CN106223709A - A kind of hoisting structure of current collection line steel tower tower material - Google Patents

A kind of hoisting structure of current collection line steel tower tower material Download PDF

Info

Publication number
CN106223709A
CN106223709A CN201610598489.6A CN201610598489A CN106223709A CN 106223709 A CN106223709 A CN 106223709A CN 201610598489 A CN201610598489 A CN 201610598489A CN 106223709 A CN106223709 A CN 106223709A
Authority
CN
China
Prior art keywords
tower
steel tower
pole
corner block
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610598489.6A
Other languages
Chinese (zh)
Inventor
陈小平
李美玲
刘贺
成林峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ceec Anhui Electric Power Construction First Engineering Co Ltd
Original Assignee
Ceec Anhui Electric Power Construction First Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ceec Anhui Electric Power Construction First Engineering Co Ltd filed Critical Ceec Anhui Electric Power Construction First Engineering Co Ltd
Priority to CN201610598489.6A priority Critical patent/CN106223709A/en
Publication of CN106223709A publication Critical patent/CN106223709A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Electric Cable Installation (AREA)

Abstract

The invention discloses the hoisting structure of a kind of current collection line steel tower tower material, include the pole being fixed on steel tower, it is fixed on the pulley of pole top-side, it is arranged on steel tower and is positioned at the high-altitude corner block of pole bottom sidepiece, it is arranged at the ground corner block of steel tower stance, and grinding machine and boom hoist cable are twisted in traction;One end of boom hoist cable is drawn from traction strand grinding machine, is wound in the most successively on ground corner block, high-altitude corner block and pulley, finally heavily draws from pulley to be connected with tower material and fixes.The present invention is relatively difficult for Work tool transport, and group tower tonnage is relatively light, exhales title height less, and root opens less or that landform is limited tower position.It is an advantage of the invention that pole is small and exquisite, the most fixing and promotes, less demanding to construction site, site layout project simplifies, and Work tool is less, and constructing operation is simple, and transition is flexible.

Description

A kind of hoisting structure of current collection line steel tower tower material
Technical field
The present invention relates to tower erection construction field, the hoisting structure of a kind of current collection line steel tower tower material.
Background technology
Arrive it is known that the Chinese government makes promise to international community in Copenhagen climate change conference in 2009 The year two thousand twenty unit GDP CO2 emissions declined 40%~50% than 2005, and non-fossil energy is by satisfied this country The energy demand of 15%, this is proposed unprecedented expectation to the development scale of China's wind-powered electricity generation in future and progress etc., accelerates wind energy money The utilizing of source realizes the Important Action of the strategy of sustainable development in becoming China considerably long one period with exploitation, to the year two thousand twenty China's wind-powered electricity generation installation reaches 2.3 hundred million KW;The best development environment and opportunity is provided for our Wind Power Development.
During the foundation construction of wind energy turbine set is built, the construction of collection electric line determines in the properly functioning of blower fan and wind energy turbine set each The normal use of item component.And steel tower is requisite a kind of structure in cable construction.The group of existing steel tower is stood Using at ground overall package steel tower, its construction requirement is high, and the requirement to landform is the highest.
Summary of the invention
The technical problem to be solved in the present invention is to provide the hoisting structure of a kind of current collection line steel tower tower material, uses pole to divide The system of solutions founds steel tower, and its lifting group is stood simple to operate, less demanding to landform.
The technical scheme is that
The hoisting structure of a kind of current collection line steel tower tower material, includes the pole being fixed on steel tower, is fixed on pole top side The pulley in face, is arranged on steel tower and is positioned at the high-altitude corner block of pole bottom sidepiece, be arranged at the ground of steel tower stance Corner block, and draw strand grinding machine and boom hoist cable;One end of described boom hoist cable is drawn from traction strand grinding machine, It is wound in the most successively on ground corner block, high-altitude corner block and pulley, finally heavily draws from pulley and be connected with tower material admittedly Fixed.
The bottom of described pole is fixed on steel tower by metal binding wire rope, and the middle-end of pole connects by waist rope is fixing In top, be used for catch pole, so it does not topple.
Described hoisting structure also includes tricing line, and the top of tricing line is fixing with tower material to be connected, the bottom of tricing line It is connected with the haulage gear on ground.
Advantages of the present invention:
The present invention is relatively difficult for Work tool transport, and group tower tonnage is relatively light, exhales title height less, and root is opened less or landform and is subject to The tower position of limit.It is an advantage of the invention that pole is small and exquisite, the most fixing and promotes, less demanding to construction site, site layout project letter Changing, Work tool is less, and constructing operation is simple, and transition is flexible.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not making creative work premise Embodiment, broadly falls into the scope of protection of the invention.
See Fig. 1, the hoisting structure of a kind of current collection line steel tower tower material, include the pole 2 being fixed on steel tower 1, fixing At the pulley 3 of pole 2 top-side, it is arranged on steel tower 1 and is positioned at the high-altitude corner block 4 of pole bottom sidepiece, be arranged at The ground corner block 5 of steel tower 1 stance, and traction strand grinding machine 6, boom hoist cable 7 and tricing line 8;The bottom of pole 2 leads to Crossing metal binding wire rope to be fixed on steel tower 1, the middle-end of pole 2 is fixedly connected on the top of steel tower 1 by waist rope 9, is used for catching Pole 2, so it does not topple;One end of boom hoist cable 7 is drawn from traction strand grinding machine 6, is wound in ground the most successively and turns On coaster 5, high-altitude corner block 4 and pulley 3, finally heavily draw from pulley 3 to be connected with tower material 10 and fix;The top of tricing line 8 Holding be connected fixing with tower material 10, the bottom of tricing line 10 is connected with the haulage gear on ground.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, permissible Understand and these embodiments can be carried out multiple change without departing from the principles and spirit of the present invention, revise, replace And modification, the scope of the present invention be defined by the appended.

Claims (3)

1. the hoisting structure of a current collection line steel tower tower material, it is characterised in that: include the pole being fixed on steel tower, fixing At the pulley of pole top-side, it is arranged on steel tower and is positioned at the high-altitude corner block of pole bottom sidepiece, be arranged at steel tower The ground corner block of stance, and draw strand grinding machine and boom hoist cable;One end of described boom hoist cable is from traction Strand grinding machine is drawn, is wound in the most successively on ground corner block, high-altitude corner block and pulley, finally heavily draws from pulley It is connected fixing with tower material.
The hoisting structure of a kind of current collection line steel tower tower material the most according to claim 1, it is characterised in that: described pole Bottom be fixed on steel tower by metal binding wire rope, the top that the middle-end of pole is fixedly connected on by waist rope, be used for catch Pole, so it does not topple.
The hoisting structure of a kind of current collection line steel tower tower material the most according to claim 1, it is characterised in that: described lifting Structure also includes tricing line, and the top of tricing line is fixing with tower material to be connected, and the bottom of tricing line connects with the haulage gear on ground Connect.
CN201610598489.6A 2016-07-27 2016-07-27 A kind of hoisting structure of current collection line steel tower tower material Pending CN106223709A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610598489.6A CN106223709A (en) 2016-07-27 2016-07-27 A kind of hoisting structure of current collection line steel tower tower material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610598489.6A CN106223709A (en) 2016-07-27 2016-07-27 A kind of hoisting structure of current collection line steel tower tower material

Publications (1)

Publication Number Publication Date
CN106223709A true CN106223709A (en) 2016-12-14

Family

ID=57532925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610598489.6A Pending CN106223709A (en) 2016-07-27 2016-07-27 A kind of hoisting structure of current collection line steel tower tower material

Country Status (1)

Country Link
CN (1) CN106223709A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110713126A (en) * 2019-10-15 2020-01-21 上海宝冶集团有限公司 Hoisting device of anemometer tower

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2232863C2 (en) * 2002-09-25 2004-07-20 Магафуров Дамир Баратевич Craneless method for mounting and dismounting drilling derricks, mast and tower constructions with enlarged sections
CN102022019A (en) * 2010-11-03 2011-04-20 河南省电力公司洛阳供电公司 Method for split tower erection of lines in complex terrain
CN202187601U (en) * 2011-05-17 2012-04-11 王海兵 Single-twisting-grinder double-pole iron tower erecting device of high-voltage power transmission line
CN202346637U (en) * 2011-10-31 2012-07-25 湖北省输变电工程公司 Holding rod of double-flat-arm spinning self-lifting seat
CN105003118A (en) * 2015-07-27 2015-10-28 中国电力科学研究院 Pole for assembling power transmission towers

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2232863C2 (en) * 2002-09-25 2004-07-20 Магафуров Дамир Баратевич Craneless method for mounting and dismounting drilling derricks, mast and tower constructions with enlarged sections
CN102022019A (en) * 2010-11-03 2011-04-20 河南省电力公司洛阳供电公司 Method for split tower erection of lines in complex terrain
CN202187601U (en) * 2011-05-17 2012-04-11 王海兵 Single-twisting-grinder double-pole iron tower erecting device of high-voltage power transmission line
CN202346637U (en) * 2011-10-31 2012-07-25 湖北省输变电工程公司 Holding rod of double-flat-arm spinning self-lifting seat
CN105003118A (en) * 2015-07-27 2015-10-28 中国电力科学研究院 Pole for assembling power transmission towers

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
国家电网公司基建部: "《国家电网公司输变电工程典型施工方法(第一辑)》", 28 February 2011 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110713126A (en) * 2019-10-15 2020-01-21 上海宝冶集团有限公司 Hoisting device of anemometer tower

Similar Documents

Publication Publication Date Title
CN104891307B (en) New climbing type wind-powered electricity generation maintenance lifting platform and the using method of heavy duty can be born
CN201729557U (en) Device with elevator and ladder stand arranged in tower tube of wind generating set
CN205779491U (en) Sectional prefabricating type concrete tower
CN106223709A (en) A kind of hoisting structure of current collection line steel tower tower material
CN101705919A (en) Reverse guy rope type cantilever of vertical shaft wind driven generator
CN201827027U (en) Self-positioning flange of wind-driven power generation tower
CN101660498A (en) Shaft vertical windmill
CN201874750U (en) Large-power umbrella-type wind power system
CN204490390U (en) A kind of solar wind-energy mixed type mine hoist equipment
CN102808742A (en) Connecting structure for tower cylinder and supporting tower frame of wind driven generator
CN202414917U (en) Vertical elevator with spare safety rope
CN201778390U (en) Structural system provided with wind turbine generator in high-rise/ultrahigh-rise building
CN207777087U (en) A kind of wind-power generating unit tower
CN107355347A (en) Energy-storage-type wind generator
CN202148983U (en) Fan blade structure for vertical axis wind power generation equipment
CN206017043U (en) The attending device of tidal power generating system
RU102066U1 (en) ALTITUDE WIND POWER INSTALLATION WITH LIFTING SAIL AEROSTAT WITH ROPES
CN108756823A (en) A kind of power generator using remaining potential energy
CN101852171A (en) Umbrella-shaped wind power system
CN207989229U (en) A kind of vertical-type Liftable type breeze wind tower
CN202266373U (en) Wind power generation device with controllable wind power
CN212690232U (en) Wind-proof device for wind power base
CN213626602U (en) Support frame for water and electricity construction
CN206917808U (en) A kind of wind tower construction maintenance platform
CN203255831U (en) Connecting and fastening device of lifting machine for external use of wind-power tower drum

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161214