CN106087745B - A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method - Google Patents

A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method Download PDF

Info

Publication number
CN106087745B
CN106087745B CN201610301377.XA CN201610301377A CN106087745B CN 106087745 B CN106087745 B CN 106087745B CN 201610301377 A CN201610301377 A CN 201610301377A CN 106087745 B CN106087745 B CN 106087745B
Authority
CN
China
Prior art keywords
construction
concrete
crossbeam
girder
fulcrum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610301377.XA
Other languages
Chinese (zh)
Other versions
CN106087745A (en
Inventor
邓青儿
于洋
金德�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201610301377.XA priority Critical patent/CN106087745B/en
Publication of CN106087745A publication Critical patent/CN106087745A/en
Application granted granted Critical
Publication of CN106087745B publication Critical patent/CN106087745B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method, the monolithic construction includes crossbeam, across a girder, it is characterised in that this method comprises the following steps:A, set across a girder steel construction in fulcrum both sides, the fulcrum includes side fulcrum and central bearing point;B, floorings and concrete beam are poured, in the position of the fulcrum casting concrete crossbeam so that the concrete beam and the concrete slab above a girder are connected as a single entity.The technical characterstic and effect of the present invention be, 1, crossbeam concrete beam, cost reduction are changed to by conventional steel structure beam;2nd, Site Welding workload is reduced, and construction method is conventional, easy, reduces difficulty of construction, construction quality is easily controlled;3rd, crossbeam and across a girder be located at same elevation plane in, both form unitary construction, are not take up too many under-clearance, and structure height is smaller, and Bridge Landscape is good;4th, late maintaining workload is reduced.

Description

A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
It is on October 17th, 2012 applying date that the present invention, which is, and Application No. 2012103943817 is entitled " a kind of The divisional application of the patent application of multiple-piece composite beam bridge top and the bottom monolithic construction and its construction method ".
Technical field
The present invention relates to the civil engineering technical field of bridge, specifically a kind of multiple-piece composite beam bridge top and the bottom are whole Body formula structure and its construction method.
Background technology
Beam bridge accounts for the overwhelming majority in conventional bridge, and beam bridge is classified by structural system, typically has system of simple supporting, continuous(Firm structure) System.Classify by construction material, typically there is concrete beam bridge, steel construction beam bridge, steel-concrete combined structure beam bridge.Steel-coagulation Native combining structure is divided into combined steel plate beam, compound section steel box girder, Corrugated webs steel-concrete composite beam etc. again according to section is different. To adapt to the situation that bridge width is larger, multiple-piece steel-concrete combined steel plate continuous beam and multiple-piece steel-concrete combination steel Case continuous beam is small due to monolithic beam lifting weight, and the advantages of simple processing, construction are rapidly, span ability is strong, which increasingly has, extensively should Trend.But steel structure beam or concrete bent cap are generally set in pier top position of the fulcrum, problems are thus brought.
During using steel structure beam, as shown in figure 1, gooseneck 11 and across a girder 12 in same elevation plane, design For the common force modes of beam in length and breadth.Gooseneck is first lifted during construction, lifts weld integral across a girder, then by both afterwards.Should The advantage of scheme is to be not take up too many under-clearance, and structure height is small, and corresponding Bridge Landscape is preferable, but rolled steel dosage is more, Cost is higher, and weld seam is intensive near fulcrum, and welding residual stress is big, there are a large amount of building site weld seams, welding condition is poor, weld seam Quality is difficult to ensure that, in addition, the application maintenance of steel structure beam adds later stage expense and workload.
During using concrete bent cap, as shown in Figure 2, although construction is more conventional, easy, late maintaining work is few, still Because superstructure 13 is supported on the bent cap 14 of substructure, position of the fulcrum structure height is that superstructure deck-molding adds bottom Structural cover depth of beam, structure height is higher, Bridge Landscape phase strain differential, it is ensured that need to raise floor elevation during under-clearance, from And increase bridge length and improve cost.
The content of the invention
It is an object of the invention to provide a kind of multiple-piece composite beam bridge top and the bottom monolithic construction, it can adapt to the modern times The structure stress requirement of bridge, it is to avoid the shortcoming of the existing Normal practice of above two, remains both advantages, convenient horizontal While beam is constructed, structure height is reduced, cost is saved, late maintaining is reduced.
To achieve these goals, the technical scheme is that:A kind of multiple-piece composite beam bridge top and the bottom monoblock type knot Structure, it mainly includes crossbeam, across a girder and across the connecting structure between girder and crossbeam, it is characterised in that:Across a girder Using multiple-piece steel-concrete combined steel plate beam or multiple-piece steel-concrete compound section steel box girder, position of the fulcrum sets crossbeam, institute Crossbeam is stated using concrete as material, prestressed strand is provided with crossbeam, connection structure is set across the steel construction part of a girder Make, poured integrally across concrete parts and the crossbeam of a girder, and above-mentioned crossbeam is connected as a single entity with the connecting structure. The connecting structure includes shear connector, is disconnected across the steel construction part of a girder at crossbeam and is anchored in horizontal stroke by shear key Beam.The connecting structure also includes deformed bar, and the deformed bar is through crossbeam and both sides across a girder steel construction Connection.The connecting structure is steel construction, and the steel construction and both sides are connected across a girder steel construction part.The Shear connection Part can be using socket cap weldering nail, perforated panel shear key etc..
Another object of the present invention is a kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method, and it can be fitted Should modern bridge structure stress requirement, it is to avoid the shortcoming of the existing Normal practice of above two, remain both advantages, While facilitating construction of beam, structure height is reduced, cost is saved, late maintaining is reduced.
To achieve these goals, technical scheme is as follows:A kind of multiple-piece composite beam bridge top and the bottom monoblock type Construction method, the monolithic construction includes crossbeam, across a girder, it is characterised in that this method comprises the following steps:A、 Set in fulcrum both sides across a girder steel construction, the fulcrum includes side fulcrum and central bearing point;B, pour floorings and concrete Crossbeam, in the position of the fulcrum casting concrete crossbeam so that the concrete beam and the concrete bridge above a girder Panel is connected as a single entity.
According to one embodiment of present invention, in step B, central bearing point casting concrete crossbeam is concretely comprised the following steps:First pour Note is together poured into a mould with concrete beam across a concrete slab for girder part, then by concrete slab near central bearing point. According to another embodiment of the present invention, in step B, central bearing point casting concrete crossbeam is concretely comprised the following steps:In first cast lower floor Fulcrum concrete beam, then between casting bay girder part concrete slab, finally pour into a mould central bearing point crossbeam concrete nearby Floorings.
It is described to be disconnected across a girder steel construction near fulcrum according to the first embodiment of the present invention, across a girder steel Structure end is provided with shear connector, step B, and casting concrete crossbeam is allowed to be connected as a single entity with the shear connector.According to this hair Bright second embodiment, it is described to be disconnected across a girder steel construction near fulcrum, cut being provided with across a girder steel construction end Power key, fulcrum both sides are also associated between a girder steel construction in deformed bar, step B, and casting concrete crossbeam makes Be connected as a single entity with the shear connector and deformed bar.According to the third embodiment of the invention, the position of the fulcrum is also provided with There is steel construction, be connected with both sides across a girder steel construction, in step B, casting concrete crossbeam is allowed to pass through with described The steel construction of fulcrum is connected as a single entity.
The obvious technical characterstic that is made up of such scheme feature of the present invention, 1, crossbeam changes by conventional steel structure beam For concrete beam, cost reduction;2nd, Site Welding workload is reduced, and construction method is conventional, easy, reduces difficulty of construction, Construction quality is easily controlled;3rd, crossbeam and across a girder be located at same elevation plane in, both form unitary construction, are not take up too Many under-clearances, structure height is smaller, and Bridge Landscape is good;4th, late maintaining workload is reduced.
Brief description of the drawings
Fig. 1 is the schematic diagram one of prior art, and wherein Fig. 1 a are elevation, and Fig. 1 b are Fig. 1 a A-A profiles.
Fig. 2 is the schematic diagram two of prior art, and wherein Fig. 2 a are elevation, and Fig. 2 b are Fig. 2 a B-B profiles.
Fig. 3 is the structural representation of one embodiment of the invention, and wherein Fig. 3 a are elevation, and Fig. 3 b are Fig. 3 a C-C sections Figure.
Fig. 4 is the structural representation of further embodiment of this invention, and wherein Fig. 4 a are elevation, and Fig. 4 b cut open for Fig. 4 a D-D Face figure.
Fig. 5 is the structural representation of another embodiment of the present invention, and wherein Fig. 5 a are elevation, and Fig. 5 b cut open for Fig. 5 a E-E Face figure.
Fig. 6 is the embodiment sequence of construction schematic diagram of middle cross beam one of the present invention.
Fig. 7 is the another embodiment sequence of construction schematic diagram of middle cross beam of the present invention.
Embodiment
With reference to the accompanying drawings and examples to further description of the present invention.
The present invention is a kind of multiple-piece composite beam bridge top and the bottom monolithic construction, and it mainly includes crossbeam 1, across a girder 2 And across a girder and the connecting structure of crossbeam, crossbeam is using concrete as material, and the top surface of crossbeam 1 is bridge top surface, across Girder includes steel construction part and is arranged on the concrete slab of steel construction upper, across the steel construction portion of a girder 2 Divide and be attached by connecting structure with crossbeam 1, is directly linked together across concrete parts and the crossbeam 1 of a girder 2.That is, Concrete slab across the concrete slab 5 of a girder 2 and the top of the concrete of crossbeam 1 and crossbeam 1 is poured integrally. 4 be the prestressed strand of crossbeam in itself in figure.
Multiple-piece steel-concrete combined steel plate beam or multiple-piece steel-concrete compound section steel box girder are generally across a girder 2, It can be needed to use freely-supported or continuous structure system according to stress.
The section of crossbeam 1 is rectangle, inverted trapezoidal or other forms.Using concrete as construction material, at the same with across Girder(It is concrete slab including steel construction and concrete roof)Entirety is linked as, can be needed to use regular reinforcement according to stress Concrete or prestressed reinforced concrete structure.
Connecting structure, when different across structure across footpath, can use different types of attachment, to ensure according to force request Structure stress safety.When longitudinal across footpath is smaller(Less than 20m)When, it will can be disconnected across the steel construction part of a girder at crossbeam, Across the end of a girder 2, shear connector 3a connecting cross beams 1 are only being set.When a girder across footpath is between 20 ~ 40m, also need Increase and pass through crossbeam to connect measure of the both sides across a girder deformed bar 3b.Further increased to when across a girder across footpath During more than 60m, near central bearing point, it can not turned off across the steel construction part of a girder, continue through crossbeam, and described logical Cross prestressed strand 4 and regular reinforcement of the perforate with crossbaring in itself in the steel construction 3c of crossbeam.Wherein, shear connector Can be using socket cap weldering nail, perforated panel shear key etc..
When across footpath is smaller(Less than 20m)When, only set shear connector 3a to be attached with crossbeam across a girder, due to disconnected The top part in face is along bridge, to bearing larger tension, section lower portion to bearing compared with huge pressing stress, and entirely breaks along bridge The shear key connector in face bears section shearing jointly, and therefore, in the distribution of WELDING STUDS, section upper position should be more close Collection, upper position can be slightly sparse, in shear key specification, and the stronger shear key of tensile capacity is preferentially selected in upper position, such as Longer weldering nail shear key of length etc..
When across footpath increase(Between 20 ~ 40m), in addition to shear connector is set, also need increase to pass through deformed bar 3b Crossbeam connects measure of the both sides across a girder.It is preferential to lose less from anchor head because length is shorter for prestressing force measure Finish rolling screw thread prestressed thick reinforcement and the anchorage of repeatable tensioning, in prestressing force arrangement, should focus primarily upon section top Part is to resist tension.Arrange and concentrate when prestressed thick reinforcement, when anchorage arrangement can not be completed on same section, it may be considered that Anchorage point is anchored into space located at different section to obtain.Arrangement and specification requirement phase of the WELDING STUDS requirement with across footpath when smaller Together.
When across footpath further increases, it can not turned off across the steel construction part of a girder, continue through crossbeam, and Prestressed strand and regular reinforcement of the perforate with crossbaring in itself in the steel construction.Opening diameter should be greater than steel beam or reinforcing bar Diameter adds twice of maximum coarse aggregate diameter, with the anchoring of reinforced steel beam and girder and concrete beam, Kong Bianyu steel beam flange plates Distance should be greater than 5cm to ensure the validity of steel beam web plate and edge of a wing plate weld.Girder steel top flange plate, bottom wing listrium and web are equal Crossbeam should be continued through.Some shear connectors can be arranged on steel beam web plate, to ensure that girder steel of the crossbeam with continuing to pass through enters Row effectively connection.Side crossbeam and moment of flexure is smaller due to bearing across the connection of a girder, can take two kinds of companies during above-mentioned small across footpath Connect mode.
The construction method of bridge still can be using conventional, ripe prefabrication combination support casting, i.e., across a girder Steel construction part is prefabricated in the factory.After the completion of live Bridge Pier Construction, in column(That is fulcrum)Both sides set up support lifting longitudinal direction across Between girder steel construction part, joint connection in site forms entirety, overarm brace, formwork erection, assembling reinforcement set up in position of the fulcrum, buries Crossbeam prestressed strand pipeline, cast floorings and concrete beam, stretch-drawing beam prestressing force, laying are mated formation, cast anticollision shield Column, is finally completed the construction of whole bridge.
Wherein, side crossbeam and neighbouring concrete slab can be to solve near central bearing point floorings along bridge with once-cast To tension it is larger the problem of, it is preferable that the floorings above last casting concrete crossbeam.Middle cross beam can use following two Plant arrangement and method for construction:1st, between first casting bay girder part concrete slab 5, reserve central bearing point nearby concrete slab with it is mixed Solidifying soil crossbeam is together poured into a mould(Fig. 6);2nd, first cast lower floor central bearing point concrete beam 2, reserves the concrete bridge deck plate portion of crossbeam Point do not pour into a mould, then between casting bay girder part concrete slab 5, finally pour into a mould central bearing point crossbeam concrete slab nearby 6(Fig. 7).
During using arrangement and method for construction 2, just with stretch-drawing beam prestressing force and it can be removed after crossbeam lower-layer concrete casting complete All bridge lower carriages, this scheme accomplishes that space under bridge is influenceed to minimize in vehicle pass-through requirement under having bridge.
According to comparative analysis is calculated, the length that reserved central bearing point concrete slab is finally poured is central bearing point center line two Each 0.1 ~ 0.2 times of across footpath in side is advisable, and the drawing that the arrangement and method for construction can reduce into upper limb concrete near central bearing point when bridge is open to traffic should Power, reduced by the 2Mpa of conventional once-cast concrete scheme to 1Mpa or so, and due to carrying out step pouring to concrete, Blockage effect can be reduced, shrinkage stress 0.5Mpa of concrete or so under least favorable Load Combination is reduced, for optimization structure Stressed effect is obvious.
With the common wide 25m of bridge, exemplified by span setting 3 × 30m steel-concrete combined steel plate continuous beams, section such as Fig. 3, Full-bridge uses steel 236.25t, and floorings use concrete 562.5m3, reinforcing bar 247.5t, crossbeam use concrete 375m3, steel Beam 11.25t, reinforcing bar 32t.Crossbeam steel about 90t is reduced compared to conventional gooseneck scheme, weld seam about 900m is reduced, wherein applying Work difficulty larger field welding about 230m, reduces the anticorrosive coating area 580m for needing to conserve2, binding beam total price reduction about 95 Ten thousand, monovalent index is converted into for 420 yuan/m2, equivalent to saving bridge superstructure cost about 14%.And adopted compared to common With the scheme of concrete bent cap, deck-molding 1.5m can be reduced, is calculated with headroom of being passed through under identical bridge, longitudinal slope considers according to 3%, whole Individual engineering will reduce bridge area 2500m2, save bridge total cost about 1500W.

Claims (4)

1. a kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method, the monolithic construction include crossbeam, across Girder, it is characterised in that this method comprises the following steps:A, fulcrum both sides set across a girder steel construction, the fulcrum includes Side fulcrum and central bearing point, it is described to be disconnected across a girder steel construction near fulcrum, cut being provided with across a girder steel construction end Power key;B, floorings and concrete beam are poured, in the position of the fulcrum casting concrete crossbeam, casting concrete crossbeam is allowed to It is connected as a single entity with the shear connector, and causes the concrete beam and the concrete slab above a girder to be linked as one Body.
2. the construction method as described in claim 1, it is characterised in that:In step B, central bearing point casting concrete crossbeam it is specific Step is:The concrete slab of girder part between first casting bay, then concrete slab near central bearing point and concrete is horizontal Beam is together poured into a mould.
3. the construction method as described in claim 1, it is characterised in that:In step B, central bearing point casting concrete crossbeam it is specific Step is:First cast lower floor central bearing point concrete beam, then between casting bay girder part concrete slab, in finally pouring into a mould Concrete slab near fulcrum crossbeam.
4. the construction method as described in claim 1, it is characterised in that:It is described to be disconnected across a girder steel construction near fulcrum, A girder steel construction end is being provided with shear connector, fulcrum both sides are connected with prestress steel between a girder steel construction In muscle, step B, casting concrete crossbeam is allowed to be connected as a single entity with the shear connector and deformed bar.
CN201610301377.XA 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method Active CN106087745B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610301377.XA CN106087745B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201210394381.7A CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof
CN201610301377.XA CN106087745B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201210394381.7A Division CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof

Publications (2)

Publication Number Publication Date
CN106087745A CN106087745A (en) 2016-11-09
CN106087745B true CN106087745B (en) 2017-11-07

Family

ID=50567252

Family Applications (3)

Application Number Title Priority Date Filing Date
CN201210394381.7A Active CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof
CN201610301377.XA Active CN106087745B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
CN201610198667.6A Active CN105862597B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201210394381.7A Active CN103774541B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction and construction method thereof

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201610198667.6A Active CN105862597B (en) 2012-10-17 2012-10-17 A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method

Country Status (1)

Country Link
CN (3) CN103774541B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104195950A (en) * 2014-08-15 2014-12-10 中交第二航务工程局有限公司 Steel-concrete composite beam cable-stayed bridge glued joint connecting method
CN105178191B (en) * 2015-08-10 2017-03-22 中交第一公路工程局有限公司 Sand bucket positioning device used for shear pin
CN106930181A (en) * 2017-04-18 2017-07-07 浙江省交通规划设计研究院 A kind of simple-supported thencontinuous steel reinforced concrete combined bridge hogging moment area structure
CN107044091B (en) * 2017-05-18 2019-03-29 中铁十六局集团铁运工程有限公司 A kind of bridge side bar formwork for placing and its casting method
CN108118610A (en) * 2017-12-26 2018-06-05 上海市政工程设计研究总院(集团)有限公司 A kind of ultra-high performance concrete and regular reinforcement concrete combination beam
CN109183615B (en) * 2018-08-17 2020-05-26 中铁大桥勘测设计院集团有限公司 Multi-main-beam type steel-concrete combined continuous beam
CN114592440B (en) * 2022-03-21 2024-03-19 武汉市规划设计有限公司 Upper structure of assembled steel-concrete combined bridge and construction process thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003041516A (en) * 2001-07-27 2003-02-13 Ttk Corp Integral structure of upper and lower parts of continuous girder bridge and method of constructing it
CN201390928Y (en) * 2009-04-16 2010-01-27 中铁二院工程集团有限责任公司 Support rail continuous beam in double track railway
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Fabricated fibrous concrete combined deck structure and construction method thereof
CN102409602A (en) * 2011-12-02 2012-04-11 四川西南交大土木工程设计有限公司 Concrete structure box, plate and joist combined beam
CN102561172A (en) * 2010-12-22 2012-07-11 中交公路规划设计院有限公司 Celled hybrid beam junction with composite connectors
CN102704394A (en) * 2012-06-15 2012-10-03 湖南大学 Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2928513A1 (en) * 1979-07-14 1981-01-29 Peter Dipl Ing Dr Techn Wagner Demountable steel flyover bridge superstructure - comprises triangular main roadway girder, side border and possibly footpath carriers
CN2816118Y (en) * 2005-06-13 2006-09-13 上海市政工程设计研究院 Prefabricated beam connection structure
CN101570960B (en) * 2009-05-08 2011-06-15 北京市市政专业设计院有限责任公司 Fastening method of T-shaped beam bridge
CN101603288B (en) * 2009-07-03 2012-05-30 中铁大桥局股份有限公司 Three-truss main girder structure of highway and railway bi-purpose cable-stayed bridge and installation method thereof
CN201546165U (en) * 2009-11-18 2010-08-11 上海市城市建设设计研究院 Simple support-continuous box girder structure
CN201648950U (en) * 2010-05-11 2010-11-24 天津市市政工程设计研究院 Novel beam structure of steel-concrete combination section
CN201924278U (en) * 2011-01-04 2011-08-10 上海市城市建设设计研究院 Continuous seam structure for bridge floor
CN102021885B (en) * 2011-01-04 2012-02-15 上海市城市建设设计研究院 Bridge deck continuous seam structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003041516A (en) * 2001-07-27 2003-02-13 Ttk Corp Integral structure of upper and lower parts of continuous girder bridge and method of constructing it
CN201390928Y (en) * 2009-04-16 2010-01-27 中铁二院工程集团有限责任公司 Support rail continuous beam in double track railway
CN102561172A (en) * 2010-12-22 2012-07-11 中交公路规划设计院有限公司 Celled hybrid beam junction with composite connectors
CN102383374A (en) * 2011-11-28 2012-03-21 湖南大学 Fabricated fibrous concrete combined deck structure and construction method thereof
CN102409602A (en) * 2011-12-02 2012-04-11 四川西南交大土木工程设计有限公司 Concrete structure box, plate and joist combined beam
CN102704394A (en) * 2012-06-15 2012-10-03 湖南大学 Steel-fiber concrete combined bridge deck structure with reinforced joints and construction method of steel-fiber concrete combined bridge deck structure

Also Published As

Publication number Publication date
CN105862597B (en) 2017-11-24
CN105862597A (en) 2016-08-17
CN103774541A (en) 2014-05-07
CN103774541B (en) 2016-08-03
CN106087745A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
CN106087745B (en) A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
CN108677685B (en) Ultra-high-performance concrete-part steel beam combined bent cap and construction method thereof
CN102220739B (en) Corrugated steel web prestressed concrete continuous box girder and construction method thereof
CN101994293B (en) High pier coping construction method
CN202131559U (en) Corrugated steel web plate prestressed concrete continuous box girder
CN101613997A (en) A kind of method for widening steel-concrete combination
CN105839510A (en) Steel-ultra-high-performance concrete combined continuous beam bridge structure and construction method thereof
CN109082998A (en) Integral prefabricated steel plate combination girder construction and construction method
CN213038218U (en) Predictive continuous rigid frame bridge capable of supplementing tensioning prestress
CN106087711B (en) Antinode work beam-steel concrete top plate-external prestressing combines T-shaped simply supported beam
CN112458877A (en) Assembled steel-concrete combined rigid frame bridge and construction method thereof
CN109958049A (en) A kind of modularization steel-is mixed to combine small box girder freely-supported continuous bridge and its construction method
CN111254800A (en) Combined beam suitable for urban bridge and construction method thereof
CN208121541U (en) In across the steel reinforced concrete composite beam bridge constructed using no mount approach
CN110644349A (en) Superstructure for wide box girder and short tower cable-stayed bridge and construction method
CN110331664B (en) Steel-concrete mixed continuous box girder bridge deck joint structure and construction method thereof
CN103205930B (en) Structure for continuous transformation of existing simply supported hollow slab girder bridge and construction method of structure
CN113356052A (en) Novel steel bar truss superposed bridge deck and production method
CN205934687U (en) Antinode worker roof beam - steel concrete roof - external prestress combination T type simple beam
CN103194963B (en) Structure for continuous modification of existing simply-supported T-shaped beam bridge and construction method thereof
CN214459548U (en) Assembled steel and concrete combined rigid frame bridge
CN205474785U (en) Steel - ultra high performance concrete combination continuous bridge structure
CN109137757A (en) A kind of anti-buckling structure of large span box girder with corrugated steel webs and construction method
CN205399174U (en) Combination steel case roof beam
CN114182620A (en) Partial cable-stayed bridge structure system of large cantilever core steel box and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant