, uses plasma segmentation
The method of cutting is cut, this kind of method cutting field width, can cut most sheet metal, and cutting speed is fast,
Efficiency is high, it is most important that cutting accuracy is higher than flame cutting.
In cutting process, now steel pipe being cut a part, be welded and fixed sheet in the part cut open, to be fixed has been welded
Bi Hou, again remains steel pipe non-cut portion and cuts, then be welded and fixed sheet in cut portion, until having been cut also by steel pipe
Having been welded by stator, this kind of mode can effectively suppress the deformation that the cutting of steel and welding cause.
After having cut, when steel beam column exists plasma cutting residue, solder flux and burr, contact not between steel beam column
Real, affect installation quality and correctional effect, but cannot remove during pickling, overall polishing need to be carried out before zinc-plated so that it is reach
To good sturdy effect.
In above-mentioned steps 106, the described Part I pipe fitting after polishing for the first time and described Part II pipe fitting are carried out
Zinc-plated process, be further:
Use the parallel zinc-plated mode risen and fallen, to the described Part I pipe fitting after polishing for the first time and described Part II
Pipe fitting carries out zinc-plated process.
Steel, when galvanizing is heated, are also susceptible to deformation, in order to control galvanizing deformation, have employed parallel herein
The zinc-plated mode fallen.After zinc-plated, correction overall polishing, remove the cadmia of residual again, it is ensured that during installation steel beam column it
Between laminating degree of compaction.
The structure glue of the present invention selects preparing neutral structure silicone adhesive, and model is 995-A.The structure glue of this kind of model has high viscous
Knot property, high resiliency model, weatherability, aging resistance, suitable environment wide etc. advantage.
Band female through hole is distributed on the stator of the present invention,
In above-mentioned steps 108, by stator, described Part I pipe fitting and described Part II pipe fitting are fixed,
It is further:
Described Part I pipe fitting and Part II pipe fitting penetrate bolt in the through hole of each stator overlapped, uses
The stator that each is overlapped by bolt is fixed so that described Part I pipe fitting and described Part II pipe fitting will rod members be reinforced
Tight.
Use structure glue, the former main material of transformation tower section is bonded together with newly adding main material, and by the way of stator
Carry out bolt connection, it is possible to strengthening the globality of structure, retrofit scheme risk is little for this, it is low to invest, exploitativeness is strong.
Embodiment 2
The present invention also provided for a kind of signal tower used after reinforcing in above-mentioned signal tower strengthening reconstruction method, this signal tower
Including: rod member 10 to be reinforced, Part I pipe fitting 20 and Part II pipe fitting 30.Part I pipe fitting 20 and Part II pipe fitting
The structure of 30 sees Fig. 2.
It is symmetrically distributed with stator 40 on described Part I pipe fitting 20 and described Part II pipe fitting 30,
Described Part I pipe fitting 20 and described Part II pipe fitting 30 by structure glue be bonded in described in rod member to be reinforced
On 10, described Part I pipe fitting 20 and described Part II pipe fitting 30 are fixed by stator 40;
Described Part I pipe fitting 20 and described Part II pipe fitting 30 are by cutting system several times along diameter of steel tube direction
Become, in the part cut out, weld described stator 40 after cutting every time;
Described stator 40 is fixed on described Part I pipe fitting 20 and described Part II pipe fitting by the way of welding
On 30, the described stator 40 positional symmetry on described Part I pipe fitting 20 and described Part II pipe fitting 30, institute of closing
When stating Part I pipe fitting 20 and described Part II pipe fitting 30, symmetrical described stator 40 overlaps;
Described Part I pipe fitting 20 and described Part II pipe fitting 30 sequentially pass through respectively for the first time overall polishing,
The overall polishing of zinc-plated process, correction and second time.
In the present invention with the use of Part I pipe fitting 20 and the length of Part II pipe fitting 30 and rod member 10 to be reinforced
Length identical, the most i.e. may utilize Part I pipe fitting 20 and Part II pipe fitting 30 by fully wrapped around for rod member 10 to be reinforced.
It addition, the internal diameter of steel pipe is more than or equal to the external diameter of rod member 10 to be reinforced in the present invention, say, that use Part I
Pipe fitting 20 and Part II pipe fitting 30 will be in time reinforcing rod member 10 and wrap up, it is possible to rod member 10 to be reinforced is completely encapsulated in first
It is in charge of part 20 and in space that Part II pipe fitting 30 is formed such that it is able to steel pipe is effectively reinforced.
Further, the signal tower after reinforcing in the present invention also includes: fixture, described fixture 50, for by signal
Rod member in tower n-th layer uses the mode of decussation to be fixed with the rod member on (n+1)th layer and (n-1)th layer respectively, sees
Fig. 4,
Wherein, n > 1, described fixture 50 is that screw is connected with the fixed form of described rod member, and described fixture 50 is gold
Belong to tubular structure or metallic rod shaped structure.Such as, above-mentioned fixing piece 50 can use the form of steel pipe or steel pole to realize.
It is situation during three pipe towers that Fig. 4 gives signal tower, and for three pipe towers, when fixing, each layer uses downwards up time
The interconnection of pin direction is reinforced, such as, when reinforcing downwards, intersected even to (n-1)th layer of B pipe by the A pipe of n-th layer with fixture 50
Connect reinforcing, with fixture 50, the B pipe of n-th layer is reinforced to (n-1)th layer of C pipe interconnection, with fixture 50, the C of n-th layer is managed
Reinforce to (n-1)th layer of A pipe interconnection;Each layer upwards uses counterclockwise interconnection to reinforce, such as when upwards reinforcing,
With fixture 50, n-th layer A pipe is reinforced to (n+1)th layer of C pipe interconnection, with fixture 50, n-th layer C pipe is managed to (n+1)th layer of B
Interconnection is reinforced, and is reinforced to (n+1)th layer of A pipe interconnection by n-th layer B pipe with fixture 50.
When signal tower is four pipe tower, the mode that interconnection is reinforced uses diagonally opposed reinforces up or down.
By this kind of mode, the rod member of adjacent for signal tower level is fixed, so that the structure of whole signal tower
More firm.
Steel pipe in the present invention uses the method for plasma segmentation cutting to cut.
Steel beam column adds man-hour, and steel pipe needs cutting, in order to reduce the deformation produced in cutting process, uses plasma segmentation
The method of cutting is cut, this kind of method cutting field width, can cut most sheet metal, and cutting speed is fast,
Efficiency is high, it is most important that cutting accuracy is higher than flame cutting.
In cutting process, existing by a steel pipe incision part, it is welded and fixed sheet 40, to be fixed 40 weldering in the part cut open
After connecing, again steel pipe is remained non-cut portion and cuts, then be welded and fixed sheet 40 in cut portion, until steel pipe is cut
Completing and welded by stator 40, this kind of mode can effectively suppress the deformation that the cutting of steel and welding cause.
After having cut, when steel beam column exists plasma cutting residue, solder flux and burr, contact not between steel beam column
Real, affect installation quality and correctional effect, but cannot remove during pickling, overall polishing need to be carried out before zinc-plated so that it is reach
To good sturdy effect.
Part I pipe fitting 20 and Part II pipe fitting 30 are plated by the parallel zinc-plated mode of rising and falling that uses of the present invention
Zinc processes, and this kind of mode is it can be avoided that deform when steel are heated in hot galvanizing process.
Band female through hole 41 is distributed on the stator 40 of the present invention, and described bolt passes described Part I pipe
On part 20 and Part II pipe fitting 30 in the through hole 41 of each stator 40 overlapped, the stator 40 each overlapped is fixed,
Make described Part I pipe fitting 20 and described Part II pipe fitting 30 will treat described reinforcing rod member tight.
The structure glue that the present invention uses is preparing neutral structure silicone adhesive, and model is 995-A.The structure glue of this kind of model has height
Caking property, high resiliency model, weatherability, aging resistance, suitable environment wide etc. advantage.
Use structure glue, the transformation Part I pipe fitting 20 of tower section, Part II pipe fitting 30 are bonded to rod member to be reinforced
On 10, and bolt is passed in the through hole 41 of stator 40, by bolt by Part I pipe fitting 20 and Part II pipe fitting 30
Fastening, makes Part I pipe fitting 20 and Part II pipe fitting 30 tightly be wrapped in pipe fitting to be reinforced peripheral, it is possible to strengthen structure
Globality, retrofit scheme risk is little for this, it is low to invest, exploitativeness is strong.
Embodiment 3
A kind of Application Example of the present invention presented below.
Base station tower mast, the platform in somewhere is reinforced and transformed, increases steel tower bearing capacity, quickly meet mobile, electric
Letter, UNICOM base station merge the demand of newly-increased antenna.
Existing tower mast is that 45m is without platform three pipe tower, original design carrying 2 cover system 6 surface antenna.For by three operators
Tower mast merges, it is contemplated that be linked with 4G construction demand (needing 3 poles), telecommunications has 4G demand (needing 3 poles), mobile LTE to need
Ask (needing 3 poles).Therefore, at this, demand is anticipated needs 9 poles, it is contemplated that transforms and reserves resource, need to increase 4 cover systems newly
With 12 surface antennas, therefore need to increase to signal tower the bearing capacity of 6 cover system 18 surface antennas.
Limited by former Deethanizer design bearing capacity, during newly-increased 4 cover system 12 surface antenna, through the inspection of the scene of a crime and checking computations, ground
And foundation bearing capacity meets requirement, but steel tower the 5th and the 6th main material of tower section is unsatisfactory for the requirement of bearing capacity, therefore need to be to this two tower section
Carry out strengthening reconstruction.
By the method for the present invention, two tower section of signal tower are reinforced, select bonding increase bar cross section long-pending and stable
Property method, by structure glue, existing rod member and newly-increased part are combined into one, and newly-increased part use steel pipe.Side
Method sees Fig. 3, specific as follows:
201, steel pipe is processed according to the length of rod member to be reinforced in signal tower, makes the length of steel pipe and bar to be reinforced
The length of part is identical.
202, plasma segmentation cutting method is used diametrically to be cut by steel pipe, by repeatedly cutting steel
Pipe is divided into two parts, respectively Part I pipe fitting and Part II pipe fitting, for the first time after cutting, welds in the part cut open
Connect stator, be further continued for cutting after being welded and fixed sheet and be welded and fixed sheet, until steel pipe to be fully cut into two parts, and two
The welding of stator is completed on partial tube.
Cutting process uses the method for plasma segmentation cutting, it is possible to reduce the deformation that steel pipe causes in cutting process.
And use the method repeatedly cut and be welded and fixed sheet, the deformation of cutting and welding process steel pipe can be reduced equally.
203, the Part I pipe fitting and Part II pipe fitting being welded with stator is carried out the most overall polishing.
After having cut, when steel beam column exists plasma cutting residue, solder flux and burr, contact not between steel beam column
Real, affect installation quality and correctional effect, but cannot remove during pickling, overall polishing need to be carried out before zinc-plated so that it is with
Rod member to be reinforced reaches good sturdy effect.
204, the Part I pipe fitting after the most overall polishing and Part II pipe fitting are carried out zinc-plated process, for
Steel pipe temperature distortion in control galvanizing process, uses the parallel zinc-plated mode risen and fallen herein.
205, to the Part I pipe fitting after zinc-plated with Part II pipe fitting is corrected and the overall polishing of second time,
To remove the cadmia of residual, it is ensured that laminating degree of compaction between steel beam column during installation.
206, structure glue is used the Part I pipe fitting after correction polishing and Part II pipe fitting to be bonded in signal tower
On rod member to be reinforced, and by stator, Part I pipe fitting and Part II pipe fitting are fixed.
Structure glue herein selects preparing neutral structure silicone adhesive, and model is 995-A.This kind of structure glue has high-adhesion, height
The advantages such as elasticity, weatherability, antiageing effect are good.
Tapped through hole is distributed on stator, by stator, Part I pipe fitting and Part II pipe fitting is entered
When row is fixing, Part I pipe fitting and Part II pipe fitting penetrates bolt in the through hole of each stator overlapped, uses spiral shell
The stator that each is overlapped by bolt is fixed, so that rod member to be reinforced closely is wrapped by Part I pipe fitting and Part II pipe fitting
Wrap up in.
By said method, complete the strengthening reconstruction to signal tower the 5th and the 6th tower section, meet newly-increased 4 cover systems and 12
The bearing capacity demand of surface antenna.And, use structure glue, the former main material of transformation tower section is bonded together with newly adding main material, and
Carrying out bolt connection by the way of stator, enhance the globality of structure, this kind of retrofit scheme risk is little, it is low to invest, can
Implementation is strong.
The said method of the present invention is applicable to all three Guan Ta, the four main materials of pipe tower are unsatisfactory for the adding of steel tower of requirement for bearing capacity
Gu transformation.
By various embodiments above, the application exists and provides the benefit that:
1) in communication base station provided by the present invention signal tower transformation reinforcement means and reinforce signal tower, pass through structure glue
Existing rod member and newly-increased part are combined into one, and newly-increased part uses steel pipe, first uses structure glue after being cut by steel pipe
Will after cutting the Part I pipe fitting of steel pipe and Part II pipe fitting bonding with former rod member, then by the Part I pipe fitting of steel pipe with
Part II pipe fitting is fixed by stator, so that be made up of steel pipe Part I pipe fitting and Part II pipe fitting tightly
It is wrapped in outside former rod member, transmits, by the frictional force between bonding force and the steel pipe of structure glue, the pressure that rod member is subject to,
Make its newly-increased part and common stress of original rod member, both added the cross-sectional area of rod member after reinforcing, and too increased rod member simultaneously
Stability so that signal tower has obtained strong reinforcing, it is possible to bear bigger load.
2) by the signal tower after the transformation reinforcement means of signal tower is reinforced in communication base station provided by the present invention, load-carrying
Ability is higher, it is possible to bear platform and the support arm of Duo Jia operator, so that the signal tower of multiple operators is integrated,
Share a signal tower to be possibly realized, therefore and then beneficially Economization on land usable floor area, reduce the wasting of resources.
3) in communication base station provided by the present invention signal tower transformation reinforcement means and reinforce signal tower, use structure
Glue, bonds to the transformation Part I pipe fitting of tower section, Part II pipe fitting on rod member to be reinforced, and by bolt through stator
Through hole in, by bolt, Part I pipe fitting and Part II pipe fitting are fastened, make Part I pipe fitting and Part II pipe
It is peripheral that part is tightly wrapped in pipe fitting to be reinforced, it is possible to strengthens the globality of structure, and retrofit scheme risk is little for this, it is low to invest, can be real
Shi Xingqiang.
Those skilled in the art are it should be appreciated that embodiments herein can be provided as method, device or computer program
Product.Therefore, the reality in terms of the application can use complete hardware embodiment, complete software implementation or combine software and hardware
Execute the form of example.And, the application can use at one or more computers wherein including computer usable program code
The upper computer program product implemented of usable storage medium (including but not limited to disk memory, CD-ROM, optical memory etc.)
The form of product.
Described above illustrate and describes some preferred embodiments of the application, but as previously mentioned, it should be understood that the application
Be not limited to form disclosed herein, be not to be taken as the eliminating to other embodiments, and can be used for other combinations various,
Amendment and environment, and can be in invention contemplated scope described herein, by above-mentioned teaching or the technology of association area or knowledge
It is modified.And the change that those skilled in the art are carried out and change are without departing from spirit and scope, the most all should be in this Shen
Please be in the protection domain of claims.
Claims (10)
1. the transformation reinforcement means of signal tower in a communication base station, it is characterised in that including:
Steel pipe is processed into the length that rod member to be reinforced with signal tower is identical;
The most repeatedly being cut by steel pipe, the part cut open forms Part I pipe fitting and Part II respectively
Pipe fitting;
It is welded and fixed sheet, described stator respectively on the described Part I pipe fitting and described Part II pipe fitting of cutting formation
Positional symmetry on described Part I pipe fitting and described Part II pipe fitting, close described Part I pipe fitting and described
During two partial tube, symmetrical described stator overlaps;
Perform pipe cutting successively and be welded and fixed the operation of sheet, until a described steel pipe to be fully cut into two of separation
Point, and on the Part I pipe fitting separated and described Part II pipe fitting, complete the welding of stator;
The described Part I pipe fitting and described Part II pipe fitting being welded with described stator is carried out the most overall polishing
Process;
Described Part I pipe fitting after the most overall polishing and described Part II pipe fitting are carried out zinc-plated process;
Described Part I pipe fitting after zinc-plated and described Part II pipe fitting are corrected and the overall polishing of second time;
Structure glue is used the described Part I pipe fitting after correction polishing and described Part II pipe fitting to be bonded in signal tower
On rod member to be reinforced, and by stator, described Part I pipe fitting and described Part II pipe fitting are fixed.
The transformation reinforcement means of signal tower in communication base station the most according to claim 1, it is characterised in that farther include:
With fixture, the rod member in signal tower n-th layer is used decussation with the rod member on (n+1)th layer and (n-1)th layer respectively
Mode is fixed,
Wherein, n > 1, described fixture is that screw is connected with the fixed form of described rod member, and described fixture is tubular metal knot
Structure or metallic rod shaped structure.
The transformation reinforcement means of signal tower in communication base station the most according to claim 1, it is characterised in that
The most repeatedly being cut by steel pipe, the part cut open forms Part I pipe fitting and Part II respectively
Pipe fitting, be further:
The method using plasma segmentation cutting, the most repeatedly cuts steel pipe, and the part cut open is respectively
Form Part I pipe fitting and Part II pipe fitting.
The transformation reinforcement means of signal tower in communication base station the most according to claim 1, it is characterised in that
Described Part I pipe fitting after polishing for the first time and described Part II pipe fitting are carried out zinc-plated process, are further:
Use the parallel zinc-plated mode risen and fallen, to the described Part I pipe fitting after polishing for the first time and described Part II pipe fitting
Carry out zinc-plated process.
The transformation reinforcement means of signal tower in communication base station the most according to claim 1, it is characterised in that
Band female through hole is distributed on described stator,
Described by stator, described Part I pipe fitting and described Part II pipe fitting are fixed, are further:
Described Part I pipe fitting and Part II pipe fitting penetrate bolt in the through hole of each stator overlapped, uses bolt
The stator each overlapped is fixed so that described Part I pipe fitting and described Part II pipe fitting are by tight for rod member to be reinforced
Parcel.
6. reinforce signal tower for one kind, it is characterised in that including: rod member to be reinforced, Part I pipe fitting and Part II pipe fitting,
It is symmetrically distributed with stator on described Part I pipe fitting and described Part II pipe fitting,
Described Part I pipe fitting and described Part II pipe fitting by structure glue be bonded in described on rod member to be reinforced, described
A part of pipe fitting and described Part II pipe fitting are fixed by stator;
Described Part I pipe fitting and described Part II pipe fitting, by being cut into several times along diameter of steel tube direction, are cut every time
In the part cut out, described stator is welded after cutting;
Described stator is fixed on described Part I pipe fitting and described Part II pipe fitting by the way of welding, described solid
Stator positional symmetry on described Part I pipe fitting and described Part II pipe fitting, close described Part I pipe fitting and institute
When stating Part II pipe fitting, symmetrical described stator overlaps;
Described Part I pipe fitting and described Part II pipe fitting sequentially pass through the most overall polishing, zinc-plated place respectively
The overall polishing of reason, correction and second time.
Reinforce signal tower the most according to claim 6, it is characterised in that farther include: some fixtures,
Described fixture, for using ten with the rod member on (n+1)th layer and (n-1)th layer respectively by the rod member in signal tower n-th layer
The mode that word intersects is fixed,
Wherein, n > 1, described fixture is that screw is connected with the fixed form of described rod member, and described fixture is tubular metal knot
Structure or metallic rod shaped structure.
Reinforce signal tower the most according to claim 6, it is characterised in that
Described steel pipe uses the method for plasma segmentation cutting to cut.
Reinforce signal tower the most according to claim 6, it is characterised in that
The mode of zinc-plated process be parallel rise and fall zinc-plated.
Reinforce signal tower the most according to claim 6, it is characterised in that farther include: bolt,
Band female through hole is distributed on described stator,
Described bolt passes on described Part I pipe fitting and Part II pipe fitting in the through hole of each stator overlapped, will be each
The stator of individual coincidence is fixed so that described Part I pipe fitting and described Part II pipe fitting will treat that described reinforcing rod member is tight
Parcel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610603384.5A CN106245925A (en) | 2016-07-27 | 2016-07-27 | In communication base station signal tower transformation reinforcement means and reinforce signal tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610603384.5A CN106245925A (en) | 2016-07-27 | 2016-07-27 | In communication base station signal tower transformation reinforcement means and reinforce signal tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106245925A true CN106245925A (en) | 2016-12-21 |
Family
ID=57604949
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610603384.5A Pending CN106245925A (en) | 2016-07-27 | 2016-07-27 | In communication base station signal tower transformation reinforcement means and reinforce signal tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106245925A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112065146A (en) * | 2020-09-07 | 2020-12-11 | 广州极诣科技有限公司 | Auxiliary device and method for building and supporting communication base station |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3411673A1 (en) * | 1984-03-29 | 1985-10-03 | Richard Dipl.-Ing. 8332 Massing Laumer | Process and steel-reinforcing element for the subsequent reinforcement of concrete structures |
CN1570333A (en) * | 2004-04-26 | 2005-01-26 | 武汉大学 | Process for reinforcing electricity transmission and transformation steel pipe frames |
CN103276937A (en) * | 2013-05-17 | 2013-09-04 | 国家电网公司 | Temporary electric pole reinforcing device |
CN205822897U (en) * | 2016-07-27 | 2016-12-21 | 中塔新兴通讯技术集团有限公司 | Reinforce signal tower |
-
2016
- 2016-07-27 CN CN201610603384.5A patent/CN106245925A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3411673A1 (en) * | 1984-03-29 | 1985-10-03 | Richard Dipl.-Ing. 8332 Massing Laumer | Process and steel-reinforcing element for the subsequent reinforcement of concrete structures |
CN1570333A (en) * | 2004-04-26 | 2005-01-26 | 武汉大学 | Process for reinforcing electricity transmission and transformation steel pipe frames |
CN103276937A (en) * | 2013-05-17 | 2013-09-04 | 国家电网公司 | Temporary electric pole reinforcing device |
CN205822897U (en) * | 2016-07-27 | 2016-12-21 | 中塔新兴通讯技术集团有限公司 | Reinforce signal tower |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112065146A (en) * | 2020-09-07 | 2020-12-11 | 广州极诣科技有限公司 | Auxiliary device and method for building and supporting communication base station |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205822897U (en) | Reinforce signal tower | |
CN106245925A (en) | In communication base station signal tower transformation reinforcement means and reinforce signal tower | |
US20140345128A1 (en) | Method for electrically connecting a cable to a contact element | |
CN102059519A (en) | Method for preparing back plate and back plate structure | |
CN103035376A (en) | Sub-frame iron core structure for disassembling and transporting transformer and transportation method | |
US11437177B2 (en) | Coil component and manufacturing method for same | |
CN209488105U (en) | A kind of cable branch housing unit | |
CN208225924U (en) | Directly draw the power battery top cover of formula downhand welding structure based on tab | |
CN110970390A (en) | Fine-spacing copper pillar wafer-level packaging structure and reliability optimization method | |
US20140217578A1 (en) | Semiconductor package process and structure thereof | |
CN106255245A (en) | Add heat pipe and manufacture method thereof | |
JP2009217993A (en) | Manufacturing method of high-temperature superconductive current lead | |
CN103346418A (en) | Welding connection piece and circuit board and antenna with welding connection piece | |
US9877399B2 (en) | Lead solder joint structure and manufacturing method thereof | |
MX2023007205A (en) | Terminal assembly and method for fabrication thereof. | |
CN104051706B (en) | Anode tab material of lithium ion battery and preparation process thereof | |
CN104425050A (en) | Hard-state tin-coated copper-clad steel wire | |
CN207503789U (en) | For the low-voltage coil and its dry-type transformer of dry-type transformer | |
CN202210777U (en) | Low-frequency crystal oscillator | |
CN105469933B (en) | A kind of pulse transformer and its manufacture method | |
CN106283118B (en) | The production method of anode rod and anode rod | |
JP6177394B1 (en) | Conductor manufacturing method and conductor | |
JP6116740B1 (en) | Flat braided wire and manufacturing method thereof | |
CN205857885U (en) | Novel single tube tower base | |
CN112074920B (en) | Intermediate yoke for power transformer and power transformer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161221 |
|
RJ01 | Rejection of invention patent application after publication |