CN106154122A - A kind of retrospective power cable detecting and controlling system - Google Patents

A kind of retrospective power cable detecting and controlling system Download PDF

Info

Publication number
CN106154122A
CN106154122A CN201510152290.6A CN201510152290A CN106154122A CN 106154122 A CN106154122 A CN 106154122A CN 201510152290 A CN201510152290 A CN 201510152290A CN 106154122 A CN106154122 A CN 106154122A
Authority
CN
China
Prior art keywords
power cable
partial discharge
detection
data
controlling system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510152290.6A
Other languages
Chinese (zh)
Inventor
黄华
罗莎
胡正勇
曹志强
万丽丽
余震明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI JONSON CABLES TECHNOLOGY Co Ltd
State Grid Shanghai Electric Power Co Ltd
Original Assignee
SHANGHAI JONSON CABLES TECHNOLOGY Co Ltd
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI JONSON CABLES TECHNOLOGY Co Ltd, State Grid Shanghai Electric Power Co Ltd filed Critical SHANGHAI JONSON CABLES TECHNOLOGY Co Ltd
Priority to CN201510152290.6A priority Critical patent/CN106154122A/en
Publication of CN106154122A publication Critical patent/CN106154122A/en
Pending legal-status Critical Current

Links

Landscapes

  • Testing Relating To Insulation (AREA)

Abstract

The present invention provides a kind of retrospective power cable detecting and controlling system, and it is connected with shelf depreciation test detector and Hi-pot Tester respectively, including: data acquisition unit, control unit, memory element and video monitoring power supply;Video monitor unit is for monitoring the process of the power cable detection of shelf depreciation test detector and Hi-pot Tester;Data acquisition unit is for Real-time Collection detection data and monitor video data;Control unit is used for controlling and guide power cable to detect, and controls video monitor unit and monitors the process of power cable detection in real time, detection data and monitor video data are integrated, analyze and process and judged;Memory element is for preserving the monitor video data through integrating and detection data and to the control of power cable detection, the process that guides, analyze and process and judge.The present invention uses existing detecting instrument, is greatly saved cost;And it is aided with video monitoring, make the testing result more cogency of power cable.

Description

A kind of retrospective power cable detecting and controlling system
Technical field
The present invention relates to the factory testing system of a kind of power cable, particularly relate to the detection of a kind of retrospective power cable and control System.
Background technology
The raising required power supply reliability along with needs and the user of power system development, it is reliable that high-tension electricity equipment runs Property receive the highest attention, but in electrical network, the Insulation Problems of cable is the most prominent, had a strong impact on power supply can Raising by property.Research finds, it is closely related that the partial discharge quantity of cable is insulated from situation, the change indication of partial discharge quantity Cable insulation and there may be the defect of harm cable running safety.
And, the inside of power cable existing defects sometimes, thus when causing power cable safe operation, there is great safety Hidden danger.Further, power cable great majority are embedded in underground, and running environment is severe, safeguard and fault is detected the most relatively difficult.One As, power cable defect uses pressure experiment to detect, and the capacity of experiment of high tension cable alternating-current voltage resistance test device can be expired The requirement of experiment of three kilometers of 110KV high tension cables of foot, and, thermal capacity is to design, for whole during detection according to every phase 5min The power cable of body, the power cable of detection entirety can completely bear the test of test voltage, thus whether judge power cable Defective.
Therefore, power cable is required for the routine inspection tested through partial discharge test and industrial frequency withstand voltage when dispatching from the factory.Still, During the practice examining of factory, tend not to operate according to standard-required.For example, for partial discharge test, Before the test, it should carry out the demarcation of partial discharge quantity, the amplification of partial discharge quantity should not regulated during measurement once again;Carry out During shelf depreciation boosting, it should be increased to 2U0Left and right keeps 10s, is slowly decreased to 1.73U the most again0, wherein U0Represent cable Specified phase voltage;Further, if terminal is not handled well, shelf depreciation can trigger terminal electric discharge;Testing crew cannot differentiate The difference that cable body electric discharge and interference electric discharge or terminal are discharged;Background noise is unsatisfactory for the requirement of test;If it occur that local Electric discharge, should record the firing potential of shelf depreciation, type of Partial Discharge etc., in order to carry out failed test sample Analyzing and processing etc..For pressure test, pressure-resistant time is unsatisfactory for standard-required etc..So will certainly cause underproof electric power Cable flows out factory so that it is in use there is bigger potential safety hazard.
Summary of the invention
The shortcoming of prior art in view of the above, it is an object of the invention to provide the detection of a kind of retrospective power cable and controls System, when being used for solving to use prior art to carry out power cable factory testing, it is impossible to is controlled and reduces the asking of detection process Topic.
For achieving the above object and other relevant purposes, the present invention provides a kind of retrospective power cable detecting and controlling system, institute State power cable detecting and controlling system to be connected with shelf depreciation test detector and Hi-pot Tester, including: data acquisition unit, Control unit, memory element and video monitoring power supply;Wherein, described video monitor unit is used for monitoring the test of described shelf depreciation The process of the power cable detection of detector and described Hi-pot Tester;Described data acquisition unit is for local described in Real-time Collection The detection data of discharge test detector and described Hi-pot Tester and the monitor video data of described video monitor unit;Institute State control unit for controlling and guide described Partial discharge detector and described Hi-pot Tester to carry out power cable detection;Control Described video monitor unit monitors the process of the power cable detection of described Partial discharge detector and described Hi-pot Tester in real time; The described detection data and the described monitor video data that gather described data acquisition unit are integrated, analyze and process and are judged; Described memory element is for preserving the described monitor video data through integrating and described detection data, and preserves described control unit The control that power cable is detected, the process guiding, analyze and process and judging.
Alternatively, the detection of described power cable is included the partial discharge detection carried out by described shelf depreciation test detector and passes through institute State the resistance test that Hi-pot Tester is carried out.
Alternatively, described detection data include partial discharge detection data and resistance test data;The described monitor video data office of including puts Detection monitor video data and resistance test monitor video data.
Alternatively, control subelement, pressure control subelement and video control subelement are put in the described control unit office of including;Wherein, Control subelement is put for controlling, guide and analyze the described partial discharge detection of described Partial discharge detector in described office;Described pressure Control subelement for controlling, guide and analyze the described resistance test of described Hi-pot Tester;Described video controls subelement and uses The power cable detection of described Partial discharge detector and described Hi-pot Tester is monitored in real time in the described video monitor unit of control Process;And it is corresponding that the described monitor video data collected by described data acquisition unit are carried out integration with described detection data.
Alternatively, described office puts control subelement and controls, guides and analyze described Partial discharge detector and include detecting described local The sensitivity of discharge detector and the qualification rate of the described partial discharge detection of detection.
Alternatively, described office puts the sensitivity of the described Partial discharge detector of control subelement detection and includes: step S21, guides And control described Partial discharge detector calibration shelf depreciation, and after shelf depreciation demarcation signal is stable, control described data acquisition Collection unit gathers shelf depreciation scalar quantity and the current voltage value of described Partial discharge detector;Step S22, it is judged that described work as Front magnitude of voltage: if described current voltage value is less than 0.5V, then judge that calibration shelf depreciation is carried out in the case of uncharged, Jump to step S23;Otherwise, described power cable detecting and controlling system reports an error;Step S23, controls described data acquisition unit Show value is put in the background interference values drawn game gathering described Partial discharge detector;Step S24, puts show value and institute according to described office State background interference values and judge the sensitivity of described Partial discharge detector.
Alternatively, the sensitivity of described Partial discharge detector and the model of power cable are relevant.
Alternatively, described office puts the qualification rate of the control subelement described partial discharge detection of detection and includes: step S31, by described number According to collecting unit according to acquisition time interval Real-time Collection detection voltage;Step S32, calculates partial discharge quantity according to detection voltage Measured value;According to described background interference values and described shelf depreciation measurement, step S33, judges whether described partial discharge detection closes Lattice.
Alternatively, described shelf depreciation measurement and the most qualified standard of described partial discharge detection all with the model phase of power cable Close.
Alternatively, described power cable detecting and controlling system also includes Tip element.
As it has been described above, the retrospective power cable detecting and controlling system of the present invention, its based on existing Partial discharge detector and Hi-pot Tester, supporting increase video monitor unit, by signals collecting, video monitoring and database information technology from existing Some Partial discharge detectors and Hi-pot Tester direct collecting test data, and the monitoring coordinating video monitor unit to monitor regards Frequency evidence, thus reduce the factory testing overall process of power cable, in order to help supervision and the check of related personnel.Further, originally Invention is based on existing Partial discharge detector and Hi-pot Tester, simply at reviewed to the electric power electricity of its external connection present invention Cable detecting and controlling system, can complete the partial discharge detection to power cable and the monitoring of resistance test, guide, analyze and judge, It is greatly saved cost;Further, the detection data of often dish power cable can be carried out real-time storage by the present invention, raw for finding Become problem present in manufacturing, be also aided with video except data and match, cable user is had more cogency;The present invention is permissible Remotely monitor and call the detection data dispatched from the factory, make for the remotely prison of user and provide possibility, decrease and supervise the man power and material made Cost.
Accompanying drawing explanation
Fig. 1 is shown as the structural representation of retrospective power cable detecting and controlling system disclosed in the embodiment of the present invention.
Fig. 2 is shown as retrospective power cable detecting and controlling system detection Partial discharge detector disclosed in the embodiment of the present invention The schematic flow sheet of sensitivity.
Fig. 3 is shown as retrospective power cable detecting and controlling system disclosed in the embodiment of the present invention and judges the conjunction of described partial discharge detection The schematic flow sheet of lattice rate.
Element numbers explanation
100 retrospective power cable detecting and controlling system
110 data acquisition units
120 control units
Put control subelement 121 innings
122 pressure control subelements
123 videos control subelement
130 memory element
140 video monitor unit
150 Tip elements
200 Partial discharge detectors
300 Hi-pot Testers
S21~S24 step
S31~S33 step
Detailed description of the invention
Below by way of specific instantiation, embodiments of the present invention being described, those skilled in the art can be by disclosed by this specification Content understand other advantages and effect of the present invention easily.The present invention can also be added by the most different detailed description of the invention To implement or application, the every details in this specification can also be based on different viewpoints and application, in the essence without departing from the present invention Various modification or change is carried out under god.It should be noted that, the feature in the case of not conflicting, in following example and embodiment Can be mutually combined.
It should be noted that the diagram provided in following example illustrates the basic conception of the present invention the most in a schematic way, then scheme Component count, shape and size when only showing the assembly relevant with the present invention rather than implement according to reality in formula are drawn, in fact When border is implemented, the kenel of each assembly, quantity and ratio can be a kind of random change, and its assembly layout kenel is likely to the most multiple Miscellaneous.
The retrospective power cable detecting and controlling system of the present invention, by signals collecting, video monitoring and database computer Information technology from existing Partial discharge detector and Hi-pot Tester direct collecting test data, thus reduce power cable detection Overall process, in order to help the supervision of related personnel and check.
Embodiment
Present embodiment discloses a kind of retrospective power cable detecting and controlling system 100, be applied to the factory testing of power cable. As it is shown in figure 1, the retrospective power cable detecting and controlling system 100 of the present embodiment respectively with existing Partial discharge detector 200 and Hi-pot Tester 300.Control Partial discharge detector 200 and Hi-pot Tester 300 carry out the detection of power cable, and Gather, analyze, process and preserve testing result.Partial discharge detector 200 and Hi-pot Tester 300 are all existing equipments. Wherein.Partial discharge detector 200 and Hi-pot Tester 300 are all for detecting the insulating properties before power cable dispatches from the factory.
Wherein, Partial discharge detector 200 includes the Partial discharge detector possessing data processing function and does not possess data process The Partial discharge detector of function.
When Partial discharge detector 200 possesses data processing function, the retrospective power cable detection of the present embodiment controls system System 100 is to operate under WINDOWS system, and wherein WINDOWS system includes WINDOWS 95, WINDOWS XP or WINDOWS 7.Power cable detecting and controlling system 100, from the software of Partial discharge detector 200, passes through bottom Internal memory read technology, directly obtain test data, and by communication interface, the test data of acquisition be transferred to power cable inspection Survey in control system 100.
When Partial discharge detector 200 does not possesses data processing function, the retrospective power cable detection of the present embodiment controls System 100 directly gathers the local discharge signal of simulation.
Hi-pot Tester 300 is applied to detect the local defect of power cable, make moist and aging, and it utilizes one higher than normal work The voltage made is added on power cable, continues the time of one section of regulation, if the voltage of superimposed only can produce the least electric leakage Stream, then assert that the insulating properties of this power cable is preferable.At present, Hi-pot Tester 300 includes but not limited to that electrical insulation strength tries Test instrument, dielectric strength tester etc..
The retrospective power cable detecting and controlling system 100 of the present embodiment as it is shown in figure 1, specifically include data acquisition unit 110, Control unit 120, memory element 130, video monitor unit 140 and Tip element 150.The present embodiment except with shelf depreciation Detector 200 and Hi-pot Tester 300 phase in succession outside, the most supporting add video monitor unit 140.Video monitor unit 140 For monitoring that user passes through Partial discharge detector 200 and Hi-pot Tester 300 detects the overall process of power cable in real time.Generally In the case of, video monitor unit 140 is two sets, a set of partial discharge detection process for monitoring Partial discharge detector 200;One Set is for monitoring the resistance test process of Hi-pot Tester 300.
Data acquisition unit 110 is for Real-time Collection Partial discharge detector 200 and the inspection of the power cable of Hi-pot Tester 300 Survey data and the monitor video data of video monitor unit 140.Wherein, the detection data of power cable include partial discharge detection Data and resistance test data;Monitor video data include partial discharge detection monitor video data and resistance test monitor video data.
Control unit 120 is used for controlling and guide Partial discharge detector 200 and Hi-pot Tester 300 to examine power cable Survey;Control the inspection that video monitor unit 140 monitors the power cable of Partial discharge detector 200 and Hi-pot Tester 300 in real time Survey process;The detection data and the monitor video data that gather data acquisition unit 110 were integrated according to the time, and at analysis Reason judges testing result.
For convenient management, control subelement 121, pressure control subelement 122 and video control are put in control unit 120 office of being divided into Subunit 123.
Office put control subelement 121 for the partial discharge detection Data Control gathered according to data acquisition unit 110, guide and analyze The Partial discharge detector 200 detection to power cable.Specifically include: detect the sensitivity of Partial discharge detector 200 and sentence Determine the qualification rate of partial discharge detection.
The process of the sensitivity of the detection Partial discharge detector 200 controlling subelement 121 is put as in figure 2 it is shown, include in office:
Step S21, guides and controls Partial discharge detector 200 and calibrate shelf depreciation, and stable at shelf depreciation demarcation signal After, control data acquisition unit 110 and gather shelf depreciation scalar quantity and the current voltage value of Partial discharge detector 200:
After retrospective power cable detecting and controlling system 100 brings into operation 5s, retrospective power cable detecting and controlling system 100 can point out " shelf depreciation calibration operation can start " automatically, and this prompting includes but not limited to voice message.Then, when After shelf depreciation demarcation signal is stable, carried out the collection of shelf depreciation scalar quantity and current voltage value by data acquisition unit 110. Further, the acquisition time of shelf depreciation scalar quantity and current voltage value is 10s, and after 10s, data acquisition unit 110 is automatically switched off Acquisition function.
Step S22, it is judged that current voltage value: if current voltage value is less than 0.5V, then judge calibration shelf depreciation be without Carry out in the case of electricity, jump to step S23;Otherwise, then it is assumed that calibration shelf depreciation is carried out in the case of charged, In the case of charged, carry out calibrating shelf depreciation do not meet power cable factory testing specification, therefore, this situation occurs, Retrospective power cable detecting and controlling system 100 can show automatically in operation mistake language hurdle: shelf depreciation calibration should Calibrating in the case of not charged, this operation does not meets standard-required.
If additionally, retrospective power cable detecting and controlling system 100 operationally between more than 30s, the most do not carry out local Discharge gauged collection, and, now corresponding current voltage value is more than 0.5V, then the detection control of retrospective power cable System 100 processed can show automatically in operation mistake language hurdle: should first carry out shelf depreciation demarcation, carry out a liter electricity the most again Pressure, this operation does not meets standard-required.
Step S23, controls data acquisition unit 110 and gathers the background interference values of Partial discharge detector 200 and gather first Shelf depreciation value in time, and extraction office puts show value.
The shelf depreciation value of the Partial discharge detector 200 that data acquisition unit 110 gathers in the first acquisition time is a number According to set, the shelf depreciation value extracting probability of occurrence in this data acquisition system the highest puts show value as office.
Step S24, puts show value according to office and background interference values judges the sensitivity of Partial discharge detector 200:
For different power cable models, the standard of the sensitivity of its Partial discharge detector 200 is different:
If power cable model is " 38/66,64/110,127/220 or 290/500 ", it is judged that background interference values * (put by office Show value/shelf depreciation scalar quantity) whether more than 2.5: if it is greater, then retrospective power cable detecting and controlling system 100 Show in operation mistake language hurdle: partial discharge test system sensitivity does not meets standard-required;If it is not greater, then Judge that the sensitivity of Partial discharge detector 200 meets the standard-required of power cable detection;
If power cable model is other models, then judge that background interference values/(show value/shelf depreciation scalar quantity is put in office) is No it is more than 5: if it is greater, then retrospective power cable detecting and controlling system 100 shows in operation mistake language hurdle: Partial discharge test system sensitivity does not meets standard-required;If it is not greater, then judge the sensitive of Partial discharge detector 200 Degree meets the standard-required of power cable detection.
Office puts control subelement 121 and meets the standard-required of power cable detection in the sensitivity judging Partial discharge detector 200 After, according to step as shown in Figure 3 carry out judge partial discharge detection qualification rate:
Step S31, by data acquisition unit 110 according to acquisition time interval Real-time Collection detection electricity in the second acquisition time Pressure, in the present embodiment, the second acquisition time is 10s.
Step S32, according to detection voltage calculating partial discharge quantity measured value:
Same, for different cable models, the method calculating shelf depreciation measurement is also different.General cable Model is defined by phase voltage and line voltage, and such as cable model is 38/66, then identify the specified phase electricity of this cable Pressure is 38kV, and rated line voltage is 66kV.
If cable model is " 38/66,64/110,127/220 or 290/500 ", it is extracted in (1.03 × 1.5 × cable Specified phase voltage, the specified phase voltage of 0.97 × 1.5 × cable) in the range of detection voltage, and, the detection voltage of extraction Number is V, and meets V × acquisition time interval more than 10, then the magnitude of voltage of the partial discharge quantity of Resurvey 10s;System Count the highest data of the magnitude of voltage probability of occurrence of the partial discharge quantity gathered in this 10s as shelf depreciation measurement E;If V × acquisition time interval is less than or equal to 10, then retrospective power cable detecting and controlling system 100 can report an error;
If cable is other models, then it is extracted in (the specified phase voltage of 1.03 × 1.73 cables, the volume of 0.97 × 1.73 × cable Phasing voltage) in the range of detection voltage;Further, the number of the detection voltage of extraction is V, and meets between V × acquisition time Every more than 10, then the magnitude of voltage of the partial discharge quantity of Resurvey 10s, and add up the interior partial discharge quantity gathered of this 10s The highest data of magnitude of voltage probability of occurrence are as shelf depreciation measurement E;If V × acquisition time interval is less than or equal to 10, The most retrospective power cable detecting and controlling system 100 can report an error;
Further, for the cable of different model, if met in detection number of voltages V extracted: V × acquisition time interval is big In 10 time, the most retrospective power cable detecting and controlling system 100 meeting prompting automatically " gather the magnitude of voltage of partial discharge quantity, and And after 10s, it is automatically switched off this acquisition function ";
Further, if met in detection number of voltages V extracted: when V × acquisition time interval is more than 20, data acquisition Unit 110 does not also carry out the collection of the magnitude of voltage of partial discharge quantity, and the most retrospective current cable detecting and controlling system 100 is behaviour Make miscue language hurdle shows: " gathering the magnitude of voltage of partial discharge quantity the most in time, do not meet standard-required ";
Further, if data acquisition unit 110 is more than 65s to the acquisition time of the magnitude of voltage of partial discharge quantity, can chase after The current cable detecting and controlling system 100 traced back shows in operation mistake language hurdle: " shelf depreciation intensifies voltage time mistake Long, do not meet standard-required "
Step S33, according to background interference values and partial discharge quantity measured value E, it is judged that the partial discharge detection of cable is the most qualified:
If cable model is " 38/66,64/110,127/220 or 290/500 ", shelf depreciation measurement meets: E < 2 The amplification of × ambient interferences/partial discharge quantity, and ambient interferences/partial discharge quantity amplification < 5, then judge the office of cable Put detection qualified, the most defective;
If cable is other models, shelf depreciation measurement E meets: the times magnification of E < 2 × ambient interferences/partial discharge quantity Number, and ambient interferences/partial discharge quantity amplification < when 10, then judge that the partial discharge detection of cable is qualified, the most defective.
Wherein, the amplification of partial discharge quantity is set in advance according to actually detected requirement.
Pressure control subelement 122 is used for the resistance test Data Control according to data acquisition unit 110 collection, guides and analyze The Hi-pot Tester 300 resistance test to power cable.
For the cable of different model, test voltage and detection time when it carries out resistance test are different.
If cable model is " 38/66,64/110,127/220 or 290/500 ", then carry out the test voltage of resistance test It is greater than the specified phase voltage of 0.97 × 2.5 × cable, and the detection time is greater than 30 minutes.In test voltage and detection time When meeting above-mentioned requirements, then judge that the resistance test of power cable is passed through.
If cable model is " 3.6/6,6/6,8.7/10,8.7/15,12/20 or 18/30 ", then carry out the examination of resistance test Electrical verification pressure is greater than the specified phase voltage of 0.97 × 3.5 × cable, and the detection time is greater than 5 minutes.When test voltage and detection Between when meeting above-mentioned requirements, then judge that the resistance test of power cable is passed through.
If cable model is 21/35 or 26/35, then the test voltage carrying out resistance test is greater than 0.97 × 3.5 × cable Specified phase voltage, and the detection time be greater than 5 minutes;Or test voltage is more than the specified phase voltage of 0.97 × 2.5 × cable, And the detection time was more than 3 minutes.When test voltage and detection time meet above-mentioned requirements, then judge the pressure inspection of power cable Survey is passed through.
Further, when power cable is carried out resistance test, data acquisition unit 110 Real-time Collection Hi-pot Tester 300 Voltage signal (i.e. test voltage), to guarantee test voltage during resistance test.
Video control subelement 123 is used for controlling video monitor unit 140 and monitors Partial discharge detector 200 and pressure survey in real time Examination instrument 300;And it is corresponding that with detection data, the monitor video data collected by data acquisition unit 110 are carried out integration.Root According to monitor video data and the classification of detection data, and the time that the time of monitor video data and power cable detection are carried out enters Row is integrated.The partial discharge detection data of identical time are corresponding with partial discharge detection monitor video Data Integration;The pressure inspection of identical time It is corresponding that survey data carry out integration with resistance test monitor video data.
Memory element 130 is for preserving the monitor video data through integrating and detection data, and it is right to preserve control unit 120 The partial discharge detection of power cable and the analyzing and processing of resistance test guide and decision process.
Tip element 150 for carrying out shelf depreciation demarcation, Partial Discharge Detection and resistance to according to control unit 120 to power cable Analysis process during pressure detection is pointed out.Such as, when detecting the sensitivity of Partial discharge detector 200, retrospective Power cable detecting and controlling system 100 brings into operation after 5s, and " shelf depreciation calibration operation can in Tip element 150 meeting prompting automatically To start ";When the current voltage value that data acquisition unit 110 gathers is more than 0.5V, Tip element 150 can show automatically: Shelf depreciation calibration should be calibrated in the case of not charged, and this operation does not meets standard-required.
Additionally, the retrospective power cable detecting and controlling system 100 of the present embodiment also includes that a client is (attached in description Figure indicates) for checking and call detection process and the data of power cable detecting and controlling system 100.Further, this visitor The position of family end according to actual needs, i.e. may be provided at Partial discharge detector 200 and the vicinity of Hi-pot Tester 300, it is possible to It is disposed at Partial discharge detector 200 and the far-end of Hi-pot Tester 300, to facilitate user to check.
In sum, the retrospective power cable detecting and controlling system of the present invention, its based on existing Partial discharge detector and Hi-pot Tester, simply at reviewed to the power cable detecting and controlling system of its external connection present invention, can complete electric power electricity The partial discharge detection of cable and the monitoring of resistance test, guide, analyze and judge, be greatly saved cost;Further, the present invention can The detection data of often dish power cable are carried out real-time storage, discovery is generated to problem present in manufacturing, except data are the most auxiliary Match with video, cable user is had more cogency;The present invention can remotely monitor and call the detection data dispatched from the factory, for The remotely prison of user is made and is provided possibility, decreases man power and material's cost that prison is made.So, the present invention effectively overcomes existing Various shortcoming in technology and have high industrial utilization.
The principle of above-described embodiment only illustrative present invention and effect thereof, not for limiting the present invention.Any it is familiar with this skill Above-described embodiment all can be modified under the spirit and the scope of the present invention or change by the personage of art.Therefore, such as All that in art, tool usually intellectual is completed under without departing from disclosed spirit and technological thought etc. Effect is modified or changes, and must be contained by the claim of the present invention.

Claims (10)

1. a retrospective power cable detecting and controlling system, it is characterised in that: described power cable detecting and controlling system respectively with office Portion's discharge test detector is connected with Hi-pot Tester, including: data acquisition unit, control unit, memory element and video Monitoring power supply;Wherein,
Described video monitor unit is for monitoring described shelf depreciation test detector and the power cable of described Hi-pot Tester The process of detection;
Described data acquisition unit is for shelf depreciation test detector and the detection of described Hi-pot Tester described in Real-time Collection The monitor video data of data and described video monitor unit;
Described control unit is used for controlling and guide described Partial discharge detector and described Hi-pot Tester to carry out power cable Detection, controls described video monitor unit and monitors described Partial discharge detector and the power cable of described Hi-pot Tester in real time The process of detection, the described detection data and the described monitor video data that gather described data acquisition unit carry out whole splitting or integrating Analysis processes and judges;
Described memory element is for preserving the described monitor video data through integrating and described detection data, and preserves described control Control that power cable is detected by unit processed, the process guiding, analyze and process and judging.
Retrospective power cable detecting and controlling system the most according to claim 1, it is characterised in that: described power cable detects Including the partial discharge detection carried out by described shelf depreciation test detector and the pressure inspection carried out by described Hi-pot Tester Survey.
Retrospective power cable detecting and controlling system the most according to claim 2, it is characterised in that: described detection data include Partial discharge detection data and resistance test data;Described monitor video data include partial discharge detection monitor video data and resistance test Monitor video data.
Retrospective power cable detecting and controlling system the most according to claim 2, it is characterised in that: described control unit includes Office puts control subelement, pressure control subelement and video and controls subelement;Wherein,
Control subelement is put for controlling, guide and analyze the described partial discharge detection of described Partial discharge detector in described office;
Described pressure control subelement is for controlling, guide and analyze the described resistance test of described Hi-pot Tester;
Described video control subelement is used for controlling described video monitor unit and monitors described Partial discharge detector and institute in real time State the process of the power cable detection of Hi-pot Tester, and the described monitor video that will be collected by described data acquisition unit It is corresponding that data carry out integration with described detection data.
Retrospective power cable detecting and controlling system the most according to claim 4, it is characterised in that: it is single that control is put in described office Unit controls, guides and analyzes described Partial discharge detector and includes detecting the sensitivity of described Partial discharge detector and judge institute State the qualification rate of partial discharge detection.
Retrospective power cable detecting and controlling system the most according to claim 5, it is characterised in that: it is single that control is put in described office Unit detects the sensitivity of described Partial discharge detector and includes:
Step S21, guides and controls described Partial discharge detector calibration shelf depreciation, and steady at shelf depreciation demarcation signal After Ding, control described data acquisition unit and gather shelf depreciation scalar quantity and the current voltage of described Partial discharge detector Value;
Step S22, it is judged that described current voltage value: if described current voltage value is less than 0.5V, then judge that calibration local is put Electricity is carried out in the case of uncharged, jumps to step S23;Otherwise, described power cable detecting and controlling system reports an error;
Step S23, display is put in the background interference values drawn game controlling the described Partial discharge detector of described data acquisition unit collection Value;
Step S24, puts show value according to described office and described background interference values judges the sensitive of described Partial discharge detector Degree.
Retrospective power cable detecting and controlling system the most according to claim 6, it is characterised in that: described Partial Discharge Detection The sensitivity of instrument is relevant to the model of power cable.
Retrospective power cable detecting and controlling system the most according to claim 6, it is characterised in that: it is single that control is put in described office Unit judges that the qualification rate of described partial discharge detection includes:
Step S31, by described data acquisition unit according to acquisition time interval Real-time Collection detection voltage;
Step S32, calculates partial discharge quantity measured value according to described detection voltage;
According to described background interference values and described shelf depreciation measurement, step S33, judges whether described partial discharge detection closes Lattice.
Retrospective power cable detecting and controlling system the most according to claim 8, it is characterised in that: described shelf depreciation measures The standard that value is the most qualified with described partial discharge detection is all relevant to the model of power cable.
Retrospective power cable detecting and controlling system the most according to claim 8, it is characterised in that: described power cable is examined Survey control system and also include Tip element.
CN201510152290.6A 2015-04-01 2015-04-01 A kind of retrospective power cable detecting and controlling system Pending CN106154122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510152290.6A CN106154122A (en) 2015-04-01 2015-04-01 A kind of retrospective power cable detecting and controlling system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510152290.6A CN106154122A (en) 2015-04-01 2015-04-01 A kind of retrospective power cable detecting and controlling system

Publications (1)

Publication Number Publication Date
CN106154122A true CN106154122A (en) 2016-11-23

Family

ID=57338319

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510152290.6A Pending CN106154122A (en) 2015-04-01 2015-04-01 A kind of retrospective power cable detecting and controlling system

Country Status (1)

Country Link
CN (1) CN106154122A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113884824A (en) * 2021-08-13 2022-01-04 杭州龙源电力有限公司 Cable voltage withstand test method based on ultralow frequency voltage
CN115222741A (en) * 2022-09-20 2022-10-21 江苏昱恒电气有限公司 Cable surface defect detection method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030160618A1 (en) * 2002-02-28 2003-08-28 Jens Titschert Method and circuit arrangement for measuring earth leakages in intrinsically safe current feeds
CN201096870Y (en) * 2007-09-04 2008-08-06 上海宝钢设备检修有限公司 Installation status diagnosis device for high-voltage AC motor
CN201373905Y (en) * 2009-03-04 2009-12-30 厦门红相电力设备股份有限公司 Safety detecting evaluation system of power cable
CN102565637A (en) * 2011-12-12 2012-07-11 广东电网公司电力科学研究院 Oscillation wave partial discharge detection system for cable based on asynchronous double-end measurement
CN202393840U (en) * 2011-08-25 2012-08-22 中国电力科学研究院 Mobile laboratory for detecting power equipment state
CN103018605A (en) * 2012-12-11 2013-04-03 工业和信息化部电子第五研究所 Electronic component detection test monitoring system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030160618A1 (en) * 2002-02-28 2003-08-28 Jens Titschert Method and circuit arrangement for measuring earth leakages in intrinsically safe current feeds
CN201096870Y (en) * 2007-09-04 2008-08-06 上海宝钢设备检修有限公司 Installation status diagnosis device for high-voltage AC motor
CN201373905Y (en) * 2009-03-04 2009-12-30 厦门红相电力设备股份有限公司 Safety detecting evaluation system of power cable
CN202393840U (en) * 2011-08-25 2012-08-22 中国电力科学研究院 Mobile laboratory for detecting power equipment state
CN102565637A (en) * 2011-12-12 2012-07-11 广东电网公司电力科学研究院 Oscillation wave partial discharge detection system for cable based on asynchronous double-end measurement
CN103018605A (en) * 2012-12-11 2013-04-03 工业和信息化部电子第五研究所 Electronic component detection test monitoring system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113884824A (en) * 2021-08-13 2022-01-04 杭州龙源电力有限公司 Cable voltage withstand test method based on ultralow frequency voltage
CN115222741A (en) * 2022-09-20 2022-10-21 江苏昱恒电气有限公司 Cable surface defect detection method

Similar Documents

Publication Publication Date Title
EP3170012B1 (en) Method and system of fault detection and localisation in dc-systems
US10317452B2 (en) Testing device, testing method, and program for power system protection control system
CN105759147A (en) Integrated test device for battery management system of electric vehicle
CN105203980A (en) Electric energy quality self-inspection system and self-inspection method thereof
KR101151742B1 (en) Portable System for Diagnosis of Partial Discharge
CN103869168A (en) Detecting and diagnosing method for secondary circuit of current transformer for electric power
CN105187608A (en) Method and device obtaining power consumption of application program in mobile terminal
CN117520951B (en) Transformer health assessment method and system based on multiple characteristic quantities
CN107884737A (en) The live capacitive apparatus on-line monitoring check system and method for wireless high-precise synchronization
CN106154122A (en) A kind of retrospective power cable detecting and controlling system
CN116760191A (en) Power load debugging method and device
CN104931798B (en) The source range impulsive measurement device and its detection localization method of out-pile Nuclear Instrument system
CN107543574B (en) Automatic detector for high-temperature aging test of airborne sensor and operation method
CN115469241A (en) Fault detection method and device for charging module of direct-current power supply system
KR101736230B1 (en) System and method for quantifying the fault detection rate
CN201199267Y (en) Radioactivity detecting instrument with fault detection function
EP2945035A1 (en) Method and system for detecting and locating one or more wiring defect in dedicated aircraft systems
CN210270227U (en) Intelligent base test box capable of realizing self diagnosis
CN110967615B (en) Circuit board fault diagnosis device and method
KR101692473B1 (en) Inspection Apparatus for Flight Data Recording Device
CN208506587U (en) A kind of safe instrument control system cabinet capacitance detecting device
CN106291195A (en) A kind of Intellectualized starting functional transformer comprehensive test device
CN105807215A (en) Test equipment and test method for secondary circuit relay of energy storage unit
CN113504498B (en) Performance detection method and system of partial discharge intelligent sensing terminal
CN211927202U (en) SF (sulfur hexafluoride)6Gas leakage on-line detection device in electrical equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161123

RJ01 Rejection of invention patent application after publication