CN106121144B CN201610531843.3A CN201610531843A CN106121144B CN 106121144 B CN106121144 B CN 106121144B CN 201610531843 A CN201610531843 A CN 201610531843A CN 106121144 B CN106121144 B CN 106121144B
Authority
CN
China
Prior art keywords
plate
bolt
connecting plate
lower connecting
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610531843.3A
Other languages
Chinese (zh)
Other versions
CN106121144A (en
Inventor
任文杰
何小林
王利强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei University of Technology
Original Assignee
Hebei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei University of Technology filed Critical Hebei University of Technology
Priority to CN201610531843.3A priority Critical patent/CN106121144B/en
Publication of CN106121144A publication Critical patent/CN106121144A/en
Application granted granted Critical
Publication of CN106121144B publication Critical patent/CN106121144B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • E04F11/022Stairways; Layouts thereof characterised by the supporting structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/36Bearings or like supports allowing movement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • E04F2011/0203Miscellaneous features of stairways not otherwise provided for
    • E04F2011/0205Stairways characterised by the use of specific materials for the supporting structure of the treads
    • E04F2011/021Stairways characterised by the use of specific materials for the supporting structure of the treads mainly of stone or stone like materials, e.g. concrete; mainly of glass
    • E04F2011/0212Stairways characterised by the use of specific materials for the supporting structure of the treads mainly of stone or stone like materials, e.g. concrete; mainly of glass mainly of concrete
    • E04F2011/0214Stairways characterised by the use of specific materials for the supporting structure of the treads mainly of stone or stone like materials, e.g. concrete; mainly of glass mainly of concrete cast in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Steps, Ramps, And Handrails (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The present invention relates to a kind of spacing bearing of concrete staircase damping and work progress, the stair include bench, bench is high-end to be equipped with upper concrete ladder beam and floor levels plate, bench is high-end to pour integrally with corresponding upper concrete ladder beam, bench low side is equipped with lower concrete ladder beam and halfpace plate, bench low side is extended with horizontal segment with corresponding lower concrete ladder beam elastic connection, the gangboard of bench, and the spacing bearing of damping is equipped between the horizontal segment and corresponding lower concrete ladder beam.The spacing bearing energy-dissipating and shock-absorbing good limit effect of a kind of concrete staircase damping of the present invention, it is easy for construction.

Description

A kind of spacing bearing of concrete staircase damping
Technical field
The present invention relates to the stair of building, and in particular to a kind of spacing bearing of concrete staircase damping and work progress.
Background technology
Traditional construction design method does not account for influence of the stair stress to integrality performance of the structure, without considering stair yet Earthquake load effects.Wenchuan earthquake earthquake shows that the staircase of the big lower building of shake effect destroys seriously, including waist slab, ladder The heavy damage of beam and cleat stanchion.
《Seismic design provision in building code》The 6.1.15 articles regulation of GB50011-2010:" for frame structure, staircase component with Agent structure is whole when pouring, and should be included in influence of the staircase component to geological process and its effect, should carry out staircase component antidetonation carrying Power checks ".And after staircase component participates in structure overall calculation, staircase component size and area of reinforcement increasing will cause staircase Local stiffness amplify again, the shearing that geological process is distributed between going downstairs increases again.In order to weaken stair and overall structure Connection,《The board-like stair of cast-in-place concrete》(11G101-2) proposes the way for sliding stair, connects in bench and low side ladder beam Connect place's design sliding support.And slide stair then becomes in bench and low side ladder beam junction design sliding support, whole bench Cantilever member, bench low side just produces violent overhanging chattering under geological process, easily make bench with high-end terraced beam Junction is by drawing crack.Notification number has invented energy-dissipating and shock-absorbing for 203569719 U Chinese patents of CN on the basis of stair are slided Bearing, in bench and low side ladder beam junction design energy-dissipating and shock-absorbing bearing.But energy-dissipating and shock-absorbing bearing is placed in structure, is become A structure part, causes the energy-dissipating and shock-absorbing bearing later stage can not overhaul and replace, and energy-dissipating and shock-absorbing pedestal configurations are complicated, construction Difficulty is big.《National building standard designs atlas》(G310-1~2) also give concrete Tulou according to stair connecting structure The construction way that is slidably connected of ladder.But the construction way interior joint connection that is slidably connected of precast concrete stair is complicated, construction Difficulty is big.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of spacing bearing of concrete staircase damping and work progress, subtract Shake spacing bearing and friction energy-dissipating is realized by the displacement difference of upper and lower floor gap, not only suppress the vertical outstanding of concrete bench low side Chattering is chosen, and prevents that concrete bench low side from coming off under big shake and horizontal jitter, the spacing bearing of damping are located at stair Outside structure, easy for construction, energy-dissipating and shock-absorbing limit effect is notable.
Technical proposal that the invention solves the above-mentioned problems is as follows:
A kind of spacing bearing of concrete staircase damping, stair include bench, and bench is high-end to be equipped with upper concrete Ti Lianghe buildings Layer landing slab, bench is high-end to pour integrally with corresponding upper concrete ladder beam, and bench low side is equipped with lower concrete ladder beam with Between landing slab, bench low side is with corresponding lower concrete ladder beam elastic connection, elastic connection structure:The gangboard of the bench Horizontal segment is extended with, the spacing bearing of damping is equipped between the horizontal segment and corresponding lower concrete ladder beam.The spacing bearing bag of damping Upper junction plate is included, upper junction plate surface is equipped with anchor bolt and caging bolt hole;Lower connecting plate, lower connecting plate surface are equipped with anchor Fixing bolt, and the anchor bolt through lower connecting plate bolt hole;Upper cover plate;Friction plate;High-strength bolt;Lower angle steel.
Anchor bolt and gangboard anchor connection of the upper junction plate by upper junction plate surface soldered, the distal end of anchor bolt has The anchoring cap being radially expanded, the size of anchor bolt, quantity and length shearing resistance as needed and stretching resistance determine;Lower company Anchor bolt and lower concrete ladder beam anchor connection of the fishplate bar by lower connecting plate surface soldered, lower connecting plate surface soldered There are the anchoring cap being radially expanded, size, quantity and the length of the anchor bolt of lower connecting plate surface soldered in the distal end of anchor bolt Shearing resistance as needed and stretching resistance determine, weld, wear through the anchor bolt after lower connecting plate bolt hole and lower connecting plate There are the anchoring cap being radially expanded, the anchor through after lower connecting plate bolt hole in the distal end for the anchor bolt crossed after lower connecting plate bolt hole The size and number of fixing bolt shearing resistance as needed and stretching resistance determine;Friction plate uses asbestos less friction plate, upper cover plate Firmly it is connected with friction plate by epoxide-resin glue, lower angle steel is firmly connected by epoxide-resin glue with friction plate;High-strength bolt Upper cover plate bolt hole, friction plate hole, upper junction plate caging bolt hole centre and lower angle steel bolt hole are each passed through, passes through nut Screw and apply pressure to adjust upper junction plate and the friction damping force of upper cover plate and lower angle steel between the two, high-strength bolt it is big Small, quantity and pressure friction damping force as needed, stretching resistance and shearing resistance determine;The anchor bolt that lower connecting plate stretches out Through lower angle steel bolt hole, pressure is applied to fix the position of lower connecting plate and lower angle steel by nut tightening, ensures lower connection Plate is firmly connected with lower angle steel.
A kind of spacing bearing work progress of concrete staircase damping is as follows:
Lower concrete ladder beam and the component of halfpace plate and its integrated connection 1. reinforcing bar is bound into first;
2. by the anchor bolt of lower connecting plate and its surface soldered and through lower connecting plate bolt hole anchor bolt together It is embedded in lower concrete ladder beam, stretches out anchor bolt;
3. to the component formwork and casting concrete of lower concrete ladder beam and halfpace plate and its integrated connection, maintenance is arrived Form removal after some strength, ensures that lower connecting plate is firmly connected with lower concrete ladder beam;
4. bind gangboard, horizontal segment, upper concrete ladder beam, the steel of floor levels board member of bench and its integrated connection Muscle;
5. upper junction plate and its anchor bolt of welding are embedded in horizontal segment together, the pre-buried length of upper junction plate and water The development length of flat section is equal, and upper junction plate caging bolt hole is located at outside stair;
6. to the gangboard of bench and its integrated connection, horizontal segment, upper concrete ladder beam, floor levels board member formwork and pour Concrete is built, conserves form removal after some strength, ensures that upper junction plate is firmly connected with horizontal segment;
7. the anchor bolt that lower connecting plate stretches out is passed through lower angle steel bolt hole, ensure lower angle steel bolt hole and upper cover plate spiral shell Both keyholes are directed at upper junction plate caging bolt hole centre position;
8. high-strength bolt is each passed through upper cover plate bolt hole, friction plate hole, among upper junction plate caging bolt hole and under Angle steel bolt hole, applies pressure to fix the position of both upper junction plate and upper cover plate and lower angle steel by nut tightening;
9. applying pressure by nut tightening to fix the position of lower connecting plate and lower angle steel, ensure lower connecting plate and inferior horn Steel firmly connects.
The present invention beneficial construction effect be:1. energy-dissipating and shock-absorbing.The displacement difference that the spacing bearing of damping passes through upper and lower floor gap Realize friction energy-dissipating, when earthquake allows the bench of concrete staircase and concrete ladder beam to produce relative displacement, effectively prevent ladder Section equivalent strong supporting role caused by compression or stretching;It is 2. spacing.It is low that the spacing bearing of damping not only suppresses concrete bench The vertical overhanging chattering at end, and prevent that concrete bench low side from coming off and horizontal jitter under big shake;3. construction party Just.The spacing bearing of damping is located at the outside of staircase structure, and convenient installation, can overhaul and replace.
Brief description of the drawings
Fig. 1 is the spacing bearing structure illustration of damping of the present invention.
Fig. 2 is the side view of the spacing bearing of damping of the present invention.
Fig. 3 is the upper junction plate structure diagram of the spacing bearing of damping of the present invention.
Fig. 4 is the upper junction plate top view of the spacing bearing of damping of the present invention.
Fig. 5 is the lower connecting plate structure diagram of the spacing bearing of damping of the present invention.
Fig. 6 is the lower connecting plate side view of the spacing bearing of damping of the present invention.
Fig. 7 is the upper cover plate structure schematic diagram of the spacing bearing of damping of the present invention.
Fig. 8 is the friction plate structure schematic diagram of the spacing bearing of damping of the present invention.
Fig. 9 is the lower steel angle structure schematic diagram of the spacing bearing of damping of the present invention.
Figure 10 is that the connection structure of the upper junction plate and upper cover plate, lower angle steel of the spacing bearing of damping of the present invention is illustrated Figure.
Figure 11 is connection structure side view of the upper junction plate with upper cover plate, lower angle steel of the spacing bearing of damping of the present invention Figure.
Figure 12 is attachment structure schematic diagram of the lower connecting plate with lower angle steel of the spacing bearing of damping of the present invention.
Figure 13 is connection structure side view of the lower connecting plate with lower angle steel of the spacing bearing of damping of the present invention.
Figure 14, Figure 15, Figure 16 are a kind of office of a concrete bench of the spacing bearing of concrete staircase damping of the present invention Portion's structure diagram, wherein Figure 14 are side view, and Figure 15 is part A schematic enlarged-scale views in Figure 14, and the A-A that Figure 16 is Figure 15 is cutd open Face figure.
In figure, 1- upper junction plate surface anchoring bolts, 2- upper junction plates, 201- upper junction plate caging bolts hole, 3- is high-strength Bolt, 4- upper cover plates, 401- upper cover plate bolts hole, 5- friction plates, 501- friction plate holes, angle steel under 6-, angle steel bolt under 601- Hole, 7- pass through the anchor bolt of lower connecting plate bolt hole, 8- lower connecting plates, 801- lower connecting plate bolts hole, 9- lower connecting plate tables Face anchor bolt, the spacing bearing of 10- dampings, 11- floor levels plates, the upper concrete ladder beams of 12-, 13- gangboards, 14- bench, 15- Lower concrete ladder beam, 16- horizontal segments, 17- halfpace plates.
Embodiment
The invention will be further described below in conjunction with the accompanying drawings.
According to Fig. 1 and Fig. 2, the spacing bearing of damping provided by the invention, including:1- upper junction plate surface anchoring spiral shells Bolt, 2- upper junction plates, 3- high-strength bolts, 4- upper cover plates, 5- friction plates, angle steel under 6-, 7- pass through the anchor of lower connecting plate bolt hole Fixing bolt, 8- lower connecting plates, 9- lower connecting plate surface anchoring bolts.
According to Fig. 3 and Fig. 4,2 pre-buried length of upper junction plate is identical with gangboard 13 extending level section, 16 length, extends water The development length of flat section 16 is not preferably less than a tread run, and anchor bolt 1, anchor are welded in the pre-buried length range of upper junction plate There is an anchoring cap being radially expanded in the distal end of fixing bolt 1, the size of anchor bolt 1, quantity and length shearing resistance as needed and Stretching resistance determines that the 201 spacing displacement of upper junction plate caging bolt hole meets that the level of 13 extending level section 16 of gangboard during big shake is sliding Dynamic displacement.
According to Fig. 5 and Fig. 6,8 surface soldered anchor bolt 9 of lower connecting plate, through after lower connecting plate bolt hole 801 Anchor bolt 7 is welded with lower connecting plate 8, lower connecting plate 8 and anchor bolt 9 and anchor bolt 7 both firmly to connect into one whole There are the anchoring cap being radially expanded, size, quantity and the length root of anchor bolt 9 in the distal end of body, anchor bolt 9 and anchor bolt 7 Determined according to the stretching resistance and shearing resistance of needs, the size and number of anchor bolt 7 stretching resistance as needed and shearing resistance are determined It is fixed.
According to Fig. 7, Fig. 8, Fig. 9, Figure 10, Figure 11, friction plate 5 uses asbestos less friction plate, and upper cover plate 4 passes through epoxy Resin glue is firmly connected with friction plate 5, and lower angle steel 6 is firmly connected by epoxide-resin glue with friction plate 5, and high-strength bolt 3 is distinguished Among through upper cover plate bolt hole 401, friction plate hole 501, upper junction plate caging bolt hole 201 and lower angle steel bolt hole 601, Pressure is applied by nut tightening to adjust upper junction plate 2 and the friction damping force of upper cover plate 4 and lower angle steel 6 between the two, it is high The size of strength bolt 3, quantity and pressure friction damping force, stretching resistance and shearing resistance as needed determine.
According to Figure 12, Figure 13, the anchor bolt 7 that lower connecting plate 8 stretches out passes through lower angle steel bolt hole 601, passes through spiral shell Mother, which screws, applies pressure to fix the position of lower connecting plate 8 and lower angle steel 6, ensures that lower connecting plate 8 is firmly connected with lower angle steel 6.
According to Figure 14, Figure 15, Figure 16, concrete staircase includes bench 14, and bench 14 is high-end to be equipped with upper concrete ladder Beam 12 and floor levels plate 11, bench 14 is high-end to pour integrally with corresponding upper concrete ladder beam 12, and 14 low side of bench is equipped with Lower concrete ladder beam 15 and halfpace plate 17,14 low side of bench and corresponding lower 15 elastic connection of concrete ladder beam, elasticity is even Binding structure is:The gangboard 13 of the bench 14 is extended with horizontal segment 16, and the development length of extending level section 16 is not preferably less than one Tread run, is equipped with the spacing bearing 10 of damping between the horizontal segment 16 and corresponding lower concrete ladder beam 15.The spacing bearing of damping 10 quantity and position are designed according to 14 width of concrete bench and required friction damping force, change the suitable of arrangement Sequence and quantity are also fallen within the scope and spirit of the invention.
The spacing bearing work progress of the concrete staircase damping is as follows:
The component of lower concrete ladder beam 15 and halfpace plate 17 and its integrated connection 1. reinforcing bar is bound into first;
2. by lower connecting plate 8 and its anchor bolt of surface soldered 9 and the anchor bolt 7 one through lower connecting plate bolt hole Rise and be embedded in lower concrete ladder beam 15, stretch out anchor bolt 7;
3. to the component formwork and casting concrete of lower concrete ladder beam 15 and halfpace plate 17 and its integrated connection, support Form removal after some strength is protected, ensures that lower connecting plate 8 is firmly connected with lower concrete ladder beam 15;
4. bind the gangboard 13 of bench 14 and its integrated connection, horizontal segment 16, upper concrete ladder beam 12, floor levels plate 11 The reinforcing bar of component;
5. the anchor bolt 1 of upper junction plate 2 and its welding is embedded in horizontal segment 16 together, 2 pre-buried length of upper junction plate Degree is equal with the development length of horizontal segment 16, and upper junction plate caging bolt hole 201 is located at outside stair;
6. to the gangboard 13 of bench 14 and its integrated connection, horizontal segment 16, upper concrete ladder beam 12,11 structure of floor levels plate Part formwork and casting concrete, conserve form removal after some strength, ensure that upper junction plate 2 is firmly connected with horizontal segment 16;
7. the anchor bolt 7 that lower connecting plate 8 is stretched out passes through lower angle steel bolt hole 601, ensure lower 601 He of angle steel bolt hole Both 201 centre positions of alignment upper junction plate caging bolt hole of upper cover plate bolt hole 401;
8. high-strength bolt 3 is each passed through upper cover plate bolt hole 401, friction plate hole 501, upper junction plate caging bolt hole With lower angle steel bolt hole 601 among 201, pressure is applied by nut tightening to fix upper junction plate 2 and upper cover plate 4 and inferior horn Both positions of steel 6;
9. pressure is applied by nut tightening to fix the position of lower connecting plate 8 and lower angle steel 6, ensure lower connecting plate 8 and Lower angle steel 6 firmly connects.
A kind of spacing bearing of concrete staircase damping being formed as described above, it is allowed to upper and lower floor gap has displacement difference, Horizontal segment 16 drives upper junction plate 2 to be slided between the two in upper cover plate 4 and lower angle steel 6 and realizes friction energy-dissipating under geological process, subtracts Shake spacing bearing and not only suppress the vertical overhanging chattering of concrete bench low side, but also prevent concrete bench low side from existing Come off under big shake and horizontal jitter, the spacing bearing of damping are located at outside staircase structure, easy for construction, energy-dissipating and shock-absorbing limit effect Significantly.
Above is the exemplary embodiments of the present invention, implementation not limited to this of the invention.

Claims (1)

1. a kind of spacing bearing of concrete staircase damping, the stair include bench (14), and bench (14) is high-end to be equipped with upper coagulation Native ladder beam (12) and floor levels plate (11), bench (14) is high-end to pour integral, ladder with corresponding upper concrete ladder beam (12) Section (14) low side is equipped with lower concrete ladder beam (15) and halfpace plate (17), bench (14) low side and corresponding lower concrete ladder Beam (15) elastic connection, elastic connection structure are:The gangboard (13) of the bench (14) is extended with horizontal segment (16), the horizontal segment (16) the spacing bearing of damping (10) is equipped between corresponding lower concrete ladder beam (15), the spacing bearing of damping (10) includes upper company Fishplate bar (2), upper junction plate surface are equipped with anchor bolt (1) and upper junction plate caging bolt hole (201);Lower connecting plate (8), lower company Fishplate bar surface is equipped with anchor bolt (9), and the anchor bolt (7) through lower connecting plate bolt hole (801);Upper cover plate (4);Rub Wiping board (5);High-strength bolt (3);Lower angle steel (6);
Anchor bolt (1) and gangboard (13) anchor connection of the upper junction plate (2) by upper junction plate surface soldered, anchor spiral shell There is an anchoring cap being radially expanded in the distal end of bolt (1), the size of anchor bolt (1), quantity and length shearing resistance as needed and Stretching resistance determines;
The lower connecting plate (8) is connected by the anchor bolt (9) of lower connecting plate surface soldered with the anchoring of lower concrete ladder beam (15) Connect, there are the anchoring cap being radially expanded, the anchor of lower connecting plate surface soldered in the distal end of the anchor bolt (9) of lower connecting plate surface soldered The size of fixing bolt (9), quantity and length shearing resistance as needed and stretching resistance determine, through lower connecting plate bolt hole (801) anchor bolt (7) after is welded with lower connecting plate (8), through the anchor bolt (7) after lower connecting plate bolt hole (801) Distal end have the anchoring cap being radially expanded, through the size and number root of the anchor bolt (7) after lower connecting plate bolt hole (801) Determined according to the shearing resistance and stretching resistance of needs;
The friction plate (5) uses asbestos less friction plate, and upper cover plate (4) is firmly connected by epoxide-resin glue with friction plate (5), Lower angle steel (6) is firmly connected by epoxide-resin glue with friction plate (5);
The high-strength bolt (3) is each passed through upper cover plate bolt hole (401), friction plate hole (501), upper junction plate caging bolt hole (201) with lower angle steel bolt hole (601) among, pressure is applied by nut tightening to adjust upper junction plate (2) and upper cover plate (4) With the friction damping force of lower angle steel (6) between the two, the size of high-strength bolt (3), quantity and pressure friction resistance as needed Buddhist nun's power, stretching resistance and shearing resistance determine;
The anchor bolt (7) that the lower connecting plate (8) is stretched out passes through lower angle steel bolt hole (601), is applied by nut tightening and pressed Power fixes the position of lower connecting plate (8) and lower angle steel (6), ensures that lower connecting plate (8) is firmly connected with lower angle steel (6);
The spacing bearing construction method of concrete staircase damping, it is characterised in that:
The component of lower concrete ladder beam (15) and halfpace plate (17) and its integrated connection 1. reinforcing bar is bound into first;
2. by the anchor bolt (9) and the anchor bolt (7) through lower connecting plate bolt hole of lower connecting plate (8) and its surface soldered It is embedded in together in lower concrete ladder beam (15), stretches out anchor bolt (7);
3. to the component formwork and casting concrete of lower concrete ladder beam (15) and halfpace plate (17) and its integrated connection, support Form removal after some strength is protected, ensures that lower connecting plate (8) is firmly connected with lower concrete ladder beam (15);
4. bind the gangboard (13) of bench (14) and its integrated connection, horizontal segment (16), upper concrete ladder beam (12), floor levels The reinforcing bar of plate (11) component;
5. the anchor bolt (1) of upper junction plate (2) and its welding is embedded in horizontal segment (16) together, upper junction plate (2) is pre- It is equal with the development length of horizontal segment (16) to bury length, upper junction plate caging bolt hole (201) is located at outside stair;
6. to the gangboard (13) of bench (14) and its integrated connection, horizontal segment (16), upper concrete ladder beam (12), floor levels plate (11) component formwork and casting concrete, conserve form removal after some strength, ensure upper junction plate (2) and horizontal segment (16) Firmly connection;
7. the anchor bolt (7) that lower connecting plate (8) stretches out is passed through lower angle steel bolt hole (601), ensure lower angle steel bolt hole (601) and both upper cover plate bolts hole (401) alignment upper junction plate caging bolt hole (201) centre position;
8. high-strength bolt (3) is each passed through upper cover plate bolt hole (401), friction plate hole (501), upper junction plate caging bolt hole (201) with lower angle steel bolt hole (601) among, pressure is applied by nut tightening to fix upper junction plate (2) and upper cover plate (4) With the position of both lower angle steel (6);
9. applying pressure by nut tightening to fix the position of lower connecting plate (8) and lower angle steel (6), ensure lower connecting plate (8) Firmly it is connected with lower angle steel (6).
CN201610531843.3A 2016-07-04 2016-07-04 A kind of spacing bearing of concrete staircase damping Expired - Fee Related CN106121144B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610531843.3A CN106121144B (en) 2016-07-04 2016-07-04 A kind of spacing bearing of concrete staircase damping

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610531843.3A CN106121144B (en) 2016-07-04 2016-07-04 A kind of spacing bearing of concrete staircase damping

Publications (2)

Publication Number Publication Date
CN106121144A CN106121144A (en) 2016-11-16
CN106121144B true CN106121144B (en) 2018-05-15

Family

ID=57282342

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610531843.3A Expired - Fee Related CN106121144B (en) 2016-07-04 2016-07-04 A kind of spacing bearing of concrete staircase damping

Country Status (1)

Country Link
CN (1) CN106121144B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643489B (en) * 2018-06-12 2023-10-31 北京工业大学 Damping stair adopting supporting type energy dissipater
CN108691380B (en) * 2018-06-28 2023-04-18 福州大学 Damping assembly type concrete floor structure and construction method thereof
CN110593500B (en) * 2019-09-27 2020-10-09 安徽建筑大学城市建设学院 Safe and firm assembled earthquake-resistant stair
CN113026959B (en) * 2019-12-24 2022-11-04 成都建工第二建筑工程有限公司 Installation method of prefabricated staircase

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0369742A (en) * 1989-08-09 1991-03-26 Haseko Corp Device for base isolation for building
CN2685421Y (en) * 2004-03-16 2005-03-16 广州大学 Building shockproof supprot
CN201762841U (en) * 2010-09-10 2011-03-16 辛力 Stair vibration isolation device
CN201952934U (en) * 2010-12-20 2011-08-31 张蓬勃 Friction damper filled with aluminum plate friction material
CN203569719U (en) * 2013-10-29 2014-04-30 广州大学 Energy-dissipation shock-absorption structure of concrete stair
CN205777188U (en) * 2016-07-04 2016-12-07 河北工业大学 A kind of spacing bearing of concrete staircase damping

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0369742A (en) * 1989-08-09 1991-03-26 Haseko Corp Device for base isolation for building
CN2685421Y (en) * 2004-03-16 2005-03-16 广州大学 Building shockproof supprot
CN201762841U (en) * 2010-09-10 2011-03-16 辛力 Stair vibration isolation device
CN201952934U (en) * 2010-12-20 2011-08-31 张蓬勃 Friction damper filled with aluminum plate friction material
CN203569719U (en) * 2013-10-29 2014-04-30 广州大学 Energy-dissipation shock-absorption structure of concrete stair
CN205777188U (en) * 2016-07-04 2016-12-07 河北工业大学 A kind of spacing bearing of concrete staircase damping

Also Published As

Publication number Publication date
CN106121144A (en) 2016-11-16

Similar Documents

Publication Publication Date Title
CN108532474B (en) Overturn-preventing reinforcing device and installation method for single-column pier bridge
CN106121144B (en) A kind of spacing bearing of concrete staircase damping
CN203200914U (en) Steel structure socle outward exposed connecting structure
CN204589822U (en) The two cantilever bent cap anchor ear Construction Support system of a kind of solely post
CN104005338B (en) A kind of long-span cablestayed bridges tower beam three-dimensional temporary consolidation structure
CN106436583B (en) A kind of interim stretch-draw anchor suspension device of great cantilever bent cap and its construction method
CN205857032U (en) The toughened internal stress Construction Support device that a kind of floor stand combines with shelf bracket
CN108589971A (en) A kind of closed-section steel deck combined concrete shear wall connecting node and production method
CN110886201A (en) Prefabricated assembled concrete-filled steel tube self-resetting pier with earthquake damage replaceable components
CN108193792A (en) A kind of novel replaceable waves energy consumption suspension column
CN108978471A (en) A kind of support device and its installation method increasing cable-stayed bridge abnormity Sarasota rigidity
CN108677690A (en) Energy dissipating Self-resetting bilayer rectangle hollow concrete filled steel tube waves Bridge Pier Structure System
CN205207907U (en) Novel pipeline bracket of tape base plinth
CN109881587B (en) Integral installation method of main tower upper cross beam support in strong wind environment
CN111455834A (en) Self-resetting prefabricated assembled pier and construction method thereof
CN109371807B (en) Bridge structure system capable of being rapidly transformed
CN102277836A (en) Construction method of tilting concrete tower base
CN106760014A (en) A kind of board-like adjustable damper embedded part of full assembled and installation method
KR101161644B1 (en) Partially earth-anchored cable-stayed bridge using hinge connection parts and construction method for the same
CN208136711U (en) It is a kind of suitable for steel bridge or the anti-pulling support of steel reinforced concrete composite beam bridge
CN206607506U (en) A kind of through type adds the capping construction support of passive stress trapezoid block
CN103614974A (en) Prestress sectional steel reinforcing system of reinforced concrete arch shell bridge body
CN206956535U (en) One kind enhancing antidetonation pier stud
Au et al. Wine industry implementation of the NZSEE guidance on the seismic design of liquid storage tanks
CN205777188U (en) A kind of spacing bearing of concrete staircase damping

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180515

Termination date: 20190704