CN106185646A - A kind of tower crane standard knot introducing device - Google Patents

A kind of tower crane standard knot introducing device Download PDF

Info

Publication number
CN106185646A
CN106185646A CN201610768195.3A CN201610768195A CN106185646A CN 106185646 A CN106185646 A CN 106185646A CN 201610768195 A CN201610768195 A CN 201610768195A CN 106185646 A CN106185646 A CN 106185646A
Authority
CN
China
Prior art keywords
dolly
standard knot
movable pulley
tower body
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610768195.3A
Other languages
Chinese (zh)
Inventor
赵伟星
胡水根
李太周
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Kerun Mechanical & Electron Engineering Co Ltd
Original Assignee
Zhengzhou Kerun Mechanical & Electron Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Kerun Mechanical & Electron Engineering Co Ltd filed Critical Zhengzhou Kerun Mechanical & Electron Engineering Co Ltd
Priority to CN201610768195.3A priority Critical patent/CN106185646A/en
Publication of CN106185646A publication Critical patent/CN106185646A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/34Self-erecting cranes, i.e. with hoisting gear adapted for crane erection purposes
    • B66C23/344Self-erecting cranes, i.e. with hoisting gear adapted for crane erection purposes adapted for transport purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Transportation (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The open a kind of tower crane standard knot introducing device of the present invention.This device includes the top bearing being positioned at tower body upper end, it is arranged on the crane arm of bearing upper end, top in hinged way, it is sleeved on the peripheral stock between bearing lower end, top and tower body upper end, the forward and backward dolly being arranged on crane arm bottom guide track, it is arranged on front dolly the advancing slip wheels being made up of front fixed pulley and front movable pulley, is arranged on rear dolly the rear wheel group being made up of rear fixed pulley and rear movable pulley;The installation site that space is standard knot to be introduced in the inner chamber of peripheral stock and between top bearing and two abutting ends of tower body;Standby pin shaft hole is all offered on corresponding fixed pulley front and back at forward and backward movable pulley.The present invention need not separately to add standby during tower body is increased, and is not required to dismount the connection between tower body and top bearing with repeating, it is achieved that lifting operation continuously, substantially increases jacking efficiency, take into account the balance of derrick runway girder simultaneously.

Description

A kind of tower crane standard knot introducing device
Technical field
The present invention relates to hoisting machinery technical field, particularly relate to the tower crane a kind of mark when lifting operation Quasi-joint introducing device.
Background technology
Along with popularizing of skyscraper, construction machinery, in order to meet the needs of corresponding construction height, the most all uses oneself The mode of jacking increases the tower body of tower crane.In order to reduce tower crane moment of flexure during jacking, it is generally required to regulation derrick runway girder and top The balance of portion's bearing: the center of gravity of superstructure to be allowed generally within top seating position near.General flat arm tower crane is introducing During standard knot be all the suspension hook utilizing self to lift standard knot, so may dispense with a set of retraction mechanism.But due to When utilizing self suspension hook to introduce standard knot, hoisting point position relatively tower body, lifting standard knot produce forward moment with hang Hang over opposing torque difference produced by the rear balancing weight of derrick runway girder tail end too big, make crane arm disequilibrium that hypsokinesis to occur Trend.Therefore, this can move suspension hook after being accomplished by being reliably connected tower body and top bearing, the most often introduces a feast-brand mark Quasi-joint is accomplished by a tower body and top bearing connects dismounting once, and suspension hook needs to lift twice, just can complete a standard knot Lifting operation.Because there is gap between peripheral stock and tower body, and top bearing ratio of rigidity being relatively big, top bearing and tower body Be difficult to centring during connection, thus the connection between bearing and tower body is tower body increase during operate the most troublesome one group even Connect.Just because of this, the lifting operation inefficiency during causing tower body to be increased, account for the three of the whole standard knot supernumerary segment time / mono-.
Summary of the invention
The purpose of the present invention is just for a kind of tower crane standard provided in place of above-mentioned the deficiencies in the prior art Joint introducing device.Present invention hanging component by tower crane self during tower body is increased lifts and introduces standard knot, no Need separately to add standby, be not required to dismount the connection between tower body and top bearing with repeating, achieve continuous jacking at lower cost Operation, substantially increases the jacking efficiency of tower crane, can take into account the balance of derrick runway girder simultaneously.
The tower crane standard knot introducing device of the present invention includes the top bearing being positioned at tower body upper end, in hinged way It is arranged on the crane arm of bearing upper end, top, is sleeved on the peripheral stock between bearing lower end, top and tower body upper end, is arranged on Forward and backward dolly on crane arm bottom guide track, is arranged on front dolly the advancing slip wheels being made up of front fixed pulley and front movable pulley, It is arranged on rear dolly the rear wheel group being made up of rear fixed pulley and rear movable pulley;Wherein, in the inner chamber of described peripheral stock, And the installation site that space is standard knot to be introduced between top bearing and two abutting ends of tower body;Before described, Rear movable pulley with all offer on corresponding forward and backward fixed pulley standby pin shaft hole (the most as the case may be, front running block and Rear movable pulley both can be connected work, it is possible to works independently.When the most front running block works independently, only need to be by rear dynamic cunning The position, standby pin shaft hole hole that rear movable pulley in wheel is corresponding with on rear fixed pulley aligns, and then fixes with standby bearing pin.This Time after, movable pulley and rear fixed pulley only have guide effect, and its function is equivalent to the leading block that hoists.In like manner, rear movable pulley list When solely working, only position, standby pin shaft hole hole corresponding with on front fixed pulley for the front movable pulley in front running block need to be aligned, so Fix with standby bearing pin afterwards).
In the present invention, the haulage cable for driving described forward and backward dolly to move horizontally is from hoist engine I extraction, one end Being fixed on the front end of front dolly after pile warp traction leading block, other end pile warp draws leading block and after rear dolly passes (front dolly and rear dolly both can be connected synchronous translational, it is possible to individually translate to be fixed on the rear end of front dolly.To be introduced During standard knot lifting lifting operation, haulage cable can be fixed with rear dolly, makes forward and backward dolly keep certain distance, synchronizes Mobile;When normal hoisting heavy at ordinary times, haulage cable and rear dolly are not connected to, and the most forward and backward dolly can individually translate).
In the present invention, the hoist rope for the lifting of described forward and backward assembly pulley is from hoist engine II extraction, pile warp successively Hoist and be fixed on the front end of crane arm after leading block, rear wheel group, advancing slip wheels.
Heretofore described front movable pulley is by the standby pin corresponding at both when needing and fix with front fixed pulley and connect Axis hole installs standby bearing pin realize connect (according to practical situation, when current movable pulley needs to be fixed on front dolly (before Movable pulley needs fixing connection with front fixed pulley), it is only necessary to front movable pulley is raised to top, and makes front movable pulley fixed sliding with front Position, standby pin shaft hole hole corresponding on wheel aligns, and then fixes with standby bearing pin.The most front movable pulley is with front fixed pulley only Only having guide effect, its function is equivalent to the leading block that hoists).
Heretofore described rear movable pulley is by the standby pin corresponding at both when needing and fix with rear fixed pulley and connect Axis hole installs standby bearing pin realize connect (according to practical situation, when rear movable pulley needs to be fixed on rear dolly (after Movable pulley needs fixing connection with rear fixed pulley), it is only necessary to rear movable pulley is raised to top, and makes rear movable pulley fixed sliding with rear Position, standby pin shaft hole hole corresponding on wheel aligns, and then fixes with standby bearing pin.After now, movable pulley is with rear fixed pulley only Only having guide effect, its function is equivalent to the leading block that hoists).
Heretofore described traction leading block is arranged on crane arm.
The heretofore described leading block that hoists is arranged on crane arm.
It is provided with the otic placode swashed for supporting peripheral stock on the most described tower body and (relies on the ear on tower body Plate, peripheral stock is climb along tower body).
The operation principle of the present invention is as follows:
Present invention hanging component by tower crane self during tower body is increased lifts and introduces standard knot, it is not necessary to separately add Equipment, is not required to, with the connection repeated between dismounting tower body and top bearing, achieve continuous lifting operation at lower cost, significantly Improve the jacking efficiency of tower crane, the balance of derrick runway girder can be taken into account simultaneously.
More specifically, the present invention lifts by the hanging component of tower crane self and introduces standard knot, it is not necessary to separately add Standby, i.e. first pass through peripheral stock between top bearing and two abutting ends of tower body, define the installation sky of standard knot to be introduced Between;Then the rear balancing weight being mounted on crane arm rear end tails is balanced by the front-end weight block mounted below front dolly, the most just It is to make both relative to positive and negative moment is roughly the same produced by bearing hinged place, top, cancel out each other, i.e. guarantees at crane arm In poised state or somewhat forward-lean state (when being in somewhat forward-lean state, the bottom surface of crane arm extension forward be fixed on The support column contact of top bearing leading flank).All the time poised state or somewhat forward-lean state it is in, thus due to crane arm After can utilizing, dolly lifts by crane safely, translates standard knot to be introduced to installation site;If needing continuous jacking to increase Tower body, the standard knot to be introduced only need to being in place by the preceding paragraph is connected with tower body end face, then by periphery stock along tower body Upper shifting, lifts by crane continuously followed by rear dolly, translates next section of standard knot to be introduced, in other words, be not required to repeating Connection between dismounting tower body and top bearing, achieves continuous lifting operation at lower cost, substantially increases self-lifting type tower The jacking efficiency of machine, can take into account the balance of derrick runway girder simultaneously.
Lifted by crane additionally, the present invention both can realize continuous jacking during tower body is increased, translated multistage mark to be introduced Quasi-joint, it is also possible to the upper end face of the one section of standard knot to be introduced that will be located in extreme higher position enters normal rising with top bearing after being connected Hang the required hoisting heavy of state lifting.And according to practical situation during specifically used, optional front running block and after Movable pulley is connected work, or select to work independently (only need to be by corresponding with on fixed pulley for temporary transient no movable pulley standby Position, pin shaft hole hole aligns, and then installs standby bearing pin and fixes);The both optional synchronizations that is connected of front dolly and rear dolly are flat Move (haulage cable and rear dolly are not connected to), it is possible to select individually translation (haulage cable can be fixed) with rear dolly.
Beneficial effects of the present invention is as follows:
Present invention hanging component by tower crane self during tower body is increased lifts and introduces standard knot, it is not necessary to separately add Equipment, is not required to, with the connection repeated between dismounting tower body and top bearing, achieve continuous lifting operation at lower cost, significantly Improve the jacking efficiency of tower crane, the balance of derrick runway girder can be taken into account simultaneously.
Accompanying drawing explanation
Fig. 1 is the structural representation (being also the present invention state diagram when lifting by crane standard knot to be introduced) of the present invention.
View when Fig. 2 is to carry out front dolly counterweight before introducing lifting (is also individually with rear dolly simultaneously View when normally lifting by crane).
Fig. 3 is the wiring figure of haulage cable.
Fig. 4 is the wiring figure (when forward and backward assembly pulley is used alone) of hoist rope.
Fig. 5 is the view (when forward and backward assembly pulley is used together) during the normal hoisting heavy of the present invention.
Fig. 6 is the wiring figure (when forward and backward assembly pulley is used together) of hoist rope.
Fig. 7 is the structural representation of advancing slip wheels (or rear wheel group).
Fig. 8 is the view being incorporated into before installation site of standard knot to be introduced.
Sequence number in figure: 1, tower body, 1-1, otic placode, 2, top bearing, 3, rear dolly, 4, rear wheel group, 4-1, rear fixed pulley, 4-2, rear movable pulley, 5, standard knot to be introduced, 6, front-end weight block, 7, advancing slip wheels, 7-1, front fixed pulley, 7-2, front movable pulley, 8, front dolly, 9, haulage cable, 10, hoist rope, 11, crane arm, 12, rear balancing weight, 13, hoist engine I, 14, traction Leading block, 15, hoist engine II, 16, hoist leading block, 17, peripheral stock, 18, hook assembly, 19, standby bearing pin, 20, Standby pin shaft hole, 21, support column, L, spacing between forward and backward dolly when introducing.
Detailed description of the invention
The present invention is further described below with reference to example (accompanying drawing):
As shown in Figure 1, 2, the tower crane standard knot introducing device of the present invention includes the top bearing 2 being positioned at tower body 1 upper end, It is arranged on the crane arm 11 of top bearing 2 upper end in hinged way, is sleeved between top bearing 2 lower end and tower body 1 upper end Peripheral stock 17, the forward and backward dolly 8,3 being arranged on crane arm 11 bottom guide track, it is arranged on front dolly 8 by front fixed pulley 7- The advancing slip wheels 7 of 1 and front movable pulley 7-2 composition, are arranged on rear dolly 3 and are made up of rear fixed pulley 4-1 and rear movable pulley 4-2 Rear wheel group 4;Wherein, in the inner chamber of described peripheral stock 17 and be positioned at top bearing 2 and tower body 1 two abutting ends it Between the installation site that space is standard knot 5 to be introduced;At described forward and backward movable pulley 7-2,4-2 and corresponding forward and backward fixed pulley (the most as the case may be, front running block 7 and rear movable pulley 4 both can be linked to be all to offer standby pin shaft hole on 7-1,4-1 One body running, it is possible to work independently.When the most front running block 7 works independently, only need to be by the rear movable pulley 4-in rear movable pulley 4 The 2 standby pin shaft hole 20 hole positions corresponding with on rear fixed pulley 4-1 align, and then fix with standby bearing pin 19.Move the most afterwards Pulley 4-2 and rear fixed pulley 4-1 only has guide effect, and its function is equivalent to the leading block 16 that hoists.In like manner, rear movable pulley 4 when working independently, only need to be by standby pin shaft hole 20 corresponding on the front movable pulley 7-2 in front running block 7 and front fixed pulley 7-1 Position, hole aligns, and then fixes with standby bearing pin 19, sees Fig. 2, Fig. 7).
In the present invention, the haulage cable 9 for driving described forward and backward dolly 8,3 to move horizontally is to draw from hoist engine I 13 Go out, after one end pile warp traction leading block 14, be fixed on the front end of front dolly 8, other end pile warp traction leading block 14 and from Rear dolly 3 be fixed on after passing front dolly 8 rear end (see Fig. 3, front dolly 8 and rear dolly 3 both can be connected with Step translation, it is possible to individually translate.When standard knot to be introduced lifting lifting operation, haulage cable 9 can be fixed with rear dolly, Forward and backward dolly is made to keep certain distance, synchronizing moving;When normal hoisting heavy at ordinary times, haulage cable 9 and rear dolly 3 are not Connecting, the most forward and backward dolly can individually translate).
In the present invention, the hoist rope 10 for the lifting of described forward and backward assembly pulley 7,4 is to draw from hoist engine II 15, depends on Secondary pile warp hoists and is fixed on the front end of crane arm 11 after leading block 16, rear wheel group 4, advancing slip wheels 7 and (sees Fig. 4, figure 6).
Heretofore described front movable pulley 7-2 and front fixed pulley 7-1 needs to fix when connecting by corresponding at both After position, standby pin shaft hole 20(hole aligns) in install standby bearing pin 19 and realize connecting and (see Fig. 7, according to practical situation, currently When movable pulley 7-2 needs to be fixed on front dolly 8 (front movable pulley 7-2 and front fixed pulley 7-1 needs fixing connection), it is only necessary to Front movable pulley 7-2 is raised to top, and allows position, standby pin shaft hole 20 hole corresponding on front movable pulley 7-2 and front fixed pulley 7-1 Align, then fix with standby bearing pin 19.The most front movable pulley 7-2 and front fixed pulley 7-1 only has guide effect, its Function is equivalent to the leading block 16 that hoists).
Heretofore described rear movable pulley 4-2 and rear fixed pulley 4-1 needs to fix when connecting by corresponding at both After position, standby pin shaft hole 20(hole aligns) in install standby bearing pin 19 realize connecting (see Fig. 7, according to practical situation, when after When movable pulley 4-2 needs to be fixed on rear dolly 3 (rear movable pulley 4-2 and rear fixed pulley 4-1 needs fixing connection), it is only necessary to Rear movable pulley 4-2 is raised to top, and allows position, standby pin shaft hole 20 hole corresponding on rear movable pulley 4-2 and rear fixed pulley 4-1 Align, then fix with standby bearing pin 19.After now, movable pulley 4-2 and rear fixed pulley 4-1 only has guide effect, its Function is equivalent to the leading block 16 that hoists).
Heretofore described traction leading block 14 is arranged on crane arm 11.
The heretofore described leading block 16 that hoists is arranged on crane arm 11.
It is provided with the otic placode 1-1 swashed for supporting peripheral stock 1 on the most described tower body 1 and (relies on tower body 1 Otic placode 1-1, peripheral stock 17 is climb along tower body 1).
The specifically used situation of the present invention is as follows:
(1) utilize and present invention introduces standard knot and add a liter tower crane height
As shown in Figure 1, Figure 2, Figure 3, Figure 4, before standard knot 5 to be introduced introduces, first, should be according to the actual feelings of complete machine The weight of the front-end weight block 6 that condition mounts below spacing L between forward and backward dolly and front dolly 8 when determining introducing, i.e. needs full Foot is mounted on the front-end weight block 6 below front dolly 8 and is mounted on the rear balancing weight 12 of crane arm 11 rear end tails relative to top Positive and negative moment produced by bearing 2 hinged place roughly the same (seeing Fig. 2), i.e. can ensure that crane arm 11 be in poised state or Somewhat forward-lean state (be in somewhat forward-lean state time, the bottom surface of crane arm 11 extension forward be fixed on front side of top bearing 2 The support column 21 in face contacts);Then, the position of rear dolly 3 is fixed, mobile front dolly 8, move to meet during introducing forward and backward During spacing L between dolly, haulage cable 9 and rear dolly 3 are fixed, make forward and backward dolly 8,3 can move to together introduce Lifting position;Then, rear movable pulley 4-2 is fixedly connected with rear fixed pulley 4-1 and rear dolly 4, the most first allows rear movable pulley 4-2 aligns with the position, standby pin shaft hole 20 hole in rear fixed pulley 4-1, then installs standby bearing pin 19;And then, before putting down Movable pulley 7-2, hangs front-end weight block 6 on hook assembly 18, and hoist balancing weight 6, by standby bearing pin 19 by front movable pulley 7-2 is fixedly connected with rear fixed pulley 7-1 and front dolly 8;It follows that pull out between rear movable pulley 4-2 and rear fixed pulley 4-1 Standby bearing pin 19, unclamp rear movable pulley 4-2, start lifting mechanism, rear dolly 3 can be freely lifted, it is possible to dynamic after utilization Pulley 4-2 and hook assembly 18 lift standard knot 5 to be introduced, and now front dolly 8 and front-end weight block 6 play regulation crane arm 11 The effect (seeing Fig. 1) of balance.Follow-up installation is exactly after standard knot 5 to be introduced is lifted to desired height, outside being drawn in by level Enclose the installation site in stock 17 inner chamber, after para-position, the bottom of standard knot 5 to be introduced and the top of tower body 1 are attached solid Fixed (seeing Fig. 8).
If needing continuous jacking to increase tower body, periphery stock 17 just moves along tower body 1 and is supported on peripheral stock 17 On corresponding otic placode 1-1, final peripheral stock 17 is sleeved on described top bearing 2 and is positioned at the tower body the superiors and is newly introduced and connects The periphery (seeing Fig. 8) of corresponding two abutting ends of the standard knot fixed, is again started up lifting mechanism, movable pulley 4-2 after utilization And hook assembly 18 lifts second segment standard knot to be introduced 5, carry out introducing and assemble.By that analogy, repeat aforesaid operations, The height can increased according to tower crane needs, it is not necessary to separately add standby, is not required to repeating between dismounting tower body 1 and top bearing 2 Connection, achieve continuous lifting operation at lower cost, substantially increase the jacking efficiency of tower crane, can hold concurrently simultaneously Turn round and look at the balance of derrick runway girder 11.
(2) present invention is utilized to carry out hoisting heavy as normal lifting tower crane
If being no longer necessary to continuous jacking when increasing tower body, the bottom on the top of the superiors' standard knot with top bearing 2 is carried out Connect fixing.Now, tower crane can serve as normally lifting by crane tower crane and uses, and carries out normal hoisting heavy (seeing Fig. 5). During as lifting tower crane, can lift by crane or be arranged on rear dolly 3 individually with the advancing slip wheels 7 being arranged on below front dolly 8 The rear wheel group 4 of lower section is lifted by crane, it is also possible to little after utilizing the advancing slip wheels 7 being arranged on below front dolly 8 simultaneously and being arranged on Rear wheel group 4 below car 3 is lifted by crane jointly.
When lifting by crane individually with the advancing slip wheels 7 below front dolly 8, by the rear wheel below temporary transient no rear dolly 3 Rear movable pulley 4-2 in group 4 is fixedly connected on rear fixed pulley 4-1 by standby bearing pin 19;Below rear dolly 3 When rear wheel group 4 is lifted by crane, by the front movable pulley 7-2 in the advancing slip wheels 7 below temporary transient no front dolly 8 by standby bearing pin 19 are fixedly connected on front fixed pulley 7-1.Now, be fixedly connected rear movable pulley 4-2 together and rear fixed pulley 4-1(or Movable pulley 7-2 and front fixed pulley 7-1 before person) function only just correspond to leading block.
Meanwhile, utilize the advancing slip wheels 7 being arranged on below front dolly 8 and be arranged on the rear wheel group 4 below rear dolly 3 During lifting, for the balance of holding torque, an equalizer bar can be mounted below front movable pulley 7-2 and rear movable pulley 4-2 After hang again weight (see Fig. 5, Fig. 6, it is possible to refer to another patent application of the applicant, Application No.: 201620854802.3, entitled " a kind of many multiplying powers balanced type becomes multiplying factor device ", the most too much describe).

Claims (8)

1. a tower crane standard knot introducing device, it is characterised in that: it includes the top bearing being positioned at tower body (1) upper end (2), it is arranged on the crane arm (11) of top bearing (2) upper end in hinged way, is sleeved on top bearing (2) lower end and tower body (1) the peripheral stock (17) between upper end, the forward and backward dolly (8,3) being arranged on crane arm (11) bottom guide track, before being arranged on The advancing slip wheels (7) being made up of front fixed pulley (7-1) and front movable pulley (7-2) on dolly (8), be arranged on rear dolly (3) by The rear wheel group (4) that rear fixed pulley (4-1) and rear movable pulley (4-2) form;Wherein, at the inner chamber of described peripheral stock (17) In and the installation position that space is standard knot to be introduced (5) that is positioned between top bearing (2) and two abutting ends of tower body (1) Put;Standby bearing pin is all offered on corresponding forward and backward fixed pulley (7-1,4-1) described forward and backward movable pulley (7-2,4-2) Hole.
Tower crane standard knot introducing device the most according to claim 1, it is characterised in that: be used for driving described before, The haulage cable (9) that rear dolly (8,3) moves horizontally is to draw from hoist engine I (13), one end pile warp traction leading block (14) being fixed on the front end of front dolly (8) after, other end pile warp traction leading block (14) also passes rear solid from rear dolly (3) It is scheduled on the rear end of front dolly (8).
Tower crane standard knot introducing device the most according to claim 1, it is characterised in that: for described forward and backward cunning The hoist rope (10) that wheels (7,4) lift by crane be from hoist engine II (15) draw, successively pile warp hoist leading block (16), after The front end of crane arm (11) it is fixed on after assembly pulley (4), advancing slip wheels (7).
Tower crane standard knot introducing device the most according to claim 1, it is characterised in that: described front movable pulley (7- 2) it is by the standby pin shaft hole (20) corresponding at both installs standby bearing pin when needing and fix with front fixed pulley (7-1) and connect (19) realize connecting.
Tower crane standard knot introducing device the most according to claim 1, it is characterised in that: described rear movable pulley (4- 2) it is by the standby pin shaft hole (20) corresponding at both installs standby bearing pin when needing and fix with rear fixed pulley (4-1) and connect (19) realize connecting.
Tower crane standard knot introducing device the most according to claim 2, it is characterised in that: described traction leading block (14) it is arranged on crane arm (11).
Tower crane standard knot introducing device the most according to claim 3, it is characterised in that hoist described in: leading block (16) it is arranged on crane arm (11).
Tower crane standard knot introducing device the most according to claim 1, it is characterised in that: on described tower body (1) It is provided with for supporting the otic placode (1-1) that peripheral stock (1) is swashed.
CN201610768195.3A 2016-08-31 2016-08-31 A kind of tower crane standard knot introducing device Pending CN106185646A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610768195.3A CN106185646A (en) 2016-08-31 2016-08-31 A kind of tower crane standard knot introducing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610768195.3A CN106185646A (en) 2016-08-31 2016-08-31 A kind of tower crane standard knot introducing device

Publications (1)

Publication Number Publication Date
CN106185646A true CN106185646A (en) 2016-12-07

Family

ID=58088808

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610768195.3A Pending CN106185646A (en) 2016-08-31 2016-08-31 A kind of tower crane standard knot introducing device

Country Status (1)

Country Link
CN (1) CN106185646A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003097509A1 (en) * 2002-05-20 2003-11-27 St-Germain Andre Self-ercting tower crane raising platform
CN201961997U (en) * 2010-12-16 2011-09-07 广西建工集团建筑机械制造有限责任公司 Electric driven platform for tower crane inner frame lifting operation
CN202322100U (en) * 2011-11-16 2012-07-11 中联重科股份有限公司 Trolley horizontal amplitude tower crane and trolley lifting appliance combined device
CN103407902A (en) * 2013-08-28 2013-11-27 哈尔滨工业大学 Arm-folding type tower crane jacking device and method for increasing height of tower crane
CN204661178U (en) * 2015-05-29 2015-09-23 郑州科润机电工程有限公司 A kind of amplitude variation trolley of large zoom rate
CN205132933U (en) * 2015-09-30 2016-04-06 徐州建机工程机械有限公司 Two load trolley structure of tower crane
CN206014281U (en) * 2016-08-31 2017-03-15 郑州科润机电工程有限公司 A kind of tower crane standard knot introducing device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003097509A1 (en) * 2002-05-20 2003-11-27 St-Germain Andre Self-ercting tower crane raising platform
CN201961997U (en) * 2010-12-16 2011-09-07 广西建工集团建筑机械制造有限责任公司 Electric driven platform for tower crane inner frame lifting operation
CN202322100U (en) * 2011-11-16 2012-07-11 中联重科股份有限公司 Trolley horizontal amplitude tower crane and trolley lifting appliance combined device
CN103407902A (en) * 2013-08-28 2013-11-27 哈尔滨工业大学 Arm-folding type tower crane jacking device and method for increasing height of tower crane
CN204661178U (en) * 2015-05-29 2015-09-23 郑州科润机电工程有限公司 A kind of amplitude variation trolley of large zoom rate
CN205132933U (en) * 2015-09-30 2016-04-06 徐州建机工程机械有限公司 Two load trolley structure of tower crane
CN206014281U (en) * 2016-08-31 2017-03-15 郑州科润机电工程有限公司 A kind of tower crane standard knot introducing device

Similar Documents

Publication Publication Date Title
CN104379488B (en) Method and installation system for assembling elevator parts
AU2010309721B2 (en) Elevator arrangement and method
US20170166419A1 (en) Method and arrangement for installing an elevator
CN101528582B (en) Elevators
CN104632088B (en) Oil-well rig derrick set assembly/installation method
JP6813123B2 (en) How to apply elevator lift extension technology
CN104495632A (en) Expanded type suspension rope lifting and hoisting system
CN102745578A (en) Lift device
CN206014281U (en) A kind of tower crane standard knot introducing device
CN101863423B (en) Steel box beam cable carrying lifter for construction of suspension bridge
CN201713229U (en) Steel box girder cable-loaded crane for suspension bridge construction
CN104870358A (en) Maintenance method for a lift
CN106185646A (en) A kind of tower crane standard knot introducing device
CN210480530U (en) Elevator shaft traction overhead two-to-one suspension ratio construction elevator
CN103539020B (en) Novel hoisting construction method and special hanging device
CN103010999A (en) Adjustable pulley block mechanism
KR101847083B1 (en) Roping system for elevator
CN203486803U (en) Crane, counterweight device and rope assembly hanging mechanism
CN106006423A (en) Multi-multiplying power balance type variable multiplying power device
CN210559113U (en) Auxiliary hoisting tool for mounting power equipment
CN208249682U (en) A kind of wind wheel slipping tail tooling
CN113653376A (en) Stage elevating platform
CN203048482U (en) Adjustable pulley block mechanism
CN208516720U (en) A kind of elevator for fixing wheelchair
CN102561954A (en) Multifunctional derrick

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161207

WD01 Invention patent application deemed withdrawn after publication