CN106154084A - Network load exception and operation risk real-time monitoring and early warning method - Google Patents

Network load exception and operation risk real-time monitoring and early warning method Download PDF

Info

Publication number
CN106154084A
CN106154084A CN201610563688.3A CN201610563688A CN106154084A CN 106154084 A CN106154084 A CN 106154084A CN 201610563688 A CN201610563688 A CN 201610563688A CN 106154084 A CN106154084 A CN 106154084A
Authority
CN
China
Prior art keywords
data
load
real
power
network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610563688.3A
Other languages
Chinese (zh)
Other versions
CN106154084B (en
Inventor
陈远扬
陈浩
李光辉
张思远
黄际元
王灿林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610563688.3A priority Critical patent/CN106154084B/en
Publication of CN106154084A publication Critical patent/CN106154084A/en
Application granted granted Critical
Publication of CN106154084B publication Critical patent/CN106154084B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a kind of network load exception and operation risk real-time monitoring and early warning method, set up the step of expert knowledge library including acquisition data;Obtain the step of real-time telemetry remote signalling amount;Determine operation of power networks state, it is judged that data fluctuations and Flushing status the step reported to the police;The step of identification operation of power networks topological structure;Identification electrical network weak link and security risk grade the step reported to the police;The control nargin judging operation of power networks section the step reported to the police.The present invention is based on the stable state supervision to plant stand telemetry, dynamic monitoring and assessment electrical network real time execution weak spot, data are not refreshed, network load fluctuation, low-frequency oscillation, safe operation of electric network risk and control the abnormal conditions such as stability margin is not enough and carry out auxiliary record and alarm prompt, for scheduling, operator on duty monitors offer important evidence in real time, alleviate operator on duty's working strength, effectively control operation of power networks risk, provide science decision for accident treatment.

Description

Network load exception and operation risk real-time monitoring and early warning method
Technical field
The invention belongs to power system automatic field, be specifically related to a kind of network load exception and operation risk is supervised in real time Control method for early warning.
Background technology
Along with the fast development of China's interconnection power system and moving forward steadily of extra-high voltage grid construction, operation of power networks Technical merit and complexity are more and more higher, and the difficulty that operation of power networks controls is increasing;
1) Traditional Man monitors the most competent modern extensive interconnected network requirement of important service data.It is responsible for provincial power network frequency Rate and the daily supervision of voltage and the scheduling operator on duty of control, take and always generate (confession) electric real-time curve, each tracking machine to saving net quarter Group has in real time, idle exerts oneself, large reservoir goes out, each plant stand busbar voltage and transmission line of electricity are netted by reservoir inflow and real time water level, province Have, idle and important operation section tidal current carries out monitoring and participate in adjust.Along with electrical network scale increases day by day, monitor number per capita Being continuously increased according to amount, Traditional Man naked eyes have been difficult to the supervision of the most complicated competent real-time running data;
2) topological structure of electric becomes increasingly complex.In recent years in power grid construction, for saving Financial cost, the power transmission line of parallel lines on same tower Road gets more and more, and its different name phase short trouble exists the operation risk of N-2, and distinguishes topological structure of electric weak spot intelligence at present The automatic technology support means known are limited, and tradition relies on the experience scheduling method of scheduling operator on duty and is difficult to find and control electricity The operation risk that net is hidden;
3) network stability control regulation is increasingly harsher.Power system operating mode professional is for electric network composition and electric load water Flat, in conjunction with electrical network typical operation modes such as electrical network summer, winters, establishment operation of power networks controls requirement, comprises start-up mode, rotation Standby requirement, transmission cross-section be normal/and maintenance mode controls limit, the surely control of plant stand Intellectual computer etc..Along with electrical network scale increases day by day Greatly, the method for operation is day by day flexible, stability contorting regulation the most complicated severe sternly, only remember by scheduling operator on duty be difficult to ensure that right Operation of power networks stability contorting requires to make the judgement of fast accurate;
4) the abnormal such as load fluctuation of electrical network is the electrical network dynamic stability problems such as the forced power oscillation of typical characteristic, low-frequency oscillation Day by day highlight.The WAMS constituted based on synchronous phasor measuring device (Phasor Measurement Unit, PMU) (Wide Area Measurement System, WAMS) has directly measurement node voltage phasor and branch current phasor, number The advantage such as high according to precision, transmission delay is short, but for state-of-the art, the whole network layout economic problems that PMU brought with And this two big bottleneck of technical problem being brought the storage process of magnanimity metric data, management and utilization, calculating communication determines Within the long duration, WAMS still needs to combine based on the number on EMS (Energy Manager System, EMS) According to gathering and monitoring system (Supervisory Control And Acquisition, SCADA), Power system dynamic process is entered Row prepares to analyze in real time.
Summary of the invention
It is an object of the invention to provide one can the most effectively analyze topological structure of electric, find that operation of power networks is weak Point and operation exception risk reporting to the police, thus alleviate operator on duty's working strength, the electrical network that effectively controls operation of power networks risk is born Lotus exception and operation risk real-time monitoring and early warning method.
This network load exception of present invention offer and operation risk real-time monitoring and early warning method, comprise the steps:
Obtain basic electrical network data and the service data of provincial power network, set up provincial power network and run the step of expert knowledge library;
The step of the electrical network EMS/SCADA real-time telemetry remote signalling amount under acquisition operation of power networks state in real time;
According to the electrical network EMS/SCADA real-time telemetry remote signalling amount obtained, determine putting into operation of electrical network unit, bus, circuit and main transformer State;Judge fluctuation status and the Flushing status of data, and the data that data fluctuations exception or Refresh Data are abnormal are reported Alert step;
According to the electrical network EMS obtained and SCADA real-time telemetry remote signalling amount, the step of the topological structure of real-time identification operation of power networks;
Electrical network EMS and SCADA real-time telemetry remote signalling amount according to the operation of power networks topological structure obtained and acquisition, identification electrical network is transported Weak link in row and security risk grade the step reported to the police;
Electrical network EMS and SCADA real-time telemetry remote signalling amount according to the operation of power networks topological structure obtained and acquisition, it is judged that electrical network is transported The control nargin of row section, and the step reported to the police is carried out when controlling nargin and being unsatisfactory for requiring.
The basic electrical network data of described provincial power network and service data, including circuit parallel lines on same tower information, transmission cross-section Control limit, the area power grid method of operation and accident investigation code regulation.
The described area power grid method of operation includes running for various places/city, each 220kV station bus of county/district's electric power, main transformer Mode, 110kV side open loop point and load prepared auto restart situation and the 110kV side grid power source method of operation.
Described accident investigation code regulation includes that various places/city under Pyatyi and above power grid risk, county/district subtract for load number Amount, ratio and other improper stoppage in transit events.
Electrical network EMS/SCADA real-time telemetry remote signalling amount under described operation of power networks state, fills including from each plant stand observing and controlling Put the remote measure and communication amount of the primary equipment of real-time measurement and be forwarded to the data value of main website from higher level, brother regulation and control center.
Described remote measure and communication amount is divided into interconnection trend between important net, Hydropower Unit to gain merit, fired power generating unit is meritorious, contact Transformer active trend and transmission line of electricity effective power flow.
Between described important net, interconnection trend interconnects and exchanges power disturbance to whole system frequency two-by-two for relating to region Produce the trend of the section of impact.
Described Hydropower Unit is gained merit and is included accessing the meritorious number of the tracking Hydropower Unit of 220kV electric pressure and above electrical network According to.
Described fired power generating unit is gained merit and is included accessing the meritorious number of the tracking fired power generating unit of 220kV electric pressure and above electrical network According to.
The three side effective power flow numbers including the interior 500kV electric pressure main transformer of province's net of described connecting transformer effective power flow According to.
Described transmission line of electricity effective power flow includes 220kV electric pressure and the effective power flow number of above transmission line of electricity in province's net According to.
The state that puts into operation of described determination electrical network unit, bus, circuit and main transformer, is specially according to the electrical network EMS/ obtained SCADA real-time telemetry remote signalling amount, obtain unit, main transformer, bus, the real-time mode of connection of circuit, and be calculated electrical network unit, The state that puts into operation of bus, circuit and main transformer.
The fluctuation status of described judgement data and Flushing status, and to data fluctuations exception or the number of Refresh Data exception According to reporting to the police, it is specially and carries out fluctuation status and the judgement of Flushing status for network load data and report to the police.
The described fluctuation status to load data judges and reports to the police, and specifically includes following steps:
A. according to the data obtained, it is judged that load type;
B. according to load type, corresponding fluctuation threshold threshold value is read;
C. the undulate quantity of calculated load data, and judge the size between the undulate quantity of load data and fluctuation threshold threshold value: if The undulate quantity of load data is more than fluctuation threshold threshold value, then recording this load data is single load data fluctuation suspicious points, Send single load fluctuation warning;
D. to single load fluctuation suspicious points, according to the size of twice load data before and after it, it is judged that this time load fluctuation is suspicious Point for forward fluctuation or reversely fluctuates;
E. in statistics load data, the number of times that load data fluctuates continuously, and enter with the frequency threshold value of fluctuation continuously arranged in advance Row contrast:
If the continuously number of times of fluctuation > continuously fluctuation frequency threshold value and continuously fluctuation be forward, reversely fluctuate regularly, then judge For low-frequency oscillation suspicious points, and report to the police;Otherwise it is judged to common load fluctuation.
The undulate quantity of described load data, specially uses following rule to calculate:
If load type is interconnection flow data between net, Hydropower Unit is meritorious or fired power generating unit is gained merit, then the ripple of load data The load data value of momentum=(the load data value of load data value sampling last time of this sampling) sampling/last time;
If load type is connecting transformer effective power flow or transmission line of electricity effective power flow, then the undulate quantity of load data is this The load data of sampling and the difference of the front load data amount once sampled.
The described Flushing status to load data judges and reports to the police, and specifically includes following steps:
. according to the data obtained, it is judged that load type;
. according to load type, read corresponding data higher limit, lower limit and do not refresh threshold threshold value;
. judge that load data is whether between data higher limit and the lower limit set: if load data is beyond data Higher limit or less than data lower limit, then assert that this load data is abnormal, and report to the police;
. if load data between data higher limit and the lower limit set, then calculates this load data and adopts with the last time Difference between the load data of sample;
. the size judging the difference described in step with not refreshing threshold threshold value: if difference is less than not refreshing threshold threshold Value, then assert that now load data does not refreshes, be designated as a secondary data and do not refresh suspicious points;
. the data that statistics occurs continuously do not refresh the number of suspicious points, if the data occurred continuously do not refresh suspicious points number of times > warning threshold that sets, then preliminary judgement data within this period do not refresh;
. the most artificial remote measurement combining load data corresponding device analog value suppresses information to enter updated load data Row real time correction, whether final this load data of judgement does not refreshes: if finally judging, this load data does not refreshes, then push automatically Change quality of data abnormality alarming.
The topological structure of described identification operation of power networks, specifically includes following steps:
1) obtained tracking power plant, the remote signalling amount of transformer station's wire-outgoing breaker in real time by EMS/SCADA system and judge power network topology Structure and start-up mode;
2) by EMS/SCADA system obtain grid equipment set, put board information, and with this system set, put the excellent of board information The principle of the data that first level obtains in real time higher than system, corrects topological structure of electric, and identification obtains opening up of operation of power networks Flutter structure.
The described weak link in identification operation of power networks and security risk grade are also reported to the police, and specifically include following steps:
1. according to the topological structure of operation of power networks, obtain and be only total to the single of bar line powering by single back transmission line or many times 220kV transformer station or multiple 220kV transformer station group linked together, and described transformer station is constituted set Mi, electrical network Middle all such transformer station constitutes set M={Mi};Obtaining bus connection type is double-bus or 3/2 wiring, and because part is female Line has a power failure and causes the 220kV that runs in single bus-bar operation mode and above power plant and transformer station, and by described power plant and power transformation Composition of standing set N;
2. number b of the 220KV transformer station comprised in number a of the 220KV transformer station comprised in set M, and set N is obtained; If a >=1 or b >=1, then judging that electrical network exists security risk, EMS system pushes the warning of Pyatyi grid event risk;
3. check the load type of all transformer stations in set M, comprise the set M of any county-level city j load for loadi, meter Calculate transformer station set MiCounty-level city's j load of burden accounts for ratio x of county-level city's j total load, obtains transformer station set MiThe county of burden The user of level city j accounts for total user's ratio y of county-level city j;
4. according to the accident investigation code of state's net, it is determined that whether the value of x and y is more than the threshold value specified: if x or y is more than regulation Threshold value, then EMS system pushes the warning of level Four grid event risk;
3. and 4. 5. for all transformer stations in set N, step is repeated, the weak link in identification operation of power networks and safety Risk class is also reported to the police.
The described control nargin judging operation of power networks section is also reported to the police, and specifically includes following steps:
A. require power plant or the power plant group unit operation number of units monitored in specifying according to the stabilization of power grids, set up set of variables Di;
B. electrical network Real-time Load amount F monitored, steady control cutting load amount Q and the definition of step a are required according to the stabilization of power grids in specifying Power plant or power plant group unit operation number of units Di, index stabilization of power grids regulation, determine each transmission cross-section under current electric grid operation level Stability limitation [Pi] and the unit of power plant or power plant group reserve spinning reserve amount [Xi];
C. the size of real-time transmission cross-section Pi and the transmission cross-section stability limitation [Pi] of calculating, and power plant or power plant in real time are compared The unit spinning reserve Xi of group and the size that spinning reserve amount [Xi] should be reserved: if transmission cross-section stability limitation is more than calculating in real time Transmission cross-section stability limitation Pi >=[Pi], or the unit spinning reserve of in real time power plant or power plant group is less than reserving spinning reserve Amount Xi≤[Xi], then EMS system pushes the alarm of stabilization of power grids nargin deficiency.
The dynamic surveillance that the present invention measures independent of PMU, based on the stable state supervision to plant stand telemetry, makes full use of into Ripe EMS/SCADA technology, by the meritorious tide of primary equipment (unit, main transformer, circuit etc.) in real-time sampling operation of power networks operating mode The main loads amounts such as stream, and above-mentioned sampled data is carried out background synchronization integration and calculating process, dynamic monitoring and assessment electrical network Real time execution weak spot, automation data is not refreshed, network load fluctuation, low-frequency oscillation, safe operation of electric network risk higher And control the abnormal conditions such as stability margin is not enough and carry out auxiliary record and alarm prompt, provide for scheduling operator on duty's prison dish in real time Another important evidence, provides science decision for accident treatment.The application of the present invention can the most effectively analyze topological structure of electric, Find operation of power networks weak spot and operation exception risk and report to the police, thus alleviating operator on duty's working strength, effectively control electrical network Operation risk.
Accompanying drawing explanation
Fig. 1 is the method flow diagram of the present invention.
Detailed description of the invention
It is illustrated in figure 1 the method flow diagram of the present invention: this network load exception that the present invention provides and operation risk Monitoring and early warning method, comprises the steps: in real time
Obtain basic electrical network data and the service data of provincial power network, control limit including circuit parallel lines on same tower information, transmission cross-section Volume, the area power grid method of operation and accident investigation code regulation etc., set up provincial power network and run the step of expert knowledge library;
The area power grid method of operation includes for various places/city, each 220kV station bus, the main transformer method of operation, the 110kV of county/district's electric power Side open loop point and load prepared auto restart situation and the 110kV side grid power source method of operation etc.;Accident investigation code regulation includes Pyatyi And various places/city, county/district subtract for load quantity, ratio and other improper stoppage in transit events etc. under above power grid risk.
The step of the electrical network EMS/SCADA real-time telemetry remote signalling amount under acquisition operation of power networks state in real time;Described electrical network Electrical network EMS/SCADA real-time telemetry remote signalling amount under running status includes the primary equipment from each plant stand measure and control device real-time measurement Remote measure and communication amount and be forwarded to the data value of main website from higher level, brother regulation and control center.
And remote measure and communication amount is divided into, and interconnection trend between important net, Hydropower Unit are meritorious, fired power generating unit is meritorious, contact becomes Depressor effective power flow and transmission line of electricity effective power flow.
Between important net, interconnection trend interconnects and exchanges power disturbance to the generation of whole system frequency two-by-two for relating to region The trend of the section of impact;Hydropower Unit is gained merit and is included accessing the tracking Hydropower Unit of 220kV electric pressure and above electrical network Meritorious data;Fired power generating unit is gained merit and is included accessing the meritorious data of the tracking fired power generating unit of 220kV electric pressure and above electrical network; The three side effective power flow data including the interior 500kV electric pressure main transformer of province's net of connecting transformer effective power flow;Transmission line of electricity has Merit trend includes 220kV electric pressure and the effective power flow data of above transmission line of electricity in province's net.
According to the electrical network EMS/SCADA real-time telemetry remote signalling amount obtained, obtain unit, main transformer, bus, the connecing in real time of circuit Line mode, and it is calculated the state that puts into operation of electrical network unit, bus, circuit and main transformer;Judge fluctuation status and the refreshing of data State, and network load data are carried out fluctuation status and the judgement of Flushing status the step reported to the police;
The fluctuation status of load data judged and report to the police, specifically including following steps:
A. according to the data obtained, it is judged that load type;
B. according to load type, corresponding fluctuation threshold threshold value is read;
C. the undulate quantity of calculated load data, and judge the size between the undulate quantity of load data and fluctuation threshold threshold value: if The undulate quantity of load data is more than fluctuation threshold threshold value, then recording this load data is single load data fluctuation suspicious points, Send single load fluctuation warning;
The undulate quantity of employing following rule calculated load data:
If load type is interconnection flow data between net, Hydropower Unit is meritorious or fired power generating unit is gained merit, then the ripple of load data The load data value of momentum=(the load data value of load data value sampling last time of this sampling) sampling/last time;
If load type is connecting transformer effective power flow or transmission line of electricity effective power flow, then the undulate quantity of load data is this The load data of sampling and the difference of the front load data amount once sampled;
D. to single load fluctuation suspicious points, according to the size of twice load data before and after it, it is judged that this time load fluctuation is suspicious Point for forward fluctuation or reversely fluctuates;
E. in statistics load data, the number of times that load data fluctuates continuously, and enter with the frequency threshold value of fluctuation continuously arranged in advance Row contrast:
If the continuously number of times of fluctuation > continuously fluctuation frequency threshold value and continuously fluctuation be forward, reversely fluctuate regularly, then judge For low-frequency oscillation suspicious points, and report to the police;Otherwise it is judged to common load fluctuation.
The Flushing status of load data judged and report to the police, then specifically including following steps:
. according to the data obtained, it is judged that load type;
. according to load type, read corresponding data higher limit, lower limit and do not refresh threshold threshold value;
. judge that load data is whether between data higher limit and the lower limit set: if load data is beyond data Higher limit or less than data lower limit, then assert that this load data is abnormal, and report to the police;
. if load data between data higher limit and the lower limit set, then calculates this load data and adopts with the last time Difference between the load data of sample;
. the size judging the difference described in step with not refreshing threshold threshold value: if difference is less than not refreshing threshold threshold Value, then assert that now load data does not refreshes, be designated as a secondary data and do not refresh suspicious points;
. the data that statistics occurs continuously do not refresh the number of suspicious points, if the data occurred continuously do not refresh suspicious points number of times > warning threshold that sets, then preliminary judgement data within this period do not refresh;
. the most artificial remote measurement combining load data corresponding device analog value suppresses information to enter updated load data Row real time correction, whether final this load data of judgement does not refreshes: if finally judging, this load data does not refreshes, then push automatically Change quality of data abnormality alarming.
According to the electrical network EMS obtained and SCADA real-time telemetry remote signalling amount, following steps are used to know the topology knot of operation of power networks Structure:
1) obtained tracking power plant, the remote signalling amount of transformer station's wire-outgoing breaker in real time by EMS/SCADA system and judge power network topology Structure and start-up mode;
2) by EMS/SCADA system obtain grid equipment set, put board information, and with this system set, put the excellent of board information The principle of the data that first level obtains in real time higher than system, corrects topological structure of electric, and identification obtains opening up of operation of power networks Flutter structure.
Electrical network EMS and SCADA real-time telemetry remote signalling amount according to the operation of power networks topological structure obtained and acquisition, uses such as Weak link in lower step identification operation of power networks and security risk grade are also reported to the police:
1. according to the topological structure of operation of power networks, obtain and be only total to the single of bar line powering by single back transmission line or many times 220kV transformer station or multiple 220kV transformer station group linked together, and described transformer station is constituted set Mi, electrical network Middle all such transformer station constitutes set M={Mi};Obtaining bus connection type is double-bus or 3/2 wiring, and because part is female Line has a power failure and causes the 220kV that runs in single bus-bar operation mode and above power plant and transformer station, and by described power plant and power transformation Composition of standing set N;
2. number b of the 220KV transformer station comprised in number a of the 220KV transformer station comprised in set M, and set N is obtained; If a >=1 or b >=1, then judging that electrical network exists security risk, EMS system pushes the warning of Pyatyi grid event risk;
3. check the load type of all transformer stations in set M, comprise the set M of any county-level city j load for loadi, meter Calculate transformer station set MiCounty-level city's j load of burden accounts for ratio x of county-level city's j total load, obtains transformer station set MiThe county of burden The user of level city j accounts for total user's ratio y of county-level city j;
4. according to the accident investigation code of state's net, it is determined that whether the value of x and y is more than the threshold value specified: if x or y is more than regulation Threshold value, then EMS system pushes the warning of level Four grid event risk;
3. and 4. 5. for all transformer stations in set N, step is repeated, the weak link in identification operation of power networks and safety Risk class is also reported to the police.
Electrical network EMS and SCADA real-time telemetry remote signalling amount according to the operation of power networks topological structure obtained and acquisition, according to such as Lower step judges the control nargin of operation of power networks section, and reports to the police when controlling nargin and being unsatisfactory for requiring:
A. require power plant or the power plant group unit operation number of units monitored in specifying according to the stabilization of power grids, set up set of variables Di;
B. electrical network Real-time Load amount F monitored, steady control cutting load amount Q and the definition of step a are required according to the stabilization of power grids in specifying Power plant or power plant group unit operation number of units Di, index stabilization of power grids regulation, determine each transmission cross-section under current electric grid operation level Stability limitation [Pi] and the unit of power plant or power plant group reserve spinning reserve amount [Xi];
C. the size of real-time transmission cross-section Pi and the transmission cross-section stability limitation [Pi] of calculating, and power plant or power plant in real time are compared The unit spinning reserve Xi of group and the size that spinning reserve amount [Xi] should be reserved: if transmission cross-section stability limitation is more than calculating in real time Transmission cross-section stability limitation Pi >=[Pi], or the unit spinning reserve of in real time power plant or power plant group is less than reserving spinning reserve Amount Xi≤[Xi], then EMS system pushes the alarm of stabilization of power grids nargin deficiency.

Claims (19)

1. network load exception and an operation risk real-time monitoring and early warning method, comprise the steps:
Obtain basic electrical network data and the service data of provincial power network, set up provincial power network and run the step of expert knowledge library;
The step of the electrical network EMS/SCADA real-time telemetry remote signalling amount under acquisition operation of power networks state in real time;
According to the electrical network EMS/SCADA real-time telemetry remote signalling amount obtained, determine putting into operation of electrical network unit, bus, circuit and main transformer State;Judge fluctuation status and the Flushing status of data, and the data that data fluctuations exception or Refresh Data are abnormal are reported Alert step;
According to the electrical network EMS obtained and SCADA real-time telemetry remote signalling amount, the step of the topological structure of real-time identification operation of power networks;
Electrical network EMS and SCADA real-time telemetry remote signalling amount according to the operation of power networks topological structure obtained and acquisition, identification electrical network is transported Weak link in row and security risk grade the step reported to the police;
Electrical network EMS and SCADA real-time telemetry remote signalling amount according to the operation of power networks topological structure obtained and acquisition, it is judged that electrical network is transported The control nargin of row section, and the step reported to the police is carried out when controlling nargin and being unsatisfactory for requiring.
Network load exception the most according to claim 1 and operation risk real-time monitoring and early warning method, it is characterised in that institute The basic electrical network data of the provincial power network stated and service data, including circuit parallel lines on same tower information, transmission cross-section control limit, District's power system operating mode and accident investigation code regulation.
Network load exception the most according to claim 1 and operation risk real-time monitoring and early warning method, it is characterised in that institute The area power grid method of operation stated includes for various places/city, each 220kV station bus, the main transformer method of operation, the 110kV of county/district's electric power Side open loop point and load prepared auto restart situation and the 110kV side grid power source method of operation.
Network load exception the most according to claim 1 and operation risk real-time monitoring and early warning method, it is characterised in that institute State accident investigation code regulation include various places/city under Pyatyi and above power grid risk, county/district subtract for load quantity, ratio and Other improper stoppage in transit events.
5. according to the network load exception one of claim 1 ~ 4 Suo Shu and operation risk real-time monitoring and early warning method, its feature The electrical network EMS/SCADA real-time telemetry remote signalling amount being under described operation of power networks state, including real from each plant stand measure and control device Time the remote measure and communication amount of primary equipment that measures and be forwarded to the data value of main website from higher level, brother regulation and control center.
Network load exception the most according to claim 5 and operation risk real-time monitoring and early warning method, it is characterised in that institute The remote measure and communication amount stated is divided into interconnection trend between important net, Hydropower Unit to gain merit, fired power generating unit is meritorious, connecting transformer is gained merit Trend and transmission line of electricity effective power flow.
Network load exception the most according to claim 6 and operation risk real-time monitoring and early warning method, it is characterised in that institute Stating interconnection trend between important net is to relate to region to interconnect and exchange power disturbance two-by-two to the generation impact of whole system frequency The trend of section.
Network load exception the most according to claim 7 and operation risk real-time monitoring and early warning method, it is characterised in that institute State Hydropower Unit to gain merit and include accessing the meritorious data of the tracking Hydropower Unit of 220kV electric pressure and above electrical network.
Network load exception the most according to claim 8 and operation risk real-time monitoring and early warning method, it is characterised in that institute State fired power generating unit to gain merit and include accessing the meritorious data of the tracking fired power generating unit of 220kV electric pressure and above electrical network.
Network load exception the most according to claim 9 and operation risk real-time monitoring and early warning method, it is characterised in that institute State the three side effective power flow data including the interior 500kV electric pressure main transformer of province's net of connecting transformer effective power flow.
11. network load exceptions according to claim 10 and operation risk real-time monitoring and early warning method, it is characterised in that Described transmission line of electricity effective power flow includes 220kV electric pressure and the effective power flow data of above transmission line of electricity in province's net.
12. network load exceptions according to claim 11 and operation risk real-time monitoring and early warning method, it is characterised in that The state that puts into operation of described determination electrical network unit, bus, circuit and main transformer, is specially according to the electrical network EMS/SCADA obtained real Time remote measure and communication amount, obtain unit, main transformer, bus, the real-time mode of connection of circuit, and be calculated electrical network unit, bus, line Road and the state that puts into operation of main transformer.
13. network load exceptions according to claim 12 and operation risk real-time monitoring and early warning method, it is characterised in that The fluctuation status of described judgement data and Flushing status, and the data that data fluctuations exception or Refresh Data are abnormal are reported Alert, it is specially and carries out fluctuation status and the judgement of Flushing status for network load data and report to the police.
14. network load exceptions according to claim 13 and operation risk real-time monitoring and early warning method, it is characterised in that The described fluctuation status to load data judges and reports to the police, and specifically includes following steps:
A. according to the data obtained, it is judged that load type;
B. according to load type, corresponding fluctuation threshold threshold value is read;
C. the undulate quantity of calculated load data, and judge the size between the undulate quantity of load data and fluctuation threshold threshold value: if The undulate quantity of load data is more than fluctuation threshold threshold value, then recording this load data is single load data fluctuation suspicious points, Send single load fluctuation warning;
D. to single load fluctuation suspicious points, according to the size of twice load data before and after it, it is judged that this time load fluctuation is suspicious Point for forward fluctuation or reversely fluctuates;
E. in statistics load data, the number of times that load data fluctuates continuously, and enter with the frequency threshold value of fluctuation continuously arranged in advance Row contrast:
If the continuously number of times of fluctuation > continuously fluctuation frequency threshold value and continuously fluctuation be forward, reversely fluctuate regularly, then judge For low-frequency oscillation suspicious points, and report to the police;Otherwise it is judged to common load fluctuation.
15. network load exceptions according to claim 14 and operation risk real-time monitoring and early warning method, it is characterised in that The undulate quantity of described load data, specially uses following rule to calculate:
If load type is interconnection flow data between net, Hydropower Unit is meritorious or fired power generating unit is gained merit, then the ripple of load data The load data value of momentum=(the load data value of load data value sampling last time of this sampling) sampling/last time;
If load type is connecting transformer effective power flow or transmission line of electricity effective power flow, then the undulate quantity of load data is this The load data of sampling and the difference of the front load data amount once sampled.
16. network load exceptions according to claim 13 and operation risk real-time monitoring and early warning method, it is characterised in that The described Flushing status to load data judges and reports to the police, and specifically includes following steps:
. according to the data obtained, it is judged that load type;
. according to load type, read corresponding data higher limit, lower limit and do not refresh threshold threshold value;
. judge that load data is whether between data higher limit and the lower limit set: if load data is beyond data Higher limit or less than data lower limit, then assert that this load data is abnormal, and report to the police;
. if load data between data higher limit and the lower limit set, then calculates this load data and adopts with the last time Difference between the load data of sample;
. the size judging the difference described in step with not refreshing threshold threshold value: if difference is less than not refreshing threshold threshold Value, then assert that now load data does not refreshes, be designated as a secondary data and do not refresh suspicious points;
. the data that statistics occurs continuously do not refresh the number of suspicious points, if the data occurred continuously do not refresh suspicious points number of times > warning threshold that sets, then preliminary judgement data within this period do not refresh;
. the most artificial remote measurement combining load data corresponding device analog value suppresses information to enter updated load data Row real time correction, whether final this load data of judgement does not refreshes: if finally judging, this load data does not refreshes, then push automatically Change quality of data abnormality alarming.
17. network load exceptions according to claim 13 and operation risk real-time monitoring and early warning method, it is characterised in that The topological structure of described identification operation of power networks, specifically includes following steps:
1) obtained tracking power plant, the remote signalling amount of transformer station's wire-outgoing breaker in real time by EMS/SCADA system and judge power network topology Structure and start-up mode;
2) by EMS/SCADA system obtain grid equipment set, put board information, and with this system set, put the excellent of board information The principle of the data that first level obtains in real time higher than system, corrects topological structure of electric, and identification obtains opening up of operation of power networks Flutter structure.
18. network load exceptions according to claim 13 and operation risk real-time monitoring and early warning method, it is characterised in that The described weak link in identification operation of power networks and security risk grade are also reported to the police, and specifically include following steps:
1. according to the topological structure of operation of power networks, obtain and be only total to the single of bar line powering by single back transmission line or many times 220kV transformer station or multiple 220kV transformer station group linked together, and described transformer station is constituted set Mi, electrical network Middle all such transformer station constitutes set M={Mi};Obtaining bus connection type is double-bus or 3/2 wiring, and because part is female Line has a power failure and causes the 220kV that runs in single bus-bar operation mode and above power plant and transformer station, and by described power plant and power transformation Composition of standing set N;
2. number b of the 220KV transformer station comprised in number a of the 220KV transformer station comprised in set M, and set N is obtained; If a >=1 or b >=1, then judging that electrical network exists security risk, EMS system pushes the warning of Pyatyi grid event risk;
3. check the load type of all transformer stations in set M, comprise the set M of any county-level city j load for loadi, calculate Transformer station set MiCounty-level city's j load of burden accounts for ratio x of county-level city's j total load, obtains transformer station set MiThat bears is at county level The user of city j accounts for total user's ratio y of county-level city j;
4. according to the accident investigation code of state's net, it is determined that whether the value of x and y is more than the threshold value specified: if x or y is more than regulation Threshold value, then EMS system pushes the warning of level Four grid event risk;
3. and 4. 5. for all transformer stations in set N, step is repeated, the weak link in identification operation of power networks and safety Risk class is also reported to the police.
19. network load exceptions according to claim 13 and operation risk real-time monitoring and early warning method, it is characterised in that The described control nargin judging operation of power networks section is also reported to the police, and specifically includes following steps:
A. require power plant or the power plant group unit operation number of units monitored in specifying according to the stabilization of power grids, set up set of variables;
B. the electrical network Real-time Load amount monitored, steady control cutting load amount and the electricity of step a definition are required according to the stabilization of power grids in specifying Factory or power plant group unit operation number of units, determine stablizing of each transmission cross-section under current electric grid operation level according to stabilization of power grids regulation The unit of limit and power plant or power plant group reserves spinning reserve amount;
C. the size of real-time transmission cross-section and the transmission cross-section stability limitation of calculating, and power plant or the machine of power plant group in real time are compared Group spinning reserve and the size that spinning reserve amount should be reserved: if transmission cross-section stability limitation is more than or equal to the transmission of electricity calculated in real time Section stability limitation, or the unit spinning reserve amount of real-time power plant or power plant group is less than reserving spinning reserve amount, then EMS system Push the alarm of stabilization of power grids nargin deficiency.
CN201610563688.3A 2016-07-18 2016-07-18 Network load exception and operation risk monitor method for early warning in real time Active CN106154084B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610563688.3A CN106154084B (en) 2016-07-18 2016-07-18 Network load exception and operation risk monitor method for early warning in real time

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610563688.3A CN106154084B (en) 2016-07-18 2016-07-18 Network load exception and operation risk monitor method for early warning in real time

Publications (2)

Publication Number Publication Date
CN106154084A true CN106154084A (en) 2016-11-23
CN106154084B CN106154084B (en) 2018-11-20

Family

ID=58059268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610563688.3A Active CN106154084B (en) 2016-07-18 2016-07-18 Network load exception and operation risk monitor method for early warning in real time

Country Status (1)

Country Link
CN (1) CN106154084B (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106897946A (en) * 2017-03-14 2017-06-27 国网天津市电力公司 A kind of monitoring system status information section comparison method
CN107153915A (en) * 2017-04-18 2017-09-12 国网河北省电力公司衡水供电分公司 A kind of transformer station does not change the method and system of telemetry automatic detection
CN107276236A (en) * 2017-08-08 2017-10-20 国网江苏省电力公司宿迁供电公司 A kind of power network remote measurement warning strategies method based on floating threshold criterion
CN107749623A (en) * 2017-11-08 2018-03-02 贵州电网有限责任公司 Single busbar trip loss of electrical load accident grade decision method under double bus scheme mode
CN107861449A (en) * 2017-11-23 2018-03-30 国家电网公司 A kind of management and running key message inspection alarm method and device
CN107942872A (en) * 2017-12-11 2018-04-20 国家电网公司 A kind of power scheduling operation management system
CN108879654A (en) * 2018-06-04 2018-11-23 国网浙江省电力有限公司 Based on telemetering unusual fluctuation unit exception remote diagnostic method
CN108899913A (en) * 2018-08-17 2018-11-27 广东电网有限责任公司 A kind of real-time monitoring and index automatic classifying method towards power grid section
CN109347090A (en) * 2018-09-25 2019-02-15 国网四川省电力公司宜宾供电公司 A kind of area power grid Line Flow autocontrol method
CN110488199A (en) * 2019-09-04 2019-11-22 国网湖南省电力有限公司 A kind of high capacity cell energy-accumulating power station battery system alarm response method
CN110889554A (en) * 2019-11-27 2020-03-17 东南大学 Power load fluctuation analysis and risk early warning method based on recurrence time interval analysis method
CN111044938A (en) * 2019-12-20 2020-04-21 许继集团有限公司 Alternating current section power loss detection method and device
CN111062584A (en) * 2019-11-28 2020-04-24 国网安徽省电力有限公司合肥供电公司 Risk monitoring method for running state of transformer
CN112414462A (en) * 2020-11-16 2021-02-26 贵州电网有限责任公司 Multistage abnormal data processing method in transformer load condition monitoring
CN112467806A (en) * 2020-12-07 2021-03-09 中国电力科学研究院有限公司 Method and system for determining power grid operation state based on DMN power grid regulation and control rule
CN112636469A (en) * 2020-12-11 2021-04-09 国网安徽省电力有限公司黄山供电公司 Method for judging reliability of operation load data of power grid transmission line
CN112736866A (en) * 2020-12-16 2021-04-30 国网安徽省电力有限公司 Relay protection self-adaptive real-time evaluation method and system based on wide area information
CN113433419A (en) * 2021-06-04 2021-09-24 国电南瑞南京控制***有限公司 Intelligent alarm method and system based on polymorphic data coprocessing
CN115545347A (en) * 2022-11-15 2022-12-30 贵州电网有限责任公司 Big data analysis-based power system risk prediction system and method
CN116228205A (en) * 2023-03-29 2023-06-06 东莞先知大数据有限公司 Charging pile outage risk diagnosis method, device and storage medium

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101814743A (en) * 2010-01-12 2010-08-25 福建省电力有限公司福州电业局 Wind power integration on-line safety early warning system based on short-term wind power prediction
CN101944766A (en) * 2010-06-01 2011-01-12 中国电力科学研究院 Operation and safety monitoring simulation system for power system
CN102737286A (en) * 2012-04-23 2012-10-17 中国电力科学研究院 Online risk analysis system and method for regional power grid
CN104616089A (en) * 2014-11-19 2015-05-13 南昌大学 Large power grid running risk evaluation system
CN104992307A (en) * 2015-08-10 2015-10-21 国网上海市电力公司 Power distribution network risk collaborative management and control system
JP2016067098A (en) * 2014-09-24 2016-04-28 株式会社日立製作所 Power system monitoring device and power system monitoring system
WO2016099478A1 (en) * 2014-12-17 2016-06-23 United Technologies Corporation Islanding detection method based on torque oscillations of internal combustion engines

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101814743A (en) * 2010-01-12 2010-08-25 福建省电力有限公司福州电业局 Wind power integration on-line safety early warning system based on short-term wind power prediction
CN101944766A (en) * 2010-06-01 2011-01-12 中国电力科学研究院 Operation and safety monitoring simulation system for power system
CN102737286A (en) * 2012-04-23 2012-10-17 中国电力科学研究院 Online risk analysis system and method for regional power grid
JP2016067098A (en) * 2014-09-24 2016-04-28 株式会社日立製作所 Power system monitoring device and power system monitoring system
CN104616089A (en) * 2014-11-19 2015-05-13 南昌大学 Large power grid running risk evaluation system
WO2016099478A1 (en) * 2014-12-17 2016-06-23 United Technologies Corporation Islanding detection method based on torque oscillations of internal combustion engines
CN104992307A (en) * 2015-08-10 2015-10-21 国网上海市电力公司 Power distribution network risk collaborative management and control system

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106897946A (en) * 2017-03-14 2017-06-27 国网天津市电力公司 A kind of monitoring system status information section comparison method
CN107153915A (en) * 2017-04-18 2017-09-12 国网河北省电力公司衡水供电分公司 A kind of transformer station does not change the method and system of telemetry automatic detection
CN107276236A (en) * 2017-08-08 2017-10-20 国网江苏省电力公司宿迁供电公司 A kind of power network remote measurement warning strategies method based on floating threshold criterion
CN107749623B (en) * 2017-11-08 2020-08-25 贵州电网有限责任公司 Single-bus tripping and load loss accident grade determination method in double-bus connection mode
CN107749623A (en) * 2017-11-08 2018-03-02 贵州电网有限责任公司 Single busbar trip loss of electrical load accident grade decision method under double bus scheme mode
CN107861449A (en) * 2017-11-23 2018-03-30 国家电网公司 A kind of management and running key message inspection alarm method and device
CN107942872A (en) * 2017-12-11 2018-04-20 国家电网公司 A kind of power scheduling operation management system
CN108879654A (en) * 2018-06-04 2018-11-23 国网浙江省电力有限公司 Based on telemetering unusual fluctuation unit exception remote diagnostic method
CN108899913A (en) * 2018-08-17 2018-11-27 广东电网有限责任公司 A kind of real-time monitoring and index automatic classifying method towards power grid section
CN109347090A (en) * 2018-09-25 2019-02-15 国网四川省电力公司宜宾供电公司 A kind of area power grid Line Flow autocontrol method
CN109347090B (en) * 2018-09-25 2021-06-01 国网四川省电力公司宜宾供电公司 Regional power grid line tide automatic control method
CN110488199A (en) * 2019-09-04 2019-11-22 国网湖南省电力有限公司 A kind of high capacity cell energy-accumulating power station battery system alarm response method
CN110488199B (en) * 2019-09-04 2021-06-01 国网湖南省电力有限公司 Alarm response method for battery system of high-capacity battery energy storage power station
CN110889554A (en) * 2019-11-27 2020-03-17 东南大学 Power load fluctuation analysis and risk early warning method based on recurrence time interval analysis method
CN111062584B (en) * 2019-11-28 2022-11-29 国网安徽省电力有限公司合肥供电公司 Risk monitoring method for running state of transformer
CN111062584A (en) * 2019-11-28 2020-04-24 国网安徽省电力有限公司合肥供电公司 Risk monitoring method for running state of transformer
CN111044938B (en) * 2019-12-20 2021-11-16 许继集团有限公司 Alternating current section power loss detection method and device
CN111044938A (en) * 2019-12-20 2020-04-21 许继集团有限公司 Alternating current section power loss detection method and device
CN112414462A (en) * 2020-11-16 2021-02-26 贵州电网有限责任公司 Multistage abnormal data processing method in transformer load condition monitoring
CN112467806A (en) * 2020-12-07 2021-03-09 中国电力科学研究院有限公司 Method and system for determining power grid operation state based on DMN power grid regulation and control rule
CN112636469A (en) * 2020-12-11 2021-04-09 国网安徽省电力有限公司黄山供电公司 Method for judging reliability of operation load data of power grid transmission line
CN112636469B (en) * 2020-12-11 2022-08-23 国网安徽省电力有限公司黄山供电公司 Method for judging reliability of power grid transmission line operation load data
CN112736866A (en) * 2020-12-16 2021-04-30 国网安徽省电力有限公司 Relay protection self-adaptive real-time evaluation method and system based on wide area information
CN112736866B (en) * 2020-12-16 2023-08-22 国网安徽省电力有限公司 Relay protection self-adaptive real-time evaluation method and system based on wide area information
CN113433419A (en) * 2021-06-04 2021-09-24 国电南瑞南京控制***有限公司 Intelligent alarm method and system based on polymorphic data coprocessing
CN115545347A (en) * 2022-11-15 2022-12-30 贵州电网有限责任公司 Big data analysis-based power system risk prediction system and method
CN116228205A (en) * 2023-03-29 2023-06-06 东莞先知大数据有限公司 Charging pile outage risk diagnosis method, device and storage medium
CN116228205B (en) * 2023-03-29 2023-11-21 东莞先知大数据有限公司 Charging pile outage risk diagnosis method, device and storage medium

Also Published As

Publication number Publication date
CN106154084B (en) 2018-11-20

Similar Documents

Publication Publication Date Title
CN106154084A (en) Network load exception and operation risk real-time monitoring and early warning method
CN103812131B (en) A kind of urban distribution network isolated island black starting-up system and method based on multiple agent
CN111525598B (en) Optimal generator tripping capacity obtaining method for inhibiting high-frequency problem of transmission-end power grid
CN103248056B (en) Reactive voltage emergency control method in concentrated grid connecting area of wind power plant
CN106655159A (en) New energy power station primary frequency modulation capability testing system and testing method thereof
CN104283308A (en) Smart central strategy control system for micro-grid
CN108134394B (en) Optimized load shedding method considering distributed power supply influence
CN108847660A (en) The prevention and control Study on Decision-making Method for Optimization checked online based on Safety system off-line strategy
CN109713793A (en) A kind of substation station power supply presence assessment system and method
CN100554976C (en) Area voltage stability monitoring method based on synchronous phasor measurement
CN104505855A (en) Online evaluation system for grid-connected characteristic of wind power plant
CN104283222A (en) Regional power grid reactive voltage control system
Roytelman et al. Volt/VAR control and Conservation Voltage Reduction as a function of advanced DMS
CN104319779B (en) Regional power grid reactive voltage control method
CN105958474A (en) Power transmission line dynamic capacity increasing method and system used for power grid regulation and control system
CN112865083B (en) Real-time running state evaluation method for power system containing renewable energy sources
CN104462769A (en) Method for detecting fault of current measurement circuit of transformer substation based on genetic algorithm
CN111969660B (en) Primary frequency modulation assessment method and system based on different working condition reward and punishment double-track operation
CN114764672A (en) Multi-factor-fused power grid equipment risk assessment method under joint learning framework
Rexhepi The dispatch center’s role in the power grid operation and control.
Zhang et al. Enhancing power grid resilience against typhoon disasters by scheduling of generators along with optimal transmission switching
Ndlela et al. Reliability and security analysis of the southern Africa power pool regional grid
Chai et al. An Assessment Method for Operational Situations of Distribution Networks with High Proportion of Distributed Photovoltaics
Liu et al. Reliability analysis of wide area measurement system based on the centralized distributed model
CN110912269B (en) Electric energy dispatching and controlling system for offshore power grid

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant