CN106245752A - Prefabricated assembled tube structure public building and its method of construction - Google Patents

Prefabricated assembled tube structure public building and its method of construction Download PDF

Info

Publication number
CN106245752A
CN106245752A CN201610865598.XA CN201610865598A CN106245752A CN 106245752 A CN106245752 A CN 106245752A CN 201610865598 A CN201610865598 A CN 201610865598A CN 106245752 A CN106245752 A CN 106245752A
Authority
CN
China
Prior art keywords
plate
prefabricated
muscle
wall body
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610865598.XA
Other languages
Chinese (zh)
Inventor
王其明
符如旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Aerospace Construction Group Co Ltd
Original Assignee
China Aerospace Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Aerospace Construction Group Co Ltd filed Critical China Aerospace Construction Group Co Ltd
Priority to CN201610865598.XA priority Critical patent/CN106245752A/en
Publication of CN106245752A publication Critical patent/CN106245752A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/562Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with fillings between the load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/64Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/04Load-carrying floor structures formed substantially of prefabricated units with beams or slabs of concrete or other stone-like material, e.g. asbestos cement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2103/00Material constitution of slabs, sheets or the like
    • E04B2103/02Material constitution of slabs, sheets or the like of ceramics, concrete or other stone-like material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention provides a kind of prefabricated assembled tube structure public building and its method of construction, belong to the realm of building construction, including building unit, each building unit includes the precast shear wall body of wall in grid type framework and includes Prefabricated hollow sandwich plate, Prefabricated hollow sandwich plate includes top plate and many laced beams, adjacent laced beam parallel interval is arranged, and many laced beams and top plate formed by integrally casting molding, Prefabricated hollow sandwich plate is positioned at the top of precast shear wall body of wall, many laced beams are overlapped on precast shear wall body of wall, many laced beams are connected by casting concrete is fixing with precast shear wall body of wall.This method of construction is used for building public building.The crucial component of this building all uses standardized designs, factorial praluction mode, while improving prefabricated components quality, also realizes the normalization of crucial component, unitizes and diversified, with the diversified demand in satisfied different house type houses.

Description

Prefabricated assembled tube structure public building and its method of construction
Technical field
The present invention relates to the realm of building construction, in particular to a kind of prefabricated assembled tube structure public building with And method of construction.
Background technology
The Chinese government puts into effect and has formulated a series of policies and measures and helps implementation building industrialization in recent years, to realize " four Save an environmental protection " requirement.At present, building trade faces labor shortage, the zooming problem of cost of labor, passes the most at present System site operation mode also faces environmental pollution, water resource waste, the building waste amount problem become increasingly conspicuous such as big, job site Construction quality or unsatisfactory, Construction Quality common fault is more.Consider from angle of sustainable development, to traditional building Industry proposes industrial transformation and upgrading requirement.On February 6th, 2016, State Council of the Central Committee of the Communist Party of China prints and distributes " about strengthening city rule further Draw some suggestions of implementation management work " explicitly point out, Development of Novel mode of construction, widely popularize assembled architecture, 10 years Inside make assembled architecture account for new building ratio and reach 30%.Therefore, reflection building industry development building industrialization again by Industry is paid close attention to, and under country's support with local government, China's fabricated construction system welcomes development opportunity again.
Inventor finds under study for action, and traditional Residential structure at least has a disadvantage in that
Building the conventional industries as China, be chronically at the production phase of extensive style, the energy and raw materials consumption are excessive, Industrialization degree is the highest, labor productivity and with low content of technology, and version is single, and construction quality is poor with function, public builds Seismic seeurity and the comfortableness of building structure are in urgent need to be improved, and therefore the appearance of prefabricated assembled concrete structure can effectively solve State problem.
Therefore, the mode of construction of tradition public building need to be improved, propose a kind of simple in construction, reasonable in design, execute Work convenience and the preferable novel prefabricated assembled tube structure public building of using effect.
Summary of the invention
It is an object of the invention to provide a kind of prefabricated assembled tube structure public building to improve living of prior art Residence construction of energy is excessive with raw materials consumption, industrialization degree is different, labor productivity and problem with low content of technology.
The present invention also aims to provide the method for construction of a kind of prefabricated assembled tube structure public building, to improve The dwelling construction energy of prior art is excessive with raw materials consumption, industrialization degree is different, labor productivity and with low content of technology Problem.
Embodiments of the invention are achieved in that
Based on above-mentioned first purpose, the invention provides a kind of prefabricated assembled tube structure public building, including building Unit, each described building unit includes the precast shear wall body of wall in grid type framework and includes Prefabricated hollow sandwich plate, Wherein:
Described Prefabricated hollow sandwich plate includes that top plate and many laced beams, adjacent described laced beam parallel interval set Putting, and many described laced beams and described top plate formed by integrally casting molding, described Prefabricated hollow sandwich plate is positioned at described prefabricated cut The top of power wall body of wall, many described laced beams are overlapped on described precast shear wall body of wall, and many described laced beams are with described Precast shear wall body of wall connects by casting concrete is fixing.
In preferred embodiment of the present invention, described laced beam includes that upper strata compression zone, middle level connecting portion and lower floor are subject to Drawing portion, described middle level connecting portion, between described upper strata compression zone and tension portion of described lower floor, is subject to described upper strata respectively The fixing connection of splenium and tension portion of described lower floor, described upper strata compression zone is fixing with described top plate to be connected.
In preferred embodiment of the present invention, described upper strata compression zone includes that multiple horizontal compression plate and multiple longitudinal direction are subject to Pressing plate, described horizontal compression plate and the described angled setting of longitudinal compression plate, each described horizontal compression plate is subject to described longitudinal direction Pressing plate is fixing with infall to be connected;One plate face of described horizontal compression plate and a plate face of described longitudinal compression plate are fitted in described On the plate face of top plate, another plate face of described horizontal compression plate is generally aligned in the same plane with another plate face of described longitudinal compression plate In.
In preferred embodiment of the present invention, described lower floor compression zone includes multiple being laterally subject to by arm-tie and multiple longitudinal direction Arm-tie, described laterally by arm-tie and the described angled setting of longitudinal tensile plate, each described laterally it is subject to described longitudinal direction by arm-tie Arm-tie is fixing with infall to be connected;Described upper strata compression zone is oppositely arranged with tension portion of described lower floor.
In preferred embodiment of the present invention, described middle level connecting portion includes that multiple middle level connects post, described upper strata pressurized Multiple crossover locations in portion are arranged with multiple crossover location one_to_one corresponding in tension portion of described lower floor, the one of described upper strata compression zone Individual crossover location constitutes an installation portion with a crossover location in tension portion of described lower floor, and each described installation portion is arranged Having described middle level to connect post, a crossover location of one end and described upper strata compression zone that described middle level connects post is fixed and is connected, Its other end is fixing with a crossover location in tension portion of described lower floor to be connected, and described middle level connects post and is perpendicular to described upper strata Plate.
In preferred embodiment of the present invention, along its length two sides of described horizontal compression plate set respectively Being equipped with the first fastening reinforcing bar, described first fastening reinforcing bar protrudes corresponding side along the length direction being parallel to described horizontal compression plate Face;The second fastening reinforcing bar it is respectively arranged with on along its length two sides of described longitudinal compression plate, described second tight Gu reinforcing bar protrudes corresponding side along the length direction being parallel to described longitudinal compression plate.
In preferred embodiment of the present invention, described first fastening reinforcing bar includes fixing muscle and absorption muscle, described fixing Muscle includes two fixed parts and the connecting portion between two described fixed parts being oppositely arranged, two described fixed parts One end is fixing with described connecting portion to be connected, and the other end of two described fixed parts is fixing with described horizontal compression plate to be connected, described Absorption muscle is arranged on described connecting portion.
In preferred embodiment of the present invention, described absorption muscle includes main muscle, the first ring-type auxiliary muscle and the second ring-type auxiliary muscle, Main ribs is perpendicular to described top plate and arranges, and one end of main ribs and described connecting portion are fixed and be connected, described first ring-type Auxiliary muscle is set in outside described second ring-type auxiliary muscle, and described first ring-type auxiliary muscle is solid in infall with described second ring-type auxiliary muscle Fixed connection, described first ring-type auxiliary muscle or described second ring-type auxiliary muscle are fixing with main ribs to be connected.
In preferred embodiment of the present invention, described laterally by the two ends along its length of arm-tie, pre-buried spiral shell is installed Bolt, described pre-embedded bolt is perpendicular to described laterally be arranged by the plate face of arm-tie, and described pre-embedded bolt protrudes described horizontal tension The lower face of plate.
Based on above-mentioned second purpose, present invention also offers the construction side of a kind of prefabricated assembled tube structure public building Method, the method comprises the steps:
Step S100, making shear wall body;First assembling steel form, make framework of steel reinforcement, framework of steel reinforcement enters mould, then Form wallboard, last standard curing 1 day~2 days with concreting, remove steel form, form prefabricated mesh formula framework-shearing Wall body of wall;
Step S200, making open-spandrel sandwich board, first assemble steel form, assembling reinforcement mesh sheet;Then with concreting, Last standard curing 1 day~2 days, removes steel form, forms the Prefabricated hollow sandwich plate with top plate and laced beam;
Step S300, construction basis, pouring reinforcement concrete foundation ring girder, reserved constructional column reinforcing bar on described foundation ring girder Head and water proof structure;
Step S400, prefabricated components are installed, and the lifting of prefabricated mesh formula frame-shear wall body of wall is shelved on described basis circle In the reserving hole of the predeterminated position of beam described constructional column steel bar end is inserted described shear wall body bottom, then carry out Grouting anchoring;Reserved connection reinforcing bar between adjacent described shear wall body is carried out nesting, pours formation concrete and connect Post;
Step S500, the installation of Prefabricated hollow sandwich plate, adjust Prefabricated hollow sandwich plate and position and in place, described prefabricated sky The level connection joint muscle of abdomen sandwich plate is nested with the reserved steel bar of described prefabricated mesh formula Frame-Shear Wall body of wall, and adjacent is described Reserved steel bar between Prefabricated hollow sandwich plate carries out nesting, reserves in the bottom of described Prefabricated hollow sandwich plate and installs at bolt Steel form, carries out concreting, forms tie-beam between adjacent described Prefabricated hollow sandwich plate;
S500 described in step S600, repeating said steps S100-the most successively constructs.
The embodiment of the present invention provides the benefit that:
In sum, the prefabricated assembled tube structure public building that the embodiment of the present invention provides, it is simple and reasonable, Being easy to manufacture processing, meanwhile, this prefabricated assembled tube structure public building has the further advantage that
1, the crucial component such as shear wall body and Prefabricated hollow sandwich plate all uses standardized designs, factorial praluction side Formula, while improving prefabricated components quality, also realizes the normalization of crucial component, unitizes and diversified, with satisfied difference The diversified demand in house type house;
2, compared with traditional tube structure public building construction, industrialized production, specialized dispensing and assemblingization are used The build model of construction, job site relies primarily on specialized machinery, and labour force uses few, and automaticity is high, speed of application Hurry up, be greatly improved efficiency of construction, reduction of erection time, ensured stability and the accuracy of tube structure public building quality, meet The requirement of building total quality performance;
3, compared with traditional public building construction, the shear wall body of grid type framework is used, it is adaptable to high-rise cylinder The assembled construction of structure public building, the use of open-spandrel sandwich board, save material and improve the sound-insulating and heat-insulating effect of building.
Accompanying drawing explanation
In order to be illustrated more clearly that the technical scheme of the embodiment of the present invention, below by embodiment required use attached Figure is briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, and it is right to be therefore not construed as The restriction of scope, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to according to this A little accompanying drawings obtain other relevant accompanying drawings.
Fig. 1 is the structure chart of the shear wall body of the prefabricated assembled tube structure public building of the embodiment of the present invention;
Fig. 2 is the structure chart of the open-spandrel sandwich board of the prefabricated assembled tube structure public building of the embodiment of the present invention;
Fig. 3 is the structure chart of the laced beam of the open-spandrel sandwich board of the embodiment of the present invention;
Fig. 4 is the structure chart of the first fastening reinforcing bar of the embodiment of the present invention.
In figure:
Open-spandrel sandwich board 110, upper strata compression zone 111, horizontal compression plate 1111, longitudinal compression plate 1112, middle level connecting portion 112, middle level connects post 1121, tension portion of lower floor 113, and laterally by arm-tie 1131, longitudinal tensile plate 1132, first fastens reinforcing bar 114, fixing muscle 1141, adsorbs muscle 1142, main muscle 1143, the first ring-type auxiliary muscle 1144, the second ring-type auxiliary muscle 1145, the second fastening Reinforcing bar 115, pre-embedded bolt 116, top plate 117,
Shear wall body 120, outer peripheral face 121, fastening reinforcement assembly 122, fastening rib 1221, crossbeam 125, longeron 126, Wallboard 127, outside framework 128, engagement groove 129.
Detailed description of the invention
For making the purpose of the embodiment of the present invention, technical scheme and advantage clearer, below in conjunction with the embodiment of the present invention In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is The a part of embodiment of the present invention rather than whole embodiments.Generally implement with the present invention illustrated described in accompanying drawing herein The assembly of example can be arranged with various different configurations and design.
Therefore, detailed description to the embodiments of the invention provided in the accompanying drawings is not intended to limit claimed below The scope of the present invention, but be merely representative of the selected embodiment of the present invention.Based on the embodiment in the present invention, this area is common The every other embodiment that technical staff is obtained under not making creative work premise, broadly falls into the model of present invention protection Enclose.
It should also be noted that similar label and letter represent similar terms, therefore, the most a certain Xiang Yi in following accompanying drawing Individual accompanying drawing is defined, then need not it be defined further and explains in accompanying drawing subsequently.
In describing the invention, it should be noted that term " on ", D score, " interior ", the orientation of the instruction such as " outward " or position Relation of putting is for based on orientation shown in the drawings or position relationship, or the orientation usually put when this invention product uses or position Put relation, be for only for ease of the description present invention and simplify description rather than instruction or imply that the device of indication or element are necessary There is specific orientation, with specific azimuth configuration and operation, be therefore not considered as limiting the invention.Additionally, term " first ", " second " etc. are only used for distinguishing and describe, and it is not intended that indicate or hint relative importance.
In describing the invention, in addition it is also necessary to explanation, unless otherwise clearly defined and limited, term " arrange ", " install ", " being connected ", " connection " should be interpreted broadly, and connect for example, it may be fixing, it is also possible to be to removably connect, or one Body ground connects;Can be to be mechanically connected, it is also possible to be electrical connection;Can be to be joined directly together, it is also possible to indirect by intermediary It is connected, can be the connection of two element internals.For the ordinary skill in the art, can be with in concrete condition understanding State term concrete meaning in the present invention.
It should be noted that in the case of not conflicting, the embodiment in the present invention and the feature in embodiment can phases Combination mutually.
Prefabricated assembled tube structure public building embodiment
Refer to Fig. 1, present embodiments provide a kind of prefabricated assembled tube structure public building, including building unit, One building unit is a Rotating fields, and multiple building units lap splice the most successively forms tier building.Many being formed During the structure of floor, the most upwards can splice based on a building unit, it is also possible to multiple building units as base Plinth, the most upwards splices, and the connecting method of multiple building units is varied, carries out respective design according to the planning of community, executes Man-hour is flexible and changeable.
Referring to Fig. 2 and Fig. 3, each building unit includes the precast shear wall body of wall 120 in grid type framework and bag Including Prefabricated hollow sandwich plate 110, Prefabricated hollow sandwich plate 110 is provided with polylith, and the polylith being positioned at same layer building unit is prefabricated Open-spandrel sandwich board 110 is arranged on the top of precast shear wall body of wall 120, and precast shear wall body of wall 120 is for surrounding outside building Body of wall.
Referring to Fig. 1, each shear wall body 120 is made by casting concrete on reinforced frame, adds man-hour, directly exists In factory good according to the first processing and manufacturing of design, directly transport during use and carry out installing to scene.Each shear wall body 120 in Frame structure, frame structure can be saved material, be reduced cost.Frame structure includes outside framework 128 and many crossbeam 125 Hes Many longerons 126, outside framework 128 is rectangle frame, it is simple to processing and manufacturing, easy for installation, many crossbeam 125 and Duo Gen longerons 126 Crisscross setting, many crossbeam 125 and Duo Gen longerons 126 define multiple rectangular-shaped through hole, many crossbeams 125 and Duo Gen Longeron 126 is positioned at the rectangular area that outside framework 128 surrounds, and fixing with outside framework 128 is respectively connected, the good longeron of crossbeam 125 The on-demand setting of quantity of 126, the distance between crossbeam 125 and longeron 126 can be altered as desired, it is possible to reserves the position of door and window Put, it is simple to the installation of follow-up door and window.Frame structure also includes wallboard 127, and wallboard 127 is fixing with outside framework 128 to be connected, wallboard The height of 127 is identical with the height of longeron 126, and wallboard 127 adds the weight capacity of entirety, and structure is more solid and reliable.Frame Shelf structure has four outer peripheral faces 121, and each outer peripheral face 121 is rectangular surfaces, two the first outer peripheral faces being respectively oppositely arranged 121 and two the second outer peripheral faces 121 being oppositely arranged, the first outer peripheral face 121 and the second outer peripheral face 121 are respectively arranged with combination Groove 129, the length direction of the length direction of engagement groove 129 and corresponding outer peripheral face 121 in the same direction, the first adjacent outer peripheral face 121 Being connected with the end of the engagement groove 129 on the second outer peripheral face 121, when carrying out concreting, engagement groove 129 can be with coagulation Soil preferably contact, it is more firm overall that the cast-in-place concrete built and shear wall body 120 form a structure, and stress is more Good.
Further, installing fastening reinforcement assembly 122 on each outer peripheral face 121 of shear wall body 120, fastening adds Strong muscle assembly 122 includes multiple fastening rib 1221 be arrangeding in parallel, and one end of each fastening rib 1221 is positioned at shear wall body 120 In, its other end stretches out the corresponding outer peripheral face 121 of shear wall body 120, is being fixed adjacent shear wall body 120 During connection, casting concrete between adjacent shear wall body 120, fastening reinforcement assembly 122 is needed to be embedded in concrete In, adding the structural strength of entirety, concrete is more tight with the combination of shear wall body 120, and structure is more solid and reliable, By fastening reinforcement assembly 122 and the common effect of engagement groove 129, after-pouring concrete can with shear wall body 120 more Adding combination closely, improve the structural strength of entirety, shock resistance is strong, safe and reliable.
Concrete, fastening rib 1221 uses a reinforcing bar to be bent into along folding line, and folding line is perpendicular to the length of reinforcing bar Degree direction, folding line is provided with two, and two folding lines be arranged in parallel, and after bending, fastening rib 1221 defines U-shape, U-shaped The opening of fastening rib 1221 is inserted in shear wall body 120, fixes with shear wall body 120 and is connected, the fastening rib of U-shaped The blind end of 1221 is positioned at outside shear wall body 120, adjacent shear wall body 120 carry out concrete cast fixing time, coagulation Soil is firmly combined with the fastening rib 1221 of U-shaped, and fastening rib 1221 is unlikely to deform in casting process, the concrete after having poured Structural strength is high, and shock resistance is strong.
Referring to Fig. 3, open-spandrel sandwich board 110 is arranged on the top of shear wall body 120, as the ceiling of substrustion Structure, also serves as the floor panel structure of superstructure.Open-spandrel sandwich board 110 include upper strata compression zone 111, middle level connecting portion 112 with And tension portion of lower floor 113, middle level connection post 1121 is between upper strata compression zone 111 and tension portion of lower floor 113, and middle level connects Portion 112 fixes be connected with upper strata compression zone 111 and tension portion of lower floor 113 respectively, and upper strata compression zone 111 is solid with top plate 117 Fixed connection.
Upper strata compression zone 111 includes multiple horizontal compression plate 1111 and multiple longitudinal compression plate 1112, horizontal compression plate 1111 fix with infall with longitudinal compression plate 1112 with longitudinal angled setting of compression plate 1112, each horizontal compression plate 1111 Connecting, be preferably arranged to, horizontal compression plate 1111 and longitudinal compression plate 1112 are vertically arranged, it is simple to processing and manufacturing, horizontal pressurized Plate 1111 and longitudinal compression plate 1112 are set to rectangular slab, simple in construction, it is simple to pour molding, and many horizontal compression plates 1111 And define the frame structure with multiple rectangular cavity between many longitudinal compression plates 1112;A laterally plate face of compression plate 1111 Being fitted on the plate face of top plate 117 with a plate face of longitudinal compression plate 1112, another plate face of horizontal compression plate 1111 is with vertical In another plate face of compression plate 1112 is generally aligned in the same plane.
Refer to Fig. 4, when being attached by multiple laced beams of same floor fixing, by taking between adjacent laced beam Build formwork for placing to carry out concreting and fix, and define the structure of tie-beam, therefore, for improving the company of adjacent laced beam Connect structural strength, and then the structural strength of the floorboard of raising entirety, at along its length the two of horizontal compression plate 1111 Being respectively arranged with the first fastening reinforcing bar 114 on individual side, the first fastening reinforcing bar 114 is along the length being parallel to horizontal compression plate 1111 Corresponding side is protruded in direction;It is respectively arranged with the second fastening on along its length two sides of longitudinal compression plate 1112 Reinforcing bar 115, the second fastening reinforcing bar 115 protrudes corresponding side along the length direction being parallel to described longitudinal compression plate 1112.
Concrete, the first fastening reinforcing bar 114 includes fixing muscle 1141 and absorption muscle 1142, and fixing muscle 1141 includes relatively Two fixed parts arranged and the connecting portion between two fixed parts, one end of two fixed parts is fixing with connecting portion even Connecing, the other end of two fixed parts is fixing with horizontal compression plate 1111 to be connected, and fixing muscle 1141 is U-shaped structure, it is preferred to use one Root reinforcing bar is bent into, and structural strength is high, and absorption muscle 1142 is arranged on connecting portion, and absorption muscle 1142 uses the side of welding Formula is fixing with fixing muscle 1141 to be connected, and sound construction is reliable.Fixing muscle 1141 uses pre-buried mode to be fixed on horizontal compression plate In 1111, the plane at fixing muscle 1141 place is parallel with the plate face of horizontal compression plate 1111, when carrying out concreting, by adjacent The corresponding fixing muscle 1141 of laced beam carry out colligation, enter to pour, improve the company of formation after concreting completes Connect the structural strength of beam.
Further, absorption muscle 1142 includes the ring-type auxiliary muscle 1144 of main muscle 1143, first and the second ring-type auxiliary muscle 1145, main Muscle 1143 is perpendicular to top plate 117 and arranges, and one end of main muscle 1143 is fixing with connecting portion to be connected, and the first ring-type auxiliary muscle 1144 is sheathed Outside the second ring-type auxiliary muscle 1145, and the first ring-type auxiliary muscle 1144 auxiliary muscle 1145 ring-type with second is fixed in infall and is connected, First ring-type auxiliary muscle 1144 or the second ring-type auxiliary muscle 1145 are fixed with main muscle 1143 and are connected.After having poured, fixing muscle 1141 It is positioned at concrete layer, the part not exposed, it is not necessary to carry out cutting process, simplify construction procedure with absorption muscle 1142. First ring-type auxiliary muscle 1144 is preferably arranged to circular, and the second ring-type auxiliary muscle 1145 is preferably arranged to circular, it is simple to processing system Make, after the first ring-type auxiliary muscle 1144 is set in outside the second ring-type auxiliary muscle 1145, the first ring-type auxiliary muscle 1144 and the second ring-type auxiliary muscle 1145 have two crossover locations, and the line between two crossover locations is to be the diameter of the first ring-type auxiliary muscle 1144, simultaneously Also being the diameter of the second ring-type auxiliary muscle 1145, after concreting, absorption muscle 1142 can the most firmly be embedded in mixed In solidifying soil, and between concrete, define adsorption, enhance the being firmly combined with property between reinforcing bar and concrete, improve phase The adjacent connectivity robustness between laced beam, and then improve the structural strength of entirety, improve shock resistance.It is preferably provided with For, the structure of the second fastening reinforcing bar 115 is identical with the structure of the first fastening reinforcing bar 114, is not described in detail at this.
Lower floor's compression zone includes multiple laterally by arm-tie 1131 and multiple longitudinal tensile plate 1132, laterally by arm-tie 1131 Setting angled with longitudinal tensile plate 1132, each laterally fixing with longitudinal tensile plate 1132 and infall even by arm-tie 1131 Connect, be preferably arranged to, be laterally respectively rectangular plate-like by arm-tie 1131 with longitudinal tensile plate 1132, and be arranged in a mutually vertical manner, enclose The frame structure with multiple rectangular cavity, upper strata compression zone 111 has been become to be oppositely arranged with tension portion of lower floor 113, i.e. upper strata pressurized Portion 111 and two parts that tension portion of lower floor 113 is that structure is identical, upper strata compression zone 111 bears pressure in loading process, Tension portion of lower floor 113 bears pulling force in loading process.When carrying out the connection of polylith waffle beam of same layer and fixing, need Carry out concreting, accordingly, it would be desirable to build template assembly, for the ease of template assembly in the bottom in tension portion of lower floor 113 Install, be preferably arranged to, laterally by the two ends along its length of arm-tie 1131, pre-embedded bolt 116, pre-embedded bolt be installed 116 are perpendicular to laterally be arranged by the plate face of arm-tie 1131, and pre-embedded bolt 116 protrudes the horizontal lower face by arm-tie 1131, with Time be laterally provided with pre-embedded bolt 116 by two sides of the length direction along longitudinal tensile plate 1132 of arm-tie 1131, Carry out template when building, main template body is hung on the pre-embedded bolt 116 on the side, meanwhile, by main template body Lower face arranges support bar, and the two ends of support bar are screwed onto on the pre-embedded bolt 116 of adjacent waffle beam respectively, template Build mode simple and reliable, it is simple to concreting molding.
Middle level connecting portion 112 includes that multiple middle level connects post 1121, multiple crossover locations of upper strata compression zone 111 and lower floor Multiple crossover location one_to_one corresponding in tension portion 113 are arranged, a crossover location of upper strata compression zone 111 and tension portion of lower floor One crossover location of 113 constitutes an installation portion, each installation portion is provided with middle level and connects post 1121, and middle level connects post One end of 1121 is fixing with a crossover location of upper strata compression zone 111 to be connected, its other end and one of tension portion of lower floor 113 Crossover location is fixing to be connected, and middle level connects post 1121 and is perpendicular to the plate face of top plate 117.
Whole waffle beam uses factory to pour one-body molded, and in frame structure, weight alleviates significantly, saves the material of construction Material, meanwhile, the waffle beam after having poured bears pressure by upper strata compression zone 111, middle level connecting portion 112 bear shearing force with And tension portion of lower floor 113 bears pulling force, while alleviating the weight of waffle beam, do not interfere with the stress of waffle beam, whole close The structural safety of girt strip is reasonable.
The method of construction embodiment of prefabricated assembled tube structure public building
Present embodiments provide the method for construction of a kind of prefabricated assembled tube structure public building, comprise the steps:
Step S100, making shear wall body 120;First assembling steel form, make framework of steel reinforcement, framework of steel reinforcement enters mould, Then form wallboard 127, last standard curing 1 day~2 days with concreting, remove steel form, form prefabricated mesh formula frame Frame-shear wall body 120;
Step S200, making open-spandrel sandwich board 110, first assemble steel form, assembling reinforcement mesh sheet;Then water with concrete Build, last standard curing 1 day~2 days, remove steel form, form the Prefabricated hollow sandwich plate with top plate 117 and laced beam 110;Open-spandrel sandwich board 110 after having poured includes top plate 117 and laced beam, laced beam have upper strata compression zone 111, in Layer connecting portion 112 and tension portion of lower floor 113, upper strata compression zone 111 is with tension portion of lower floor 113 by middle level connecting portion 112 even Connecing, middle level connecting portion 112 includes that multiple middle level connects the part of the force division of post 1121, i.e. laced beam uniformly, upper strata compression zone Between 111 and tension portion of lower floor 113 in addition to being provided with middle connection post, other regions are hollow-core construction, significantly reduce on an empty stomach The weight of sandwich plate 110.Using the open-spandrel sandwich board 110 that concreting is formed, be formed in one structure, and sound construction can Leaning on, transport carries out installing to scene, saves the time of construction.
Step S300, construction basis, pouring reinforcement concrete foundation ring girder, reserved constructional column reinforcing bar on described foundation ring girder Head and water proof structure;Foundation ring girder is to connect under ground portion and the intermediate structure of wall part, and the overall space improving house is firm Degree, the globality of increase building, play the effect of waist hoop, improve the shearing resistance of body of wall, tensile strength, prevent due to ground building Base differential settlement, earthquake or other larger vibration load cracking destructions to house.
Step S400, prefabricated components are installed, and the lifting of prefabricated mesh formula frame-shear wall body of wall 120 is shelved on described basis In the reserving hole of the predeterminated position of collar tie beam described constructional column steel bar end is inserted described shear wall body 120 bottom, so After carry out grouting anchoring;Reserved connection reinforcing bar between adjacent described shear wall body 120 is carried out nesting, pours formation mixed Solidifying soil connects post;
Step S500, the installation of Prefabricated hollow sandwich plate 110, adjust Prefabricated hollow sandwich plate 110 and position and in place, prefabricated The level connection joint muscle of open-spandrel sandwich board 110 is nested with the reserved steel bar of prefabricated mesh formula Frame-Shear Wall body of wall 120, adjacent Reserved steel bar between Prefabricated hollow sandwich plate 110 carries out nesting, reserves in the bottom of Prefabricated hollow sandwich plate 110 and pacifies at bolt Steel loading template, carries out concreting, forms tie-beam between adjacent Prefabricated hollow sandwich plate 110;Open-spandrel sandwich board 110 is Hollow-core construction, when open-spandrel sandwich board 110 is fixed with shear wall body 120 and adjacent open-spandrel sandwich board 110, is watered by scene Build the fixing connection of concrete, first have to the bottom at open-spandrel sandwich board 110, namely the tension portion of lower floor 113 of open-spandrel sandwich board 110 Bottom build template assembly, main template body connects by the pre-embedded bolt 116 in tension portion of lower floor 113 is fixing, easy for installation Reliably, adjacent open-spandrel sandwich board 110 defines concrete coupling beams, open-spandrel sandwich board 110 and Shear Walls after having poured After body 120 has poured, the multiple middle levels near shear wall body 120 connect post 1121 and shear wall body 120 is fixing even Connecing, define concrete and connect post, easy construction is reliable, has poured form removal assembly after concrete coagulation, has completed to execute Work.
S500 described in step S600, repeating said steps S100-the most successively constructs, and builds gestalt and becomes multilamellar to build The structure built, when carrying out the fixing construction of concreting of tier building unit, the correspondence of the building unit of adjacent two-layer Shear wall body 120 and the open-spandrel sandwich board between the building unit of adjacent two layers 110 are integrated knot after having poured Structure, a concreting can realize the corresponding shear wall body 120 of adjacent architectural unit and consolidating of open-spandrel sandwich board 110 Fixed, convenient and quick construction.
The foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, for the skill of this area For art personnel, the present invention can have various modifications and variations.All within the spirit and principles in the present invention, that is made any repaiies Change, equivalent, improvement etc., should be included within the scope of the present invention.

Claims (10)

1. a prefabricated assembled tube structure public building, it is characterised in that include building unit, each described building unit Including the precast shear wall body of wall in grid type framework and include Prefabricated hollow sandwich plate, wherein:
Described Prefabricated hollow sandwich plate includes that top plate and many laced beams, adjacent described laced beam parallel interval are arranged, And many described laced beams and described top plate formed by integrally casting molding, described Prefabricated hollow sandwich plate is positioned at described precast shear wall The top of body of wall, many described laced beams are overlapped on described precast shear wall body of wall, and many described laced beams are prefabricated with described Shear wall body connects by casting concrete is fixing.
Prefabricated assembled tube structure public building the most according to claim 1, it is characterised in that described laced beam includes Upper strata compression zone, middle level connecting portion and tension portion of lower floor, described middle level connecting portion is in described upper strata compression zone and described Between tension portion of lower floor, fix with described upper strata compression zone and tension portion of described lower floor respectively and be connected, described upper strata compression zone Fix with described top plate and be connected.
Prefabricated assembled tube structure public building the most according to claim 2, it is characterised in that described upper strata compression zone Including multiple horizontal compression plates and multiple longitudinal compression plate, described horizontal compression plate is angled with described longitudinal compression plate to be set Putting, each described horizontal compression plate is fixing with described longitudinal compression plate and infall to be connected;One plate face of described horizontal compression plate It is fitted on the plate face of described top plate with a plate face of described longitudinal compression plate, another plate face of described horizontal compression plate and institute Another plate face stating longitudinal compression plate is generally aligned in the same plane interior.
Prefabricated assembled tube structure public building the most according to claim 3, it is characterised in that described lower floor compression zone Including multiple laterally by arm-tie and multiple longitudinal tensile plate, described laterally set by arm-tie is angled with described longitudinal tensile plate Putting, each described horizontal being fixed with described longitudinal tensile plate and infall by arm-tie is connected;Described upper strata compression zone with described under Layer tension portion is oppositely arranged.
Prefabricated assembled tube structure public building the most according to claim 4, it is characterised in that described middle level connecting portion Multiple crossover locations in post, multiple crossover locations of described upper strata compression zone and tension portion of described lower floor are connected including multiple middle levels One_to_one corresponding is arranged, and a crossover location of described upper strata compression zone constitutes with a crossover location in tension portion of described lower floor One installation portion, each described installation portion is provided with described middle level connect post, described middle level connect post one end with described on One crossover location of layer compression zone is fixing to be connected, and a crossover location in its other end and tension portion of described lower floor is fixing even Connect, and described middle level connects post and is perpendicular to described top plate.
6. according to the prefabricated assembled tube structure public building described in any one of claim 3-5, it is characterised in that described Laterally it is respectively arranged with the first fastening reinforcing bar, described first fastening reinforcing bar edge on along its length two sides of compression plate The length direction being parallel to described horizontal compression plate protrudes corresponding side;Along its length the two of described longitudinal compression plate Being respectively arranged with the second fastening reinforcing bar on individual side, described second fastening reinforcing bar is along the length side being parallel to described longitudinal compression plate To protruding corresponding side.
Prefabricated assembled tube structure public building the most according to claim 6, it is characterised in that described first fastening steel Muscle includes fixing muscle and absorption muscle, described fixing muscle include be oppositely arranged two fixed parts and be positioned at two described fixing Connecting portion between portion, one end of two described fixed parts and described connecting portion are fixing to be connected, another of two described fixed parts Holding be connected fixing with described horizontal compression plate, described absorption muscle is arranged on described connecting portion.
Prefabricated assembled tube structure public building the most according to claim 7, it is characterised in that described absorption muscle includes Main muscle, the first ring-type auxiliary muscle and the second ring-type auxiliary muscle, main ribs be perpendicular to described top plate arrange, one end of main ribs with Described connecting portion is fixing to be connected, and described first ring-type auxiliary muscle is set in outside described second ring-type auxiliary muscle, and described first ring-type Auxiliary muscle and described second ring-type auxiliary muscle are connected in infall is fixing, described first ring-type auxiliary muscle or described second ring-type auxiliary muscle and Main ribs is fixing to be connected.
Prefabricated assembled tube structure public building the most according to claim 8, it is characterised in that described laterally by arm-tie Two ends along its length pre-embedded bolt is installed, described pre-embedded bolt is perpendicular to described laterally be set by the plate face of arm-tie Put, and described pre-embedded bolt protrudes described laterally by the lower face of arm-tie.
10. the method for construction of a prefabricated assembled tube structure public building, it is characterised in that the method includes walking as follows Rapid:
Step S100, making shear wall body;First assembling steel form, make framework of steel reinforcement, framework of steel reinforcement enters mould, then with mixed Solidifying soil pours formation wallboard, last standard curing 1 day~2 days, removes steel form, forms prefabricated mesh formula Frame-Shear Wall wall Body;
Step S200, making open-spandrel sandwich board, first assemble steel form, assembling reinforcement mesh sheet;Then with concreting, finally Standard curing 1 day~2 days, removes steel form, forms the Prefabricated hollow sandwich plate with top plate and laced beam;
Step S300, construction basis, pouring reinforcement concrete foundation ring girder, on described foundation ring girder reserved constructional column steel bar end and Water proof structure;
Step S400, prefabricated components are installed, and the lifting of prefabricated mesh formula frame-shear wall body of wall is shelved on described foundation ring girder Predeterminated position and by described constructional column steel bar end insert described shear wall body bottom reserving hole in, be then in the milk Anchoring;Reserved connection reinforcing bar between adjacent described shear wall body is carried out nesting, pours formation concrete and connect post;
Step S500, the installation of Prefabricated hollow sandwich plate, adjust Prefabricated hollow sandwich plate and position and in place, and described Prefabricated hollow presss from both sides The level connection joint muscle of laminate is nested with the reserved steel bar of described prefabricated mesh formula Frame-Shear Wall body of wall, and adjacent is described prefabricated Reserved steel bar between open-spandrel sandwich board carries out nesting, reserves installation punching block at bolt in the bottom of described Prefabricated hollow sandwich plate Plate, carries out concreting, forms tie-beam between adjacent described Prefabricated hollow sandwich plate;
S500 described in step S600, repeating said steps S100-the most successively constructs.
CN201610865598.XA 2016-09-29 2016-09-29 Prefabricated assembled tube structure public building and its method of construction Pending CN106245752A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610865598.XA CN106245752A (en) 2016-09-29 2016-09-29 Prefabricated assembled tube structure public building and its method of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610865598.XA CN106245752A (en) 2016-09-29 2016-09-29 Prefabricated assembled tube structure public building and its method of construction

Publications (1)

Publication Number Publication Date
CN106245752A true CN106245752A (en) 2016-12-21

Family

ID=57611069

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610865598.XA Pending CN106245752A (en) 2016-09-29 2016-09-29 Prefabricated assembled tube structure public building and its method of construction

Country Status (1)

Country Link
CN (1) CN106245752A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958318A (en) * 2017-05-10 2017-07-18 三筑工科技有限公司 Wall panel element and basis, multiple layer combination panel structure and construction technology
CN113858400A (en) * 2021-08-26 2021-12-31 北京星航机电装备有限公司 Assembling die for prefabricated parts

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1275667A (en) * 2000-04-02 2000-12-06 张云富 Light type rib floor and construction method
CN201236492Y (en) * 2008-06-13 2009-05-13 陈世荣 House building structure
JP2013213387A (en) * 2012-04-02 2013-10-17 Noboru Watanabe Prefabrication type sw construction having steel pipe pile foundation strong against major earthquake
CN103628567A (en) * 2013-12-17 2014-03-12 王睿敏 Integrally assembled shear wall, floor building system and construction method
CN103882991A (en) * 2014-03-26 2014-06-25 初明进 Connecting piece with steel bar rings
CN103924711A (en) * 2014-05-01 2014-07-16 西安科技大学 Assembled type gridding shearing wall structural system and construction technology of assembled type gridding shearing wall structural system
CN205242783U (en) * 2015-11-03 2016-05-18 中国航天建设集团有限公司 Novel steel - concrete combination laced beam system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1275667A (en) * 2000-04-02 2000-12-06 张云富 Light type rib floor and construction method
CN201236492Y (en) * 2008-06-13 2009-05-13 陈世荣 House building structure
JP2013213387A (en) * 2012-04-02 2013-10-17 Noboru Watanabe Prefabrication type sw construction having steel pipe pile foundation strong against major earthquake
CN103628567A (en) * 2013-12-17 2014-03-12 王睿敏 Integrally assembled shear wall, floor building system and construction method
CN103882991A (en) * 2014-03-26 2014-06-25 初明进 Connecting piece with steel bar rings
CN103924711A (en) * 2014-05-01 2014-07-16 西安科技大学 Assembled type gridding shearing wall structural system and construction technology of assembled type gridding shearing wall structural system
CN205242783U (en) * 2015-11-03 2016-05-18 中国航天建设集团有限公司 Novel steel - concrete combination laced beam system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106958318A (en) * 2017-05-10 2017-07-18 三筑工科技有限公司 Wall panel element and basis, multiple layer combination panel structure and construction technology
CN113858400A (en) * 2021-08-26 2021-12-31 北京星航机电装备有限公司 Assembling die for prefabricated parts
CN113858400B (en) * 2021-08-26 2022-09-16 北京星航机电装备有限公司 Assembling die for prefabricated parts

Similar Documents

Publication Publication Date Title
CN106013454B (en) Building and method of construction based on large spatial structure body and free-standing peripheral structure
CN203174770U (en) Connection structure of prefabricated column and construction site base and building
CN106436894B (en) A kind of prefabricated dwelling house and its method of construction
CN108385904B (en) Roofing parapet wall and construction method thereof
CN106149882A (en) A kind of lateral resisting and antigravity separate steel structure of housing system and construction method thereof
CN111424850A (en) Prefabricated reinforced concrete shear wall and construction method
CN110080287A (en) A kind of assembled flat-top has the open cutting construction method of column underground structure
CN111962675A (en) Construction method of large-span special-shaped cast-in-place reinforced concrete open-web truss
JP5496732B2 (en) Construction method for reinforced concrete buildings
CN206090815U (en) Prefabricated assembled tube structure public building
CN2921139Y (en) Combined hollow large panel ceiling for storied building
CN204645253U (en) A kind of prefabricated house
CN204112525U (en) Band perps precast shear wall structure in strong concrete precast frame
CN106245752A (en) Prefabricated assembled tube structure public building and its method of construction
CN106436975A (en) Built-in girder shear wall
CN206015882U (en) The steel structure of housing system that a kind of lateral resisting and antigravity separate
CN210066817U (en) Assembly integral vault is striden no post underground structure greatly
CN112681511A (en) Reinforced concrete structure construction method using section steel to replace part of reinforcing steel bars
CN208618627U (en) A kind of precast floor slab and its connection structure
CN216920677U (en) First-layer supporting structure of large rockery outer package
CN216475803U (en) Novel prefabricated floor slab structure applied to shear wall system
CN110080291A (en) A kind of assembled flat-top is greatly across no column underground structure
CN206090818U (en) Novel prefabricated constructional building
CN210066816U (en) Assembled vault is striden no post underground structure greatly
CN211286039U (en) Node for connecting steel beam and reinforced concrete column

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161221

RJ01 Rejection of invention patent application after publication