CN106097661B CN201610596732.0A CN201610596732A CN106097661B CN 106097661 B CN106097661 B CN 106097661B CN 201610596732 A CN201610596732 A CN 201610596732A CN 106097661 B CN106097661 B CN 106097661B
Authority
CN
China
Prior art keywords
information
early warning
hidden danger
warning
meteorological
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610596732.0A
Other languages
Chinese (zh)
Other versions
CN106097661A (en
Inventor
张炜
吴秋莉
郭丽娟
邬蓉蓉
邓雨荣
吕泽承
陶松梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Guangxi Power Grid Co Ltd
Original Assignee
Electric Power Research Institute of Guangxi Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Guangxi Power Grid Co Ltd filed Critical Electric Power Research Institute of Guangxi Power Grid Co Ltd
Priority to CN201610596732.0A priority Critical patent/CN106097661B/en
Publication of CN106097661A publication Critical patent/CN106097661A/en
Application granted granted Critical
Publication of CN106097661B publication Critical patent/CN106097661B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/02Alarms for ensuring the safety of persons
    • G08B21/10Alarms for ensuring the safety of persons responsive to calamitous events, e.g. tornados or earthquakes
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B31/00Predictive alarm systems characterised by extrapolation or other computation using updated historic data

Landscapes

  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Engineering & Computer Science (AREA)
  • Computing Systems (AREA)
  • Alarm Systems (AREA)

Abstract

The invention discloses a kind of meter and the power equipment method for prewarning risk and system of meteorological disaster, comprising the following steps: obtains current weather disaster early-warning information;Obtain current electric grid security risk information;Judge power grid security hidden danger region with the presence or absence of meteorological disaster early warning;Judge the type and degree of the region early warning of power grid security hidden danger;Issue security risk early warning.The present invention is based on geographical location information matching techniques, expertise, by carrying out location matches research between the position of the region of Public meteorology disaster alarm, type, severity and electric power facility security risk, type and severity, association analysis etc., realize the accurate and timely early warning to electric power facility security risk, under the conditions of can effectively promoting special weather, the timeliness and specific aim of electric power facility security risk early warning, and then accomplish accurately and timely early warning hidden danger, improve the thinking and means of hidden danger processing.

Description

It is a kind of meter and meteorological disaster power equipment method for prewarning risk
Technical field
The present invention relates to power equipment state monitoring and fault diagnosis technology field, a kind of meter and gas are concretely related to As the power equipment method for prewarning risk and system of disaster.
Background technique
Public meteorology disaster alarm plays increasingly key player, state in resident living, enterprise's production activity at present Weather bureau of family is typical also to the meteorological disaster specification of different type, different severity mark, publication process and counter-measure Meteorological disaster type have heavy rain, high temperature, cooling strong wind, strong convective weather, sandstorm, Strong Breezes Over, dense fog, haze, cold wave, sudden and violent 11 seed types of snow and typhoon etc., grade have blue, yellow, orange and red respectively indicate general, heavier, serious and especially severe.Meteorological calamity Evil warning information generally comprises city, area, type, grade, state, issuing time, renewal time and early warning text.
Power grid and its equipment are run among environment, are necessarily influenced by environment, especially when meteorological condition becomes When change.Power equipment is influenced also different because of differences such as its type, local environment, self-conditions by different meteorological conditions; In electric power facility security risk management aspect, the publication of hidden danger of electric power enterprise specification, processing process.Electric power facility is hidden safely Building can be divided into according to its type, construction, screen of trees, side slope, mountain fire, Bird's Nest, flare object, stack the types such as sundries, description by suffering from Information generally comprises affiliated company, title, place, description, hidden danger source, type, discovery date, state, grade, consequence etc..
Currently, the influence for meteorological disaster early warning and its to power equipment mainly passes through GIS-Geographic Information System, by gas Image data, the location sets application including forecast data, real time data and power equipment, main there are two aspects: (1) showing electricity There is what power equipment perhaps its current or history meteorological condition of facility in the weather circumstance condition of net, such as certain region How;It (2) can be according to the meteorological condition of history, when judging that current meteorological condition reaches certain rank, to the shadow of power grid generation It rings;By the way that by the data fusion of these two aspects, to exploitation, more application brings possibility.But when larger due to power grid, only The meteorological influence to entire power grid of analysis is not accurate enough, can not carry out selective analysis to the point for needing to pay close attention to existing for power grid.
With the arriving in smart grid epoch, grid company needs to make full use of power grid, especially has existed hidden danger The Public meteorology environmental data of power grid and its facility realizes the development and change for reflecting electric power facility hidden danger precisely, in time, with reply Manpower and power grid scale constantly expand between unmatched contradiction, more preferably monitor and process hidden danger.
Summary of the invention
The present invention is in order to accurate, the timely outside weather environmental change and difference for reflecting electric power facility security risk Influence of the meteorological condition to hidden danger it is horizontal, propose the power equipment method for prewarning risk and system of a kind of meter and meteorological disaster, May be implemented the possibility that electric power facility hidden danger under comprehensive analysis DIFFERENT METEOROLOGICAL CONDITIONS deteriorates with the presence or absence of development, and by system into Row hidden danger early warning publication, to effectively promote grid company to the regulatory level of security risk.
In order to solve the above technical problems, the technical solution of the present invention is as follows:
It is a kind of meter and meteorological disaster power equipment method for prewarning risk, which comprises the following steps:
S1: current weather disaster early-warning information is obtained;
S2: current electric grid security risk information is obtained;
S3: judge power grid security hidden danger region with the presence or absence of meteorological disaster early warning;
S4: judge the type and degree of the region early warning of power grid security hidden danger;
S5: publication security risk early warning.
Preferably, in the step S1 obtain current weather disaster early-warning information mode be meteorological system active push or It is acquired from public network, the meteorological disaster warning information includes the information that newly-increased disaster early-warning information, early warning are eliminated and pre- The information of alert variation.
Preferably, in the step S2, obtain current electric grid security risk information the step of are as follows:
S21: power worker's on-the-spot make an inspection tour, it may be found that power grid security hidden danger information be registered in safety production system;
S22: when thering is hidden danger to generate, eliminate or variation, the safety production system active push power grid security hidden danger Information;
S23: the safety production system identifies the security risk information for not wherein also being disposed or increasing newly, and will processing The security risk information filtering finished is fallen.
Preferably, in the step S3, judge that power grid security hidden danger region whether there is the side of meteorological disaster early warning Method is compared by the geographical location information to power grid security hidden danger and meteorological disaster alarm, to judge meteorological disaster early warning Whether region contains the position of hidden danger point, specific steps are as follows:
S31: the closed area that meteorological disaster early warning is covered is determined according to the meteorological disaster information that meteorological system pushes Longitude and latitude boundary;
S32: the station location marker in obtaining step S23 in each security risk information;
S33: longitude and latitude numerical value corresponding to above-mentioned each station location marker is obtained one by one by correlation inquiry;
S34: whether each longitude and latitude numerical value obtained in comparison step S33 one by one is comprised in determined by step S31 In longitude and latitude boundary.
Preferably, the method for type and degree that the region early warning of power grid security hidden danger is judged in the step S4 is pass Join analysis method, judgment criteria is obtained based on expertise and pertinent arts foundation, refinement;Specific steps are as follows:
S41: according to step S34's as a result, one by one judgement be included in determined by meteorological disaster early warning in longitude and latitude boundary Each power grid security hidden danger point and meteorological disaster early warning between, if there are interactional relationships, if there is related shadow Power grid security hidden danger point is then associated by loud relationship with meteorological disaster early warning;
S42: coming into force, cancel, degrade and rising for power grid security hidden danger early warning is determined according to the validity period of meteorological disaster early warning Grade judges the mode of processing according to the different type of meteorological disaster early warning information are as follows:
(1) meteorological disaster early warning comes into force, and judges that power grid security hidden danger associated with meteorological disaster early warning whether there is, and Show that there are power grid security hidden danger after if it is determined that, then power grid security hidden danger early warning validation message generates;
(2) when the grade of meteorological disaster early warning changes, power grid security hidden danger associated with meteorological disaster early warning Grade it can also happen that variation then needs to issue power grid peace if it is determined that associated power grid security hidden danger grade changes Full hidden danger early warning change message;
(3) meteorological disaster early warning is failed, then the associated previous meteorological disaster early warning to come into force and according to this gas As disaster alarm judge the early warning of power grid security hidden danger fail, need to issue power grid security hidden danger early warning thrashing message.
Preferably, the channel that early warning is issued in the step S5 is one of short message, mail and wechat mode or more Kind, specific steps are as follows:
S51: different according to used publication channel require assembling early warning information;The early warning information breath includes that power grid is pacified Full hidden danger early warning validation message, power grid security hidden danger early warning change message and power grid security hidden danger early warning thrashing message;
S52: relevant configuration information in reading system as needed is packaged above-mentioned early warning information;
S53: early warning information is sent by the channel of selection;
S54: the acknowledgement information that other side sends is received;
S55: early warning information and acknowledgement information are saved in memory.
It is a kind of meter and meteorological disaster power equipment Warning System, it is characterised in that: including data acquisition subsystem, Data analytics subsystem, early warning publication subsystem and memory;The data analytics subsystem respectively with the data acquisition System is connected with early warning publication subsystem, and the early warning publication subsystem is connected with the memory;The data acquisition Subsystem is for obtaining current weather disaster early-warning information and current electric grid security risk information;The data analytics subsystem is used With the presence or absence of meteorological disaster early warning and power grid security hidden danger location is judged in analytical judgment power grid security hidden danger region The type and degree of domain early warning;The early warning publication subsystem is for issuing security risk early warning information and receiving acknowledgement information. The memory is for storing early warning information and acknowledgement information.
Preferably, it is meteorological system active that the data acquisition subsystem, which obtains the mode of current weather disaster early-warning information, Push is acquired from public network, and the mode for obtaining current electric grid security risk information is safety production system active push.
Preferably, the data analytics subsystem is for analyzing power grid security hidden danger region with the presence or absence of meteorological disaster The method of early warning is used by the way that the power grid security hidden danger is compared with the geographical location information of the meteorological disaster early warning It is association analysis method in the type of analysis power grid security hidden danger region early warning and the method for degree, judgment criteria is to be based on Expertise and pertinent arts are established, refinement obtains.
Preferably, the early warning publication subsystem is short message, mail for issuing the channel of security risk early warning information With one of wechat mode or a variety of.
Compared to the prior art, the beneficial effect that the present invention generates is: the present invention is based on geographical location information to match skill Art, expertise pass through the position in the region of Public meteorology disaster alarm, type, severity and electric power facility security risk It sets, carry out location matches research between type and severity, association analysis etc. is realized to the accurate of electric power facility security risk With timely early warning, under the conditions of effectively can promoting special weather, the timeliness and specific aim of electric power facility security risk early warning are accomplished Accurately and timely early warning hidden danger, so as to improve the thinking and means of hidden danger processing.Specific advantage is as follows:
1) present invention research and development, apply it is a kind of meter and meteorological disaster power equipment Warning System, overcome defeated change The matched problem of coordinate position between electric equipment and special weather region, improves the timeliness of electric power facility security risk early warning And specific aim.
2) the invention proposes a kind of meter and the power equipment method for prewarning risk of meteorological disaster, identification location is solved The problem of the type of power transmission and transforming equipment security risk and degree in domain improves the thinking and hand of the processing of power equipment safety hidden danger Section.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings other Attached drawing, in which:
Fig. 1 is method flow schematic diagram of the invention;
Fig. 2 is system structure diagram of the invention;
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description.Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in invention, every other reality obtained by those of ordinary skill in the art without making creative efforts Example is applied, shall fall within the protection scope of the present invention.
Fig. 1 is the flow diagram of the power equipment method for prewarning risk of a kind of meter of the present invention and meteorological disaster, such as Fig. 1 institute Show, the described method comprises the following steps:
S1: current weather disaster early-warning information is obtained;
S2: current electric grid security risk information is obtained;
S3: judge power grid security hidden danger region with the presence or absence of meteorological disaster early warning;
S4: judge the type and degree of the region early warning of power grid security hidden danger;
S5: publication security risk early warning
In step sl, obtain current weather disaster early-warning information can by with weather bureau sign professional service side Formula is provided from weather bureau to this system, can also obtain the Public meteorology data that weather bureau externally issues, phase by internet Comparatively, signing the mode safety of Professional Services Agreement, data reliability is all more secure.The acquisition of weather warning information Mode is changing push usually by meteorological system active push, that is, meteorological when having disaster early-warning information to occur or change System will be pushed to this system.
In the present embodiment, by meteorological system obtain meteorological disaster warning information there are three types of:
(1) newly-increased disaster early-warning information, format are as follows: [cold yellow early warning of the city XX] meteorological observatory of city is when 26 days 17 complete Issue cold yellow early warning in city land, it is contemplated that 27 city the Wo lowest temperatures will drop to 10 DEG C hereinafter, signal may continue 3-4 days, Pay attention to keeping warm, place of temporarily going to a winter resort is open.
(2) information that early warning is eliminated, format are as follows: [city XX cancel Lightning Warning] thunderstorm cloud cluster has weakened, meteorological observatory of city in 55 divide in the whole city's cancellation Lightning Warning at 29 days 15.
(3) information of early warning variation, general format are as follows: [city XX cold orange warning is downgraded to yellow] meteorological observatory of city is in 20 10 divide whole city's cold orange warning being downgraded to yellow when days 10, indicate that temperature gos up, but the morning and evening lowest temperature still will be less than 10 DEG C, pay attention to warming.
After warning information obtains, different subsequent processings is carried out to it for above-mentioned three kinds of different types of warning information, For newly-increased disaster early-warning information, it is subsequent need to judge its region with the presence or absence of hidden danger, and judge final early warning etc. Grade;For the warning information of elimination, need to judge whether its corresponding meteorological disaster early warning has corresponded to electric power safety hidden danger early warning, If so, then the early warning of electric power safety hidden danger is also required to the message that publication is eliminated, do not need to handle if not;Become for early warning The information of change needs whether to have corresponded to security risk early warning according to its corresponding original early warning, and rejudge early warning grade, The variation of type.
In step s 2, the acquisition of power grid security hidden danger information is hair when carrying out on-the-spot make an inspection tour by work about electric power personnel After existing hidden danger, register hidden danger and report to realize.Generally Recognized as safe hidden danger information can be registered in safety production system, therefore Power grid security hidden danger information is that ought be had hidden danger to generate, eliminate by safety production system active push or be become in the present embodiment When change, the information is just pushed to this system.
The format of hidden danger information is general are as follows: XX power supply bureau, 110kVXX line N44-N45 tower, under line and line side are planted high bar and planted Object, 5 meters of headroom, quantity about 60, discovery time on January 7th, 2013, grade be it is general, hidden danger consequence is to may cause Pyatyi Event, it is temporarily untreated at present.
After getting security risk information, the processing that this system is done be identification state therein in processing, the tables such as newly-increased The information that bright hidden danger still remains, and the hidden danger being disposed is filtered out.Because only that the hidden danger currently still remained just needs The analysis of weather disaster early warning is carried out, the hidden danger handled, which indicates it no longer, influences the safe operation of power grid, therefore not Further analysis is needed to handle.
Step S3 is to judge occurring on the basis of obtaining meteorological disaster warning information and power grid security hidden danger information Region where the electrical network facilities of security risk, if there are weather warning disasters.Since power grid security hidden danger is mainly with hidden danger The form of point exists, and meteorological disaster warning information is issued in the form of region, therefore mainly by power grid security hidden danger It is compared with the geographical location information of meteorological disaster alarm, to judge whether meteorological disaster prewarning area contains hidden danger point Position and determine.
In weather monitoring field, a city is generally divided into several closed rectangular areas, and passes through weather monitoring system The meteorological disaster information obtained of uniting is as previously mentioned, contain this closed region of administrative region and meteorological system division. In order to accurate early warning, the present embodiment directly applies closed area to judge.The longitude and latitude contour description of closed area is as follows:
Region 1: longitude range (114.5833,114.5933) dimensional extent (25.54,25.55)
And the location information of hidden danger is then determined by the longitude and latitude of the electric power facility of its position occurred in electric system, than As home position is XX power supply bureau 110kV XX line N44-N45 tower in above-mentioned security risk information.At this point it is possible to correlation inquiry About the information Registration Module of the shaft tower in the information system of above-mentioned acquisition security risk, its longitude and latitude numerical value is obtained, is then sentenced Whether the longitude and latitude of the shaft tower of breaking is comprised within the scope of the longitude and latitude of meteorological disaster warning information.
It is to be noted that
(1) range of meteorological disaster early warning is often more much larger than the position of power grid security hidden danger, therefore in a meteorological calamity In evil early warning range, it is understood that there may be multiple security risk early warning need to judge one by one;
(2) hidden danger is influenced have range by meteorological disaster, such as within 1 kilometer of radius of circle or in line corridor;
(3) the impacted region of hidden danger is incessantly on point, but within the scope of one, it is therefore desirable to introduce line corridor half Diameter judges that line corridor radius refers to the direction along route, the region in the much radius in two sides is also affected area Domain.
The association analysis of step S4 refer to when analyze hidden danger and meteorology disaster alarm position and then judge this two Between the information of seed type, if there are interactional relationship, influence is positive or negative.Such as transmission line of electricity The dense fog of contamination hidden danger and weather, sandstorm and haze early warning are negative impact relationships, i.e., dense fog, sandstorm and haze can promote to accumulate It is dirty to develop more seriously, more quickly.The relationship judgment criteria of the two is based on expertise and pertinent arts are established, refined Obtain, simple correlation model can be described as: when there are haze early warning, transmission line of electricity contamination class security risk can in the presence of what is deteriorated Can, wherein the haze early warning of II grades (namely red scale) or more generates II to contamination class security risk more than general type Grade early warning.
When incidence relation judges, it is also necessary to determine the coming into force of early warning according to the validity period of meteorological disaster early warning, cancel, degrade With upgrading etc., according to the several types of meteorological disaster warning information, it is following several to judge that the mode of processing has:
(1) meteorological disaster early warning comes into force, and judges that power grid security hidden danger associated with meteorological disaster early warning whether there is, and Show that there are power grid security hidden danger after if it is determined that, then power grid security hidden danger early warning validation message generates;
(2) when the grade of meteorological disaster early warning changes, power grid security hidden danger associated with meteorological disaster early warning Grade it can also happen that variation then needs to issue power grid peace if it is determined that associated power grid security hidden danger grade changes Full hidden danger early warning change message;
(3) meteorological disaster early warning is failed, then the associated previous meteorological disaster early warning to come into force and according to this gas As disaster alarm judge the early warning of power grid security hidden danger fail, need to issue power grid security hidden danger early warning thrashing message.
The complexity of judgment criteria between hidden danger and meteorological disaster is between hidden danger and meteorological disaster it is not one-to-one Relationship, but the complex relationship coexisted of mutually promoting and prevent of multi-to-multi.Such as when there are haze early warning, in addition to paying close attention to it Except influence to contamination class hidden danger, also to judge whether early warning and duration that arid or heavy rain has occurred, because What is played the role of for arid is to aggravate hidden danger, and heavy rain is then just opposite.According to expertise in the present invention, and it is total Historical data is tied, arrangement obtains all kinds of meteorological disaster early warning and its severity and power grid security hidden danger type and its severity Between incidence relation standard conclude to update and sentence as the foundation of judgement, and according to the service conditions actually occurred being recorded Disconnected standard.
Step S5 is the publication for completing the early warning of electric power facility security risk.The effect of early warning publication is to keep predetermined user logical Different channel receptions are crossed to modes such as early warning informations, such as short message, mail and wechat.Early warning information is generated in previous step On the basis of, by means of different channels, early warning information is assembled into the storage of the forms such as short message, Email to database In, the assembling of early warning information needs to meet the requirement of two aspects: first is that meet the limitation of different types of message format, such as Every 70 Chinese characters of short message are a message, then require to split message more than 70;Second is that will be according to preset message format group Dress, for example starting unified format in short message is " [early warning platform] ".
After early warning information assembles, it is also necessary to the recipient information of the message, mail that are configured in reading system, such as hand Machine number or mail address.Using system and SMS platform, the interface of mailing system, send messages to recipient and by pair Method, system obtains message and sends receipt.Promoter's feedback that the result of pre-alert notification is also stored into database to issue to early warning The result of notice.
In conclusion by five basic steps, complete the security risk early warning for considering weather warning factor judgement, Identification and publication.
Fig. 2 is the structural schematic diagram of the power equipment Warning System of a kind of meter of the present invention and meteorological disaster.Such as Fig. 2 It is shown, the system comprises: data acquisition subsystem, data analytics subsystem, early warning publication subsystem and memory;The number It is connect respectively with the data acquisition subsystem and early warning publication subsystem according to analyzing subsystem, subsystem is issued in the early warning System is connected with the memory;The data acquisition subsystem is for obtaining current weather disaster early-warning information and current electric grid peace Full hidden danger information;The data analytics subsystem is for analyzing and determining power grid security hidden danger region with the presence or absence of meteorological disaster Early warning and the type and degree for judging the region early warning of power grid security hidden danger;The early warning publication subsystem is for issuing peace Full hidden danger early warning information and reception early warning information send acknowledgement information;The memory is for storing early warning information and receipt letter Breath.
Data acquisition subsystem obtain the type of current weather disaster early-warning information include newly-increased disaster early-warning information, it is pre- The information etc. of the alert information eliminated and early warning variation, acquisition modes are meteorological system active push or are acquired from public network, one As take by the mode of meteorological system active push, and be changing push, that is, there is disaster early-warning information to occur or when variation, gas As system will active push to this system, this ensures that the timeliness of information, accuracy, safety and reliability.And When the mode for obtaining current electric grid security risk information is by work about electric power personnel progress on-the-spot make an inspection tour, after scenting a hidden danger, Hidden danger and report are registered come what is realized, Generally Recognized as safe hidden danger information can be registered in safety production system in time, therefore this implementation In example by safety production system active push, i.e., when having hidden danger to generate, eliminate or variation, i.e., power grid security hidden danger information is Active push is to this system.
Data analytics subsystem, which is used to analyze power grid security hidden danger region, whether there is the method for meteorological disaster early warning It is to be compared by the geographical location information to power grid security hidden danger and meteorological disaster alarm, for analyzing power grid security hidden danger The type of region early warning and the method for degree are association analysis method, and judgment criteria is based on expertise and related fields Knowledge is established, refinement obtains.
Early warning publication subsystem is in short message, mail and wechat mode for issuing the channel of security risk early warning information It is one or more.After early warning information assembles, it is also necessary to recipient's letter of the message, mail that are configured in reading system Breath, such as phone number or mail address.Using the interface of system and SMS platform, mailing system, reception is sent messages to Person simultaneously sends acknowledgement information by obtaining message to method, system.The result of pre-alert notification be also stored into the database of memory with The result for the promoter's feedback notification issued to early warning.
The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although with reference to the foregoing embodiments Invention is explained in detail, those skilled in the art should understand that: it still can be to aforementioned each implementation Technical solution documented by example is modified or equivalent replacement of some of the technical features;And these modification or Replacement, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution.

Claims (4)

1. the power equipment method for prewarning risk of a kind of meter and meteorological disaster, which comprises the following steps:
S1: current weather disaster early-warning information is obtained;
S2: obtaining current electric grid security risk information, the specific steps are that:
S21: power worker's on-the-spot make an inspection tour, it may be found that power grid security hidden danger information be registered in the safety production system of our unit;
S22: when thering is hidden danger to generate, eliminate or variation, the safety production system active push power grid security hidden danger information;
S23: the security risk information that identification is not wherein also disposed or increases newly, and the hidden danger information filtering that will be disposed Fall;
S3: judging that power grid security hidden danger region whether there is meteorological disaster early warning, the specific steps are that:
S31: the longitude and latitude boundary for the closed area that it is covered is determined according to the meteorological disaster information that meteorological system pushes;
S32: the station location marker in obtaining step S23 in each security risk information;
S33: longitude and latitude numerical value corresponding to above-mentioned each station location marker is obtained one by one by correlation inquiry;
S34: whether each longitude and latitude numerical value obtained in comparison step S33 one by one is comprised in longitude and latitude determined by step S31 It spends in boundary;
S4: judge the type and degree of the region early warning of power grid security hidden danger;
S5: publication security risk early warning.
2. the power equipment method for prewarning risk of a kind of meter according to claim 1 and meteorological disaster, it is characterised in that: institute It states and obtains the mode of current weather disaster early-warning information in step S1 as meteorological system active push or be acquired from public network, institute State the information that meteorological disaster warning information includes newly-increased disaster early-warning information, the information that early warning is eliminated and early warning variation.
3. the power equipment method for prewarning risk of a kind of meter according to claim 1 and meteorological disaster, it is characterised in that: institute It states and judges the type of power grid security hidden danger region early warning in step S4 and the standard of degree is based on expertise and correlation Domain knowledge is established, refinement obtains.
4. the power equipment method for prewarning risk of a kind of meter according to claim 1 and meteorological disaster, it is characterised in that: institute Stating the channel that early warning in step S5 is issued is one of short message, mail and wechat mode or a variety of, the specific steps are that:
S51: different according to used publication channel require assembling warning information;
S52: relevant configuration information in reading system as needed is packaged above-mentioned warning information;
S53: warning information is sent by the channel of selection;
S54: the acknowledgement information that other side sends is received;
S55: warning information and acknowledgement information are saved in memory.
CN201610596732.0A 2016-07-27 2016-07-27 It is a kind of meter and meteorological disaster power equipment method for prewarning risk Active CN106097661B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610596732.0A CN106097661B (en) 2016-07-27 2016-07-27 It is a kind of meter and meteorological disaster power equipment method for prewarning risk

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610596732.0A CN106097661B (en) 2016-07-27 2016-07-27 It is a kind of meter and meteorological disaster power equipment method for prewarning risk

Publications (2)

Publication Number Publication Date
CN106097661A CN106097661A (en) 2016-11-09
CN106097661B true CN106097661B (en) 2019-02-01

Family

ID=57449487

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610596732.0A Active CN106097661B (en) 2016-07-27 2016-07-27 It is a kind of meter and meteorological disaster power equipment method for prewarning risk

Country Status (1)

Country Link
CN (1) CN106097661B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107248251A (en) * 2017-07-06 2017-10-13 国家电网公司 A kind of anti-mountain fire external force destruction management-control method of transmission line of electricity
CN107464058A (en) * 2017-08-07 2017-12-12 平顶山学院 A kind of engineering management geographic information check system
CN109446289B (en) * 2018-10-18 2020-07-10 国网山东省电力公司应急管理中心 Electric wire netting GIS meticulous early warning system based on environmental risk
CN112330061A (en) * 2020-11-25 2021-02-05 广东省气象公共安全技术支持中心 Service object-oriented differential meteorological disaster risk early warning system
CN115223336A (en) * 2022-06-23 2022-10-21 中核核信信息技术(北京)有限公司 Disaster early warning analysis system and method based on location service

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103679296A (en) * 2013-12-24 2014-03-26 云南电力调度控制中心 Grid security risk assessment method and model based on situation awareness
CN204089886U (en) * 2014-09-24 2015-01-07 国网山东省电力公司泰安供电公司 Based on the electrical network dynamic monitoring early warning system of weather information
CN104484348A (en) * 2014-11-27 2015-04-01 国家电网公司 Data display method and device
CN104680260B (en) * 2015-03-17 2018-08-28 云南电力调度控制中心 A kind of power grid visualization sensor model construction method and system
CN105448154A (en) * 2015-09-21 2016-03-30 中国南方电网有限责任公司 Integrated-platform-based substation operation training cabin

Also Published As

Publication number Publication date
CN106097661A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
CN106097661B (en) It is a kind of meter and meteorological disaster power equipment method for prewarning risk
JP4511560B2 (en) Method and system for automated location-dependent recognition of flood risk
CN103477606B (en) Systems for Detecting, Collecting, Communicating, and Using Information About Environmental Conditions and Occurrences
CN105069558A (en) Warning and analyzing method for power facility damage based on meteorological data
CN107391697A (en) Customizable synoptic analysis system, method and computer-readable medium
Rogers et al. Implementing hazard early warning systems
CN113344735B (en) Disaster prevention and reduction monitoring and early warning system of power grid equipment
Jacob et al. Indicators and monitoring
CN103150598A (en) Processing system and method for sudden failure of power transmission network
KR101722989B1 (en) Apparatus and method for managing disaster using floating population of base station
Tang et al. The Shanghai multi-hazard early warning system: addressing the challenge of disaster risk reduction in an urban megalopolis
CN205941952U (en) Weather information early warning system
KR102143039B1 (en) Remote monitoring and control apparatus for the type of multi-path
CN211264434U (en) Geographic information dynamic early warning deployment and control system
CN116911597A (en) Automatic monitoring and early warning system for meteorological disasters of power distribution network
CN115798177A (en) Multi-source data dynamic threshold proximity alarm method and system
CN104992520A (en) Wide-area forest fire remote sensing monitoring information intelligent service platform
Zogou et al. Analysis of Data From Ambient PM10 Concentration Monitoring in Volos in the Period 2005-2010
JP5365444B2 (en) Information management apparatus, information management method, and information management program
US20220207986A1 (en) Monitoring system
KR102152409B1 (en) Grouwth Process Record Integrated Management System
CN111968348B (en) Rare waterfowl real-time monitoring and early warning information management method, device and system
Navarra et al. A global perspective on cadastres and Geo-ICT for sustainable urban governance in view of climate change
KR102454028B1 (en) Intelligent integrated national disaster safety management system and processing method thereof
CN104992521A (en) Intelligent forest fire remote sensing monitoring information service method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant