CN1062045C - Dusting stirring extruding compact pile forming technology - Google Patents

Dusting stirring extruding compact pile forming technology Download PDF

Info

Publication number
CN1062045C
CN1062045C CN 97119862 CN97119862A CN1062045C CN 1062045 C CN1062045 C CN 1062045C CN 97119862 CN97119862 CN 97119862 CN 97119862 A CN97119862 A CN 97119862A CN 1062045 C CN1062045 C CN 1062045C
Authority
CN
China
Prior art keywords
drilling rod
pile
hole
aggregate
spiral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 97119862
Other languages
Chinese (zh)
Other versions
CN1186891A (en
Inventor
秦忠泽
秦洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 97119862 priority Critical patent/CN1062045C/en
Publication of CN1186891A publication Critical patent/CN1186891A/en
Application granted granted Critical
Publication of CN1062045C publication Critical patent/CN1062045C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The present invention provides technology for the filed cast of concrete piles in foundation engineering. The present invention is characterized in that a spiral driller drills holes in the mode of positive rotation and then rotates reversely; when the spiral driller rotates reversely, skeletal material is added and squeezed to be dense, and powdery material is injected from a drill tip through a drill rod central hole by using compressed air; the skeletal material, the powdery material and interstitial water are sufficiently stirred through the reverse rotation of blades and squeezed into a pile. The pile formation process of the technology is continuous, and the spiral driller rotates reversely to squeeze the material from the bottom of a hole to the top of the pile step by step; therefore, the technology can overcome the defects of constriction, pile breakage, separation, hole bottom sediment, etc. The present invention has the advantages of high quality of pile bodies, little cement consumption quantity and low cost, and is particularly suitable for low-intensity concrete piles.

Description

A kind of job practices of in situ pile
The present invention relates to the technology of in-site pouring concrete in the Foundation Design or similar concrete pile, especially build stake without mould-pipe or other template.
At present, the method for in-site pouring concrete pile has perfusion in the immersed tube pipe, catheter perfusion, pressure injection.Tube-sinking cast-in-situ pile is a method of using vibration or hammering, and steel pipe is sunk in the soil, and concrete perfusion in pipe falls into the hole pile with concrete by the pipe end during tube drawing then, and its defective is big, the easy broken pile of vibrating noise, is unsuitable for constructing in the urban district.
The catheter perfusion stake is to utilize conduit concrete to be poured into the method for pile in the boring behind the pore-forming, the shortcoming of this method is that the tube drawing height be difficult for to be grasped, and forms defectives such as broken pile, necking down, segregation, folder mud, sediment are thick easily, because of the need concrete flowability big, cement consumption is big, the cost height.
The pressure injection stake be with press water mud, mortar or concrete by the drilling rod center by the apex point injection hole that falls at the bottom of the hole at the bottom of, the slurry that the water in the hole is injected into ejects ground, drops into aggregate then, to the stake top.China's patent gazette disclosed application number on June 14th, 95 is 93120641.3, name is called " piling technology by depositing concrete into cement slurry in hole ", on April 21st, 95 disclosed application number be 93115834.6, to be called " process of stake on the perfusion reinforced concrete " be exactly two examples to name.The defective of pressure injection stake is that required concrete flowability is higher, and cement consumption is more, waste is big, cost is high.
The technology that the purpose of this invention is to provide the in-site pouring concrete pile that a kind of cost is low, pile quality is high, easy to operation.
Technical scheme of the present invention is: just changing into the hole with auger machine, not blocked for guaranteeing bit nozzle, in pore-forming and whereabouts drilling rod process, be blown into compressed air by the drilling rod center, aggregate is sent into compacted from the stake hole by helical blade during counter-rotating, and then the pulverulent material of cement and mixing thereof sent into by apex point by the drilling rod centre bore with compressed air spray, aggregate, pulverulent material and interstitial water are fully stirred by the counter-rotating of drilling rod blade and are compacted, compacted along with filler, drilling rod slowly rises, and all forms until pile body.
Owing to take technique scheme, counter-rotating by the rig blade, it is compacted that aggregate, powder and interstitial water are fully stirred, form harder concrete, because of formation of pile auger machine counter-rotating compacted continuously to the stake top at the bottom of being, so can overcome drawback such as sediment at the bottom of concrete pile necking down, broken pile, segregation, the hole, the pile quality height, especially more suitable to Low Intensity Concrete Piles.Comparing with the pressure injection stake, is not free-flowing material because of what add, and required cement consumption is few, and cost is low; Cause does not adopt conduit, immersed tube etc., so labour intensity is low, and is easy and simple to handle.
Further describe below in conjunction with embodiments of the invention:
Embodiment:
1, it is meter dark that auger machine is just being changeed boring to 10, in boring, be blown into compressed air, 2, drilling rod is proposed to remove clean earth, put a funnel in aperture, stake hole, again drilling rod is fallen, 3, when falling, continues by drilling rod in the drilling rod centre bore, to be blown into compressed air with non-fouling nozzle, after drilling rod drops down onto at the bottom of the hole, drilling rod is reversed, the blade that reaches by counter-rotating from the stake hole different stone of particle diameter of packing into simultaneously, the aggregate that aggregate chips or coarse sand are formed, discharge the part water in the aggregate in the compacted process, the drilling rod counter-rotating sprays into every cubic metre of 210 kilograms of No. 325 dry powder cement by the drilling rod centre bore more then, the drilling rod blade that continues counter-rotating is with pulverulent material, aggregate, and the interstitial water between aggregate fully stirs and compacted 4, the drilling rod of counter-rotating is slowly risen, continue filler again and form until pile body.

Claims (1)

1, a kind of job practices of in situ pile, it comprises the steps: a, auger machine just changeed holing to desired depth, at pore-forming be lowered in the process of drilling rod and be blown into compressed air by the drilling rod center, b, drilling rod is proposed to remove clean earth, drilling rod is fallen at the bottom of the hole again, c, drilling rod is reversed, it is compacted to send into aggregate from the stake hole by blade simultaneously, d, spray into the pulverulent material of cement or its compound by the drilling rod centre bore, the drilling rod blade that continues counter-rotating is with pulverulent material, aggregate, and the interstitial water between aggregate fully stirs and compacted e, along with filler, drilling rod slowly rises, and all forms until pile body.
CN 97119862 1997-12-26 1997-12-26 Dusting stirring extruding compact pile forming technology Expired - Fee Related CN1062045C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 97119862 CN1062045C (en) 1997-12-26 1997-12-26 Dusting stirring extruding compact pile forming technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 97119862 CN1062045C (en) 1997-12-26 1997-12-26 Dusting stirring extruding compact pile forming technology

Publications (2)

Publication Number Publication Date
CN1186891A CN1186891A (en) 1998-07-08
CN1062045C true CN1062045C (en) 2001-02-14

Family

ID=5175623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 97119862 Expired - Fee Related CN1062045C (en) 1997-12-26 1997-12-26 Dusting stirring extruding compact pile forming technology

Country Status (1)

Country Link
CN (1) CN1062045C (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1307262C (en) * 2003-01-10 2007-03-28 中国科学院成都有机化学研究所 Nano high-molecular microsphere with conductivity and magnetism and its preparation method
EP2213802B1 (en) * 2009-02-02 2012-10-10 BAUER Maschinen GmbH Supply device for supplying concrete and glass into the drill ribbon of a drilling device when creating a concrete borehole and method for setting a concrete borehole
CN105649053A (en) * 2016-02-05 2016-06-08 沙焕焕 Construction method of multielement stiffness composite pile

Also Published As

Publication number Publication date
CN1186891A (en) 1998-07-08

Similar Documents

Publication Publication Date Title
US11214938B2 (en) Construction method for pouring concrete in karst cave
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
CN101532290B (en) Granule grouting pile of ripple plastic sleeve with hole for strengthening soft soil foundation and strengthening method
CN206956714U (en) Down-the-hole impacts rotating spraying mixture pile construction equipment
CN105604001B (en) Drilling tool is stirred in the stake of stiff-core cement soil cylinder and the rotation of construction method and tubular
CN100519951C (en) Construction method for increasing dry auger boring pouring pile bearing capacity
CN1814915A (en) Apparatus and method for long spiral-drilling enlarging-base agitation and reaming-in-hole concrete filling to form pile
CN201395793Y (en) Long spiral high-pressure spraying mud injecting stirring pile-forming device
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
JP2008088746A (en) Replacing construction method of column
CN109183790A (en) A kind of Screw Pile and its construction tool and construction method
CN103603344A (en) Rotary drilling and pile filling construction method capable of preventing hole collapse
CN104846820B (en) Hold type screw-type Squeezing Soil Pile pile-forming equipment and bore forming method in a kind of end
CN106481277A (en) High pressure base expanding and base expanding screw rod drilling equipment and its stake end enlarged footing
CN116427396A (en) Stirring pile construction method and composite pile construction method thereof
CN1062045C (en) Dusting stirring extruding compact pile forming technology
CN1202318C (en) Method and apparatus for pile making by boring and pumping mass concrete and rotation jetting slurry
CN106049462A (en) Displacement pile and construction method and drilling tool thereof
CN110924385B (en) High-pressure jet grouting pile construction process
CN106759296A (en) Drainable irregular-section bamboo joint pipe pile and root planting type construction method thereof
CN103603345A (en) Cement mixing grouting pile foundations and forming method
CN1109793C (en) Method and apparatus for triple pipe rotary spray of reinforced concrete pile foundation
CN103711121B (en) The underlying original state in stake top fetches earth the construction method of cast-with-pressure concrete pile
CN209162815U (en) A kind of Screw Pile and its construction tool
CN208415227U (en) A kind of mold-bagged concrete stake

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee