CN106193747B - Stacked Self-resetting energy dissipation brace in a kind of assembling - Google Patents

Stacked Self-resetting energy dissipation brace in a kind of assembling Download PDF

Info

Publication number
CN106193747B
CN106193747B CN201610584720.6A CN201610584720A CN106193747B CN 106193747 B CN106193747 B CN 106193747B CN 201610584720 A CN201610584720 A CN 201610584720A CN 106193747 B CN106193747 B CN 106193747B
Authority
CN
China
Prior art keywords
spring
guide rod
baffle
word pattern
outer tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610584720.6A
Other languages
Chinese (zh)
Other versions
CN106193747A (en
Inventor
徐龙河
要世乾
李忠献
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiaotong University
Original Assignee
Beijing Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiaotong University filed Critical Beijing Jiaotong University
Priority to CN201610584720.6A priority Critical patent/CN106193747B/en
Publication of CN106193747A publication Critical patent/CN106193747A/en
Application granted granted Critical
Publication of CN106193747B publication Critical patent/CN106193747B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • E04H9/022Bearing, supporting or connecting constructions specially adapted for such buildings and comprising laminated structures of alternating elastomeric and rigid layers

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Vibration Prevention Devices (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

Stacked Self-resetting energy dissipation brace in a kind of assembling of the present invention, including outer tube, yi word pattern bar and guide rod, the middle part of guide rod is equipped with medium altitude groove, in the medium altitude groove of yi word pattern bar insertion guide rod, yi word pattern bar is fixedly connected with guide rod by high-strength bolt, and friction plate is equipped between yi word pattern bar and guide rod.The first spring, second spring, the 3rd spring and the 4th spring are arranged on guide rod between adjacent block, outer tube is set in outside guide rod, the both ends of outer tube are fixed with end plate and outer tube left side end plate on the right side of outer tube, the left end of yi word pattern bar is pierced by end plate on the left of outer tube, and the right end of the guide rod is pierced by end plate on the right side of outer tube.The main stress of the invention is an entirety with force-transmitting part, it avoids the steel microstructure caused by welding and mechanical performance changes and welding residual stress, stress performance is more stablized, and main resetting apparatus and rubbing device are clear and definite, structure unitary construction is simple, processing with it is easy for installation.

Description

Stacked Self-resetting energy dissipation brace in a kind of assembling
Technical field
The present invention relates to Self-resetting energy dissipation brace technical fields, and in particular to stacked Self-resetting energy consumption branch in a kind of assembling Support.
Background technology
China is an earthquake-prone countries, and earthquake causes the damage of building even to collapse, and is brought substantial amounts of Casualties and economic loss.China's current seismic design specification uses Ductility Design thought, passes through the elastoplasticity of structural elements Earthquake energy is deformed, expenditure of construction is reduced while structural seismic capacity is improved.But after shake, the residual deformation of component The normal use of structure can be influenced, while brings the rehabilitation expense of great number or even structure can only be pushed over to reconstruction.It is asked to solve this Topic, researcher propose to add energy dissipation brace system in structure, are supported when earthquake occurs and play energy consumption effect, dissipation seismic energy Amount protects main member, and reduces structure relative storey displacement angle.The structural seismic capacity of additional energy dissipation brace is improved, But residual deformation angle is still a problem, therefore researcher proposes Self-resetting energy dissipation brace on the basis of energy dissipation brace, This residual deformation that structure can be decreased or even eliminated while be supported on energy consumption, the time required to reducing structure repair and takes With.
Support can be divided into according to working method and design feature:Common support, anti-buckling support and Self-resetting energy dissipation brace. Common support is consumed energy using the surrender of Low Yield Point Steel, and anti-buckling support phase is more excellent to common support performance, is eliminated common The asymmetric problem of tensile and compressive property is supported, dissipative system is combined by Self-resetting support with Self-resetting system, has excellent consumption Can ability and self-resetting capability, Self-resetting system is mainly by deformed bar or the novel intelligent material group with reset capability Into.
From working performance, more than several be supported by following features:Common support slenderness ratio is larger, and when compression is easy Buckling causes the reciprocal poor performance of its tension and compression, and hysteresis loop is not asymmetric, full, and energy dissipation capacity declines to a great extent after compressive buckling, It is difficult to effectively to consume earthquake and is passed to energy, meanwhile, under big shake effect, support is subject to reciprocating load, and component is in itself and connection System is susceptible to destruction so that common support functional reliability is very low;Anti-buckling be supported on the basis of common support increases about Beam mechanism, constraint inner tube energy consumption section ensure that tensile and compressive property etc. of support is full to, hysteresis loop, there is very strong energy dissipation capacity, but The problem of this support system is maximum is to surrender under geological process, and there are larger residual deformations after shake so that reinforcing is repaiied Multiple difficulty, which increases or even exists, is difficult to the situation repaired, and causes serious economic loss;Self-resetting support has reset function, It spontaneous can be resetted in its normal work stage, this characteristic can decrease or even eliminate the residual deformation of structure, reset system System generally use marmem or deformed bar.The elasticity of marmem is good, has self-resetting capability, can be real The Self-resetting now supported, but Properties of Shape-Memory Alloys is affected by temperature so that the feasibility of the support in practical applications It substantially reduces;The flexible deformation of deformed bar is small, limits the application of the support system.
From structure composition:Common support and buckling-resistant support structure form are simple, assembled position generally use weldering Realization is connect, has residual deformation and residual stress;Self-resetting support construction using marmem or presstressed reinforcing steel is usual Equipped with inner tube and outer tube, resetting apparatus and rubbing device are arranged between inner and outer pipes, while reasonable Arrangement is needed to reset system, therefore Self-resetting support structure is complicated, and connecting portion is mainly realized by welding, and be easy to cause residual deformation and residual stress.
Accordingly, it is desirable to provide stacked Self-resetting energy dissipation brace in a kind of assembling, using pre-compressed spring as a kind of reset material Material consumes energy in combination with friction plate, and the collaborative work for resetting system and dissipative system so that the hysteresis loop of the system is full, residual It is remaining to be deformed into zero, there is excellent reseting performance and energy-dissipating property, it is on the other hand complicated to solve other Self-resetting support structures And the problem of needing welding, propose stacked Self-resetting energy dissipation brace in assembling.
The content of the invention
The technical problem to be solved in the present invention is to provide stacked Self-resetting energy dissipation braces in a kind of assembling, solve existing common The tension and compression of support are asymmetric, hysteresis loop is not full, have residual deformation, shape memory alloy properties under anti-buckling support geological process The shortcomings that being affected by temperature, proposes stacked Self-resetting energy dissipation brace in assembling, and component species is few, and structure type is simple, processing It is convenient, it is easy to mass production, assembly line processing.System stiffness can be changed by adjusting spring specification simultaneously, by changing The energy consumption of system can be changed by becoming dissipative system parameter, have good controllability, can extensive use.
In order to solve the above technical problems, the present invention uses following technical proposals:
Stacked Self-resetting energy dissipation brace in a kind of assembling, including outer tube, yi word pattern bar and guide rod, in the guide rod Portion is equipped with medium altitude groove, and the outer surface of the guide rod is from left to right equipped with the first block of guide rod, guide rod second gear successively Block, guide rod third gear block, guide rod fourth gear block and guide rod fifth gear block are equipped with bolt hole, institute between adjacent block The front side edge and back side edge for stating yi word pattern bar are from left to right equipped with the first block of yi word pattern bar, yi word pattern bar second gear successively Block, yi word pattern bar third gear block, yi word pattern bar fourth gear block and yi word pattern bar fifth gear block, the middle part of the yi word pattern bar are equipped with Bolt straight slot, in the medium altitude groove of yi word pattern bar insertion guide rod, the bolt straight slot of the yi word pattern bar and guide rod Bolt hole is fixedly connected by the first high-strength bolt, the second high-strength bolt, the 3rd high-strength bolt and the 4th high-strength bolt, and described one Upper friction plate is equipped between the upper surface of font bar and guide rod, is equipped with down between the lower surface of the yi word pattern bar and guide rod Friction plate.
From left to right it is arranged with the first spring, second spring, the 3rd bullet on the guide rod between adjacent block successively Spring and the 4th spring, the both ends of first spring are equipped with baffle and the first spring right-hand apron on the left of the first spring, and described the The both ends of two springs are equipped with baffle and second spring right-hand apron on the left of second spring, and the both ends of the 3rd spring are equipped with the 3rd Baffle and the 3rd spring right-hand apron on the left of spring, the both ends of the 4th spring are equipped with baffle and the 4th bullet on the left of the 4th spring Spring right-hand apron is respectively equipped on the outside of baffle and the first spring right-hand apron on the left of first spring attached on the left of the first spring Add the outside point of additional stops on the right side of baffle and number one spring, the second spring left side baffle and second spring right-hand apron Not She You additional stops on the right side of additional stops and second spring on the left of second spring, baffle and the 3rd bullet on the left of the 3rd spring Additional stops and the 3rd spring right side additional stops, the 4th bullet on the left of the 3rd spring are respectively equipped on the outside of spring right-hand apron On the left of spring additional stops and the 4th spring right side on the left of the 4th spring are respectively equipped on the outside of baffle and the 4th spring right-hand apron Additional stops.
The outer tube is set in outside guide rod, and the both ends of the outer tube are fixed with end plate and outer tube left-hand end on the right side of outer tube Plate, the left end of the yi word pattern bar are pierced by end plate on the left of outer tube, and the right end of the guide rod is pierced by end plate on the right side of outer tube.
Preferably, the outer diameter of first spring, second spring, the 3rd spring and the 4th spring is respectively less than the interior of outer tube Footpath.First spring, second spring, the internal diameter of the 3rd spring and the 4th spring are more than the outer ruler of guide rod and yi word pattern bar It is very little.First spring, second spring, the 3rd spring and the 4th spring opposite on the guide bar can slide.
Preferably, baffle, the first spring right-hand apron, second spring left side baffle, the second bullet on the left of first spring Gear on the right side of baffle, the 3rd spring right-hand apron, the 4th spring left side baffle and the 4th spring on the left of spring right-hand apron, the 3rd spring Plate is the circular baffle plate of intermediate making circular hole, and outer diameter is respectively less than the internal diameter of outer tube, and the diameter of intermediate round hole is more than guide rod With the outside dimension of the block of yi word pattern bar, the difficulty of assembling is reduced, while each spring stop can occur relatively on the guide bar It slides.Spring stop is used for connecting spring, squeezes spring and transfers the power between guide rod and yi word pattern bar.
Preferably, additional stops, number one spring right side additional stops, second spring left side are attached on the left of first spring Add baffle, second spring right side additional stops, the 3rd spring left side additional stops, the 3rd spring right side additional stops, the 4th bullet Additional stops and the 4th spring right side additional stops open the circular baffle plate of rectangular opening for centre on the left of spring, and outer diameter is respectively less than outer tube Internal diameter, the size in intermediate rectangular hole is more than the outside dimension of guide rod and yi word pattern bar, less than guide rod and the gear of yi word pattern bar The outside dimension of block.Spring additional stops are assembled by high-strength bolt by the identical Semicircular baffle of two shapes, spring Additional stops ensure that spring stop can be free to slide in the case where yi word pattern pole spacing block is subject to be promoted with guide rod block.
Preferably, the material of end plate is normal carbon structure Q235 steel on the left of the outer tube, outer tube right side end plate and outer tube. First spring, second spring, the material of the 3rd spring and the 4th spring are 60CrMnA.The yi word pattern bar, guide rod, Baffle, the first spring right-hand apron, second spring left side baffle, second spring right-hand apron, the 3rd spring on the left of first spring Left side baffle, the 3rd spring right-hand apron, the 4th spring left side baffle, the material of the 4th spring right-hand apron are low-alloy high-strength Spend structure Q345 steel.First high-strength bolt, the second high-strength bolt, the material of the 3rd high-strength bolt and the 4th high-strength bolt are 20MnTiB, intensity are 10.9 grades.
Beneficial effects of the present invention are as follows:
Stacked Self-resetting energy dissipation brace is as a result of above technical scheme, main member in a kind of assembling of the present invention It is obtained by milling, main stress is an entirety with force-transmitting part, and main force part does not weld, avoids causing because of welding Steel microstructure and mechanical performance changes and welding residual stress so that behavior of members under loading more stablize.Assembling Interior stacked Self-resetting energy dissipation brace generally assembled, main resetting apparatus and rubbing device are clear and definite, and structure unitary construction is simple, Used component species is few so that the processing of support with it is easy for installation.
With conventional support, it is anti-buckling support, using the self-recovery energy dissipation brace of marmem, using deformed bar Self-recovery energy dissipation brace compared to having the advantage that:
(1) compared with conventional support, dissipative system is used by stacked Self-resetting energy dissipation brace in assembling of the invention Friction energy-dissipating system, by the friction of friction plate come the seismic energy that dissipates, while this is supported on tensile and compressive property etc. under geological process To, i.e. hysteresis loop symmetry is good, and shape is full, and energy-dissipating property is excellent, using the structure of the support after shake residual deformation It is smaller or there is no residual deformation, while the support structure configuration is simple, simple to install is feasible, is safeguarded after shake, replaces easy, contracting The time of structure normal use is influenced after short shake.
(2) with anti-buckling support phase ratio, stacked Self-resetting energy dissipation brace can effectively eliminate structure in assembling of the invention Residual deformation, reduce shake after structure repair expense.
(3) compared with using the Self-resetting energy dissipation brace of marmem, in normal operation, stacked in assembling The performance of Self-resetting energy dissipation brace be affected by temperature it is small, have good applicability.
(4) compared with using the Self-resetting energy dissipation brace of deformed bar, the row of stacked Self-resetting energy dissipation brace in assembling Cheng Geng great, that is, deformability is stronger, can meet the deformation requirements of general structure.
Description of the drawings
The specific embodiment of the present invention is described in further detail below in conjunction with the accompanying drawings.
Fig. 1 shows the structure diagram of stacked Self-resetting energy dissipation brace in a kind of assembling of the present invention.
Fig. 2 shows the outer tube of stacked Self-resetting energy dissipation brace in a kind of assembling of the present invention, end plate and outer tube on the left of outer tube The structure diagram of right side end plate.
Fig. 3 shows the guide rod main structure diagram of stacked Self-resetting energy dissipation brace in a kind of assembling of the present invention.
Fig. 4 shows the guide rod overlooking the structure diagram of stacked Self-resetting energy dissipation brace in a kind of assembling of the present invention.
Fig. 5 shows the yi word pattern bar main structure diagram of stacked Self-resetting energy dissipation brace in a kind of assembling of the present invention.
Fig. 6 shows the yi word pattern bar overlooking the structure diagram of stacked Self-resetting energy dissipation brace in a kind of assembling of the present invention.
Fig. 7 shows the A-A directional profile schematic diagrames in Fig. 1 of the present invention.
Fig. 8 shows the B-B directional profile schematic diagrames in Fig. 1 of the present invention.
Fig. 9 shows the C-C directional profile schematic diagrames in Fig. 1 of the present invention.
It is respectively marked in figure as follows:1 yi word pattern bar, 2 guide rods, 3 outer tubes, 4 outer tubes right side end plate, 5 outer tubes left side end plate, 6 Baffle on the left of first spring, 7 first spring right-hand aprons, 8 second springs left side baffle, 9 second spring right-hand aprons, 10 the 3rd Baffle on the left of spring, 11 the 3rd spring right-hand aprons, 12 the 4th springs left side baffle, 13 the 4th spring right-hand aprons, 14 first Additional stops on the left of spring, 15 number one springs right side additional stops, 16 second springs left side additional stops, 17 second springs are right Side additional stops, 18 the 3rd springs left side additional stops, 19 the 3rd springs right side additional stops, 20 the 4th springs left side additional gear position Plate, 21 the 4th springs right side additional stops, 22 first high-strength bolts, 23 second high-strength bolts, 24 the 3rd high-strength bolts, 25 the 4th High-strength bolt, friction plate on 26,27 times friction plates, 28 the first blocks of guide rod, 29 the second blocks of guide rod, 30 guide rods the 3rd Block, 31 guide rod fourth gear blocks, 32 guide rod fifth gear blocks, 33 the first blocks of yi word pattern bar, 34 the second blocks of yi word pattern bar, 35 yi word pattern bar third gear blocks, 36 yi word pattern bar fourth gear blocks, 37 yi word pattern bar fifth gear blocks, 38 first springs, 39 second bullets Spring, 40 the 3rd springs, 41 the 4th springs.
Specific embodiment
In order to illustrate more clearly of the present invention, the present invention is done further with reference to preferred embodiments and drawings It is bright.Similar component is indicated with identical reference numeral in attached drawing.It will be appreciated by those skilled in the art that institute is specific below The content of description is illustrative and be not restrictive, and should not be limited the scope of the invention with this.
As shown in Fig. 1-Fig. 9, stacked Self-resetting energy dissipation brace in a kind of assembling including outer tube 3, yi word pattern bar 1 and is oriented to Bar 2, the middle part of the guide rod 2 are equipped with medium altitude groove, and the outer surface of the guide rod 2 is from left to right equipped with guide rod the successively One block 28, the second block of guide rod 29, guide rod third gear block 30, guide rod fourth gear block 31 and guide rod fifth gear block 32, bolt hole is equipped between adjacent block, the front side edge and back side edge of the yi word pattern bar 1 are from left to right equipped with one successively The first block of font bar 33, the second block of yi word pattern bar 34, yi word pattern bar third gear block 35, yi word pattern bar fourth gear block 36 and one Font bar fifth gear block 37, the middle part of the yi word pattern bar 1 are equipped with bolt straight slot, and the yi word pattern bar 1 is inserted into guide rod 2 In empty groove, the bolt straight slot of the yi word pattern bar 1 is high-strength by the first high-strength bolt 22, second with the bolt hole of guide rod 2 Bolt 23, the 3rd high-strength bolt 24 are fixedly connected with the 4th high-strength bolt 25, upper surface and the guide rod 2 of the yi word pattern bar 1 Between be equipped with upper friction plate 26, between the lower surface of the yi word pattern bar 1 and guide rod 2 be equipped with lower friction plate 27.
From left to right it is arranged with the first spring 38, second spring 39, on the guide rod 2 between adjacent block successively Three springs 40 and the 4th spring 41, the both ends of first spring 38 are equipped on the left of the first spring on the right side of 6 and first spring of baffle Baffle 7, the both ends of the second spring 39 are equipped with baffle 8 and second spring right-hand apron 9, the 3rd bullet on the left of second spring The both ends of spring 40 are equipped with 10 and the 3rd spring right-hand apron 11 of baffle on the left of the 3rd spring, and the both ends of the 4th spring 41 are equipped with 12 and the 4th spring right-hand apron 13 of baffle on the left of 4th spring, the first spring left side 6 and first spring of baffle right side gear The outside of plate 7 is respectively equipped with additional stops 14 and number one spring right side additional stops 15, second bullet on the left of the first spring The outside of baffle 8 and second spring right-hand apron 9 is respectively equipped with additional stops 16 and second spring on the left of second spring on the left of spring Right side additional stops 17, the outside of the 3rd spring left side 10 and the 3rd spring right-hand apron 11 of baffle are respectively equipped with the 3rd bullet Additional stops 19 on the right side of 18 and the 3rd spring of additional stops on the left of spring, the 4th spring left side 12 and the 4th spring of the baffle right side The outside of baffle 13 is respectively equipped on the left of the 4th spring additional stops 21 on the right side of 20 and the 4th spring of additional stops.
The outer tube 3 is set in outside guide rod 2, and the both ends of the outer tube 3 are fixed with end plate 4 and an outer tube left side on the right side of outer tube Side end panel 5, the left end of the yi word pattern bar 1 are pierced by end plate 5 on the left of outer tube, and the right end of the guide rod 2 is pierced by outer tube right-hand end Plate 4.
First spring 38, second spring 39, the outer diameter of the 3rd spring 40 and the 4th spring 41 are respectively less than the interior of outer tube 3 Footpath.First spring 38, second spring 39, the internal diameter of the 3rd spring 40 and the 4th spring 41 are more than guide rod 2 and yi word pattern The outside dimension of bar 1.
Baffle 6, the first spring right-hand apron 7, second spring left side baffle 8, second spring are right on the left of first spring Baffle 10, the 3rd spring right-hand apron 11, the 4th spring left side 12 and the 4th spring of baffle are right on the left of side shield 9, the 3rd spring Side shield 13 is the circular baffle plate of intermediate making circular hole, and outer diameter is respectively less than the internal diameter of outer tube 3, and the diameter of intermediate round hole is more than The outside dimension of guide rod 2 and the block of yi word pattern bar 1.
Additional stops 14, number one spring right side additional stops 15, second spring left side are additional on the left of first spring Baffle 16, additional stops 17 on the right side of second spring, additional stops 18 on the left of the 3rd spring, additional stops 19 on the right side of the 3rd spring, Additional stops 21 open the circular baffle plate of rectangular opening, and outer diameter for centre on the right side of 20 and the 4th spring of additional stops on the left of 4th spring The respectively less than internal diameter of outer tube 3, the size in intermediate rectangular hole is more than the outside dimension of guide rod 2 and yi word pattern bar 1, less than guide rod 2 With the outside dimension of the block of yi word pattern bar 1.
The material of end plate 4 and outer tube left side end plate 5 is normal carbon structure Q235 steel on the right side of the outer tube 3, outer tube.It is described First spring 38, second spring 39, the material of the 3rd spring 40 and the 4th spring 41 are 60CrMnA.The yi word pattern bar 1 is led Baffle 6, the first spring right-hand apron 7, second spring left side baffle 8, second spring right-hand apron on the left of to bar 2, the first spring 9th, baffle 10, the 3rd spring right-hand apron 11, the 4th spring left side baffle 12, the 4th spring right-hand apron 13 on the left of the 3rd spring Material be low-alloy high-strength structure Q345 steel.First high-strength bolt 22, the second high-strength bolt 23, the 3rd high-strength bolt 24 and the 4th high-strength bolt 25 material for 20MnTiB, intensity is 10.9 grades.
In a kind of assembling of the present invention stacked Self-resetting energy dissipation brace the specific implementation process is as follows:In application, according to stress It is required that applying initial precompression to spring, spring travel is set according to deformation requirements, by stacked Self-resetting energy consumption branch in assembling Between support is hinged on building structure levels as bearing diagonal, 2 leftmost side connecting pin of guide rod layer company upper (lower) with building structure Connect, 1 rightmost side connecting pin of yi word pattern bar under building structure (on) layer is connected.In the state of normal use, pass through spring Precompression and frictional force provide lateral resisting for structure.When structure is subject to geological process, stacked Self-resetting energy dissipation brace in assembling Stress deforms, and relative motion, the upper friction plate between yi word pattern bar 1 and guide rod 2 occur for yi word pattern bar 1 and guide rod 2 26 and lower friction plate 27 start the energy of dissipation Seismic input, when geological process terminates, structure unloading, the reset based on spring System by provide restoring force make structure be restored to deformation before state.
When under tension is supported to start to work, it may be assumed that yi word pattern bar 1 is relatively fixed, then guide rod 2 is with respect to yi word pattern Bar 1 moves right, and drives the first block of guide rod 28 that additional stops 14, the second block of guide rod 29 on the left of the first spring is promoted to push away Additional stops 16, guide rod third gear block 30 promote on the left of the 3rd spring additional stops 18, guide rod the on the left of dynamic second spring Four blocks 31 promote additional stops 20 on the left of the 4th spring, and the first spring left side additional stops 14, which move right, promotes the first spring Additional stops 16, which move right, on the left of left side baffle 6, second spring promotes baffle 8 on the left of second spring, the 3rd spring left side attached Baffle 18 is added, which to move right, promotes baffle 10 on the left of the 3rd spring, the 4th spring left side additional stops 20 to move right promotion the 4th Baffle 12 on the left of spring, the first spring left side baffle 6 move right to squeeze the first spring 38, second spring left side baffle 8 Move right to squeeze second spring 39, baffle 10 moves right to squeeze the 3rd spring the 40, the 4th on the left of the 3rd spring Baffle 12 moves right to squeeze the 4th spring 41 on the left of spring, while the first spring 38 is subject to the first spring right-hand apron 7 It is subject to second spring right-hand apron 9 right with second spring with the limitation of additional stops 15, second spring 39 on the right side of number one spring The limitation of side additional stops 17, the 3rd spring 40 are subject to additional stops 19 on the right side of the 3rd spring right-hand apron 11 and the 3rd spring Limitation, the 4th spring 41 are limited be subject to the 4th spring right-hand apron 13 and additional stops 21 on the right side of the 4th spring, number one bullet 15 and first spring right-hand apron 7 of additional stops is subject to the position-limiting action of the second block of yi word pattern bar 34, second spring on the right side of spring Right side additional stops 17 are subject to the position-limiting action of yi word pattern bar third gear block 35, the 3rd spring right with second spring right-hand apron 9 Additional stops 19 and the 3rd spring right-hand apron 11 in side is subject to the position-limiting action of yi word pattern bar fourth gear block 36, the 4th spring right side 21 and the 4th spring right-hand apron 13 of additional stops is subject to the position-limiting action of yi word pattern bar fifth gear block 37, with respect to yi word pattern bar 1 It does not move, so as to ensure that the first spring 38, second spring 39, the 3rd spring 40 and the 4th spring 41 are compressed;When unloading During load, the first spring 38 promotes the first spring left side 14 and first spring of additional stops left side baffle 6 to left movement, second spring 39 promote additional stops 16 on the left of second spring to promote the 3rd bullet to left movement, the 3rd spring 40 with baffle 8 on the left of second spring Baffle 10 promotes additional gear position on the left of the 4th spring to left movement, the 4th spring 41 on the left of 18 and the 3rd spring of additional stops on the left of spring Baffle 12 is to left movement on the left of 20 and the 4th spring of plate, and movement progress guide rod 2 is to left movement to the left for spring stop, so as to whole Structure can be restored to the state before deforming after complete unloading.The structure of stacked Self-resetting energy dissipation brace exists in additional assembling Can inputting seismic energy be consumed by friction energy-dissipating during deformation, while resetting apparatus provides reseting performance, after being supported on shake It can recover initial position, reduce structure residual deformation.
When support is under pressure start-up operation, it may be assumed that yi word pattern bar 1 is relatively fixed, then guide rod 2 is with respect to yi word pattern Bar 1 drives the second block of guide rod 29 to promote additional stops 15, guide rod third gear block 30 on the right side of number one spring to left movement Additional stops 17 on the right side of second spring, guide rod fourth gear block 31 is promoted to promote additional stops 19, guide rod on the right side of the 3rd spring Fifth gear block 32 promotes additional stops 21 on the right side of the 4th spring, movement progress first to the left of additional stops 15 on the right side of number one spring Movement progress second spring right-hand apron 9, the 3rd spring are right to the left for additional stops 17 on the right side of spring right-hand apron 7, second spring Side additional stops 19 the 3rd spring right-hand apron 11 of movement progress, the movement progress to the left of additional stops 21 on the right side of the 4th spring to the left 4th spring right-hand apron 13, the first spring right-hand apron 7 is to left movement so as to squeezing the first spring 38, gear on the right side of second spring Plate 9 is to left movement so as to squeezing second spring 39, the 3rd spring right-hand apron 11 to left movement so as to squeezing the 3rd spring 40, Four spring right-hand aprons 13 are to left movement so as to squeeze the 4th spring 41, while the first spring 38 is subject to baffle on the left of the first spring 6 and first limitation of additional stops 14 on the left of spring, second spring 39 be subject on the left of second spring baffle 8 on the left of second spring The limitation of additional stops 16, the 3rd spring 40 by 10 and the 3rd spring of baffle left side additional stops 18 on the left of the 3rd spring limit System, the 4th spring 41 are limited be subject to baffle 12 on the left of the 4th spring and additional stops 20 on the left of the 4th spring, and the first spring is left Baffle 6 is subject to the position-limiting action of the first block of yi word pattern bar yi word pattern bar 33, second on the left of 14 and first spring of side additional stops Additional stops 16 are subject to the position-limiting action of the second block of yi word pattern bar 34, the 3rd bullet with baffle 8 on the left of second spring on the left of spring Baffle 10 is subject to the position-limiting action of yi word pattern bar third gear block 35, the 4th spring on the left of 18 and the 3rd spring of additional stops on the left of spring Baffle 12 is subject to the position-limiting action of yi word pattern bar fourth gear block 36 on the left of 20 and the 4th spring of left side additional stops, with respect to yi word pattern Bar 1 does not move, so as to ensure that the first spring 38, second spring 39, the 3rd spring 40 and the 4th spring 41 are compressed;When During unloading, the first spring 38 promotes the first spring right-hand apron 7 to be moved right with additional stops 15 on the right side of number one spring, second Spring 39 promotes second spring right-hand apron 9 to be moved right with additional stops 17 on the right side of second spring, the 3rd spring 40 promotes the Additional stops 19 move right on the right side of three spring right-hand aprons 11 and the 3rd spring, the 4th spring 41 is promoted and kept off on the right side of the 4th spring Plate 13 is moved right with additional stops 21 on the right side of the 4th spring, and movement progress guide rod 2 moves right spring stop to the right, from And overall structure can be restored to the state before deforming after complete unloading.Structure deformation when can by friction energy-dissipating come Inputting seismic energy is consumed, while resetting apparatus provides reseting performance, is supported on post earthquake recovery initial position, and it is remaining to reduce structure Deformation.
Obviously, the above embodiment of the present invention is only intended to clearly illustrate example of the present invention, and is not pair The restriction of embodiments of the present invention for those of ordinary skill in the art, may be used also on the basis of the above description To make other variations or changes in different ways, all embodiments can not be exhaustive here, it is every to belong to this hair Bright technical solution changes and variations that derived from are still in the row of protection scope of the present invention.

Claims (9)

1. a kind of stacked Self-resetting energy dissipation brace in assembling, it is characterised in that:Including outer tube (3), yi word pattern bar (1) and guide rod (2), the middle part of the guide rod (2) is equipped with medium altitude groove, and the outer surface of the guide rod (2) is from left to right equipped with successively to be oriented to The first block of bar (28), the second block of guide rod (29), guide rod third gear block (30), guide rod fourth gear block (31) and guiding Bar fifth gear block (32) is equipped with bolt hole between adjacent block, and the front side edge and back side edge of the yi word pattern bar (1) are from a left side The first block of yi word pattern bar (33), the second block of yi word pattern bar (34), yi word pattern bar third gear block (35), one are equipped with successively to right Font bar fourth gear block (36) and yi word pattern bar fifth gear block (37), the middle part of the yi word pattern bar (1) are equipped with bolt straight slot, institute In the medium altitude groove for stating yi word pattern bar (1) insertion guide rod (2), bolt straight slot and the guide rod (2) of the yi word pattern bar (1) Bolt hole passes through the first high-strength bolt (22), the second high-strength bolt (23), the 3rd high-strength bolt (24) and the 4th high-strength bolt (25) it is fixedly connected, upper friction plate (26), a word is equipped between the upper surface of the yi word pattern bar (1) and guide rod (2) Lower friction plate (27) is equipped between the lower surface of type bar (1) and guide rod (2);
From left to right be arranged with successively between adjacent block on the guide rod (2) the first spring (38), second spring (39), 3rd spring (40) and the 4th spring (41), the both ends of first spring (38) are equipped on the left of the first spring baffle (6) and the One spring right-hand apron (7), the both ends of the second spring (39) are equipped with baffle (8) and second spring right side on the left of second spring Baffle (9), the both ends of the 3rd spring (40) are equipped with baffle (10) and the 3rd spring right-hand apron (11) on the left of the 3rd spring, The both ends of 4th spring (41) are equipped with baffle (12) and the 4th spring right-hand apron (13) on the left of the 4th spring, and described first Be respectively equipped on the outside of baffle (6) and the first spring right-hand apron (7) on the left of spring the first spring left side additional stops (14) and The outside of additional stops (15) on the right side of number one spring, the second spring left side baffle (8) and second spring right-hand apron (9) Additional stops (16) and second spring right side additional stops (17) on the left of second spring are respectively equipped with, are kept off on the left of the 3rd spring Additional stops (18) and the 3rd spring on the left of the 3rd spring are respectively equipped on the outside of plate (10) and the 3rd spring right-hand apron (11) Right side additional stops (19) are respectively equipped on the outside of baffle (12) and the 4th spring right-hand apron (13) on the left of the 4th spring Additional stops (20) and the 4th spring right side additional stops (21) on the left of 4th spring;
The outer tube (3) is set in guide rod (2) outside, and the both ends of the outer tube (3) are fixed on the right side of outer tube end plate (4) and outside End plate (5) on the left of pipe, the left end of the yi word pattern bar (1) are pierced by end plate (5), the right end of the guide rod (2) on the left of outer tube and wear Go out outer tube right-hand end plate (4).
2. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 1, it is characterised in that:First spring (38), the outer diameter of second spring (39), the 3rd spring (40) and the 4th spring (41) is respectively less than the internal diameter of outer tube (3).
3. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 2, it is characterised in that:First spring (38), the internal diameter of second spring (39), the 3rd spring (40) and the 4th spring (41) is more than guide rod (2) and yi word pattern bar (1) Outside dimension.
4. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 3, it is characterised in that:First spring Left side baffle (6), the first spring right-hand apron (7), second spring left side baffle (8), second spring right-hand apron (9), the 3rd Baffle (10), the 3rd spring right-hand apron (11), the 4th spring left side baffle (12) and the 4th spring right-hand apron on the left of spring (13) it is the circular baffle plate of intermediate making circular hole, and outer diameter is respectively less than the internal diameter of outer tube (3), the diameter of intermediate round hole, which is more than, leads To bar (2) and the outside dimension of the block of yi word pattern bar (1).
5. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 4, it is characterised in that:First spring Additional stops (15), second spring left side additional stops (16), second spring on the right side of left side additional stops (14), number one spring Additional stops (18), the 3rd spring right side additional stops (19), the 4th spring are left on the left of right side additional stops (17), the 3rd spring Additional stops (21) open the circular baffle plate of rectangular opening for centre on the right side of side additional stops (20) and the 4th spring, and outer diameter is respectively less than The internal diameter of outer tube (3), the size in intermediate rectangular hole is more than the outside dimension of guide rod (2) and yi word pattern bar (1), less than guide rod (2) with the outside dimension of the block of yi word pattern bar (1).
6. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 1, it is characterised in that:The outer tube (3), The material of end plate (4) and outer tube left side end plate (5) is normal carbon structure Q235 steel on the right side of outer tube.
7. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 1, it is characterised in that:First spring (38), the material of second spring (39), the 3rd spring (40) and the 4th spring (41) is 60CrMnA.
8. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 1, it is characterised in that:The yi word pattern bar (1), guide rod (2), baffle (6) on the left of the first spring, the first spring right-hand apron (7), baffle (8) on the left of second spring, the Baffle (10), the 3rd spring right-hand apron (11), the 4th spring left side baffle on the left of two spring right-hand aprons (9), the 3rd spring (12), the material of the 4th spring right-hand apron (13) is low-alloy high-strength structure Q345 steel.
9. stacked Self-resetting energy dissipation brace in a kind of assembling according to claim 1, it is characterised in that:Described first is high-strength Bolt (22), the second high-strength bolt (23), the material of the 3rd high-strength bolt (24) and the 4th high-strength bolt (25) are 20MnTiB, Intensity is 10.9 grades.
CN201610584720.6A 2016-07-22 2016-07-22 Stacked Self-resetting energy dissipation brace in a kind of assembling Active CN106193747B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610584720.6A CN106193747B (en) 2016-07-22 2016-07-22 Stacked Self-resetting energy dissipation brace in a kind of assembling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610584720.6A CN106193747B (en) 2016-07-22 2016-07-22 Stacked Self-resetting energy dissipation brace in a kind of assembling

Publications (2)

Publication Number Publication Date
CN106193747A CN106193747A (en) 2016-12-07
CN106193747B true CN106193747B (en) 2018-05-29

Family

ID=57492326

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610584720.6A Active CN106193747B (en) 2016-07-22 2016-07-22 Stacked Self-resetting energy dissipation brace in a kind of assembling

Country Status (1)

Country Link
CN (1) CN106193747B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107489294B (en) * 2017-07-18 2019-05-21 北京交通大学 A kind of built-in spring self-restoring concrete shear force wall
CN110453801B (en) * 2019-07-25 2024-05-10 湖北文理学院 Multidirectional damping protection system with high-flexibility structure and damping method thereof
CN112012547B (en) * 2020-06-17 2021-09-14 同济大学 Speed-related energy consumption-self-reset function integrated support
CN113958018B (en) * 2021-10-25 2022-08-23 北京交通大学 Tension-compression unequal-toughness hinge device and assembling method
CN114592600A (en) * 2022-03-19 2022-06-07 山东舜博金属制品有限公司 Stainless steel container
CN114575650A (en) * 2022-03-19 2022-06-03 山东舜博金属制品有限公司 Stainless steel warehouse
CN114622651A (en) * 2022-03-19 2022-06-14 山东舜博金属制品有限公司 Stainless steel factory building

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100451259C (en) * 2007-01-12 2009-01-14 清华大学 Steel tube anti-flex energy dissipation support
CN101440639B (en) * 2008-12-10 2010-11-10 上海维固工程实业有限公司 Flexion energy dissipation preventing support
CN101545289B (en) * 2009-04-13 2010-09-08 清华大学 All-steel buckling-preventing energy-consuming brace
CN101718123B (en) * 2009-12-21 2011-05-11 清华大学 E-shaped fastener constrained type assembled buckling-restrained energy-consumed brace
TW201400677A (en) * 2012-06-22 2014-01-01 Chong-Shien Tsai Automatic return construction damper

Also Published As

Publication number Publication date
CN106193747A (en) 2016-12-07

Similar Documents

Publication Publication Date Title
CN106193747B (en) Stacked Self-resetting energy dissipation brace in a kind of assembling
CN106567324B (en) A kind of all steel self reset curvature-prevention support based on disc spring
CN105507439B (en) A kind of piston type filling compression spring Self-resetting energy dissipation brace
CN107386479B (en) A kind of multiple surrender type shock-absorbing support component
CN105256913B (en) A kind of anti-buckling support of shape memory alloy twisted wire Self-resetting friction
CN102808464B (en) Fiber pre-stretched rod type self-centering steel buckling-restrained brace
CN106223696B (en) A kind of I-shaped inner tube precompressed disc spring Self-resetting energy dissipation brace of assembled
CN105064531B (en) A kind of Self-resetting mr fluid damper
CN104005490B (en) Anti-buckling limit support member for reinforcing post-yield stiffness
CN109653395B (en) Two-stage performance target self-resetting friction type energy dissipation support
CN102261140A (en) Segmental energy-consumption buckling-restrained brace method and device
CN106121078B (en) A kind of magnetic fluid variable damping energy dissipation brace with reset function
CN109798011A (en) Series connection disc spring large deformation energy-dissipation beam column node
CN102852245A (en) Fiber pre-drawing-rod type self-centering round tube buckling restrained support
CN104929265B (en) Spring Self-reset anti-flexure support device
CN110295780A (en) A kind of dual pipe restricted type Self-reset anti-flexure support device of multistage surrender
CN109267806A (en) Lower-prestressed Self-resetting energy dissipation brace
CN110173146B (en) Self-resetting viscous composite damper
CN105927019B (en) The square-section two-stage surrenders anti-buckling support
CN104947826B (en) Self-reset anti-flexure support device
CN208202202U (en) A kind of semi-girder truss main diagonal of band bending surrender Wasted-energy steel plate
CN213683435U (en) Self-resetting buckling restrained brace
CN208309868U (en) A kind of buckling restrained brace device
CN202248249U (en) Buckling restrained brace
CN205677329U (en) The anti-buckling support of square-section two-stage surrender

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant