CN106093563A - A kind of substation secondary side power measuring system and measuring method thereof - Google Patents

A kind of substation secondary side power measuring system and measuring method thereof Download PDF

Info

Publication number
CN106093563A
CN106093563A CN201610370582.1A CN201610370582A CN106093563A CN 106093563 A CN106093563 A CN 106093563A CN 201610370582 A CN201610370582 A CN 201610370582A CN 106093563 A CN106093563 A CN 106093563A
Authority
CN
China
Prior art keywords
clock synchronization
electric energy
wireless communication
communication module
synchronization module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610370582.1A
Other languages
Chinese (zh)
Inventor
王文庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongguan Lianzhou Intellectual Property Operation and Management Co Ltd
Original Assignee
Dongguan Lianzhou Intellectual Property Operation and Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Lianzhou Intellectual Property Operation and Management Co Ltd filed Critical Dongguan Lianzhou Intellectual Property Operation and Management Co Ltd
Priority to CN201610370582.1A priority Critical patent/CN106093563A/en
Publication of CN106093563A publication Critical patent/CN106093563A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R22/00Arrangements for measuring time integral of electric power or current, e.g. electricity meters
    • G01R22/06Arrangements for measuring time integral of electric power or current, e.g. electricity meters by electronic methods
    • G01R22/10Arrangements for measuring time integral of electric power or current, e.g. electricity meters by electronic methods using digital techniques
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R22/00Arrangements for measuring time integral of electric power or current, e.g. electricity meters
    • G01R22/06Arrangements for measuring time integral of electric power or current, e.g. electricity meters by electronic methods
    • G01R22/061Details of electronic electricity meters
    • G01R22/063Details of electronic electricity meters related to remote communication
    • GPHYSICS
    • G08SIGNALLING
    • G08CTRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
    • G08C17/00Arrangements for transmitting signals characterised by the use of a wireless electrical link
    • G08C17/02Arrangements for transmitting signals characterised by the use of a wireless electrical link using a radio link
    • GPHYSICS
    • G08SIGNALLING
    • G08CTRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
    • G08C23/00Non-electrical signal transmission systems, e.g. optical systems
    • G08C23/06Non-electrical signal transmission systems, e.g. optical systems through light guides, e.g. optical fibres

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a kind of substation secondary side power measuring system, including: voltage transformer, current transformer, the first optical transmitter, the second optical transmitter, the first optical receiver, the second optical receiver, combining unit, optical Ethernet switch, electric energy meter, calculating control centre, clock synchronization module, wireless communication module etc..It is remote that the present invention solves Intelligent substation merging unit distance, the unsafe problem of Site Detection, it is possible to achieve the combining unit of strange land distribution and the synchronization electric energy measurement of the electric energy meter of branch road, measures numerical value accurate, can keep synchronizing, improve accuracy and the reliability of the electric energy metrical of transformer station.This device has conveniently, succinct, efficiently and the feature such as safety.

Description

A kind of substation secondary side power measuring system and measuring method thereof
Technical field:
The invention belongs to Electric Energy Metering Technology field, be specifically related to a kind of substation secondary side power measuring system and Measuring method.
Background technology:
In recent years, along with intelligent substation Switching, photoelectric current transformer, once operation equipment on-line state-detection, change Training on operation emulation technology is run in power station, the network one-tenth increasingly developing the technology such as application in real-time system told by computer Ripe, for transformer station information gathering, transmit and measure, measure, the aspect such as protection realize digitized processing provide theory and Material base.The development of photoelectricity, microelectronics, computer and communication technology makes the various intelligent apparatus in transformer station possess number The features such as word, intellectuality and low-power consumption.The equipment that combining unit is accompanied by intelligent substation rise and occurs, current intelligence Can transformer substation system build mainly include several parts such as key-course, process layer, wall, process layer be responsible for transmit analog quantity, The signal such as switching value, tripping operation, and combining unit is one of nucleus equipment of transformer station process layer, respectively with electronic type mutual inductance The secondary side data-interface of device connects, and the data port of protection measuring and controlling equipment connects, in order to realize transformer station's electric current and electricity The synchronous acquisition of the analog quantitys such as pressure and merging treatment.
Electric energy meter metering to having put into operation carries out in-site measurement, typically uses On-line Measuring Method, i.e. substation secondary side Loop combining unit measurement and branch road electric energy meter metering.But owing to electric current merges circuit units, voltage merging loop It is distributed that unit and electric energy meter are generally strange land, surveys carrying out substation secondary side electric energy on-line metering by loop combining unit When amount and electric energy meter measure, it is consistent that the moment of measurement, period and duration are unable to reach more accurate synchronization, often produces one Fixed error in dipping, lacks metering secondary is entered the quality of power supply of line to analyze in real time and comparison, for when peak of power consumption simultaneously The electric energy metrical of the special periods such as section, the metering numerical value causing the secondary side electric energy of transformer station and electric energy meter is not accurate enough so that The result that final school is surveyed is not satisfactory, causes the accuracy of the electric energy metrical of transformer station and reliability to reduce.
Summary of the invention:
To this end, the technical problem to be solved is in prior art the secondary side electric energy measurement for transformer station System meters numerical value is inaccurate, it is impossible to keeping synchronizing, the accuracy and the reliability that ultimately result in the electric energy metrical of transformer station are low, from And a kind of substation secondary side power measuring system and measuring method thereof are proposed.
For reaching above-mentioned purpose, technical scheme is as follows:
A kind of substation secondary side power measuring system, including:
Voltage transformer, described voltage transformer connects the first optical transmitter.
Current transformer, described current transformer connects the second optical transmitter.
Combining unit, described combining unit is connected to the first optical receiver and the second optical receiver, described first light Receptor and described first optical transmitter communication connection, described second optical receiver and described second optical transmitter communication connection.
Optical Ethernet switch, the first end of described optical Ethernet switch is connected with described combining unit.
Electric energy meter, described electric energy meter is connected with the second end of described optical Ethernet switch.
Calculating control centre, described calculating control centre is connected with described optical Ethernet switch.
Clock synchronization module, described clock synchronization module include the first clock synchronization module, second clock synchronization module, Three clock synchronization modules, described first clock synchronization module is connected with described combining unit, described second clock synchronization module with Described electric energy meter connects, and described 3rd clock synchronization module is connected with described calculating control centre.
Preferred as technique scheme, also includes:
Wireless communication module, described wireless communication module include the first wireless communication module, the second wireless communication module, Three wireless communication modules, described first wireless communication module is connected with described combining unit, described second wireless communication module with Described electric energy meter connects, and described 3rd wireless communication module is connected with described calculating control centre.
Preferred as technique scheme, described first wireless communication module, described second wireless communication module, described 3rd wireless communication module is WIFI communication module.
Preferred as technique scheme, described electric energy meter is digitalized electrical energy meter.
Preferred as technique scheme, described optical Ethernet switch and described combining unit, described electric energy meter, institute State calculating control centre and use fiber optic communication mode.
Preferred as technique scheme, described first clock synchronization module, described second clock synchronization module, described 3rd clock synchronization module is gps clock synchronization module, is provided with pulse per second (PPS) device and B in described gps clock synchronization module Code advertiser.
A kind of substation secondary side electric energy measurement method, comprises the steps:
S1: select the combining unit that substation secondary side is tested, make outfan correspondence access by optical Ethernet switch The voltage circuit of electric energy meter and current loop.
S2: be combined list respectively by the first clock synchronization module, second clock synchronization module, the 3rd clock synchronization module Unit, electric energy meter, calculating control centre carry out time synchronized.
S3: voltage transformer measures acquisition the first voltage measuring value, and is sent to merge by the first optical transmitter Unit, current transformer measures acquisition the first current measurement value, and is sent to combining unit by the second optical transmitter, closes And the first voltage measuring value and the first current measurement value are sent to calculate control centre by unit by the first wireless communication module.
Electric energy meter obtains electrical energy pulse measured value, and is sent to calculate control centre by the second wireless communication module.
S4: calculate control centre by the 3rd wireless communication module receive the first voltage measuring value, the first current measurement value, Electrical energy pulse measured value, and carry out total score analysis and calculating, obtain measurement result.
S5: complete to measure.
The beneficial effects of the present invention is: it is remote that the present invention solves Intelligent substation merging unit distance, and Site Detection is not The problem of safety, it is possible to achieve the combining unit of strange land distribution and the synchronization electric energy measurement of the electric energy meter of branch road, measures numerical value Accurately, it is possible to keep synchronizing, improve accuracy and the reliability of the electric energy metrical of transformer station.This device has conveniently, succinct, Efficiently and the feature such as safety.
Accompanying drawing illustrates:
The following drawings is only intended to, in schematically illustrating the present invention and explaining, not delimit the scope of the invention.Wherein:
Fig. 1 is the substation secondary side power measuring system structural representation of one embodiment of the invention;
Fig. 2 is the substation secondary side electric energy measurement method flow diagram of one embodiment of the invention.
Symbol description in figure:
1-voltage transformer, 2-the first optical transmitter, 3-current transformer, 4-the second optical transmitter, 5-combining unit, 6- First optical receiver, 7-the second optical receiver, 8-optical Ethernet switch, 9-electric energy meter, 10-calculates control centre, 11-clock Synchronization module, 12-wireless communication module, 1101-the first clock synchronization module, 1102-second clock synchronization module, 1103- Three clock synchronization modules, 1201-the first wireless communication module, 1202-the second wireless communication module, 1203-the 3rd radio communication Module.
Detailed description of the invention:
Embodiment 1
As it is shown in figure 1, the substation secondary side power measuring system of the present invention, including:
Voltage transformer 1, described voltage transformer 1 connects the first optical transmitter 2.
Current transformer 3, described current transformer 3 connects the second optical transmitter 4.
Combining unit 5, described combining unit 5 is connected to the first optical receiver 6 and the second optical receiver 7, and described One optical receiver 6 communicates to connect with described first optical transmitter 2, and described second optical receiver 7 leads to described second optical transmitter 4 Letter connects.
Optical Ethernet switch 8, the first end of described optical Ethernet switch 8 is connected with described combining unit 5.This enforcement In example, described optical Ethernet switch 8 uses light with described combining unit 5, described electric energy meter 9, described calculating control centre 10 Fiber communication mode.
Electric energy meter 9, described electric energy meter 9 is connected with the second end of described optical Ethernet switch 8.In the present embodiment, described Electric energy meter 9 is digitalized electrical energy meter.
Calculating control centre 10, described calculating control centre 10 is connected with described optical Ethernet switch 8.
Clock synchronization module 11, described clock synchronization module 11 includes that the first clock synchronization module 1101, second clock are same Step module the 1102, the 3rd clock synchronization module 1103, described first clock synchronization module 1101 is connected with described combining unit 5, Described second clock synchronization module 1102 is connected with described electric energy meter 9, described 3rd clock synchronization module 1103 and described calculating Control centre 10 connects.In the present embodiment, described first clock synchronization module 1101, described second clock synchronization module 1102, Described 3rd clock synchronization module 1103 is gps clock synchronization module, is provided with pulse per second (PPS) in described gps clock synchronization module Device and B code advertiser.
Wireless communication module 12, described wireless communication module 12 includes first wireless communication module the 1201, second channel radio Letter module the 1202, the 3rd wireless communication module 1203, described first wireless communication module 1201 is connected with described combining unit 5, Described second wireless communication module 1202 is connected with described electric energy meter 9, described 3rd wireless communication module 1203 and described calculating Control centre 10 connects.Described first wireless communication module 1201, described second wireless communication module 1202, described 3rd wireless Communication module 1203 is WIFI communication module.
Substation secondary side power measuring system described in the present embodiment, including: voltage transformer, current transformer, The exchange of one optical transmitter, the second optical transmitter, the first optical receiver, the second optical receiver, combining unit, optical Ethernet is mechanical, electrical Can table, calculating control centre, clock synchronization module, wireless communication module etc..The present invention solves Intelligent substation merging unit Distance is remote, the unsafe problem of Site Detection, it is possible to achieve the combining unit of strange land distribution and the synchronization of the electric energy meter of branch road Electric energy measurement, measures numerical value accurate, it is possible to keeps synchronizing, improves accuracy and the reliability of the electric energy metrical of transformer station.This Device has conveniently, succinct, efficiently and the feature such as safety.
Embodiment 2
As in figure 2 it is shown, the substation secondary side electric energy measurement method of the present invention, comprise the steps:
S1: select the combining unit 5 that substation secondary side is tested, make outfan correspondence connect by optical Ethernet switch 8 Enter voltage circuit and the current loop of electric energy meter 9.
S2: by the first clock synchronization module 1101, second clock synchronization module the 1102, the 3rd clock synchronization module 1103 Be combined respectively unit 5, electric energy meter 9, calculate control centre 10 carry out time synchronized.
S3: voltage transformer 1 measures acquisition the first voltage measuring value, and is sent to close by the first optical transmitter 2 And unit 5, current transformer 3 measures acquisition the first current measurement value, and is sent to merge list by the second optical transmitter 4 Unit 5, the first voltage measuring value and the first current measurement value are sent to meter by the first wireless communication module 1201 by combining unit 5 Calculate control centre 10.
Electric energy meter 9 obtains electrical energy pulse measured value, and is sent to calculate in control by the second wireless communication module 1202 The heart 10.
S4: calculate control centre 10 and receive the first voltage measuring value, the first electric current by the 3rd wireless communication module 1203 Measured value, electrical energy pulse measured value, and carry out total score analysis and calculating, obtain measurement result.
S5: complete to measure.
Obviously, above-described embodiment is only for clearly demonstrating example, and not restriction to embodiment.Right For those of ordinary skill in the field, can also make on the basis of the above description other multi-form change or Variation.Here without also cannot all of embodiment be given exhaustive.And the obvious change thus extended out or Change among still in the protection domain of the invention.

Claims (7)

1. a substation secondary side power measuring system, it is characterised in that including:
Voltage transformer (1), described voltage transformer (1) connects the first optical transmitter (2);
Current transformer (3), described current transformer (3) connects the second optical transmitter (4);
Combining unit (5), described combining unit (5) is connected to the first optical receiver (6) and the second optical receiver (7), institute State the first optical receiver (6) to communicate to connect with described first optical transmitter (2), described second optical receiver (7) and described second Optical transmitter (4) communicates to connect;
Optical Ethernet switch (8), the first end of described optical Ethernet switch (8) is connected with described combining unit (5);
Electric energy meter (9), described electric energy meter (9) is connected with the second end of described optical Ethernet switch (8);
Calculating control centre (10), described calculating control centre (10) is connected with described optical Ethernet switch (8);
Clock synchronization module (11), described clock synchronization module (11) includes the first clock synchronization module (1101), second clock Synchronization module (1102), the 3rd clock synchronization module (1103), described first clock synchronization module (1101) merges list with described Unit (5) connects, and described second clock synchronization module (1102) is connected with described electric energy meter (9), described 3rd clock synchronization module (1103) it is connected with described calculating control centre (10).
Substation secondary side the most according to claim 1 power measuring system, it is characterised in that also include:
Wireless communication module (12), described wireless communication module (12) includes the first wireless communication module (1201), second wireless Communication module (1202), the 3rd wireless communication module (1203), described first wireless communication module (1201) merges list with described Unit (5) connects, and described second wireless communication module (1202) is connected with described electric energy meter (9), described 3rd wireless communication module (1203) it is connected with described calculating control centre (10).
Substation secondary side the most according to claim 2 power measuring system, it is characterised in that:
Described first wireless communication module (1201), described second wireless communication module (1202), described 3rd radio communication mold Block (1203) is WIFI communication module.
Substation secondary side the most according to claim 3 power measuring system, it is characterised in that:
Described electric energy meter (9) is digitalized electrical energy meter.
Substation secondary side the most according to claim 4 power measuring system, it is characterised in that:
Described optical Ethernet switch (8) and described combining unit (5), described electric energy meter (9), described calculating control centre (10) Use fiber optic communication mode.
Substation secondary side the most according to claim 5 power measuring system, it is characterised in that:
Described first clock synchronization module (1101), described second clock synchronization module (1102), described 3rd clock synchronize mould Block (1103) is gps clock synchronization module, is provided with pulse per second (PPS) device and B code signal dress in described gps clock synchronization module Put.
7. a substation secondary side electric energy measurement method, it is characterised in that comprise the steps:
S1: select the combining unit (5) that substation secondary side is tested, make outfan correspondence connect by optical Ethernet switch (8) Enter voltage circuit and the current loop of electric energy meter (9);
S2: by the first clock synchronization module (1101), second clock synchronization module (1102), the 3rd clock synchronization module (1103) be combined respectively unit (5), electric energy meter (9), calculate control centre (10) carry out time synchronized;
S3: voltage transformer (1) measures acquisition the first voltage measuring value, and is sent to close by the first optical transmitter (2) And unit (5), current transformer (3) is measured acquisition the first current measurement value, and is sent to by the second optical transmitter (4) Combining unit (5), the first voltage measuring value and the first current measurement value are passed through the first wireless communication module by combining unit (5) (1201) it is sent to calculate control centre (10);
Electric energy meter (9) obtains electrical energy pulse measured value, and is sent to calculate in control by the second wireless communication module (1202) The heart (10);
S4: calculate control centre (10) and receive the first voltage measuring value, the first electric current by the 3rd wireless communication module (1203) Measured value, electrical energy pulse measured value, and carry out total score analysis and calculating, obtain measurement result;
S5: complete to measure.
CN201610370582.1A 2016-05-27 2016-05-27 A kind of substation secondary side power measuring system and measuring method thereof Pending CN106093563A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610370582.1A CN106093563A (en) 2016-05-27 2016-05-27 A kind of substation secondary side power measuring system and measuring method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610370582.1A CN106093563A (en) 2016-05-27 2016-05-27 A kind of substation secondary side power measuring system and measuring method thereof

Publications (1)

Publication Number Publication Date
CN106093563A true CN106093563A (en) 2016-11-09

Family

ID=57229498

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610370582.1A Pending CN106093563A (en) 2016-05-27 2016-05-27 A kind of substation secondary side power measuring system and measuring method thereof

Country Status (1)

Country Link
CN (1) CN106093563A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110940854A (en) * 2019-11-14 2020-03-31 国网江西省电力有限公司电力科学研究院 Alternating current synchronous electric energy metering system based on Beidou/GPS clock
CN111090003A (en) * 2019-11-14 2020-05-01 国网江西省电力有限公司电力科学研究院 Synchronous direct current electric energy metering system based on Beidou/GPS clock

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102305922A (en) * 2011-05-25 2012-01-04 湖南省电力公司科学研究院 On-load detection method and device for intelligent optical fiber electric energy meter in substation
CN102809741A (en) * 2012-08-14 2012-12-05 河南弘正电气科技有限公司 Intelligent monitoring and managing information system for electric energy metering devices of substations
CN103472433A (en) * 2013-09-12 2013-12-25 国家电网公司 Intelligent substation electric energy measuring secondary system virtual load error detection device and method
CN203433104U (en) * 2013-09-12 2014-02-12 国家电网公司 Real load error detector for secondary electric-energy metering loop of intelligent transformer station
CN103630868A (en) * 2013-09-23 2014-03-12 中国电子科技集团公司第二十七研究所 Remote substation electrical energy metering information detection system
CN203811795U (en) * 2013-09-23 2014-09-03 中国电子科技集团公司第二十七研究所 Remote detection system for electric energy metering information of transformer station
CN204065388U (en) * 2014-03-28 2014-12-31 云南电力试验研究院(集团)有限公司电力研究院 A kind of Secondary Circuit of Potential Transformer pressure drop wireless detection device
CN105467352A (en) * 2015-07-13 2016-04-06 国家电网公司 Intelligent substation secondary side electric energy metering system detection method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102305922A (en) * 2011-05-25 2012-01-04 湖南省电力公司科学研究院 On-load detection method and device for intelligent optical fiber electric energy meter in substation
CN102809741A (en) * 2012-08-14 2012-12-05 河南弘正电气科技有限公司 Intelligent monitoring and managing information system for electric energy metering devices of substations
CN103472433A (en) * 2013-09-12 2013-12-25 国家电网公司 Intelligent substation electric energy measuring secondary system virtual load error detection device and method
CN203433104U (en) * 2013-09-12 2014-02-12 国家电网公司 Real load error detector for secondary electric-energy metering loop of intelligent transformer station
CN103630868A (en) * 2013-09-23 2014-03-12 中国电子科技集团公司第二十七研究所 Remote substation electrical energy metering information detection system
CN203811795U (en) * 2013-09-23 2014-09-03 中国电子科技集团公司第二十七研究所 Remote detection system for electric energy metering information of transformer station
CN204065388U (en) * 2014-03-28 2014-12-31 云南电力试验研究院(集团)有限公司电力研究院 A kind of Secondary Circuit of Potential Transformer pressure drop wireless detection device
CN105467352A (en) * 2015-07-13 2016-04-06 国家电网公司 Intelligent substation secondary side electric energy metering system detection method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110940854A (en) * 2019-11-14 2020-03-31 国网江西省电力有限公司电力科学研究院 Alternating current synchronous electric energy metering system based on Beidou/GPS clock
CN111090003A (en) * 2019-11-14 2020-05-01 国网江西省电力有限公司电力科学研究院 Synchronous direct current electric energy metering system based on Beidou/GPS clock

Similar Documents

Publication Publication Date Title
CN202720296U (en) Platform for detecting function and performance of power distribution automatic terminal apparatus
CN103278791A (en) Electronic transformer amplitude and phase error checking system with networked detection function
CN206559654U (en) A kind of transformer station management system positioned based on UWB
CN102590619B (en) Method for detecting time synchronization capacity of real-time measurement equipment based on timing variable
CN102819004A (en) Comprehensive detecting and analyzing platform for performance of digital electric energy metering systems of intelligent transformer substations
CN103389441A (en) Fault detection and positioning system for power line
CN106597419B (en) The underground coal mine accurate positioning method synchronous without clock
CN105021891B (en) Power distribution network base station type phase checking device
CN106199201A (en) Urban track traffic rail ground transition resistance test system and method
CN107942167A (en) Intelligent substation synchronous phasor measuring device boss, which stands, tests system and method
CN108732527A (en) Quality of transformer performance on-line monitoring system based on wide area synchro measure
CN206524912U (en) Recreation ground high precision wireless alignment system
CN108896953A (en) Multi-compartment digital metering test macro based on wireless synchronization
CN106658712B (en) Communication terminal positioning method and system
CN106093563A (en) A kind of substation secondary side power measuring system and measuring method thereof
CN103698742B (en) A kind of underground location method based on signal relative field strength
CN204256149U (en) A kind of Performance Test System of merge cells tester
CN116381599A (en) Device and method for realizing portable programmable high-precision positioning by using UWB technology
CN105548947B (en) A kind of synchronous source tracing method of digitalized electrical energy meter and system
CN103809154A (en) Moving target locating method based on relative signal strength for mine
CN207799002U (en) A kind of non-contact travelling wave ranging system of distribution
CN106199489A (en) Laboratory reproduction type digitalized electric energy measuring equipment remote calibration system and method
CN104392603A (en) Intelligent diagnosis system of on-site power consumption information acquisition device
CN105842649A (en) On-line detection system for secondary side power metering system of smart substation and detection method thereof
CN204679570U (en) Secondary equipment of intelligent converting station Commissioning Analysis platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109

RJ01 Rejection of invention patent application after publication