CN106193617A - Hydraulic sliding construction method for transfer beam - Google Patents

Hydraulic sliding construction method for transfer beam Download PDF

Info

Publication number
CN106193617A
CN106193617A CN201610527792.7A CN201610527792A CN106193617A CN 106193617 A CN106193617 A CN 106193617A CN 201610527792 A CN201610527792 A CN 201610527792A CN 106193617 A CN106193617 A CN 106193617A
Authority
CN
China
Prior art keywords
conversion beam
conversion
jack
construction method
hydraulic pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610527792.7A
Other languages
Chinese (zh)
Other versions
CN106193617B (en
Inventor
马义俊
冯锋
姚钊
冉旭勇
甘霖
严小霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science And Industry Co ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201610527792.7A priority Critical patent/CN106193617B/en
Publication of CN106193617A publication Critical patent/CN106193617A/en
Application granted granted Critical
Publication of CN106193617B publication Critical patent/CN106193617B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the technical field of welding, in particular to a hydraulic sliding construction method of a transfer beam, which comprises the following steps: A. erecting a sliding platform between the support columns in the sliding direction; B. hoisting the conversion beam to an initial sliding position of the sliding platform, and then placing a jack at the initial position, wherein the output end of the jack abuts against the end part of the conversion beam; C. starting a pump station, and pushing the conversion beam to a limit position by the jack; D. then moving the jack to the end part of the conversion beam, and repeating the step C until the next conversion beam can be placed in the initial sliding position; E. placing the jack at the end part of the next transfer beam, starting a pump station until the next transfer beam is contacted with the previous transfer beam, and then welding and connecting the two transfer beams; steps C, D and E are repeated until all transfer beams are slid into place. The construction method has low requirements on the hillside road and high construction efficiency.

Description

A kind of hydraulic pressure gliding construction method of conversion beam
Technical field
The present invention relates to welding technology field, more specifically to the hydraulic pressure gliding construction method of a kind of conversion beam.
Background technology
Along with the development of China's economic level, the people's material and cultural life level has reached a new height.People To building (particularly public building) demand idea also there occurs that essence changes, function, safety requirements are being carried day by day While height, there is higher demand the most than ever to building performance attractive in appearance.Between nearly 15 years, domestic all kinds of new in structures, Peculiarly shaped steel building emerges in an endless stream.Constantly pursue performance with attractive in appearance while, to structure steel fabrication, installation, especially It is that weld job proposes bigger challenge and higher requirement.
In the construction of existing conversion beam, every section of conversion beam is lifted into precalculated position and then welds, under this scheme mainly has Row limiting factor, under the condition of construction of top, hillside, sidehill road need to meet truck crane and component transportation vehicle walking requires and executes Work progress need to meet construction speed requirement.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of accelerating construction progress, and sidehill road requires relatively low turning Change the hydraulic pressure gliding construction method of beam.
The present invention is achieved in that the hydraulic pressure gliding construction method of a kind of conversion beam, comprises the following steps:
A. sliding platform is set up between the support column in glide direction;
B. conversion beam is winched to the initial slippage position of sliding platform, then at initial position placement jack, described thousand The end of described conversion beam supported by jin top outfan;
C. starting pumping plant, described in described jack pushing tow, conversion beam is to extreme position;
The most then jack for moving is to described conversion beam end, repeats step C, until a rear conversion beam can be put into Initial slippage position;
E. described jack is placed on the end of a rear conversion beam, starts pumping plant, to a described rear conversion beam with Then two conversion beams are welded to connect by previous conversion beam contact;
F. repeat step C, D and E, put in place to whole conversion beam slidings.
Further, in described step A, described sliding platform includes sliding beam and support beam, initial slippage position Set up sliding beam between two support columns, between the support column of back segment slip locations, set up support beam.
Further, described sliding beam and support beam are welded to connect between described support column by bracket part.
Further, in described step B and E, some conversion beams being disbursed from the cost and expenses on dagger adjacent in glide direction are same Step sliding, uses connecting rod to be welded to connect, and its end is respectively placed with described jack between the described conversion beam of some row.
Further, glide direction is provided with two row conversion beam synchronization-slidings.
Further, it is provided with push rod between described conversion beam and described jack.
Further, it is connected by screw between described push rod and described conversion beam.
Further, described push rod and jack are together placed on the end of a rear conversion beam.
Compared with prior art, there is following beneficial effect: it is solid that this construction method only need to use crane to be winched to by conversion beam A fixed position, crane and transport vehicle only need to travel to a point, it is not necessary to move back and forth, it is not necessary to repeatedly adjust position Putting, require relatively low to sidehill road, decrease the most mobile simultaneously and readjust the required time, efficiency of construction is higher.
Accompanying drawing explanation
Fig. 1 is the step A schematic diagram of a preferred embodiment of the present invention;
Fig. 2 is the step B schematic diagram of a preferred embodiment of the present invention;
Fig. 3 is the step D schematic diagram of a preferred embodiment of the present invention;
Fig. 4 is the step E schematic diagram of a preferred embodiment of the present invention;
Fig. 5 is another angle schematic diagram of Fig. 2.
In figure: 1-support column 2-conversion beam 3-jack 4-sliding beam 5-support beam 6-connecting rod 7-bracket part
Detailed description of the invention
In order to make the purpose of the present invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, right The present invention is further elaborated.
As it is shown in figure 1, be a preferred embodiment of the present invention, the hydraulic pressure gliding construction method of a kind of conversion beam, including following Step:
A. sliding platform is set up between the support column 1 in glide direction;
B. winch to conversion beam 2 the initial slippage position of sliding platform, then place jack 3 at initial position, very heavy Push up 3 outfans and support the end of conversion beam 2;
C. pumping plant (not shown), jack 3 pushing tow conversion beam 2 to extreme position are started;
The most then jack for moving 3 to conversion beam 2 end, repeats step C, until a rear conversion beam 2 can be put into Initial slippage position;
E. jack 3 is placed on the end of a rear conversion beam 2, starts pumping plant, to a rear conversion beam 2 with previous Conversion beam 2 contacts, and is then welded to connect by two conversion beams 2;
F. repeat step C, D and E, put in place to the sliding of whole conversion beam 2.
This construction method only need to use crane to winch to conversion beam 2 fix a position, and crane and transport vehicle only need to travel To a point, it is not necessary to move back and forth, it is not necessary to repeatedly adjust position, sidehill road is required relatively low, also reduce simultaneously Each movement and readjust the required time, efficiency of construction is higher.
In step, sliding platform includes sliding beam 4 and supports 5 beams, between two support columns 1 of initial slippage position Set up sliding beam 4, between the support column 1 of back segment slip locations, set up support beam 5.Sliding beam 4 and support beam 5 are by bracket part 7 It is welded to connect between support column 1.In step B and E, some conversion beams 2 being disbursed from the cost and expenses on dagger 1 adjacent in glide direction Synchronization-sliding, uses connecting rod 6 to be welded to connect, and its end is respectively placed with jack 3 between some row conversion beams 2.In sliding Direction is provided with two row conversion beam 2 synchronization-slidings.Multiple row conversion beam 2 sliding simultaneously can increase sliding steadiness.Conversion beam 2 with Push rod (not shown) it is provided with between jack 3.It is connected by screw between push rod and conversion beam 3.By push rod and jack 4 Together it is placed on the end of a rear conversion beam 3.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention Any amendment, equivalent and the improvement etc. made within god and principle, should be included within the scope of the present invention.

Claims (8)

1. the hydraulic pressure gliding construction method of a conversion beam, it is characterised in that comprise the following steps:
A. sliding platform is set up between the support column in glide direction;
B. winch to conversion beam the initial slippage position of sliding platform, then place jack, described jack at initial position The end of described conversion beam supported by outfan;
C. starting pumping plant, described in described jack pushing tow, conversion beam is to extreme position;
The most then jack for moving is to described conversion beam end, repeats step C, until a rear conversion beam can be put into initially Slip locations;
E. described jack is placed on the end of a rear conversion beam, starts pumping plant, to a described rear conversion beam with previous Root conversion beam contacts, and is then welded to connect by two conversion beams;
F. repeat step C, D and E, put in place to whole conversion beam slidings.
The hydraulic pressure gliding construction method of a kind of conversion beam the most according to claim 1, it is characterised in that in described step A In, described sliding platform includes sliding beam and support beam, sets up sliding beam, back segment between two support columns of initial slippage position Support beam is set up between the support column of slip locations.
The hydraulic pressure gliding construction method of a kind of conversion beam the most according to claim 2, it is characterised in that described sliding beam with Support beam is welded to connect between described support column by bracket part.
The hydraulic pressure gliding construction method of a kind of conversion beam the most according to claim 1, it is characterised in that in described step B With in E, some conversion beam synchronization-slidings being disbursed from the cost and expenses on dagger adjacent in glide direction, the chien shih of the described conversion beam of some row It is welded to connect by connecting rod, and its end is respectively placed with described jack.
The hydraulic pressure gliding construction method of a kind of conversion beam the most according to claim 4, it is characterised in that in glide direction It is provided with two row conversion beam synchronization-slidings.
The hydraulic pressure gliding construction method of a kind of conversion beam the most according to claim 1, it is characterised in that described conversion beam with It is provided with push rod between described jack.
The hydraulic pressure gliding construction method of a kind of conversion beam the most according to claim 6, it is characterised in that described push rod and institute State and be connected by screw between conversion beam.
The hydraulic pressure gliding construction method of a kind of conversion beam the most according to claim 7, it is characterised in that in described step E In, described push rod and jack are together placed on the end of a rear conversion beam.
CN201610527792.7A 2016-07-06 2016-07-06 Hydraulic sliding construction method for transfer beam Active CN106193617B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610527792.7A CN106193617B (en) 2016-07-06 2016-07-06 Hydraulic sliding construction method for transfer beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610527792.7A CN106193617B (en) 2016-07-06 2016-07-06 Hydraulic sliding construction method for transfer beam

Publications (2)

Publication Number Publication Date
CN106193617A true CN106193617A (en) 2016-12-07
CN106193617B CN106193617B (en) 2019-08-09

Family

ID=57466314

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610527792.7A Active CN106193617B (en) 2016-07-06 2016-07-06 Hydraulic sliding construction method for transfer beam

Country Status (1)

Country Link
CN (1) CN106193617B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110435674A (en) * 2019-08-30 2019-11-12 北京起重运输机械设计研究院有限公司 Supporting beam switching device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202865994U (en) * 2011-12-02 2013-04-10 中国建筑股份有限公司 Numerical-control hydraulic pressure sliding construction creeprail device
JP5184311B2 (en) * 2008-11-17 2013-04-17 鉄建建設株式会社 Steel structure construction method
CN103216109A (en) * 2013-04-26 2013-07-24 江苏沪宁钢机股份有限公司 Construction method of track gauge variation block slippage of long span spatial composite roof truss
CN203213623U (en) * 2013-04-26 2013-09-25 江苏沪宁钢机股份有限公司 Slide guiding and rectifying device
CN103938880A (en) * 2014-03-31 2014-07-23 中冶天工上海十三冶建设有限公司 Overall sliding construction method for large-span special-shaped space grid pipe truss

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5184311B2 (en) * 2008-11-17 2013-04-17 鉄建建設株式会社 Steel structure construction method
CN202865994U (en) * 2011-12-02 2013-04-10 中国建筑股份有限公司 Numerical-control hydraulic pressure sliding construction creeprail device
CN103216109A (en) * 2013-04-26 2013-07-24 江苏沪宁钢机股份有限公司 Construction method of track gauge variation block slippage of long span spatial composite roof truss
CN203213623U (en) * 2013-04-26 2013-09-25 江苏沪宁钢机股份有限公司 Slide guiding and rectifying device
CN103938880A (en) * 2014-03-31 2014-07-23 中冶天工上海十三冶建设有限公司 Overall sliding construction method for large-span special-shaped space grid pipe truss

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中国建筑协会工程项目管理委员会: "《2013年度全国建设工程优秀项目管理成果选编 下》", 30 September 2014 *
王瑞伟等: "依山特殊地形下塔吊起重能力分析", 《四川建材》 *
黄胜等: "钢桁梁斜拉桥液压顶推滑移管件技术", 《施工技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110435674A (en) * 2019-08-30 2019-11-12 北京起重运输机械设计研究院有限公司 Supporting beam switching device
CN110435674B (en) * 2019-08-30 2024-05-28 北京起重运输机械设计研究院有限公司 Support beam switching device

Also Published As

Publication number Publication date
CN106193617B (en) 2019-08-09

Similar Documents

Publication Publication Date Title
CN102587291B (en) Walking type multipoint pushing construction method and walking type multipoint pushing construction system for steel box girder
CN100494042C (en) Self-walking column type overhead operation platform
CN111945580B (en) Bridge deck erection method for large-radian curve type steel box girder
CN103423105B (en) A kind of impeller of wind turbine set assembling device and impeller assembling method
CN102992198A (en) Bridge crane having climbing function
CN205129322U (en) Steering column bearing assembly fixture
CN107503296A (en) Bailey bridge in-place method
CN101302888B (en) Dual-purpose wheeled combined scissors fork elevating scaffold with frame
CN102373670A (en) Mobile platform carrying and erecting integrated machine and bridge erecting method
CN106193617A (en) Hydraulic sliding construction method for transfer beam
CN101302889B (en) Dual-purpose wheeled combined scissors fork elevating scaffold
CN208474649U (en) Architectural engineering indoor environment pipeline auxiliary device for moving
CN105947377A (en) Movable plastic turnover box
CN215405650U (en) Pushing mechanism for bridge or steel structure roof pushing construction
CN205170224U (en) Crawler -type moves tower crane
CN201128424Y (en) Passive lifting tool trolley
CN204777769U (en) Axle is stepped on to two -way movable type of taking off and land
CN202187297U (en) Movable platform conveying frame all-in-one machine
CN210683047U (en) Loading and unloading vehicle device suitable for large-scale component
CN103274318B (en) Platform structure and engineering mechanical device
CN203834805U (en) Cross beam structure for portal frame
CN205976403U (en) Removal operation platform that indoor long corridor was used
CN203834660U (en) Supporting structure for portal frame
CN206407869U (en) The hydraulic lifting mechanism of waggon
CN101092230B (en) Forklift truck with combination of foldaway attached frame with changeable fork

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Science And Industry Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Futian District Che Kung Temple Binhe Tairan industry tipping 17 storey building No. 17A

Patentee before: China Construction Steel Structure Corp.,Ltd.

CP03 Change of name, title or address