CN106157177A - A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar - Google Patents

A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar Download PDF

Info

Publication number
CN106157177A
CN106157177A CN201610606054.1A CN201610606054A CN106157177A CN 106157177 A CN106157177 A CN 106157177A CN 201610606054 A CN201610606054 A CN 201610606054A CN 106157177 A CN106157177 A CN 106157177A
Authority
CN
China
Prior art keywords
snowfall
miniradar
transmission line
electricity
parameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610606054.1A
Other languages
Chinese (zh)
Inventor
谷山强
王剑
曹永兴
冯万兴
蒲路
赵淳
郭钧天
梁文勇
曾瑜
王佩
李涛
何君
吴驰
丁国宁
闵毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of State Grid Sichuan Electric Power Co Ltd
Electric Power Research Institute of State Grid Shaanxi Electric Power Co Ltd
Original Assignee
Wuhan NARI Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan NARI Ltd filed Critical Wuhan NARI Ltd
Priority to CN201610606054.1A priority Critical patent/CN106157177A/en
Publication of CN106157177A publication Critical patent/CN106157177A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01WMETEOROLOGY
    • G01W1/00Meteorology
    • G01W1/10Devices for predicting weather conditions
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A90/00Technologies having an indirect contribution to adaptation to climate change
    • Y02A90/10Information and communication technologies [ICT] supporting adaptation to climate change, e.g. for weather forecasting or climate simulation

Abstract

The present invention discloses a kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar, it is characterised in that said method comprising the steps of: step 1: obtain power transmission line corridor real-time weather situation by miniradar;Step 2: judge whether to reach snowfall condition;Step 3: gather meteorological data near shaft tower;Step 4: judge circuit snow depth;Step 5: combined circuit shaft tower parameter and historical failure data;Step 6: obtain line drop snow disaster evil threshold value of warning;Step 7: carry out circuit snowfall Monitoring and forecasting system in real-time.Present invention firstly provides and transmission line of electricity is carried out snowfall monitoring, at icing, wave etc. before ice disaster occurs and give warning in advance;Present invention lead-in line pole tower historical failure data in snowfall early warning first, sets snowfall threshold value of warning in conjunction with tower structure parameter, highly reliable.

Description

A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar
Technical field
The present invention relates to a kind of monitoring and pre-alarming method, be specifically related to a kind of transmission line of electricity snowfall wide area based on miniradar Monitoring and pre-alarming method.
Background technology
Snowfall transmission line of electricity can be caused to occur icing, ice dodge, wave, fall the accident such as tower, broken string, serious threat electrical network Safe operation.Power transmission line corridor snowfall situation is monitored early warning, is conducive to improving line corridor ice disaster protection energy Power, ensures electrical network reliably, stably run.
Prior art mainly utilizes weather forecast data or automatic weather station, microclimate device to carry out weather monitoring and pre- Alert.The advantage that monitoring range is wide although weather forecast data have, space scale is big, but wide, the major part of distribution is arranged in The transmission line of electricity in field, the meteorologic parameter provided is the finest, it is impossible to observe the meteorological shape near concrete overhead line structures Condition;Although automatic weather station, microclimate device can describe weather parameters with becoming more meticulous, but because of the least limitation of monitoring range, Transmission line of electricity snowfall wide area to be realized is monitored, and networking is required arranges that website is more, causes plant maintenance workload big, increases line Road operation maintenance personnel workload.
In view of this, it is necessary to a kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar is provided, with Solve the problems referred to above.
Summary of the invention
In order to overcome above-mentioned the deficiencies in the prior art, it is an object of the invention to provide a kind of transmission of electricity based on miniradar Circuit snowfall wide area monitoring and pre-alarming method, utilizes miniradar to obtain power transmission line corridor real-time weather situation, it may be judged whether to reach To snowfall condition;Gather meteorological data near shaft tower, it is judged that circuit snow depth, combined circuit shaft tower parameter and historical failure number According to, obtain the threshold value of warning causing circuit disaster under Snowfall, circuit snowfall is carried out Monitoring and forecasting system in real-time.
In order to realize foregoing invention purpose, the present invention adopts the following technical scheme that: a kind of power transmission line based on miniradar Road snowfall wide area monitoring and pre-alarming method, it is characterised in that said method comprising the steps of:
Step 1: obtain power transmission line corridor real-time weather parameter by miniradar;
Step 2: the meteorologic parameter that analytical procedure 1 radar returns, it may be judged whether reach snowfall condition;
Step 3: gather meteorological data near shaft tower by automatic weather station or microclimate device;
Step 4: meteorological data near the shaft tower that analytical procedure 3 returns, whether checking accumulated snow condition is set up;If accumulated snow condition becomes Vertical, then judge circuit snow depth;
Step 5: obtain overhead line structures parameter and historical failure data;
Step 6: the overhead line structures parameter of analytical procedure 5 acquisition and historical failure data, obtains line drop snow disaster evil threshold value of warning;
Step 7: when reaching threshold value of warning, carries out circuit snowfall Monitoring and forecasting system in real-time.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar as above, it is characterised in that described In step 1, miniradar is arranged near transmission line of electricity, Radar meteorology parameter is back at backstage by wireless transmission method Reason center, described Radar meteorology parameter includes that echo strength, multilayer reflectivity, many interval velocities, multilayered particles, vertically-supplying air are wide Line;Meteorologic parameter predictive time scope scope is 50m × 50m ~ 2km × 2km.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar as above, it is characterised in that described In step 2, use meteorological treatment technology, including plane position indicator PPI image recognition, expansion rate orientation display EVAD skill Art, analyzes radar and returns meteorologic parameter, it is judged that whether meet the condition of snowfall under the conditions of current weather.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar as above, it is characterised in that described In step 3, automatic weather station, microclimate device are arranged on overhead line structures or near shaft tower, by wireless transmission method by bar Near tower, meteorological data is back to background process center, and near described shaft tower, meteorological data comprises temperature, humidity, wind speed.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar as above, it is characterised in that described In step 4, owing to the temperature near accumulated snow and circuit has direct relation, need to utilize automatic weather station, microclimate device to return Shaft tower temperature, humidity, the meteorological data that becomes more meticulous of wind speed, checking accumulated snow condition whether set up;If accumulated snow condition is set up, then profit With the empirical value corresponding with Radar meteorology parameter of snowfall under Snowfall, it is determined that circuit snow depth.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar as above, it is characterised in that described In step 5, long data when shaft tower parameter comprises pole and tower design load, tower, electric pressure, insulator type, military service;History event Barrier packet contains the sudden strain of a muscle of line insulator ice, wire icing, waves casualty data.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar as above, it is characterised in that described In step 6, dodge by statistics snow depth, snowfall duration, the parameter of shaft tower parameter with shaft tower tower, line insulator ice, lead Line icing, the relation waved between the historical failure data of accident, respectively obtain circuit tower, ice sudden strain of a muscle, icing, accident of waving exist Threshold value of warning under Snowfall.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar as above, it is characterised in that described In step 7, when reaching threshold value of warning, utilize note or wechat mode, by circuit real-time early warning result, comprise advanced warning grade, Early warning shaft tower, circuit disaster distribution, at times, classification do not sends to line upkeep staff, it is achieved line drop snow disaster Evil Monitoring and forecasting system in real-time.
Compared with prior art, the present invention has a following beneficial effect:
1, the present invention monitors line corridor meteorological condition, the monitoring range of existing mesoscale by miniradar, can provide again Locally become more meticulous meteorological data in real time;
2, the present invention utilizes miniradar to realize constructing communication network, and networking website is few, and plant maintenance workload is little;
3, present invention firstly provides transmission line of electricity is carried out snowfall monitoring, at icing, wave etc. before ice disaster occurs and carry Front early warning;
4, present invention lead-in line pole tower historical failure data in snowfall early warning first, sets snowfall in conjunction with tower structure parameter Threshold value of warning, highly reliable.
Accompanying drawing explanation
Fig. 1 is the flow chart of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar.
Detailed description of the invention
In order to be more fully understood that the present invention, it is further elucidated with present disclosure below in conjunction with embodiment, but the present invention Content is not limited solely to the following examples.The present invention can be made various changes or modifications by those skilled in the art, these The equivalent form of value is equally within the scope of claims listed by the application limit.
Such as Fig. 1, the present invention provides a kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar, described side Method comprises the following steps:
Step 1: obtain power transmission line corridor real-time weather parameter by miniradar;
Step 2: the meteorologic parameter that analytical procedure 1 radar returns, it may be judged whether reach snowfall condition;
Step 3: gather meteorological data near shaft tower by automatic weather station or microclimate device;
Step 4: meteorological data near the shaft tower that analytical procedure 3 returns, whether checking accumulated snow condition is set up;If accumulated snow condition becomes Vertical, then judge circuit snow depth;
Step 5: obtain overhead line structures parameter and historical failure data;
Step 6: the overhead line structures parameter of analytical procedure 5 acquisition and historical failure data, obtains line drop snow disaster evil threshold value of warning;
Step 7: when reaching threshold value of warning, carries out circuit snowfall Monitoring and forecasting system in real-time.
In described step 1, miniradar is arranged near transmission line of electricity (such as transformer station, residential block etc.), by wireless biography Radar meteorology parameter is back to background process center by defeated mode, and described Radar meteorology parameter includes that echo strength, multilamellar are anti- Penetrate rate, many interval velocities, multilayered particles, vertical wind profile etc.;Meteorologic parameter predictive time scope scope is 50m × 50m ~ 2km × 2km.
In described step 2, use meteorological treatment technology, such as plane position indicator (being called for short PPI) image recognition, extension speed Degree orientation shows technology such as (being called for short EVAD), analyzes radar and returns meteorologic parameter, it is judged that whether meets fall under the conditions of current weather The condition of snow.
In described step 3, automatic weather station, microclimate device are arranged on overhead line structures or near shaft tower, by wireless Meteorological data near shaft tower is back to background process center by transmission means, near described shaft tower meteorological data comprise temperature, Humidity, wind speed etc..
In described step 4, owing to the temperature near accumulated snow and circuit has direct relation, need to utilize automatic weather station, micro- The meteorological datas that become more meticulous such as the shaft tower temperature of Meteorological Device return, humidity, wind speed, whether checking accumulated snow condition is set up;If accumulated snow Condition is set up, the empirical value that under recycling Snowfall, snowfall is corresponding with Radar meteorology parameter, it is determined that circuit snow depth.
In described step 5, shaft tower parameter comprises such as pole and tower design load, tower, electric pressure, insulator type, military service The data such as duration;Historical failure data comprises the sudden strain of a muscle of line insulator ice, wire icing, the casualty data such as waves.
In described step 6, fall tower, circuit by the statistics parameter such as snow depth, snowfall duration, shaft tower parameter and shaft tower exhausted The sudden strain of a muscle of edge ice, wire icing, the relation waved between the historical failure data such as accident, respectively obtain circuit tower, ice dodges, covers Ice, the accident threshold value of warning under Snowfall such as wave.
In described step 7, when reaching threshold value of warning, utilize the mode such as note or wechat, by circuit real-time early warning result (comprising advanced warning grade, early warning shaft tower, circuit disaster distribution etc.) at times, classification do not send to line upkeep work people Member, it is achieved line drop snow disaster evil Monitoring and forecasting system in real-time.
The content that this specification is not described in detail belongs to prior art known to professional and technical personnel in the field.

Claims (8)

1. a transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar, it is characterised in that described method includes Following steps:
Step 1: obtain power transmission line corridor real-time weather parameter by miniradar;
Step 2: the meteorologic parameter that analytical procedure 1 radar returns, it may be judged whether reach snowfall condition;
Step 3: gather meteorological data near shaft tower by automatic weather station or microclimate device;
Step 4: meteorological data near the shaft tower that analytical procedure 3 returns, whether checking accumulated snow condition is set up;If accumulated snow condition becomes Vertical, then judge circuit snow depth;
Step 5: obtain overhead line structures parameter and historical failure data;
Step 6: the overhead line structures parameter of analytical procedure 5 acquisition and historical failure data, obtains line drop snow disaster evil threshold value of warning;
Step 7: when reaching threshold value of warning, carries out circuit snowfall Monitoring and forecasting system in real-time.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar the most according to claim 1, its feature exists In, in described step 1, miniradar is arranged near transmission line of electricity, Radar meteorology parameter is returned by wireless transmission method To background process center, described Radar meteorology parameter includes echo strength, multilayer reflectivity, many interval velocities, multilayered particles, hangs down Straight Wind outline;Meteorologic parameter predictive time scope scope is 50m × 50m ~ 2km × 2km.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar the most according to claim 1, its feature exists In, in described step 2, use meteorological treatment technology, show including plane position indicator PPI image recognition, expansion rate orientation Show EVAD technology, analyze radar and return meteorologic parameter, it is judged that under the conditions of current weather, whether meet the condition of snowfall.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar the most according to claim 1, its feature exists In, in described step 3, automatic weather station, microclimate device are arranged on overhead line structures or near shaft tower, by the side of being wirelessly transferred Meteorological data near shaft tower is back to background process center by formula, and near described shaft tower, meteorological data comprises temperature, humidity, wind Speed.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar the most according to claim 1, its feature exists In, in described step 4, owing to the temperature near accumulated snow and circuit has direct relation, need to utilize automatic weather station, microclimate to fill Putting the meteorological data that becomes more meticulous of the shaft tower temperature of return, humidity, wind speed, whether checking accumulated snow condition is set up;If accumulated snow condition becomes Vertical, that under recycling Snowfall, snowfall is corresponding with Radar meteorology parameter empirical value, it is determined that circuit snow depth.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar the most according to claim 1, its feature exists In, in described step 5, long number when shaft tower parameter comprises pole and tower design load, tower, electric pressure, insulator type, military service According to;Historical failure data comprises the sudden strain of a muscle of line insulator ice, wire icing, waves casualty data.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar the most according to claim 1, its feature exists In, in described step 6, fall tower, line insulator by statistics snow depth, snowfall duration, parameter and the shaft tower of shaft tower parameter Ice sudden strain of a muscle, wire icing, the relation waved between the historical failure data of accident, respectively obtain circuit and fall tower, ice sudden strain of a muscle, icing, dance Dynamic accident threshold value of warning under Snowfall.
Transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar the most according to claim 1, its feature exists In, in described step 7, when reaching threshold value of warning, utilize note or wechat mode, by circuit real-time early warning result, comprise pre- Alert grade, early warning shaft tower, circuit disaster distribution, at times, classification do not sends to line upkeep staff, it is achieved circuit Snowfall disaster Monitoring and forecasting system in real-time.
CN201610606054.1A 2016-07-29 2016-07-29 A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar Pending CN106157177A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610606054.1A CN106157177A (en) 2016-07-29 2016-07-29 A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610606054.1A CN106157177A (en) 2016-07-29 2016-07-29 A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar

Publications (1)

Publication Number Publication Date
CN106157177A true CN106157177A (en) 2016-11-23

Family

ID=58060307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610606054.1A Pending CN106157177A (en) 2016-07-29 2016-07-29 A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar

Country Status (1)

Country Link
CN (1) CN106157177A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106845822A (en) * 2017-01-18 2017-06-13 国家电网公司 One kind is ice-covering-proof to wave technological transformation project efficiency evaluation method and system
CN108643252A (en) * 2018-06-28 2018-10-12 武汉智网兴电科技开发有限公司 A kind of electric power line pole tower column foot landslide detecting system
CN109782376A (en) * 2019-02-13 2019-05-21 南京信大气象科学技术研究院有限公司 A kind of radar snow depth automatic observer based on Step Frequency
CN111291027A (en) * 2020-01-15 2020-06-16 杭州华网信息技术有限公司 Data preprocessing method
CN111443400A (en) * 2019-10-29 2020-07-24 国网电力科学研究院武汉南瑞有限责任公司 Wind power prediction method, prediction device, prediction system and storage medium
CN111458769A (en) * 2020-05-26 2020-07-28 南京大学 Method and system for predicting environmental meteorological data of power transmission line
CN113126182A (en) * 2019-12-31 2021-07-16 北京四维智联科技有限公司 Accumulated snow depth prediction method and system
CN113447998A (en) * 2021-06-29 2021-09-28 国网山西省电力公司电力科学研究院 Power transmission line severe weather monitoring and early warning method and monitoring and early warning device
CN114049755A (en) * 2021-12-13 2022-02-15 夏若凡 Environment testing system and testing method
CN117471452A (en) * 2023-12-28 2024-01-30 江苏讯汇科技股份有限公司 Method for monitoring conductor galloping of power transmission line based on millimeter wave radar

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101915596A (en) * 2010-07-26 2010-12-15 吕强 Method and system for monitoring ice coating state of overhead cable
CN102590893A (en) * 2012-02-22 2012-07-18 四川电力科学研究院 Intelligent microclimate monitoring system of transmission lines
CN103033855A (en) * 2012-12-12 2013-04-10 江苏省电力公司电力科学研究院 Grid meteorological disaster monitoring and early warning system
CN104483562A (en) * 2014-11-27 2015-04-01 国家电网公司 Method and device for early warning of power equipment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101915596A (en) * 2010-07-26 2010-12-15 吕强 Method and system for monitoring ice coating state of overhead cable
CN102590893A (en) * 2012-02-22 2012-07-18 四川电力科学研究院 Intelligent microclimate monitoring system of transmission lines
CN103033855A (en) * 2012-12-12 2013-04-10 江苏省电力公司电力科学研究院 Grid meteorological disaster monitoring and early warning system
CN104483562A (en) * 2014-11-27 2015-04-01 国家电网公司 Method and device for early warning of power equipment

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106845822A (en) * 2017-01-18 2017-06-13 国家电网公司 One kind is ice-covering-proof to wave technological transformation project efficiency evaluation method and system
CN106845822B (en) * 2017-01-18 2020-08-11 国家电网公司 Icing-galloping-prevention technically improved project efficiency evaluation method and system
CN108643252A (en) * 2018-06-28 2018-10-12 武汉智网兴电科技开发有限公司 A kind of electric power line pole tower column foot landslide detecting system
CN109782376A (en) * 2019-02-13 2019-05-21 南京信大气象科学技术研究院有限公司 A kind of radar snow depth automatic observer based on Step Frequency
CN109782376B (en) * 2019-02-13 2020-12-11 南京信大气象科学技术研究院有限公司 Radar snow depth automatic observation instrument based on step frequency
CN111443400A (en) * 2019-10-29 2020-07-24 国网电力科学研究院武汉南瑞有限责任公司 Wind power prediction method, prediction device, prediction system and storage medium
CN111443400B (en) * 2019-10-29 2022-03-18 国网电力科学研究院武汉南瑞有限责任公司 Wind power prediction method, prediction device, prediction system and storage medium
CN113126182A (en) * 2019-12-31 2021-07-16 北京四维智联科技有限公司 Accumulated snow depth prediction method and system
CN111291027A (en) * 2020-01-15 2020-06-16 杭州华网信息技术有限公司 Data preprocessing method
CN111291027B (en) * 2020-01-15 2023-08-15 浙江华网恒业科技有限公司 Data preprocessing method
CN111458769A (en) * 2020-05-26 2020-07-28 南京大学 Method and system for predicting environmental meteorological data of power transmission line
CN113447998A (en) * 2021-06-29 2021-09-28 国网山西省电力公司电力科学研究院 Power transmission line severe weather monitoring and early warning method and monitoring and early warning device
CN114049755A (en) * 2021-12-13 2022-02-15 夏若凡 Environment testing system and testing method
CN117471452A (en) * 2023-12-28 2024-01-30 江苏讯汇科技股份有限公司 Method for monitoring conductor galloping of power transmission line based on millimeter wave radar
CN117471452B (en) * 2023-12-28 2024-03-08 江苏讯汇科技股份有限公司 Method for monitoring conductor galloping of power transmission line based on millimeter wave radar

Similar Documents

Publication Publication Date Title
CN106157177A (en) A kind of transmission line of electricity snowfall wide area monitoring and pre-alarming method based on miniradar
CN101989767B (en) Comprehensive measuring and controlling device of high voltage pole tower
CN103837769B (en) A kind of transmission line of electricity damage to crops caused by thunder method for early warning and system thereof
CN202153251U (en) Power transmission line comprehensive measurement and control device
CN102590651B (en) Measured lightning data-based transmission line failure probability evaluation method
CN201966688U (en) Comprehensive measure and control device of a high-pressure shaft tower
CN104065016B (en) Online icing-prevention and snow-coverage-prevention method for electric transmission line by utilizing separate-excitation resonance
CN102508046B (en) Real-time lightning stroke prewarning method and device for outdoor electric equipment
CN202928616U (en) Transmission line conducting wire icing and galloping on-line monitoring system
CN103207340A (en) On-line transmission line lightning shielding failure trip early-warning method
CN103236666A (en) Differentiated lightning protection method for power transmission lines
CN104216387A (en) Intelligent power grid monitoring system based on ZigBee and GSM/GPRS
CN104614783A (en) Method for determining meteorological risks of surrounding of transmission tower in electric power system
CN103968799A (en) Three-dimensional monitoring method for deformation of tower of power transmission line
CN106707096A (en) Multi-source data based grid fault positioning and analysis report automatic generating method
CN104793062A (en) Field terminal equipment lightning protection method based on agricultural internet of things
CN204374177U (en) A kind of transmission line wire insulator contamination real-time monitoring system
CN102903018B (en) A kind of transmission line of electricity wind speed early warning information disposal route based on GIS
CN103955609A (en) Automatic anticipated fault set generation method based on typhoon model
CN103592580A (en) Insulator haze and pollution flashover online monitoring system and method
CN106781229A (en) Coated by ice of overhead power transmission line method for early warning
CN109784683A (en) A kind of power grid wide area meteorological disaster integrated campaign method
CN204461532U (en) A kind of distribution substation water level segmental alarm and shearing device
CN103399233A (en) Lightning trip-out risk prediction method for power transmission line
CN106370147A (en) Wind deflection based power transmission line's wind deflection early warning system and method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20170814

Address after: 430074 Hubei Province, Wuhan city Hongshan District Luoyu Road No. 143

Applicant after: Wuhan Nari Limited Liability Company of State Grid Electric Power Research Institute

Applicant after: Electric Power Research Institute, State Grid Shaanxi Electric Power Company

Applicant after: Electric Power Sciences Research Institute of Sichuan Electric Power Corporation

Address before: 430074 Hubei Province, Wuhan city Hongshan District Luoyu Road No. 143

Applicant before: Wuhan Nari Limited Liability Company of State Grid Electric Power Research Institute

TA01 Transfer of patent application right
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161123

WD01 Invention patent application deemed withdrawn after publication