CN106208049A - The practical approach that a kind of power distribution network simple state is estimated - Google Patents

The practical approach that a kind of power distribution network simple state is estimated Download PDF

Info

Publication number
CN106208049A
CN106208049A CN201610670874.7A CN201610670874A CN106208049A CN 106208049 A CN106208049 A CN 106208049A CN 201610670874 A CN201610670874 A CN 201610670874A CN 106208049 A CN106208049 A CN 106208049A
Authority
CN
China
Prior art keywords
switch
power
load
line
distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610670874.7A
Other languages
Chinese (zh)
Other versions
CN106208049B (en
Inventor
崔立忠
张瑞雪
程向向
郭秋野
马志斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Beijing Kedong Electric Power Control System Co Ltd
Original Assignee
State Grid Corp of China SGCC
Beijing Kedong Electric Power Control System Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Beijing Kedong Electric Power Control System Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610670874.7A priority Critical patent/CN106208049B/en
Publication of CN106208049A publication Critical patent/CN106208049A/en
Application granted granted Critical
Publication of CN106208049B publication Critical patent/CN106208049B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/003Load forecast, e.g. methods or systems for forecasting future load demand

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

A kind of method that the present invention relates to electric field state estimation, particularly relates to the practical approach that a kind of power distribution network simple state is estimated, comprises the steps: (1) Historic Section Data Matching;(2) power distribution network topological tree generates;(3) switch remote signalling identification;(4) remote measurement polishing;(5) cyclization analysis;(6) examination statistics;(7) daily load prediction.The application provides the practical approach that a kind of power distribution network simple state is estimated, thus the remote signalling value of identification switch/disconnecting link, polishing switch remote measurement value, estimate the most believable system running state.

Description

The practical approach that a kind of power distribution network simple state is estimated
Technical field
A kind of method that the present invention relates to electric field state estimation, particularly relates to a kind of power distribution network simple state and estimates The practical approach of meter.
Background technology
State estimation also referred to as " filtering ", be the redundancy of utilization examining system to get rid of irrational wrong data, Improve the precision of data, the running status of estimating system, provide credible, consistent flow data.It is to join that state of electric distribution network is estimated The basis of electrical network analysis, can be that the senior application such as idle work optimization, voltage & var control provides credible, consistent basic data. While improving data reliability, improve the practical level of each senior application.
At present, power distribution network measure configuration is few, intelligent and automatization level is relatively low.Using with adopt the metrical information of distribution transforming as Pseudo-measure, still can not obtain higher redundancy, but it is estimated that system close on unobservable in the case of system the most credible Running status.
Power distribution network only has feeder line service entrance switch and the block switch of minority, on-load switch to have measure configuration at present, and deposits In the inaccurate problem of measurement that the problems such as factor data collection and communication port cause, distribution main website with the extraction system time not Synchronicity, causes the unmatched problem of inter-system data section.
Prior art simplifies electric connecting relation, it is believed that a feeder line generates a distribution sub-island, according to circuit Kirchhoff's law takes remote measurement the pretreatment of data, sharing of load and load assemble the remote measurement polishing carrying out switching, use Sectional carries out the method for local state estimation.And in reality, when between feeder line, interconnection switch closes position, it is impossible to determine load/distribution transforming By which section feeder line powered, it is impossible to simply a feeder line is generated a distribution sub-island, simplify electric connecting relation unreasonable;Real The not all distribution transforming in border all has measure configuration and metric data, it is also difficult to ensure with adopting distribution transforming and distribution main website mates completely, It is irrational that prior art processes the mode of load/distribution transforming;Prior art being thought, the remote signalling value of switch/disconnecting link is correct nothing By mistake, only switch remote measurement value being carried out pretreatment, processing mode is not inconsistent with practical situation.
Summary of the invention
The purpose of the present invention, is to combine power distribution network to run present situation, it is provided that the practicality side that a kind of power distribution network simple state is estimated Method, thus the remote signalling value of identification switch/disconnecting link, polishing switch remote measurement value, estimate the most believable system running state.
Technical scheme is as follows:
The practical approach that a kind of power distribution network simple state is estimated, comprises the steps:
(1) Historic Section Data Matching
Read with extraction system 96 power curve data every day and corresponding section moment, choose in distribution main website section The section in time closest to this section moment and the section in first 5 minutes of this section moment and latter 5 minutes, choose by the merit adopting distribution transforming Rate curve is gained merit data, by platform area code set up main website distribution transforming with adopting the matching relationship of distribution transforming, by calculating between two systems 3 The distribution transforming active power error matched in individual section, splices with extraction system with the main website section that error is minimum, with Adopt the section moment as section complete after splicing in the section moment;With with adopting the power curve data assignment main website side of distribution transforming mutually The distribution low-voltage winding power joined measures;
(2) power distribution network topological tree generates
First, Article 1 line bus1 and Article 2 line bus2 represents that interconnection switch between two feeder lines closes the situation of position, when the Article one, line bus1, Article 2 line bus2 side load summation be all higher than or the most respective service entrance switch power measurement (such as: Time 100kW), illustrate to measure and forbidden, the most do not generate topological tree;If Article 1 line bus1 side total load is less than Article 1 line bus1 Side service entrance switch measures, and Article 2 line bus2 side total load measures more than Article 2 line bus2 side service entrance switch, and contact is described Switch power is flowed to Article 2 line bus2 by Article 1 line bus1, by the service entrance switch of Article 2 line bus2 side, according to electricity The regular tap of gas annexation traversal point position, till the loading assembled is more than service entrance switch, dividing this switch upstream The switch of looped network, as untiing the switch of looped network, is untied with this in Article 1 line bus1 and Article 2 line bus2 side by bit switch respectively Topological tree is generated for cut-off condition;Vice versa;
Through above-mentioned steps, all feeder lines being generated topological tree, the process generating topological tree is: disregard switch/disconnecting link State, carries out depth-first search with the interconnection switch of point position or the switch specified for border, generate comprise bus, switch/ The topological tree of disconnecting link, load/distribution transforming equipment, searchable equipment;During topology, with root node i.e. substation exit bus to Line end recursive search, and mark the flow direction of power, i.e. according to first searching nd or znd of equipment to determine this equipment Power flow direction;
(3) switch remote signalling identification
Upstream and downstream topological relation, the state of upstream equipment and measuring value according to equipment, upstream device be the most charged, with or without The information such as other plant-grid connection state based on following principle judgement switch:
Divide position state of switch/disconnecting link downstream to connect the load/distribution transforming measuring absolute value more than 0, and supply without other power supply Electricity, then this switch/disconnecting link of accurate recognition is for closing position and being modified to close position;
State point position and measure absolute value switch/disconnecting link downstream more than 0 and do not have load/distribution transforming, switch/disconnecting link state and Measuring the situation of contradiction, this switch/disconnecting link remote signalling is suspicious;
Switch/disconnecting link state closes position, downstream load/distribution transforming and switch measure be 0 and upstream without the switch/cutter of point position Lock, then this switch/disconnecting link remote signalling is suspicious;
For the switch of wobble variation, owing to its time of day cannot be determined, use the above principle can be with accurate recognition Close position, or be recognized as suspicious point of position;
(4) remote measurement polishing
After remote signalling identification, distribution sub-island generate, add up the injecting power of each junction point in each distribution sub-island, through with Lower process determines electric current and the power of branch road:
F) assume that the whole network voltage is root node voltage U, it is known that each junction point power, branch resistance G and reactance B parameter, depend on Branch power can be calculated according to following equation;
P i j = U i 2 G i j + U i U j ( G i j cos q i j + B i j sin q i j )
Q i j = N i 2 B i j + U i U j ( G i j sin q i j + B i j cos q i j )
G) against power flow direction, calculate forward with branch power according to node injecting power, calculate each branch power and electricity Stream;
H) along power flow direction, according to each branch power and first node voltage, branch voltage fall is calculated;
I) two processes of b, c are repeated, until the voltage difference of all nodes less than a limit value or reaches the meter specified Till calculating number of times;
J) close line segment serial number sec, zsec that the switch both sides of position connect, find with not line segment sequence number for the side of-1 Line segment, with this line segment electric current, meritorious, the electric current of idle polishing switch, power measurement;If sec Yu isec is-1, statistic switch The line segment that both sides connect, if the node number zbs of the line segment other end is more than the bs of switch, the most respectively by this line current, meritorious, nothing Merit is sued for peace, with the electric current of result polishing switch, power measurement after summation;
(5) cyclization analysis
After generating topological tree remote signalling identification, carry out sectional, bus analysis, electrical island analysis generation distribution sub-island;
(6) examination statistics
After remote signalling identification correction, with a point position state, the switch of power measurement is had to generate section for border, in section The switch of trip is that power flows into switch, and remaining flows out switch for power, and the difference calculating power carries out regional imbalance statistics, no Aequum comprises meritorious with idle;Setting voltage bound, busbar voltage measures and carries out busbar voltage compared with voltage bound Out-of-limit statistics, for single phase model, voltage takes AB phases line voltage, takes current measurement maximum and the screening of switch in A, B, C three-phase Disconnected capacity carries out switching heavy duty/out-of-limit analysis;Being less than 100% more than setting value is heavy duty, is out-of-limit more than 100%;
The reason of topology failure feeder line is divided into: feeder line can not find bus, feeder line can not find cyclization between service entrance switch and feeder line; During generating distribution sub-island, search another outlet bus then cyclization with side substation exit bus, add up cyclization feeder line; To each distribution sub-island, its island internal loading summation and service entrance switch power measurement carry out initial network loss statistics;Through examination statistics Function, the result of display state directly perceived estimation and effect;
(7) daily load prediction
The partial data section that Historic Section Data Matching obtains, has 96 complete data section every day, by every day 96 Individual data section obtains 288 data section every day according to linear interpolation method, according to the similar day date the most to be predicted forward 10 The load data on it similar date and the Forecasting Methodology of linear extrapolation, for with adopting the distribution transforming that distribution transforming matches, carry out bearing day Lotus is predicted;Predict the load data of 24 hours days to be predicted, carry out real-time status estimation in conjunction with distribution main website real time data.
Further, in described step (1), for a distribution transforming unmatched, if winding power measurement in high-pressure side is meritorious, Idle occur the most in pairs, calculates idle with the power factor of the service entrance switch of feeder line belonging to this distribution transforming, make distribution transforming high-pressure side gain merit, Idle measurement occurs in pairs;If main website high-pressure side load is without measuring, then the power measurement of the on-load switch connected with this distribution transforming is composed Value high-pressure side winding power measures, and to ensure equally to gain merit, idle paired appearance.
Further, described step (3) detailed process is:
E) traversal measures the load/distribution transforming more than 0, the hierarchical relationship in topological tree find the on-load switch of upstream, if This on-load switch divides position, then this on off state mistake is described, and is modified to close position;
F) regular tap of position is divided to the direction of circuit head end traversal with line end, with this switch to line end (root Determine according to power flow direction) search for the load/distribution transforming measured more than 0 or be modified to close the switch of position, if searching, then this point of position Regular tap status error, and be modified to close position;If not searching the magnitude of current of the regular tap of load/distribution transforming and this point of position Survey more than 0, then illustrate that this point of bit switch state is suspicious;
G) traversal measurement is the load/distribution transforming of 0, according to the conjunction bit switch of the hierarchical relationship search upstream in topological tree, if The conjunction bit switch current measurement searched is 0, and this conjunction bit switch does not exist the switch of point position to root node, then illustrate that this closes position On off state is suspicious;
H) switch is after identification terminates, it is judged that the switch of the switch of accurate recognition/suspicious identification whether wobble variation, if so, Then save as and accurately close position or suspicious point of position.
Further, in described step (5), for closed loop design, the power distribution network of open loop operation, due to opening of instantaneity Close combination operation, remote signalling data problem causes cyclization between feeder line;Show as when electrical island is analyzed from a substation exit bus Search another substation exit bus, push back before employing and cannot process the situation of cyclization between this feeder line for Load flow calculation, When generating distribution sub-island, the feeder line of cyclization between feeder line is filtered, be not involved in Load flow calculation and measure polishing;Wherein, dual power supply Power actual can only be by power supplying from one direction, the situation determined by prepared auto restart equipment is not belonging to cyclization, need to negative by dual power supply Lotus splits into two independent loads, is powered by two ends power supply respectively, and cyclization filters out the situation of dual power supply when analyzing.
The beneficial effects of the present invention is:
(1) according to the upstream and downstream topological relation of switch/disconnecting link equipment, the measurement information of upstream and downstream equipment, load/distribution transforming it is No charged, carry out switching/disconnecting link remote signalling identification with or without information such as other plant-grid connection, it is possible to be accurately judged to opening of remote signalling mistake Close, the switch that remote signalling is suspicious, the accurate wobble variation closing position and suspicious point of position switch.There is significant identification effect.
(2) use the electric current of approximation Load flow calculation polishing switch and the method for power measurement, do not have what calculating did not restrained Situation, compares the method for estimating state such as orthogonal transformation, least-squares estimation, singular value decomposition, have faster calculate speed and Precision.
(3) service entrance switch is only had to have measure configuration with part regular tap, gain merit not become with reactive power for power distribution network To the present situation occurred, measure configuration is low, the present invention also can estimate the most believable fortune of system under less measure configuration present situation Row state.
Accompanying drawing explanation
Fig. 1 show interconnection switch between two feeder lines of bus1 and bus2 and closes the situation of position.
Fig. 2 show the example of switch remote signalling identification step, and wherein k2, k3 are the switch that state is suspicious.
Fig. 3 show in remote measurement polishing step, with electric current, the power sum polishing switch phase of line segment sec1, sec2, sec3 The example that should measure.
Detailed description of the invention
Technical term in the present invention is described below:
Topological tree generates: according to the connection node of electrical equipment, the equipment that search is associated, to characterize father and son's brotherhood The tree equipment that searches of storage organization storage.The topological tree generated characterizes annexation and the upstream and downstream level pass of equipment room System.The present invention generates a kind of tree-like storage structure comprising the equipment such as bus, switch, load/distribution transforming, it is simple to equipment of searching connects Relation and the topological tree of hierarchical relationship.
Daily load prediction: for distribution transforming historical load data, by following 24 hours of similar day linear extrapolation method prediction The load data of interior every five minutes, carries out real-time data analysis using the load value of prediction as Real-time Load metric data.
Remote signalling identification: switch/disconnecting link remote signalling value is divided into: close position and point position (i.e. the state of switch/disconnecting link), by switching/ Disconnecting link upstream and downstream equipment is the most charged, equipment amount measured value, switch/disconnecting link remote measurement value judges that the state of switch is the most correct.Energy Enough it is accurately judged to incorrect switch, corrects its remote signalling value (i.e. state);It is judged as the switch that remote signalling value (state) is suspicious, right Its mark.
Remote measurement polishing: estimate the electric current of each branch road, meritorious, idle with power distribution network forward-backward sweep method, statistic switch with open Close the relation of relative branch, the electric current of relative branch, the switch correspondence giving measurement disappearance meritorious, idle are measured.
Historic Section Data Matching: electrical power distribution automatization system main website profile data and electricity consumption acquisition system distribution transforming profile data Coupling, the distribution transforming of distribution main website mated by platform area code with adopting distribution transforming, by by the power assignment main website side phase adopting distribution transforming The low-pressure side winding power of coupling distribution transforming.
Depth-first search: depth-first search belongs to the one of nomography, english abbreviation is DFS i.e. Depth First Search. its process be in simple terms the individual path that each is possible is deep into can not more deeply till, and each joint Point can only access once.
Below in conjunction with the accompanying drawings, technical scheme is made detailed elaboration.
The present invention comprises the following specific steps that:
1, Historic Section Data Matching
For carrying out Load flow calculation, all loads of power distribution network/distribution transforming point is needed to have load data, yet with field measurement Configuration is not enough, or measurement terminal is in state to be repaired, it is difficult to ensure the load data of all load point.Access marketing system The continuous data of system, mates the distribution transforming of distribution main website with adopting distribution transforming according to platform area code, with by the power curve adopting distribution transforming Load/switching data that data assignment main website side matches.
Read with extraction system 96 power curve data every day and corresponding section moment, choose in distribution main website section The section in time closest to this section moment and the section in first 5 minutes of this section moment and latter 5 minutes, choose by the merit adopting distribution transforming Rate curve is gained merit data, by platform area code set up main website distribution transforming with adopting the matching relationship of distribution transforming, by calculating between two systems 3 The distribution transforming active power error matched in individual section, splices with extraction system with the main website section that error is minimum.With with Adopt the section moment as section complete after splicing in the section moment.
Measure with the distribution low-voltage winding power matched with the power curve data assignment main website side adopting distribution transforming;For The distribution transforming unmatched, occurs the most in pairs if winding power measurement in high-pressure side is meritorious, idle, opens with the inlet wire of feeder line belonging to this distribution transforming The power factor closed calculates idle, makes that distribution transforming high-pressure side is meritorious, idle measurement occurs in pairs;If main website high-pressure side load is immeasurable Survey, then the power measurement assignment high-pressure side winding power of the on-load switch connected with this distribution transforming measures, and to ensure equally to gain merit, nothing Merit occurs in pairs.
2, power distribution network topological tree generates
According to the electric connecting relation of equipment, do not consider the folding condition of switch/disconnecting link, use the plan of depth-first search Slightly travel through all of equipment, generate the topological tree characterizing upstream and downstream equipment connecting relation.Due to load transfer, network reconfiguration, inspection The operation such as repair, cause the situation that feeder line lower part load is powered by other feeder line by interconnection switch.Can not be simply by one Under feeder line, all devices generates topological tree.
As shown in Figure 1: between two feeder lines of bus1 and bus2, interconnection switch closes the situation of position, and when bus1, bus2 side, load is total Be all higher than or during power measurement (such as: 100kW) of the most respective service entrance switch, illustrate to measure inaccurate, the most do not generate and open up Flutter tree;If bus1 side total load measures less than bus1 side service entrance switch, and bus2 side total load is more than bus2 side service entrance switch amount Survey, illustrate that interconnection switch power is flowed to bus2 by bus1, by the service entrance switch of bus2 side, travel through according to electric connecting relation Divide the regular tap of position, till the loading assembled is more than service entrance switch, using point bit switch of this switch upstream as untiing The switch of looped network, generates topological tree with this switch untiing looped network for cut-off condition to bus1 Yu bus2 side respectively;Vice versa.
After Fig. 1, all feeder lines being generated topological tree, the process generating topological tree is: disregard the state of switch/disconnecting link, Carrying out depth-first search with the interconnection switch of point position or the switch specified for border, the present invention only generates for the time being and comprises mother The topological tree of line, switch/disconnecting link, load/distribution transforming equipment, searchable equipment.During topology, with root node, (transformer station goes out Mouthful bus) to line end recursive search, and mark the flow direction of power, i.e. come really according to nd or znd first searching equipment The power flow direction of this equipment fixed.
3, switch remote signalling identification
Upstream and downstream topological relation, the state of upstream equipment and measuring value according to equipment, upstream device be the most charged, with or without The information such as other plant-grid connection state based on following principle judgement switch:
Divide position state of switch/disconnecting link downstream to connect the load/distribution transforming measuring absolute value more than 0, and supply without other power supply Electricity, then this switch/disconnecting link of accurate recognition is for closing position and being modified to close position;
State point position and measure absolute value switch/disconnecting link downstream more than 0 and do not have load/distribution transforming, switch/disconnecting link state and Measuring the situation of contradiction, this switch/disconnecting link remote signalling is suspicious;
Switch/disconnecting link state closes position, downstream load/distribution transforming and switch measure be 0 and upstream without the switch/cutter of point position Lock, then this switch/disconnecting link remote signalling is suspicious.
For the switch of wobble variation, owing to its time of day cannot be determined, use the above principle can be with accurate recognition Close position, or be recognized as suspicious point of position.
Detailed process is:
I) traversal measures the load/distribution transforming more than 0, the hierarchical relationship in topological tree find the on-load switch of upstream, if This on-load switch divides position, then this on off state mistake is described, and is modified to close position;
J) regular tap of position is divided to the direction of circuit head end traversal with line end, with this switch to line end (root Determine according to power flow direction) search for the load/distribution transforming measured more than 0 or be modified to close the switch of position, if searching, then this point of position Regular tap status error, and be modified to close position;If not searching the magnitude of current of the regular tap of load/distribution transforming and this point of position Survey more than 0, then illustrate that this point of bit switch state is suspicious;
K) traversal measurement is the load/distribution transforming of 0, according to the conjunction bit switch of the hierarchical relationship search upstream in topological tree, if The conjunction bit switch current measurement searched is 0, and this conjunction bit switch does not exist the switch of point position to root node, then illustrate that this closes position On off state is suspicious;
L) switch is after identification terminates, it is judged that the switch of the switch of accurate recognition/suspicious identification whether wobble variation, if so, Then save as and accurately close position or suspicious point of position.
In Fig. 2, switch k2, k3 are the switch that state is suspicious.
4, remote measurement polishing
After remote signalling identification, distribution sub-island generate, add up the injecting power of each junction point in each distribution sub-island, through with Lower process determines electric current and the power of branch road:
K) assume that the whole network voltage is root node voltage U, it is known that each junction point power, branch resistance G and reactance B parameter, depend on Branch power can be calculated according to following equation;
P i j = U i 2 G i j + U i U j ( G i j cos q i j + B i j sin q i j )
Q i j = N i 2 B i j + U i U j ( G i j sin q i j + B i j cos q i j )
L) against power flow direction, calculate forward with branch power according to node injecting power, calculate each branch power and electricity Stream;
M) along power flow direction, according to each branch power and first section of node voltage, branch voltage fall and each node electricity are calculated Pressure;
N) two processes of b, c are repeated, until the voltage difference of all nodes less than a limit value or reaches the meter specified Till calculating number of times;
O) close line segment serial number sec, zsec that the switch both sides of position connect, find with not line segment sequence number for the side of-1 Line segment, with this line segment electric current, meritorious, the electric current of idle polishing switch, power measurement;If sec Yu isec is-1, statistic switch The line segment that both sides connect, if the node number zbs of the line segment other end is more than the bs of switch, the most respectively by this line current, meritorious, nothing Merit is sued for peace, with the electric current of result polishing switch, power measurement after summation.
As shown in Figure 3: with electric current, the corresponding measurement of power sum polishing switch of line segment sec1, sec2, sec3.
5, cyclization analysis
After generating topological tree remote signalling identification, carry out sectional, bus analysis, electrical island analysis generation distribution sub-island. For closed loop design, the power distribution network of open loop operation, owing to switch combination operation, the remote signalling data problem of instantaneity cause between feeder line Cyclization.Show as searching another substation exit bus from a substation exit bus when electrical island is analyzed.Before employing Push back and cannot process the situation of cyclization between this feeder line for Load flow calculation, when generating distribution sub-island, by the feedback of cyclization between feeder line Line filters, and is not involved in Load flow calculation and measures polishing.Wherein, dual power supply (actual can only be passed through prepared auto restart by power supplying from one direction Equipment determines) situation be not belonging to cyclization, the load of dual power supply need to be split into two independent loads, respectively by two ends Power supply is powered, and cyclization filters out the situation of dual power supply when analyzing.
6, examination statistics
After remote signalling identification correction, with a point position state, the switch of power measurement is had to generate section for border, in section The switch of trip is that power flows into switch, and remaining flows out switch for power, and the difference calculating power carries out regional imbalance statistics, no Aequum comprises meritorious with idle;Setting voltage bound (such as: 10.7,9.3), busbar voltage measures compared with voltage bound Carrying out the out-of-limit statistics of busbar voltage, for single phase model, voltage takes AB phases line voltage;Take current measurement in A, B, C three-phase maximum Value carries out switching heavy duty/out-of-limit analysis with the rupturing capacity of switch, and being less than 100% more than setting value (such as: 80%) is heavy duty, greatly It is out-of-limit in 100%;The reason of topology failure feeder line is divided into: feeder line can not find bus, feeder line can not find service entrance switch and feeder line Between cyclization;During generating distribution sub-island, searching another outlet bus then cyclization with side substation exit bus, statistics is closed Ring feeder line;To each distribution sub-island, its island internal loading summation and service entrance switch power measurement carry out initial network loss statistics;Through examining Nuclear statistics function, the result of display state directly perceived estimation and effect.
7, daily load prediction
The partial data section that Historic Section Data Matching obtains, has 96 complete data section every day, by every day 96 Individual data section obtains 288 data section every day according to linear interpolation method, according to similar day (the 10 days forward date to be predicted The load data on similar date) and the Forecasting Methodology of linear extrapolation, for with adopting the distribution transforming that distribution transforming matches, carry out daily load Prediction.The load data of 24 hours days to be predicted can be predicted, carry out real-time status estimation in conjunction with distribution main website real time data.
The key problem in technology point of the present invention and to be intended to protect be a little what
1. the Historic Section number that electrical power distribution automatization system main website profile data mates with between extraction system distribution transforming profile data According to coupling.
2. annexation and hierarchical relationship, electriferous state, measuring value according to upstream and downstream equipment carry out switching/disconnecting link remote signalling Identification.
3. to switch the switching current of power flow solutions polishing measurement disappearance of associate device, quantity of power after approximation Load flow calculation Measured value, completes to switch remote measurement polishing.
4. load/distribution transforming the historical data of linear interpolation method completion disappearance, similar day is born with linear extrapolation prediction distribution transforming Lotus.

Claims (4)

1. the practical approach that a power distribution network simple state is estimated, it is characterised in that described method comprises the steps:
(1) Historic Section Data Matching
Read with extraction system 96 power curve data every day and corresponding section moment, access time in distribution main website section Closest to section and the section in first 5 minutes of this section moment and latter 5 minutes in this section moment, choose the power with adopting distribution transforming bent Line is gained merit data, sets up main website distribution transforming with adopting the matching relationship of distribution transforming by platform area code, breaks by calculating between two systems 3 The distribution transforming active power error matched in face, splices with extraction system with the main website section that error is minimum, with disconnected with adopting The face moment is as the section moment of section complete after splicing;With match with the power curve data assignment main website side adopting distribution transforming Distribution low-voltage winding power measures;
(2) power distribution network topological tree generates
First, Article 1 line bus1 and Article 2 line bus2 represents that between two feeder lines, interconnection switch closes the situation of position, works as Article 1 Line bus1, Article 2 line bus2 side load summation are all higher than or the power measurement (such as: 100kW) of the most respective service entrance switch Time, illustrate to measure and forbidden, the most do not generate topological tree;If Article 1 line bus1 side total load is less than Article 1 line bus1 side inlet wire Switch measures, and Article 2 line bus2 side total load measures more than Article 2 line bus2 side service entrance switch, and interconnection switch merit is described Rate is flowed to Article 2 line bus2 by Article 1 line bus1, by the service entrance switch of Article 2 line bus2 side, according to electrical connection Relationship traversal divides the regular tap of position, till the loading assembled is more than service entrance switch, by point bit switch of this switch upstream As untiing the switch of looped network, respectively Article 1 line bus1 is untied the switch of looped network for cut-off with Article 2 line bus2 side with this Condition generates topological tree;Vice versa;
Through above-mentioned steps, all feeder lines being generated topological tree, the process generating topological tree is: disregard the state of switch/disconnecting link, Carry out depth-first search with the interconnection switch of point position or the switch specified for border, generate comprise bus, switch/disconnecting link, The topological tree of load/distribution transforming equipment, searchable equipment;During topology, with the i.e. substation exit bus of root node to circuit End recursive search, and mark the flow direction of power, i.e. according to first searching nd or znd of equipment to determine the power of this equipment Flow to;
(3) switch remote signalling identification
Upstream and downstream topological relation, the state of upstream equipment and measuring value according to equipment, upstream device are the most charged, with or without other The information such as plant-grid connection state based on following principle judgement switch:
Divide position state of switch/disconnecting link downstream to connect the load/distribution transforming measuring absolute value more than 0, and power without other power supply, then This switch/disconnecting link of accurate recognition is for closing position and being modified to close position;
State point position and measurement absolute value switch/disconnecting link downstream more than 0 do not have load/distribution transforming, switch/disconnecting link state and measurement The situation of contradiction, this switch/disconnecting link remote signalling is suspicious;
Switch/disconnecting link state closes position, downstream load/distribution transforming and switch measure be 0 and upstream without the switch/disconnecting link of point position, then This switch/disconnecting link remote signalling is suspicious;
For the switch of wobble variation, owing to its time of day cannot be determined, use above principle can with accurate recognition for close position, Or it is recognized as suspicious point of position;
(4) remote measurement polishing
After remote signalling identification, distribution sub-island generate, add up the injecting power of each junction point in each distribution sub-island, through following mistake Journey determines electric current and the power of branch road:
A) assume that the whole network voltage is root node voltage U, it is known that each junction point power, branch resistance G and reactance B parameter, according under Row formula can calculate branch power;
P i j = U i 2 G i j + U i U j ( G i j cos q i j + B i j sin q i j )
Q i j = U i 2 B i j + U i U j ( G i j sin q i j + B i j c o s q i j )
B) against power flow direction, calculate forward with branch power according to node injecting power, calculate each branch power and electric current;
C) along power flow direction, according to each branch power and first node voltage, branch voltage fall is calculated;
D) two processes of b, c are repeated, until the voltage difference of all nodes less than a limit value or reaches the calculating time specified Till number;
E) close line segment serial number sec, zsec that the switch both sides of position connect, find line with not line segment sequence number for the side of-1 Section, with this line segment electric current, meritorious, the electric current of idle polishing switch, power measurement;If sec Yu isec is-1, statistic switch two The line segment that side connects, if the node number zbs of the line segment other end is more than the bs of switch, the most respectively by this line current, meritorious, idle Sue for peace, with the electric current of result polishing switch, power measurement after summation;
(5) cyclization analysis
After generating topological tree remote signalling identification, carry out sectional, bus analysis, electrical island analysis generation distribution sub-island;
(6) examination statistics
After remote signalling identification correction, with a point position state, the switch of power measurement is had to generate section for border, with section middle and upper reaches Switching and flow into switch for power, remaining flows out switch for power, and the difference calculating power carries out regional imbalance statistics, uneven Amount comprises meritorious with idle;Setting voltage bound, it is out-of-limit that busbar voltage measurement carries out busbar voltage compared with voltage bound Statistics, for single phase model, voltage takes AB phases line voltage, takes the blocking of current measurement maximum and switch in A, B, C three-phase and holds Amount carries out switching heavy duty/out-of-limit analysis;Being less than 100% more than setting value is heavy duty, is out-of-limit more than 100%;
The reason of topology failure feeder line is divided into: feeder line can not find bus, feeder line can not find cyclization between service entrance switch and feeder line;Generate During distribution sub-island, search another outlet bus then cyclization with side substation exit bus, add up cyclization feeder line;To often Individual distribution sub-island, its island internal loading summation and service entrance switch power measurement carry out initial network loss statistics;Through examination statistical function, The result of display state estimation directly perceived and effect;
(7) daily load prediction
The partial data section that Historic Section Data Matching obtains, has 96 complete data section every day, by number every day 96 288 data section every day are obtained according to linear interpolation method, according to similar day date the most to be predicted 10 days phases forward according to section Like load data and the Forecasting Methodology of linear extrapolation on date, for with adopting the distribution transforming that distribution transforming matches, carry out daily load pre- Survey;Predict the load data of 24 hours days to be predicted, carry out real-time status estimation in conjunction with distribution main website real time data.
The practical approach that a kind of power distribution network simple state the most according to claim 1 is estimated, it is characterised in that: described step (1) in, for a distribution transforming unmatched, occur the most in pairs, belonging to this distribution transforming if winding power measurement in high-pressure side is meritorious, idle The power factor of the service entrance switch of feeder line calculates idle, makes that distribution transforming high-pressure side is meritorious, idle measurement occurs in pairs;If main website high pressure Side load is without measuring, then the power measurement assignment high-pressure side winding power of the on-load switch connected with this distribution transforming measures, and wants equally Ensure meritorious, idle paired appearance.
The practical approach that a kind of power distribution network simple state the most according to claim 1 is estimated, it is characterised in that described step (3) detailed process is:
A) traversal measures the load/distribution transforming more than 0, the hierarchical relationship in topological tree find the on-load switch of upstream, if this is born Lotus switch point position, then illustrate this on off state mistake, and be modified to close position;
B) regular tap of position is divided to the direction of circuit head end traversal with line end, with this switch to line end (according to merit Rate flows to determine) search for the load/distribution transforming measured more than 0 or be modified to close the switch of position, if searching, then this point of position is general Open up off status mistake, and be modified to close position;If the current measurement not searching the regular tap of load/distribution transforming and this point of position is big In 0, then illustrate that this point of bit switch state is suspicious;
C) traversal measurement is the load/distribution transforming of 0, according to the conjunction bit switch of the hierarchical relationship search upstream in topological tree, if search To conjunction bit switch current measurement be 0, and there is not the switch of point position in this conjunction bit switch to root node, then illustrate that this closes bit switch State is suspicious;
D) switch is after identification terminates, it is judged that the switch of the switch of accurate recognition/suspicious identification whether wobble variation, the most then protect Save as and accurately close position or suspicious point of position.
The practical approach that a kind of power distribution network simple state the most according to claim 1 is estimated, it is characterised in that described step (5) in, for closed loop design, the power distribution network of open loop operation, owing to switch combination operation, the remote signalling data problem of instantaneity cause Cyclization between feeder line;Show as searching another substation exit bus from a substation exit bus when electrical island is analyzed, Push back before employing and cannot process the situation of cyclization between this feeder line for Load flow calculation, when generating distribution sub-island, will close between feeder line The feeder line of ring filters, and is not involved in Load flow calculation and measures polishing;Wherein, dual power supply is actual can only be passed through by power supplying from one direction The situation that prepared auto restart equipment determines is not belonging to cyclization, the load of dual power supply need to split into two independent loads, respectively Being powered by two ends power supply, cyclization filters out the situation of dual power supply when analyzing.
CN201610670874.7A 2016-08-15 2016-08-15 Practical method for estimating simple state of power distribution network Expired - Fee Related CN106208049B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610670874.7A CN106208049B (en) 2016-08-15 2016-08-15 Practical method for estimating simple state of power distribution network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610670874.7A CN106208049B (en) 2016-08-15 2016-08-15 Practical method for estimating simple state of power distribution network

Publications (2)

Publication Number Publication Date
CN106208049A true CN106208049A (en) 2016-12-07
CN106208049B CN106208049B (en) 2021-07-16

Family

ID=57521588

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610670874.7A Expired - Fee Related CN106208049B (en) 2016-08-15 2016-08-15 Practical method for estimating simple state of power distribution network

Country Status (1)

Country Link
CN (1) CN106208049B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107239848A (en) * 2017-04-14 2017-10-10 国网福建省电力有限公司泉州供电公司 Bad data recognition method based on load prediction
CN108429344A (en) * 2018-03-27 2018-08-21 国网山东省电力公司潍坊供电公司 A kind of substation equipment method of operation accuracy is from check method
CN108667013A (en) * 2018-05-22 2018-10-16 国网浙江省电力有限公司电力科学研究院 A kind of multi-source heterogeneous power distribution network position of the switch identification analysis method
CN109752629A (en) * 2017-11-07 2019-05-14 中国电力科学研究院有限公司 A kind of power grid measurement problem intelligent diagnosing method and system
CN110222469A (en) * 2019-06-21 2019-09-10 唐颖 A kind of circuital current voltage emulated computation method
CN110490464A (en) * 2019-08-21 2019-11-22 国网浙江省电力有限公司杭州供电公司 A kind of urban power distribution network power supply capacity Tapping Potential Method based on line load recombination
CN111064180A (en) * 2019-10-23 2020-04-24 国网天津市电力公司电力科学研究院 Medium-voltage distribution network topology detection and identification method based on AMI power flow matching
CN111224385A (en) * 2019-12-09 2020-06-02 国网江苏省电力有限公司镇江供电分公司 Disconnection protection method for comparing voltage amplitude difference of two side wires of line and matching of spare power automatic switching
CN111756031A (en) * 2019-03-29 2020-10-09 中国电力科学研究院有限公司 Power grid operation trend estimation method and system
CN112803402A (en) * 2021-02-23 2021-05-14 重庆大学 Radiation network forward-push back substitution robust state estimation method containing bad data preprocessing
CN113258578A (en) * 2021-06-16 2021-08-13 北京德风新征程科技有限公司 Power flow data generation method and device, electronic equipment and computer readable medium
CN114725941A (en) * 2022-06-09 2022-07-08 沈阳易鑫泰电力科技有限公司 Rural overhead power distribution network frame reconstruction system and automatic reconstruction method
CN116961012A (en) * 2023-09-21 2023-10-27 国网吉林省电力有限公司松原供电公司 Controllable load switch identification method and system based on shortest path search out-of-limit equipment

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102185315A (en) * 2011-05-16 2011-09-14 广东电网公司深圳供电局 Enhanced-message-service (EMS)-based method for reconstructing 110kV regional grid network
CN102522824A (en) * 2011-12-26 2012-06-27 国电南瑞科技股份有限公司 Distributed state estimation calculation method based on centralized control station scheduling main station
CN103077480A (en) * 2013-01-07 2013-05-01 中国电力科学研究院 Safety checking method for power system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102185315A (en) * 2011-05-16 2011-09-14 广东电网公司深圳供电局 Enhanced-message-service (EMS)-based method for reconstructing 110kV regional grid network
CN102522824A (en) * 2011-12-26 2012-06-27 国电南瑞科技股份有限公司 Distributed state estimation calculation method based on centralized control station scheduling main station
CN103077480A (en) * 2013-01-07 2013-05-01 中国电力科学研究院 Safety checking method for power system

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107239848A (en) * 2017-04-14 2017-10-10 国网福建省电力有限公司泉州供电公司 Bad data recognition method based on load prediction
CN109752629A (en) * 2017-11-07 2019-05-14 中国电力科学研究院有限公司 A kind of power grid measurement problem intelligent diagnosing method and system
CN108429344A (en) * 2018-03-27 2018-08-21 国网山东省电力公司潍坊供电公司 A kind of substation equipment method of operation accuracy is from check method
CN108667013B (en) * 2018-05-22 2020-08-11 国网浙江省电力有限公司电力科学研究院 Method for identifying and analyzing switch positions of multi-source heterogeneous power distribution network
CN108667013A (en) * 2018-05-22 2018-10-16 国网浙江省电力有限公司电力科学研究院 A kind of multi-source heterogeneous power distribution network position of the switch identification analysis method
CN111756031A (en) * 2019-03-29 2020-10-09 中国电力科学研究院有限公司 Power grid operation trend estimation method and system
CN111756031B (en) * 2019-03-29 2023-11-03 中国电力科学研究院有限公司 Power grid operation trend estimation method and system
CN110222469A (en) * 2019-06-21 2019-09-10 唐颖 A kind of circuital current voltage emulated computation method
CN110222469B (en) * 2019-06-21 2023-04-07 唐颖 Circuit current and voltage simulation calculation method
CN110490464A (en) * 2019-08-21 2019-11-22 国网浙江省电力有限公司杭州供电公司 A kind of urban power distribution network power supply capacity Tapping Potential Method based on line load recombination
CN110490464B (en) * 2019-08-21 2023-01-20 国网浙江省电力有限公司杭州供电公司 Urban power distribution network power supply capacity diving method based on line load recombination
CN111064180A (en) * 2019-10-23 2020-04-24 国网天津市电力公司电力科学研究院 Medium-voltage distribution network topology detection and identification method based on AMI power flow matching
CN111064180B (en) * 2019-10-23 2024-01-26 国网天津市电力公司电力科学研究院 Medium-voltage distribution network topology detection and identification method based on AMI (advanced mechanical arm) power flow matching
CN111224385A (en) * 2019-12-09 2020-06-02 国网江苏省电力有限公司镇江供电分公司 Disconnection protection method for comparing voltage amplitude difference of two side wires of line and matching of spare power automatic switching
CN112803402A (en) * 2021-02-23 2021-05-14 重庆大学 Radiation network forward-push back substitution robust state estimation method containing bad data preprocessing
CN112803402B (en) * 2021-02-23 2023-03-31 重庆大学 Radiation network forward-push back substitution robust state estimation method containing bad data preprocessing
CN113258578B (en) * 2021-06-16 2021-10-15 北京德风新征程科技有限公司 Power flow data generation method and device, electronic equipment and computer readable medium
CN113258578A (en) * 2021-06-16 2021-08-13 北京德风新征程科技有限公司 Power flow data generation method and device, electronic equipment and computer readable medium
CN114725941A (en) * 2022-06-09 2022-07-08 沈阳易鑫泰电力科技有限公司 Rural overhead power distribution network frame reconstruction system and automatic reconstruction method
CN116961012A (en) * 2023-09-21 2023-10-27 国网吉林省电力有限公司松原供电公司 Controllable load switch identification method and system based on shortest path search out-of-limit equipment
CN116961012B (en) * 2023-09-21 2024-01-16 国网吉林省电力有限公司松原供电公司 Controllable load switch identification method and system based on shortest path search out-of-limit equipment

Also Published As

Publication number Publication date
CN106208049B (en) 2021-07-16

Similar Documents

Publication Publication Date Title
CN106208049A (en) The practical approach that a kind of power distribution network simple state is estimated
CN110120668B (en) Method and system for automatically identifying distribution area topology
CN103413044B (en) A kind of electric system local topology method of estimation based on transformer station's measurement information
CN113078630B (en) Low-voltage distribution network topology identification method based on real-time measurement data
CN101777757A (en) Small current grounding route selection method
CN110289613A (en) The identification of distribution net topology and line parameter circuit value discrimination method based on sensitivity matrix
EP3642636B1 (en) Method for detecting impedances in an electrical power distribution grid
CN108711852A (en) A kind of distribution network failure parametric sensitivity computational methods based on fault estimator
More et al. A literature review on optimal placement of phasor measurement units
US11824354B2 (en) Online state estimation and topology identification using advanced metering infrastructure (AMI) measurements
CN104821657B (en) Data identification implementation method based on SSD models
Gamm et al. New EPS state estimation algorithms based on the technique of test equations and PMU measurements
CN104537161A (en) Medium voltage distribution network diagnostic analysis method based on power supply safety standards
Asprou et al. The effect of PMU measurement chain quality on line parameter calculation
Janssen et al. Monitoring, protection and fault location in power distribution networks using system-wide measurements
Wellssow et al. Identification of topology faults by smart meter data in meshed low voltage grids
CN107565549A (en) A kind of Power System Network Topology Analysis Using method measured based on synchronized phasor
Wang et al. Generate distribution circuit model using AMI data
CN110780129A (en) Electricity stealing and leakage positioning method based on current deviation analysis technology
Yamashita et al. Predicting power system voltage health index with PMUs and graph convolutional networks
CN105044517A (en) Intelligent transformer station protection vector diagnosis method based on trend characteristic value
CN107565547A (en) A kind of power distribution network operation reliability evaluation and optimization system
Farzanehrafat Power quality state estimation
Peppanen et al. Secondary circuit model creation and validation with AMI and transformer measurements
Pereira et al. Fault location algorithm for primary distribution feeders based on voltage sags

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210716