CN106115922B - A kind of construction method of the clean water treatment for Landscape Park - Google Patents

A kind of construction method of the clean water treatment for Landscape Park Download PDF

Info

Publication number
CN106115922B
CN106115922B CN201610511250.0A CN201610511250A CN106115922B CN 106115922 B CN106115922 B CN 106115922B CN 201610511250 A CN201610511250 A CN 201610511250A CN 106115922 B CN106115922 B CN 106115922B
Authority
CN
China
Prior art keywords
region
landscape park
sundries
purification
water quality
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610511250.0A
Other languages
Chinese (zh)
Other versions
CN106115922A (en
Inventor
周伟波
许育锋
陈伟
严密
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jing Chang Construction Co., Ltd.
Original Assignee
Zhejiang Jing Chang Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jing Chang Construction Co Ltd filed Critical Zhejiang Jing Chang Construction Co Ltd
Priority to CN201610511250.0A priority Critical patent/CN106115922B/en
Publication of CN106115922A publication Critical patent/CN106115922A/en
Application granted granted Critical
Publication of CN106115922B publication Critical patent/CN106115922B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F3/00Biological treatment of water, waste water, or sewage
    • C02F3/32Biological treatment of water, waste water, or sewage characterised by the animals or plants used, e.g. algae
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F3/00Biological treatment of water, waste water, or sewage
    • C02F3/34Biological treatment of water, waste water, or sewage characterised by the microorganisms used
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W10/00Technologies for wastewater treatment
    • Y02W10/10Biological treatment of water, waste water, or sewage

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Microbiology (AREA)
  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • Organic Chemistry (AREA)
  • Botany (AREA)
  • Biotechnology (AREA)
  • Purification Treatments By Anaerobic Or Anaerobic And Aerobic Bacteria Or Animals (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of construction methods of clean water treatment for Landscape Park, include the following steps: (a) surveying setting-out;(b) sundries blocking region is set;(c) greenbelt purification of water quality region is built;(d) scene cleaning and maintenance;(e) aquatic plant purification region is set up;(f) Landscape Park water quality monitoring.The present invention carries out functional regional division to Landscape Park, successively construct to sundries blocking region, greenbelt purification of water quality region and aquatic plant purification region, Landscape Park is enabled to obtain carrying out three-level water quality purified treatment, improve clean-up effect, the ornamental value of Landscape Park is improved, while this method has pollution-free, short construction period, it is at low cost, the quick feature of water treatment.

Description

A kind of construction method of the clean water treatment for Landscape Park
Technical field
The invention belongs to water treatment technical fields, and in particular to a kind of construction party of the clean water treatment for Landscape Park Method.
Background technique
Social economy, cultural development have all effectively driven the raising of living standards of the people, accordingly to living environment It is also had higher requirement with city integrated environment, and landscape water becomes one of the important means of improvement urban environment.But due to Starting evening, development are slow, and especially management measure is not in place, and the water quality of landscape water is caused to have gradually changed, some water quality become Change more serious place, influences the normal life of neighbouring resident.
Water environment is closely related with people's lives quality, as the deterioration of water environment is faced with increasingly severeer shape Gesture, natural black-odor riverway are difficult to administer, and new river is constantly contaminated.The water quality of artificial lake water will face huge examine It tests.Due to the influence of natural environment and hydrological environment, all there is more or less problem in many artificial Lake Waters, and cause dirt , mainly there is the following aspects in the reason of dye: 1, rainwash and underground percolation;2, initial rainwater;3, breeding pollution;4, aquatic Plant;5, bed mud;6, dissolved oxygen in water body.
But Landscape Park quality problem still fails to the attention for causing relevant departments, and existing processing mode is most of also only It is limited to artificial hillock, fountain, and these processing modes easily cause the vigorous breeding of algae, and there is smelly situation.
Summary of the invention
Above-mentioned technical problem present in present invention aims to solve the prior art provides a kind of for Landscape Park The construction method of clean water treatment carries out functional regional division to Landscape Park, successively net to sundries blocking region, greenbelt water quality Change region and aquatic plant purification region is constructed, enables Landscape Park to obtain carrying out three-level water quality purified treatment, improve Clean-up effect improves the ornamental value of Landscape Park, while this method has pollution-free, short construction period, at low cost, water treatment Quick feature.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme:
A kind of construction method of the clean water treatment for Landscape Park, it is characterised in that include the following steps:
(a) surveying setting-out: according to Landscape Park water treatment position coordinates, the baseline, base being arranged on overall construction site plan Landscape Park water treatment region is divided into greenbelt purification of water quality region, sundries blocking area by plinth data and elevation control point Domain and aquatic plant purification region three zones region, and carry out site survey with theodolite, level and steel ruler and set, respectively green Change band purification of water quality region, sundries blocking region and aquatic plant purification region and establish construction control points, then in three zones Boundary stake is released at region, and controls stake in each boundary setting transverse direction and longitudinal direction;
(b) sundries blocking region is set: manual cleaning sundries being used according to the sundries blocking region of division first, and is tamped Soil, then horizontal control lines are pulled up out in control stake, then manually fixed plate is inserted on limited post, and limited post is installed Onto pedestal, the assembly of blocking apparatus is completed, then blocking apparatus is placed at sundries blocking region, by horizontal control lines Blocking apparatus is abutted two-by-two, then blocking apparatus is hit under 4-6 with mallet, then blocking apparatus taken out, and to sinking at Blocking apparatus, is then placed at fixing groove, is then pounded with mallet to blocking apparatus by vertical lower digging fixing groove, until Stop beaing when the cover board of base top is attached at soil surface, then according to the setting position of blocking apparatus, is being located at sundries Spud pile is arranged in the side for intercepting the outermost blocking apparatus in region, then penetrates iron wire in fixed plate, and by the end of iron wire Head is wrapped on spud pile, then removes horizontal control lines;
(c) it builds greenbelt purification of water quality region: first according to greenbelt purification of water quality setting area, being carried out using excavator It cuts the earth, then carries out supporting with plank in the foundation pit boundary of excavation, anchor pole is then inserted into foundation pit, be then in same water Straw rope is pulled out between anchor pole on horizontal line, then backfills soil in the foundation pit centre of excavation, and carry out layering throwing in soil surface Then stone is embedded to the earthwork between adjacent two straw ropes, the earthwork on kind is implanted with greenbelt, then backfills between adjacent two pieces of earthwork Then soil carries out irrigation effect with irrigation water;
(d) scene cleaning and maintenance;
(e) it sets up aquatic plant purification region: being first put into planting pot in the ecologic planting slot of ecological kickboard, then planting Soil is inserted in basin, then planting aquatic plants in the soil, then slide into ecological kickboard on two battens, then by button block It snaps on batten, button block withstands the ecological kickboard of outermost end, then batten is fixed on fixed frame, then in water plant Purification sets up timber structure road in region, and further according to timber structure road setting area, fixed frame is fixed to timber structure road Bottom launches bivalves and spiral shell into water body setting up aquatic plant purification region 8-10d, launches grass into water body after 15-20d Fish, 20-25d launch ominivore-fish into water body;
(f) Landscape Park water quality monitoring.
Further, in step (b), at least three pieces of fixed plates are set on single limited post, it is longitudinal in monolithic fixed plate Across at least three iron wires, at least two iron wires are horizontally through in monolithic fixed plate.
Further, in step (c), shoveling work successively carries out longitudinal construction from top to bottom, and reserved 10-20cm is thick when shoveling Layer is rebuild, it is whole to dig to designed elevation, then drainage channel is excavated in two sides.
Further, in step (d), scene cleaning and maintenance work include carrying out the sundries left in work progress clearly Reason, while construction tool is arranged, unified placement is carried out, was then irrigated greenbelt and trimmed maintainer every 10-15 days Make.
Further, in step (e), fixed frame is fixed to before the bottom of timber structure road, it will using two traction ropes Fixed frame is connected on timber structure road, and two traction rope length are identical and are arranged in parallel, when fixed frame is fixed to timber structure road When the bottom on road, traction rope is removed.
Further, in the water quality monitoring of step (f) Landscape Park, water quality monitoring is carried out using on-line monitoring system, it is online to supervise Examining system is monitored work using Instrument measuring, network delivery, monitoring and management platform.
The present invention is by adopting the above-described technical solution, have the advantages that
1, the present invention carries out functional regional division to Landscape Park, and the greenbelt purification of water quality region of construction is land and water ecology System carries out the important place of substance transfer and energy transmission, can mitigate earth's surface and interflow subsurface drainage to landscape water bring and endanger journey Degree, greenbelt are removed in runoff by seepage flow, delay, filtering, the absorption of soil particle, plant absorption, being converted for microorganism The substances such as solid particulate matter, suspended matter, organic matter, pathogen, hazardous compound, heavy metal ion, play first order purification The effect of water body;The sundries blocking region of setting is the barrier of greenbelt and Landscape Park, will be in greenbelt purification of water quality region Dirty sundries is filtered, and be can be reduced sundries and is entered in the water body of Landscape Park, and the effect of second level purifying water body is played; The aquatic plant purification region set up is important place of the water plant to the absorption of inorganic nutrients salt, accumulation and conversion, is The basis of restoration of the ecosystem can integrally build a kind of affine environmental benefit of natural style ecology, play third level purifying water body Effect.
2, the present invention first to setting sundries blocking region, then builds greenbelt purification of water quality area during Specific construction Then aquatic plant purification region is set up in domain, can reduce the sundries that generates in work progress to the direct shadow of Landscape Park water body It rings;In setting sundries blocking region work progress, blocking apparatus is placed at sundries blocking region by horizontal control lines, Blocking apparatus is driven into soil in two stages using mallet, accelerates the setting speed of blocking apparatus, and energy will be two neighboring Blocking apparatus precisely aligns, and convenient for penetrating iron wire between the fixing plates, improves construction efficiency, iron wire carries out blocking work to sundries With so that blocking apparatus plays the role of filtering sundries;In construction greenbelt purification of water quality region work progress, in foundation pit It is inserted into anchor pole, and pulls out straw rope between the anchor pole in same horizontal line, the region of greenbelt laying is marked off, avoids soil Side is laid with inclination, improves efficiency and aesthetics that greenbelt is laid with;In setting up aquatic plant purification region work progress, ecology Kickboard, which directly slides on two battens, is spliced, then batten is fixed on fixed frame, then can directly pass through fixed spiral shell Fixed frame is fixed to the bottom of timber structure road by silk, reduces the ecological mutual assembled step of kickboard and to ecological kickboard Fixing step improves construction efficiency.The present invention improve clean-up effect, improve the ornamental value of Landscape Park, at the same have it is pollution-free, Short construction period, at low cost, the quick feature of water treatment.
Detailed description of the invention
The present invention will be further explained below with reference to the attached drawings:
Fig. 1 is the structural schematic diagram after present invention construction;
Structural schematic diagram when Fig. 2 is present invention setting sundries blocking region;
Structural schematic diagram when Fig. 3 is present invention setting fixed plate;
Fig. 4 is the structural schematic diagram when present invention sets up aquatic plant purification region.
Specific embodiment
The scope of application of the invention: it is suitable for Landscape Park water treatment.
As shown in Figures 1 to 4, a kind of construction method of the clean water treatment for Landscape Park, includes the following steps:
(a) surveying setting-out: according to Landscape Park water treatment position coordinates, the baseline, base being arranged on overall construction site plan Landscape Park water treatment region is divided into greenbelt purification of water quality region 1, sundries blocking area by plinth data and elevation control point 3 three zones region of domain 2 and aquatic plant purification region, and carry out site survey with theodolite, level and steel ruler and set, exist respectively Construction control points are established in greenbelt purification of water quality region 1, sundries blocking region 2 and aquatic plant purification region 3, then big three Boundary stake is released at functional area, and controls stake in each boundary setting transverse direction and longitudinal direction.
(b) sundries blocking region 2 is set: manual cleaning sundries being used according to the sundries blocking region 2 of division first, and is rammed Real soil, then horizontal control lines are pulled up out in control stake, then manually fixed plate 4 is inserted on limited post 5, and by limited post 5 are installed on pedestal 6, complete the assembly of blocking apparatus 9, then blocking apparatus 9 is placed at sundries blocking region 2, by Horizontal control lines abut blocking apparatus 9 two-by-two, are then hit under 4-6 with mallet blocking apparatus 9, then blocking apparatus 9 is taken Out, and to vertically lower at sinking fixing groove is dug, then blocking apparatus 9 is placed at fixing groove, then interception is filled with mallet It sets 9 to pound, stops beaing when the cover board at 6 top of pedestal is attached at soil surface, then setting according to blocking apparatus 9 Spud pile 7 is arranged in the side for being located at the outermost blocking apparatus 9 in sundries blocking region 2, then in fixed plate 4 in seated position Iron wire 8 is penetrated, and the end of iron wire 8 is wrapped on spud pile 7, then removes horizontal control lines.It is set on single limited post 5 At least three pieces of fixed plates 4 are set, longitudinally through at least three iron wires 8 in monolithic fixed plate 4, are laterally worn in monolithic fixed plate 4 Cross at least two iron wires 8.
(c) build greenbelt purification of water quality region 1: first according to greenbelt purification of water quality setting area, using excavator into Row is cut the earth, and shoveling work successively carries out longitudinal construction from top to bottom, and when shoveling, reserved 10-20cm thickness rebuild layer, whole to dig to setting Absolute altitude is counted, then excavates drainage channel in two sides.Supporting is carried out with plank in the foundation pit boundary of excavation again, then in foundation pit It is inserted into anchor pole, then pulls out straw rope, then the foundation pit centre backfill in excavation between the anchor pole in same horizontal line Earth, and layering jackstone is carried out in soil surface, it then is embedded to the earthwork between adjacent two straw ropes, the earthwork on kind is implanted with greening Band, then soil is backfilled between adjacent two pieces of earthwork, then irrigation effect is carried out with irrigation water.
(d) scene is cleared up and conserved: scene is cleared up and maintenance work includes carrying out the sundries left in work progress clearly Reason, while construction tool is arranged, unified placement is carried out, was then irrigated greenbelt and trimmed maintainer every 10-15 days Make.
(e) it sets up aquatic plant purification region 3: being first put into planting pot in the ecologic planting slot of ecological kickboard 10, then Soil is inserted in planting pot, then planting aquatic plants in the soil, then slide into ecological kickboard 10 on two battens 11, Button block 12 is snapped on batten 11 again, button block 12 withstands the ecological kickboard 10 of outermost end, is then fixed to batten 11 and fixes On frame 13, timber structure road 14 is then set up in aquatic plant purification region 3, further according to 14 setting area of timber structure road, Fixed frame 13 is fixed to the bottom of timber structure road 14.Fixed frame 13 is fixed to before the bottom of timber structure road 14, is adopted Fixed frame 13 is connected on timber structure road 14 with two traction ropes, two traction rope length are identical and are arranged in parallel, when solid When determining bottom of the frame 13 fixed to timber structure road 14, traction rope is removed.Set up aquatic plant purification region 38-10d to Bivalves and spiral shell are launched in water body, grass carp are launched into water body after 15-20d, 20-25d launches ominivore-fish into water body.
(f) Landscape Park water quality monitoring: water quality monitoring is carried out using on-line monitoring system, on-line monitoring system uses instrument Measurement, network delivery, monitoring and management platform are monitored work.It is mounted on the monitoring instrument in Landscape Park shelter, it can be with The special parameter measurement of water quality is carried out to the monitoring point in Landscape Park water body, then needs to be equipped with long-range in terms of network transmission The data collector of communication function, monitoring then need the software systems of a set of perfect in shape and function with management platform, are able to achieve data and adopt The functions such as collection, storage, alarm, inquiry, report, scheduling, early warning.
The present invention carries out functional regional division to Landscape Park, and the greenbelt purification of water quality region 1 of construction is land and water ecology System carries out the important place of substance transfer and energy transmission, can mitigate earth's surface and interflow subsurface drainage to landscape water bring and endanger journey Degree, greenbelt are removed in runoff by seepage flow, delay, filtering, the absorption of soil particle, plant absorption, being converted for microorganism The substances such as solid particulate matter, suspended matter, organic matter, pathogen, hazardous compound, heavy metal ion, play first order purification The effect of water body;The sundries blocking region 2 of setting is the barrier of greenbelt and Landscape Park, by greenbelt purification of water quality region 1 In flow down sundries be filtered, can be reduced sundries and enter in the water body of Landscape Park, play the effect of second level purifying water body Fruit;The aquatic plant purification region 3 set up is important field of the water plant to the absorption of inorganic nutrients salt, accumulation and conversion Institute is the basis of restoration of the ecosystem, can integrally build a kind of affine environmental benefit of natural style ecology, play third level purified water The effect of body.
The present invention first to setting sundries blocking region 2, then builds greenbelt purification of water quality region during Specific construction 1, aquatic plant purification region 3 is then set up, the sundries that generates in work progress can be reduced to the direct shadow of Landscape Park water body It rings;In setting 2 work progress of sundries blocking region, blocking apparatus 9 is placed into sundries blocking region 2 by horizontal control lines Blocking apparatus 9, is driven into soil by place in two stages using mallet, accelerates the setting speed of blocking apparatus 9, and energy will be adjacent Two blocking apparatus 9 precisely align, and convenient for penetrating iron wire 8 between fixed plate 4, improve construction efficiency, iron wire 8 carries out sundries Barrier effect, so that blocking apparatus 9 plays the role of filtering sundries;In construction 1 work progress of greenbelt purification of water quality region, It is inserted into anchor pole in foundation pit, and pulls out straw rope between the anchor pole in same horizontal line, marks off the area of greenbelt laying Domain avoids the earthwork from being laid with inclination, improves efficiency and aesthetics that greenbelt is laid with;It constructs setting up aquatic plant purification region 3 In the process, ecological kickboard 10 directly slides on two battens 11 and is spliced, then batten 11 is fixed on fixed frame 13, so Fixed frame 13 can be directly fixed to by fixed screw the bottom of timber structure road 14 afterwards, reduce ecological kickboard 10 between each other Assembled step and fixing step to ecological kickboard 10, improve construction efficiency.The present invention improves clean-up effect, and it is public to improve landscape The ornamental value in garden, while there is pollution-free, short construction period, at low cost, the quick feature of water treatment.
One, design principle
1, scientific and reasonable principle.For the Landscape Park engineering of different situations, used water treatment technology also has difference It is different.Design will select suitable process according to the actual conditions of Landscape Park, carry out refinement.
2, economical and practical principle.The purpose of water treatment system setting: first is that in order to guarantee landscape effect;Second is that saving water money Recycling for water is accomplished in source as far as possible.So landscape water treatment technology must be economical and practical, meet the requirement of green energy conservation, Operating cost is controlled in reasonable range, otherwise will cause the waste of resource, also influences the holding of water landscape effect.
3, the principle of long-term effect.Water treatment system must be able to the water quality of permanently effective guarantee landscape water body.
Two, daily management
The holding of park landscape water quality cannot be the maintenance of equipment, daily only by designing reasonable water treatment system The management of operation requires the cooperation of infrastructure management company's management.In addition, such as encountering the water pollution accident of burst, water treatment system pair The restitution of water body seems unable to do what one wishes, it is necessary to by the water contamination accident for forcing intervening measure reply burst.
External source pollution is controlled, the processing pressure of water treatment system is mitigated.Publicity is increased, the conscious protection meaning of the public is improved Know.The normal operation of water holding processing system guarantees the dirty removal capacities of system.
Management unit will arrange special messenger to participate in the professional training of daily maintenance while adapter tube water scenery;Periodic detection water Matter situation, carries out the maintenance of water processing establishment, and establishes operation and record of examination, it is ensured that and extend the service life of equipment, It accumulates water scenery and manages relevant working experience;The sundries such as leaf, the withered grass in water body are salvaged in time, prevent the polluted-water that rots.
The above is only specific embodiments of the present invention, but technical characteristic of the invention is not limited thereto.It is any with this hair Based on bright, to solve essentially identical technical problem, essentially identical technical effect is realized, made simple change, etc. With replacement or modification etc., all it is covered by among protection scope of the present invention.

Claims (6)

1. a kind of construction method of the clean water treatment for Landscape Park, it is characterised in that include the following steps:
(a) surveying setting-out: according to the Landscape Park water treatment position coordinates, baseline, basic number being arranged on overall construction site plan Accordingly and elevation control point, by Landscape Park water treatment region be divided into greenbelt purification of water quality region, sundries blocking region and Aquatic plant purification region three zones region, and carry out site survey with theodolite, level and steel ruler and set, respectively in greenbelt Construction control points are established in purification of water quality region, sundries blocking region and aquatic plant purification region, then in three zones region Place releases boundary stake, and controls stake in each boundary setting transverse direction and longitudinal direction;
(b) sundries blocking region is set: manual cleaning sundries being used according to the sundries blocking region of division first, and tamps soil Earth, then horizontal control lines are pulled up out in control stake, then manually fixed plate is inserted on limited post, and limited post is installed to On pedestal, the assembly of blocking apparatus is completed, then blocking apparatus is placed at sundries blocking region, it will by horizontal control lines Blocking apparatus abuts two-by-two, is then hit under 4-6 with mallet blocking apparatus, then blocking apparatus is taken out, and hang down at sinking Blocking apparatus, is then placed at fixing groove, is then pounded with mallet to blocking apparatus, until bottom by straight lower digging fixing groove The cover board at seat top stops beaing when being attached at soil surface, then according to the setting position of blocking apparatus, blocks positioned at sundries Spud pile is arranged in the side of the outermost blocking apparatus of regions, then penetrates iron wire in fixed plate, and by the end of iron wire It is wrapped on spud pile, then removes horizontal control lines;
(c) it builds greenbelt purification of water quality region: first according to greenbelt purification of water quality setting area, being dug using excavator Soil, then supporting is carried out with plank in the foundation pit boundary of excavation, it is then inserted into anchor pole in foundation pit, is then being in same level Straw rope is pulled out between anchor pole on line, then backfills soil in the foundation pit centre of excavation, and carry out layering jackstone in soil surface, Then the earthwork is embedded between adjacent two straw ropes, the earthwork on kind is implanted with greenbelt, then the backfill between adjacent two pieces of earthwork Then earth carries out irrigation effect with irrigation water;
(d) scene cleaning and maintenance;
(e) it sets up aquatic plant purification region: being first put into planting pot in the ecologic planting slot of ecological kickboard, then in planting pot Soil is inserted, then planting aquatic plants in the soil, then slid into ecological kickboard on two battens, then button block is buckled into Onto batten, button block withstands the ecological kickboard of outermost end, then batten is fixed on fixed frame, then in aquatic plant purification Timber structure road is set up in region, and further according to timber structure road setting area, fixed frame is fixed to the bottom of timber structure road, Bivalves and spiral shell are launched into water body setting up aquatic plant purification region 8-10d, and grass carp is launched into water body after 15-20d, 20-25d launches ominivore-fish into water body;
(f) Landscape Park water quality monitoring.
2. a kind of construction method of clean water treatment for Landscape Park according to claim 1, it is characterised in that: step (b) in, at least three pieces of fixed plates are set on single limited post, longitudinally through at least three iron wires in monolithic fixed plate, At least two iron wires are horizontally through in monolithic fixed plate.
3. a kind of construction method of clean water treatment for Landscape Park according to claim 1, it is characterised in that: step (c) in, shoveling work successively carries out longitudinal construction from top to bottom, and when shoveling, reserved 10-20cm thickness rebuild layer, whole to dig to designing Then absolute altitude excavates drainage channel in two sides.
4. a kind of construction method of clean water treatment for Landscape Park according to claim 1, it is characterised in that: step (d) in, scene cleaning and maintenance work include that the sundries that will be left in work progress is cleared up, while arranging construction tool, Unified placement is carried out, was then irrigated greenbelt and trimmed maintenance work every 10-15 days.
5. a kind of construction method of clean water treatment for Landscape Park according to claim 1, it is characterised in that: step (e) in, fixed frame is fixed to before the bottom of timber structure road, fixed frame is connected to timber structure road using two traction ropes On the road, two traction rope length are identical and are arranged in parallel, and when fixed frame is fixed to the bottom of timber structure road, traction rope is torn open It removes.
6. a kind of construction method of clean water treatment for Landscape Park according to claim 1, it is characterised in that: step (f) in Landscape Park water quality monitoring, using on-line monitoring system carry out water quality monitoring, on-line monitoring system using Instrument measuring, Network delivery, monitoring and management platform are monitored work.
CN201610511250.0A 2016-06-27 2016-06-27 A kind of construction method of the clean water treatment for Landscape Park Active CN106115922B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610511250.0A CN106115922B (en) 2016-06-27 2016-06-27 A kind of construction method of the clean water treatment for Landscape Park

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610511250.0A CN106115922B (en) 2016-06-27 2016-06-27 A kind of construction method of the clean water treatment for Landscape Park

Publications (2)

Publication Number Publication Date
CN106115922A CN106115922A (en) 2016-11-16
CN106115922B true CN106115922B (en) 2019-07-19

Family

ID=57468019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610511250.0A Active CN106115922B (en) 2016-06-27 2016-06-27 A kind of construction method of the clean water treatment for Landscape Park

Country Status (1)

Country Link
CN (1) CN106115922B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107720968B (en) * 2017-10-30 2019-12-06 浙江寰龙环境科技有限公司 Sewage treatment device for river channel and treatment method thereof
CN115156270A (en) * 2022-07-25 2022-10-11 天津华勘环保科技有限公司 Method for repairing groundwater in pollution area of green belt

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1546796A (en) * 2003-12-08 2004-11-17 �Ϻ���ͨ��ѧ Sewage treatment method for construction wetland of ditch and river bank
KR101158247B1 (en) * 2010-12-14 2012-07-20 주식회사 동호 System for ecologically restoring a river and purifying fluid using wetland structure
CN203080678U (en) * 2013-01-15 2013-07-24 朱加林 Environment-friendly community shock-resistant rainwater ecological utilizing system
CN104230100A (en) * 2014-09-04 2014-12-24 上海汀滢环保科技有限公司 Three-dimensional ecological corridor system and method for in-situ restoration of river water body

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1546796A (en) * 2003-12-08 2004-11-17 �Ϻ���ͨ��ѧ Sewage treatment method for construction wetland of ditch and river bank
KR101158247B1 (en) * 2010-12-14 2012-07-20 주식회사 동호 System for ecologically restoring a river and purifying fluid using wetland structure
CN203080678U (en) * 2013-01-15 2013-07-24 朱加林 Environment-friendly community shock-resistant rainwater ecological utilizing system
CN104230100A (en) * 2014-09-04 2014-12-24 上海汀滢环保科技有限公司 Three-dimensional ecological corridor system and method for in-situ restoration of river water body

Also Published As

Publication number Publication date
CN106115922A (en) 2016-11-16

Similar Documents

Publication Publication Date Title
CN105862549B (en) Band and its construction method are detained in biological cleaning for sponge urban municipal road
CN102071697B (en) Hard reinforced concrete revetment slope biological repairing method
CN106193259B (en) A kind of Rainwater collection system and construction method for sponge city
CN106192665B (en) A kind of sponge urban road rain infiltration system and its construction method
CN106088289A (en) A kind of water storage system for sponge Front river course road and construction method
Woodbury et al. Water control systems of the Tehuacan Valley
CN102322066A (en) Three-in-one slope collapse managing method employing slope management, slope lowering and slope stabilization
CN107100227A (en) A kind of pergola on the city road LID biologies are detained ditch construction method
CN106958264A (en) A kind of highway greenbelt and its construction method
CN108612047B (en) Ecological repairing structure of river and lake bank slope
CN106115922B (en) A kind of construction method of the clean water treatment for Landscape Park
CN209798667U (en) Ecological bank protection of hydraulic engineering
CN208346836U (en) A kind of hidden drainage system
CN1296735A (en) Method for transplanting old and noble trees
CN208501715U (en) A kind of Rain Garden
CN206693154U (en) A kind of town and country river course slope protection system
CN105155386A (en) Water blocking type kerb and construction method thereof
CN214301528U (en) Sponge transformation system for urban river retaining wall
CN214402046U (en) Saline and alkaline land afforestation salt elimination infiltration structure
CN212064807U (en) Rocky desertification area soil and water loss treatment system
CN209660100U (en) A kind of Rocky Desertification Region rainwater-collecting recharge system
CN106894387A (en) A kind of town and country river course slope protection system and method for paving
CN112144469A (en) Bank slope water purification wetland structure combined with ecological revetment
CN112813758A (en) Highway spoil heap processing system
CN204919265U (en) Waterproofing type curb

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhou Weibo

Inventor after: Xu Yufeng

Inventor after: Chen Wei

Inventor after: Yan Mi

Inventor before: Liu Xueying

Inventor before: Si Menglong

Inventor before: Liu Lijun

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20170803

Address after: 323500, Fenghuang Road, Hongxing street, Jingning County, Zhejiang Province, 198

Applicant after: Zhejiang Jing Chang Construction Co., Ltd.

Address before: Hangzhou City, Zhejiang province 310018 Xiasha Higher Education Institutions in East Street No. 508

Applicant before: Zhejiang University of Water Resources and Electric Power

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant