CN106121232A - The installation method of distribution box in a kind of secondary structure - Google Patents

The installation method of distribution box in a kind of secondary structure Download PDF

Info

Publication number
CN106121232A
CN106121232A CN201610711709.1A CN201610711709A CN106121232A CN 106121232 A CN106121232 A CN 106121232A CN 201610711709 A CN201610711709 A CN 201610711709A CN 106121232 A CN106121232 A CN 106121232A
Authority
CN
China
Prior art keywords
distribution box
angle steel
secondary structure
shear force
force wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610711709.1A
Other languages
Chinese (zh)
Inventor
周铖
曹磊
刘光辉
尤克泉
陈赛菊
吴广浩
吴晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd Tianjin Branch
Original Assignee
Zhongtian Construction Group Co Ltd Tianjin Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd Tianjin Branch filed Critical Zhongtian Construction Group Co Ltd Tianjin Branch
Priority to CN201610711709.1A priority Critical patent/CN106121232A/en
Publication of CN106121232A publication Critical patent/CN106121232A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses the installation method of distribution box in a kind of secondary structure, comprise the following steps: step one, concrete shear force wall is installed angle steel;Step 2, is fixed on distribution box on mounted angle steel;Step 3, is connected spool reserved during main body construction with distribution box;Step 4, starts secondary structure and builds by laying bricks or stones, and the angle steel on distribution box is removed after having built by laying bricks or stones by secondary structure;Angle steel uses bolt to be connected with concrete shear force wall, and needed for the horizontally and vertically position of angle steel and distribution box, position to be mounted matches, and distribution box employing self-tapping screw is connected with the angle steel being arranged on concrete shear force wall;When the present invention solves distribution box installation in traditional secondary structure, distribution box installation site is inaccurate, spool connection has some setbacks, threading difficulty, noise and environmental pollution is easily caused during cutting building block, the problem that construction cost is higher, easy construction, construction cost is relatively low, is effectively improved quality and efficiency that in secondary structure, distribution box is installed.

Description

The installation method of distribution box in a kind of secondary structure
Technical field
The invention belongs to technical field of building construction, particularly relate to the installation method of distribution box in a kind of secondary structure.
Background technology
At present, in construction projects secondary structure is constructed, the installation of distribution box is typically to construct at secondary structure Installing in journey, need to cut secondary structure building block during installation, in building block, spool installed by grooving, uses this kind of construction method easy The position causing distribution box to install is inaccurate, and spool connection has some setbacks, and threading difficulty easily causes noise and environment during cutting building block Pollute, there is no small drawback.
Summary of the invention
It is an object of the invention to provide the installation method of distribution box in a kind of secondary structure, it is intended to solve at present in building In the construction of project under construction secondary structure, the installation of distribution box is typically to install in secondary structure work progress, needs during installation Cutting secondary structure building block, in building block, spool installed by grooving, uses this kind of construction method to easily cause the position that distribution box is installed Putting inaccurate, spool connection has some setbacks, and threading difficulty easily causes noise and environmental pollution during cutting building block, and construction cost is higher Problem.
The present invention is achieved in that the installation method of distribution box in a kind of secondary structure, distribution box in this secondary structure Installation method comprise the following steps:
Step one, installs angle steel on concrete shear force wall;
Step 2, is fixed on distribution box on mounted angle steel;
Step 3, is connected spool reserved during main body construction with distribution box;
Step 4, starts secondary structure and builds by laying bricks or stones, and the angle steel on distribution box is removed after having built by laying bricks or stones by secondary structure.
Further, in step one, described angle steel uses bolt to be connected with concrete shear force wall, and the level of angle steel is with perpendicular Needed for position with distribution box, position to be mounted matches.
Further, in step 2, described distribution box uses self-tapping screw and the angle steel being arranged on concrete shear force wall It is connected.
In the secondary structure that the present invention provides, the installation method of distribution box, comprises the following steps: step one, cuts at concrete Angle steel is installed on power wall;Step 2, is fixed on distribution box on mounted angle steel;Step 3, by reserve during main body construction Spool is connected with distribution box;Step 4, start secondary structure build by laying bricks or stones, secondary structure built by laying bricks or stones after by the angle steel on distribution box Remove;Angle steel uses bolt to be connected with concrete shear force wall, and the horizontally and vertically position of angle steel is required with distribution box installs Position match, distribution box use self-tapping screw be connected with the angle steel being arranged on concrete shear force wall;The present invention solves When in traditional secondary structure, distribution box is installed, distribution box installation site is inaccurate, spool connect have some setbacks, threading difficulty, cutting Easily causing noise and environmental pollution during building block, the problem that construction cost is higher, easy construction, construction cost is relatively low, effectively Improve quality and efficiency that in secondary structure, distribution box is installed.
Accompanying drawing explanation
Fig. 1 is the flowchart of the installation method of distribution box in the secondary structure that the embodiment of the present invention provides;
Fig. 2 is the scheme of installation of distribution box in the secondary structure that the embodiment of the present invention provides.
In figure: 1, angle steel;2, bolt;3, concrete shear force wall;4, distribution box;5, self-tapping screw;6, spool.
Detailed description of the invention
In order to make the purpose of the present invention, technical scheme and advantage clearer, below in conjunction with embodiment, to the present invention It is further elaborated.Should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not used to Limit the present invention.
Below in conjunction with the accompanying drawings and the application principle of the present invention is further described by specific embodiment.
As it is shown in figure 1, the installation method of distribution box in the secondary structure of embodiment of the present invention offer, comprise the following steps:
Step S101, installs angle steel 1 on concrete shear force wall 3;
Step S102, is fixed on distribution box 4 on mounted angle steel 1;
Step S103, is connected spool 6 reserved during main body construction with distribution box 4;
Step S104, starts secondary structure and builds by laying bricks or stones, and the angle steel 1 on distribution box 4 is removed after having built by laying bricks or stones by secondary structure.
In embodiments of the present invention, in step S101, described angle steel 1 uses bolt 2 to be connected with concrete shear force wall 3 Connecing, needed for the horizontally and vertically position of angle steel 1 and distribution box 4, position to be mounted matches.
In embodiments of the present invention, in step s 102, described distribution box 4 uses self-tapping screw 5 and is arranged on concrete Angle steel 1 on shear wall 3 is connected.
As in figure 2 it is shown, the concrete installation process of distribution box is in the secondary structure of embodiment of the present invention offer: at concrete Using bolt 2 to install angle steel 1 on shear wall 3, angle steel 1 uses bolt 2 to be connected with concrete shear force wall 3, horizontally and vertically position Put all with distribution box 4 needed for position to be mounted match;Distribution box 4 self-tapping screw 5 is fixed on mounted angle steel 1 On, distribution box 4 uses self-tapping screw 5 to be connected with mounted angle steel 1, and the position of the mounted position of distribution box 4 and design is protected Hold consistent;Spool 6 reserved during main body construction is connected with distribution box 4;Start secondary structure to build by laying bricks or stones, by distribution after having built by laying bricks or stones Angle steel 1 on case 4 is removed.
Use the installation method of distribution box in the secondary structure of embodiment of the present invention offer, it is possible to solve secondary knot well The problem that in structure, distribution box 4 produces when installing, distribution box 4 position is installed accurately, does not results in threading difficulty, does not has noise and ring Environment pollution, and the most do not increase construction cost.
In the secondary structure that the embodiment of the present invention provides, the installation method of distribution box, comprises the following steps: step one, mixed On solidifying soil shear wall 3, angle steel 1 is installed;Step 2, is fixed on distribution box 4 on mounted angle steel 1;Step 3, executes main body The spool 6 that man-hour is reserved is connected with distribution box 4;Step 4, starts secondary structure and builds by laying bricks or stones, and secondary structure will be joined after having built by laying bricks or stones Angle steel 1 on electronic box 4 is removed;Angle steel 1 uses bolt 2 to be connected with concrete shear force wall 3, the horizontally and vertically position of angle steel 1 Matching with position to be mounted needed for distribution box 4, distribution box 4 uses self-tapping screw 5 and is arranged on concrete shear force wall on 3 Angle steel 1 is connected;When the present invention solves that in traditional secondary structure, distribution box 4 is installed, distribution box 4 installation site is inaccurate, line Pipe 6 connection has some setbacks, threading difficulty, easily causes noise and environmental pollution during cutting building block, the problem that construction cost is higher, construction Convenient, construction cost is relatively low, is effectively improved quality and efficiency that in secondary structure, distribution box 4 is installed.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention Any amendment, equivalent and the improvement etc. made within god and principle, should be included within the scope of the present invention.

Claims (3)

1. the installation method of distribution box in a secondary structure, it is characterised in that the installation method of distribution box in this secondary structure Comprise the following steps:
Step one, installs angle steel on concrete shear force wall;
Step 2, is fixed on distribution box on mounted angle steel;
Step 3, is connected spool reserved during main body construction with distribution box;
Step 4, starts secondary structure and builds by laying bricks or stones, and the angle steel on distribution box is removed after having built by laying bricks or stones by secondary structure.
2. the installation method of distribution box in secondary structure as claimed in claim 1, it is characterised in that in step one, described Angle steel uses bolt to be connected with concrete shear force wall, position to be mounted needed for the horizontally and vertically position of angle steel and distribution box Match.
3. the installation method of distribution box in secondary structure as claimed in claim 1, it is characterised in that in step 2, described Distribution box uses self-tapping screw to be connected with the angle steel being arranged on concrete shear force wall.
CN201610711709.1A 2016-08-24 2016-08-24 The installation method of distribution box in a kind of secondary structure Pending CN106121232A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610711709.1A CN106121232A (en) 2016-08-24 2016-08-24 The installation method of distribution box in a kind of secondary structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610711709.1A CN106121232A (en) 2016-08-24 2016-08-24 The installation method of distribution box in a kind of secondary structure

Publications (1)

Publication Number Publication Date
CN106121232A true CN106121232A (en) 2016-11-16

Family

ID=57273958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610711709.1A Pending CN106121232A (en) 2016-08-24 2016-08-24 The installation method of distribution box in a kind of secondary structure

Country Status (1)

Country Link
CN (1) CN106121232A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636683A (en) * 2020-06-01 2020-09-08 中天华南建设投资集团有限公司 Complete method for embedding indoor electric box
CN112112232A (en) * 2020-08-03 2020-12-22 五冶集团上海有限公司 Urine sensor installation method
CN114498372A (en) * 2022-01-27 2022-05-13 四川省第四建筑有限公司 One-time installation construction process for strong and weak current box in masonry

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101247029A (en) * 2008-03-27 2008-08-20 成都市第四建筑工程公司 Construction method for installing wire pipe and wire box on the wall
CN203387110U (en) * 2013-07-17 2014-01-08 成都市第二建筑工程公司 Floor type installation assembly for embedded box
CN203839870U (en) * 2014-05-22 2014-09-17 国家电网公司 Wall-mounted concealed distribution box
CN105762728A (en) * 2016-03-08 2016-07-13 中国五冶集团有限公司 Method for pre-burying of strong and weak electricity box and electrical tubing

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101247029A (en) * 2008-03-27 2008-08-20 成都市第四建筑工程公司 Construction method for installing wire pipe and wire box on the wall
CN203387110U (en) * 2013-07-17 2014-01-08 成都市第二建筑工程公司 Floor type installation assembly for embedded box
CN203839870U (en) * 2014-05-22 2014-09-17 国家电网公司 Wall-mounted concealed distribution box
CN105762728A (en) * 2016-03-08 2016-07-13 中国五冶集团有限公司 Method for pre-burying of strong and weak electricity box and electrical tubing

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636683A (en) * 2020-06-01 2020-09-08 中天华南建设投资集团有限公司 Complete method for embedding indoor electric box
CN112112232A (en) * 2020-08-03 2020-12-22 五冶集团上海有限公司 Urine sensor installation method
CN114498372A (en) * 2022-01-27 2022-05-13 四川省第四建筑有限公司 One-time installation construction process for strong and weak current box in masonry

Similar Documents

Publication Publication Date Title
CN204118627U (en) A kind of pre-buried wiring electricity box being exclusively used in xoncrete structure
CN106121232A (en) The installation method of distribution box in a kind of secondary structure
CN104405128B (en) Infilled wall concealed distribution box is direct installation method in advance
CN103321436A (en) Pre-installation construction method for wire box on building bricked body and pre-installation supporting frame thereof
CN203270599U (en) Foundation bolt pre-buried die
CN207685818U (en) It is a kind of it is repeatable utilize lead wall device
KR102130359B1 (en) Wind turbine Re-powering Foundation structures
CN105317230A (en) Fixing method of beam and wall pre-embedded horizontal sleeve
CN204626957U (en) Gap, floor wind and smoke road capping tools formula mould bases
CN103343577A (en) Shear wall water stopping method of detachable butted screw rods
CN202990418U (en) Slurry-leaking protection device preventing cast-in-place concrete column root from rotting
CN204706792U (en) Distribution box
CN204941579U (en) The pre-buried orifice tube of a kind of pit shaft borehole wall grouting
CN204571265U (en) A kind of reusable pre-buried anchor ring
CN204252171U (en) The rubber fastening band at basement shrinkage joint installs fixing special tool
CN203878968U (en) Connecting structure between scaffold and main body structure
CN204174910U (en) A kind of wall-connecting device of scaffold
CN202258138U (en) Corner type path identifying device of power cable
CN205171542U (en) Adjustable type rag bolt
CN105401720A (en) Fixing tool for plate-permeable embedded casing pipe
CN203230710U (en) Bolt sleeve
CN104836132A (en) Power distribution box and installation method thereof
CN110173113A (en) A kind of Lin Qiang hangs hole constructing structure and method
CN201245974Y (en) UPVC casing tube performing and pre-embedding system
CN205296216U (en) Temporary operation platform of underground factory building rock anchor crane beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161116