CN106049558B - A kind of pipe gallery information early warning system and method - Google Patents

A kind of pipe gallery information early warning system and method Download PDF

Info

Publication number
CN106049558B
CN106049558B CN201610363092.9A CN201610363092A CN106049558B CN 106049558 B CN106049558 B CN 106049558B CN 201610363092 A CN201610363092 A CN 201610363092A CN 106049558 B CN106049558 B CN 106049558B
Authority
CN
China
Prior art keywords
piping lane
value
bed course
threedimensional model
pipe gallery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610363092.9A
Other languages
Chinese (zh)
Other versions
CN106049558A (en
Inventor
王述红
侯文帅
王鹏宇
张丙吉
韩冰
李晓冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeastern University China
Original Assignee
Northeastern University China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeastern University China filed Critical Northeastern University China
Priority to CN201610363092.9A priority Critical patent/CN106049558B/en
Publication of CN106049558A publication Critical patent/CN106049558A/en
Application granted granted Critical
Publication of CN106049558B publication Critical patent/CN106049558B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/08Investigation of foundation soil in situ after finishing the foundation structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/10Miscellaneous comprising sensor means

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Soil Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention, which provides a kind of pipe gallery information early warning system and method, the system, to be included:Strain transducer, strain gauge, soil pressure cell, Reinforcement Stress-count, water pressure sensor, water-level gauge, computer.It is provided with computer:Foundation soil prewarning unit, piping lane bed course prewarning unit, piping lane liner structure prewarning unit.The present invention contributes to pipe gallery building course information-based, the three-dimensional information model of pipe gallery is established using Parameterized design software, with being easily modified, three-dimensional visible, the characteristics of accurate output municipal administration synthesis pipe gallery construction drawing, the present invention has engineering anticipation warning function in addition, in engineering application can monitor indices of the pipe gallery in work progress and provide early warning in real time, so that workmen adjusts construction in time.Be advantageous to designer's reasonable construction, reduce check of drawings work, reduction is done over again and design alteration, is accomplished live accurate construction, is ensured underground pipe gallery head room, the maintenance and maintenance being easy to during pipe gallery use.

Description

A kind of pipe gallery information early warning system and method
Technical field
The invention belongs to construction project informationization technology field, and in particular to a kind of pipe gallery information early warning system and side Method.
Background technology
The construction of municipal administration synthesis pipe gallery in China also in the starting stage, due to its exclusive advantage obtained it is more and more The concern of designer.Traditional piping lane two-dimensional design includes piping lane flat sectional drawing, is drawn completely by designer by the imagination, by It is numerous in pipeline and interspersed frequent, chain reaction can be produced when adjusting pipeline absolute altitude, that is, adjust collision at one and can produce new Collision, this mistake is easy to be ignored in two-dimensional design.Designer designs drafting flat cutting faces only by the imagination, easily There are mistakes and omissions and cause the puzzlement in work progress, even if designer's clear thinking, complicated two-dimentional drawing is when reporting Can bring puzzlement, owner can not fast understanding designer wish, cause the inconvenience on linking up.
Pipe gallery traditional construction procedural information degree is low, and job site is relative with designing technique personnel to disconnect, for The emergency case that job site occurs, technical staff can not obtain information in time and be handled so that the engineering problem of appearance without Method solves in time, causes certain loss.For underground structure, because technical staff is difficult to obtain subsurface picture, foundation soil It is unknown with the physical and mechanical parameter of structure, cause construction quality to be difficult to ensure that, the problems such as being difficult to repair to the quality accident of appearance.
The content of the invention
The problem of existing for prior art, the present invention provide a kind of pipe gallery information early warning system and method.
The technical scheme is that:
A kind of pipe gallery information early warning system, including:
Strain transducer:It is laid between piping lane bed course and foundation soil, gathers the strain value at the top of foundation soil in real time;
Strain gauge:It is laid on table in piping lane liner structure cover top surface and lower surface, piping lane liner structure riser Face and outer surface, the stress value of piping lane liner structure top plate and the stress value of riser are gathered in real time;
Soil pressure cell:Installed in pipe gallery construction and excavation bottom of foundation ditch and side wall, foundation pit earth pressure value is gathered in real time;
Reinforcement Stress-count:On the steel bar stress in piping lane liner structure, the steel of piping lane liner structure is gathered in real time Muscle stress value;
Water pressure sensor:Piping lane bed course bottom is laid on, gathers the hydraulic pressure force value of piping lane bed course in real time;
Water-level gauge:Level of ground water installed in piping lane bed course bottom, in real time collection piping lane bed course bottom;
Computer:Foundation soil threedimensional model, piping lane bed course three are established according to building technology requirement and build the side condition Dimension module, piping lane liner structure threedimensional model, the assembly of each threedimensional model is generated into pipe gallery entirety threedimensional model, according to synthesis Soil pressure force value in piping lane work progress, the stress value at the top of foundation soil, the stress value of piping lane liner structure top plate and riser The reinforcement stresses value of strain value, piping lane liner structure at the top of stress value, foundation soil, information early warning is carried out to pipe gallery.
It is provided with the computer:
Foundation soil prewarning unit:Establish the foundation soil threedimensional model based on data-driven, according to the severe of foundation soil, Moisture content, internal friction angle, cohesion, earth pressure theory value is calculated, according to foundation pit earth pressure value to foundation soil in work progress Threedimensional model is identified, and the color of the bigger mark of numerical value is deeper, when foundation pit earth pressure value exceedes earth pressure theory value, then by ground Correspondence position is highlighted early warning in base soil layer threedimensional model;
Piping lane bed course prewarning unit:The piping lane bed course threedimensional model based on data-driven is established, according to the foundation soil of collection The strain value at layer top, judge whether piping lane bed course has strain value mutation, be, then pipe gallery has the wind that differential settlement occurs It is dangerous, early warning, and positional information at output mutation are highlighted at the mutation in piping lane bed course threedimensional model, otherwise, is not sent out The risk of raw differential settlement;When piping lane bed course somewhere level of ground water exceedes piping lane elevation of bottom, carried out according to hydraulic pressure force value Antifloating computation, if checking computations are unqualified, this is in piping lane bed course threedimensional model and is highlighted early warning, and output position information;
Piping lane liner structure prewarning unit:It is different according to piping lane section configuration, position in storehouse number, subsiding crack positional information structure The piping lane liner structure threedimensional model based on data-driven, the stress of piping lane liner structure top plate, the stress or steel of riser Muscle stress value exceedes given threshold, then piping lane liner structure threedimensional model corresponding site is highlighted early warning.
The method that pipe gallery information early warning is carried out using described pipe gallery information early warning system, including:
Foundation soil threedimensional model, piping lane bed course threedimensional model, piping lane liner structure threedimensional model are established, by each three-dimensional mould The assembled generation pipe gallery block mold of type;
In foundation soil work progress, according to the severe of foundation soil, moisture content, internal friction angle, cohesion, soil pressure is calculated Theoretical value, in pipe gallery construction and excavation bottom of foundation ditch and side wall installation soil pressure cell, foundation pit earth pressure value is gathered in real time;Ground Foundation soil threedimensional model is identified according to foundation pit earth pressure value in soil layer work progress, the color of the bigger mark of numerical value is more It is deep;When foundation pit earth pressure value exceedes earth pressure theory value, then correspondence position in foundation soil threedimensional model is highlighted early warning, Otherwise piping lane cushion construction process is carried out;
During piping lane cushion construction, strain transducer is laid between piping lane bed course and foundation soil, in piping lane bed course Bottom laying water pressure sensor, water-level gauge, hydraulic pressure force value, the underground water of piping lane bed course bottom of piping lane bed course are gathered in real time Position;According to the strain value at the top of the foundation soil of collection, judge whether piping lane bed course has strain value mutation, be, then pipe gallery There is the risk that differential settlement occurs, early warning is highlighted at the mutation in piping lane bed course threedimensional model, and at output mutation Positional information, otherwise, the risk of differential settlement does not occur;
When piping lane bed course somewhere level of ground water exceedes piping lane elevation of bottom, antifloating computation is carried out according to hydraulic pressure force value, if Check unqualified, this is in piping lane bed course threedimensional model and is highlighted early warning, and output position information, so that workmen enters The processing of row precipitation, otherwise, carry out the construction of piping lane liner structure;
In piping lane liner structure work progress, in piping lane liner structure cover top surface and lower surface, piping lane liner structure Riser inner surface and outer surface mount stress sensor, Reinforcement Stress-count is installed on the steel bar stress in piping lane liner structure, Stress value, the reinforcement stresses value of piping lane liner structure of the stress value of collection piping lane liner structure top plate and riser in real time;If pipe The stress of corridor liner structure top plate, the stress of riser or reinforcement stresses value exceed given threshold, then piping lane liner structure is three-dimensional Model corresponding site is highlighted early warning, and otherwise, pipe gallery information early warning terminates.
Beneficial effect:
The system and method for the present invention contributes to pipe gallery building course information-based, is established using Parameterized design software The three-dimensional information model of pipe gallery, have and be easily modified, three-dimensional visible, the accurate spy for exporting municipal administration synthesis pipe gallery construction drawing Point, in addition the present invention have engineering anticipation warning function, in engineering application can monitor pipe gallery in work progress Indices simultaneously provide early warning in real time, so that workmen adjusts construction in time.Be advantageous to designer's reasonable construction, reduce and examine Figure work, reduction is done over again and design alteration, is accomplished live accurate construction, is ensured underground pipe gallery head room, be easy to pipe gallery Maintenance and maintenance during use;Three-dimensional display can be carried out to user using pipe gallery threedimensional model, be advantageous to design Communication between personnel and user, is easy to project to be smoothed out.In building course, for the engineering problem of appearance, technical staff The warning message provided for the present invention takes corresponding solution.
Brief description of the drawings
Fig. 1 is specific embodiment of the invention pipe gallery information early warning system structured flowchart;
Fig. 2 is specific embodiment of the invention foundation soil threedimensional model standard paragraphs schematic diagram;
Fig. 3 is specific embodiment of the invention piping lane liner structure threedimensional model standard paragraphs schematic diagram;
Fig. 4 is specific embodiment of the invention pipe gallery entirety threedimensional model schematic diagram;
Fig. 5 is the particular flow sheet of specific embodiment of the invention step 2;
Fig. 6 is the particular flow sheet of specific embodiment of the invention step 3;
Fig. 7 is the particular flow sheet of specific embodiment of the invention step 5.
Embodiment
The specific implementation to the present invention elaborates below in conjunction with the accompanying drawings.
A kind of pipe gallery information early warning system, as shown in figure 1, including:
Strain transducer:It is laid between piping lane bed course and foundation soil, gathers the strain value at the top of foundation soil in real time;
Strain gauge:It is laid on table in piping lane liner structure cover top surface and lower surface, piping lane liner structure riser Face and outer surface, the stress value of piping lane liner structure top plate and the stress value of riser are gathered in real time;
Soil pressure cell:Installed in pipe gallery construction and excavation bottom of foundation ditch and side wall, foundation pit earth pressure value is gathered in real time;
Reinforcement Stress-count:On the steel bar stress in piping lane liner structure, the steel of piping lane liner structure is gathered in real time Muscle stress value;
Water pressure sensor:Piping lane bed course bottom is laid on, gathers the hydraulic pressure force value of piping lane bed course in real time;
Water-level gauge:Level of ground water installed in piping lane bed course bottom, in real time collection piping lane bed course bottom;
Computer:Foundation soil threedimensional model, piping lane bed course three are established according to building technology requirement and build the side condition Dimension module, piping lane liner structure threedimensional model, the assembly of each threedimensional model is generated into pipe gallery entirety threedimensional model, according to synthesis Soil pressure force value in piping lane work progress, the stress value at the top of foundation soil, the stress value of piping lane liner structure top plate and riser The reinforcement stresses value of strain value, piping lane liner structure at the top of stress value, foundation soil, information early warning is carried out to pipe gallery.
It is provided with computer:
Foundation soil prewarning unit:Establish the foundation soil threedimensional model based on data-driven, according to the severe of foundation soil, Moisture content, internal friction angle, cohesion, earth pressure theory value is calculated, according to foundation pit earth pressure value to foundation soil in work progress Threedimensional model is identified, and the color of the bigger mark of numerical value is deeper, when foundation pit earth pressure value exceedes earth pressure theory value, then by ground Correspondence position is highlighted early warning in base soil layer threedimensional model;
Piping lane bed course prewarning unit:The piping lane bed course threedimensional model based on data-driven is established, according to the foundation soil of collection The strain value at layer top, judge whether piping lane bed course has strain value mutation, be, then pipe gallery has the wind that differential settlement occurs It is dangerous, early warning, and positional information at output mutation are highlighted at the mutation in piping lane bed course threedimensional model, otherwise, is not sent out The risk of raw differential settlement;When piping lane bed course somewhere level of ground water exceedes piping lane elevation of bottom, carried out according to hydraulic pressure force value Antifloating computation, if checking computations are unqualified, this is in piping lane bed course threedimensional model and is highlighted early warning, and output position information;
Piping lane liner structure prewarning unit:It is different according to piping lane section configuration, position in storehouse number, subsiding crack positional information structure The piping lane liner structure threedimensional model based on data-driven, the stress of piping lane liner structure top plate, the stress or steel of riser Muscle stress value exceedes given threshold, then piping lane liner structure threedimensional model corresponding site is highlighted early warning.
It is pre- that present embodiment also provides a kind of pipe gallery information early warning system progress pipe gallery information described in Alert method, including:
Step 1, according to build require and site condition establish foundation soil threedimensional model, piping lane bed course threedimensional model, pipe Corridor liner structure threedimensional model, by the assembled generation pipe gallery block mold of each threedimensional model;
Each threedimensional model of present embodiment realizes that change threedimensional model is a part of or a few by Parametric designing Partial size, the change to relevant portion in threedimensional model is automatically performed, so as to realize that driving of the size to model is realized Data-driven, wherein being driven required geological information and topology information by Computer Automatic Extraction;It is meanwhile detailed in part In table, related data can also make respective change;The mechanics parameter of comprehensive pipe gallery structure can also edit and storage.Selection It is three-dimensional that the Revit softwares of autodesk, inc. carry out foundation soil threedimensional model, piping lane bed course threedimensional model, piping lane liner structure The foundation of model, by the assembled generation pipe gallery block mold of each threedimensional model.
The foundation of foundation soil threedimensional model:Built from top to bottom according to soil layer actual distribution situation, each soil layer is only Vertical race(Component collection), component collection model is established using fusion setting-out order, in the longitudinally spaced certain distance interception of pipe gallery Two sections, the profile of each soil layer included in section is drawn on a section according to situation about being cut section, another The profile of each soil layer included in section is drawn on one section, the path of setting-out is then drawn, generates preliminary component, to coming in and going out Mouth, discharge port, air inlet, exhaust outlet are sheared using hollow mould on the preliminary component of generation, edit each soil layer institute Comprising information, generate the component collection model of soil layer, i.e. foundation soil threedimensional model.
The foundation of piping lane bed course threedimensional model:Component collection model is established using stretching order, according to settlement slot setting situation Segmentation drafting is carried out to piping lane bed course, piping lane bed course cross-sectional profiles is drawn, is then longitudinally stretched in pipe gallery, is edited The attribute of piping lane bed course, generate the structure collection model of piping lane bed course, i.e. piping lane bed course threedimensional model.
The foundation of piping lane liner structure threedimensional model:Component collection model is established using stretching order, according to settlement slot setting Situation is segmented, and its profile is drawn according to the cross-sectional design figure of piping lane liner structure, is then longitudinally carried out in pipe gallery Stretching, generates preliminary component, and hollow mould is used in the preliminary structure of generation to gateway, discharge port, air inlet, exhaust outlet Sheared on part, liner structure is created using stretching order at gateway, discharge port, liner structure at gateway, discharge port Elevation of top to ground, edit the attribute of liner structure, generate the structure collection model of piping lane liner structure, i.e. piping lane lining cutting knot Structure threedimensional model.
By the foundation soil threedimensional model established, piping lane bed course threedimensional model, the addition of piping lane liner structure threedimensional model Into same project, assembled, generation pipe gallery block mold is carried out according to pipe gallery design route, and pipe gallery is overall The design information of each several part is included in model, pipeline layout, collision detection, clear height inspection etc. can be carried out by importing Navisworks Operation, also lays a good foundation for follow-up operational management.
Due to the design feature of comprehensive pipe gallery structure, present embodiment longitudinally takes standard paragraphs to illustrate along piping lane, and Fig. 2 is shown The standard paragraphs of foundation soil threedimensional model, Fig. 3 show the standard paragraphs of piping lane liner structure threedimensional model, and Fig. 4 shows comprehensive Close the standard paragraphs of piping lane block mold.
In step 2, foundation soil work progress, according to the severe of foundation soil, moisture content, internal friction angle, cohesion, calculate Earth pressure theory value, in pipe gallery construction and excavation bottom of foundation ditch and side wall installation soil pressure cell, foundation ditch soil pressure is gathered in real time Value;Foundation soil threedimensional model is identified according to foundation pit earth pressure value in foundation soil work progress, the bigger mark of numerical value Color it is deeper;When foundation pit earth pressure value exceedes earth pressure theory value, then correspondence position in foundation soil threedimensional model is highlighted Early warning is shown, otherwise carries out piping lane cushion construction process, as shown in Figure 5;
During step 3, piping lane cushion construction, strain transducer is laid between piping lane bed course and foundation soil, in pipe Corridor bed course bottom laying water pressure sensor, water-level gauge, hydraulic pressure force value, the ground of piping lane bed course bottom of piping lane bed course are gathered in real time Lower water level;According to the strain value at the top of the foundation soil of collection, judge whether piping lane bed course has strain value mutation, be, then integrate Piping lane has the risk that differential settlement occurs, and early warning is highlighted at the mutation in piping lane bed course threedimensional model, and exports prominent Positional information at change, otherwise, the risk of differential settlement does not occur;When piping lane bed course somewhere level of ground water exceedes piping lane bottom During absolute altitude, antifloating computation is carried out according to hydraulic pressure force value, if checking computations are unqualified, this is in piping lane bed course threedimensional model and is highlighted Early warning, and output position information, so that workmen carries out precipitation processing, otherwise, carry out the construction of piping lane liner structure, such as Fig. 6 It is shown;
In step 4, piping lane liner structure work progress, in piping lane liner structure cover top surface and lower surface, piping lane lining Structure riser inner surface and outer surface mount stress sensor are built, installing reinforcing bar on the steel bar stress in piping lane liner structure should Power meter, the stress value of piping lane liner structure top plate and stress value, the reinforcement stresses value of piping lane liner structure of riser are gathered in real time; If the stress or reinforcement stresses value of the stress of piping lane liner structure top plate, riser exceed given threshold, piping lane liner structure Threedimensional model corresponding site is highlighted early warning, and otherwise, pipe gallery information early warning terminates, as shown in Figure 7.

Claims (2)

1. a kind of pipe gallery information early warning system, including:
Strain transducer:It is laid between piping lane bed course and foundation soil, gathers the strain value at the top of foundation soil in real time;
Strain gauge:Be laid on piping lane liner structure cover top surface and lower surface, piping lane liner structure riser inner surface and Outer surface, the stress value of piping lane liner structure top plate and the stress value of riser are gathered in real time;
Soil pressure cell:Installed in pipe gallery construction and excavation bottom of foundation ditch and side wall, foundation pit earth pressure value is gathered in real time;
Reinforcement Stress-count:On the steel bar stress in piping lane liner structure, the reinforcing bar for gathering piping lane liner structure in real time should Force value;
Water pressure sensor:Piping lane bed course bottom is laid on, gathers the hydraulic pressure force value of piping lane bed course in real time;
Water-level gauge:Level of ground water installed in piping lane bed course bottom, in real time collection piping lane bed course bottom;
Computer:Foundation soil threedimensional model, piping lane bed course three-dimensional mould are established according to building technology requirement and build the side condition Type, piping lane liner structure threedimensional model, the assembly of each threedimensional model is generated into pipe gallery entirety threedimensional model, according to pipe gallery Soil pressure force value in work progress, stress value, the stress value of piping lane liner structure top plate and the stress of riser at the top of foundation soil Strain value, the reinforcement stresses value of piping lane liner structure at the top of value, foundation soil, information early warning is carried out to pipe gallery;
Characterized in that, it is provided with the computer:
Foundation soil prewarning unit:The foundation soil threedimensional model based on data-driven is established, according to the severe of foundation soil, aqueous Rate, internal friction angle, cohesion, earth pressure theory value is calculated, it is three-dimensional to foundation soil according to foundation pit earth pressure value in work progress Model is identified, and the color of the bigger mark of numerical value is deeper, when foundation pit earth pressure value exceedes earth pressure theory value, then by foundation soil Correspondence position is highlighted early warning in layer threedimensional model;
Piping lane bed course prewarning unit:The piping lane bed course threedimensional model based on data-driven is established, according to the foundation soil top of collection The strain value in portion, judges whether piping lane bed course has strain value mutation, is, then pipe gallery has the risk that differential settlement occurs, Early warning, and positional information at output mutation are highlighted at mutation in piping lane bed course threedimensional model, otherwise, is not occurred not The risk of uniform settlement;When piping lane bed course somewhere level of ground water exceedes piping lane elevation of bottom, anti-floating is carried out according to hydraulic pressure force value Checking computations, if checking computations are unqualified, are in piping lane bed course threedimensional model by this and are highlighted early warning, and output position information;
Piping lane liner structure prewarning unit:Different bases is built according to piping lane section configuration, position in storehouse number, subsiding crack positional information In the piping lane liner structure threedimensional model of data-driven, the stress of piping lane liner structure top plate, the stress of riser or reinforcing bar should Force value exceedes given threshold, then piping lane liner structure threedimensional model corresponding site is highlighted early warning.
2. carrying out the method for pipe gallery information early warning using the pipe gallery information early warning system described in claim 1, it is special Sign is, including:
Require to establish foundation soil threedimensional model, piping lane bed course threedimensional model, piping lane liner structure with site condition according to building Threedimensional model, by the assembled generation pipe gallery block mold of each threedimensional model;
In foundation soil work progress, according to the severe of foundation soil, moisture content, internal friction angle, cohesion, earth pressure theory is calculated Value, in pipe gallery construction and excavation bottom of foundation ditch and side wall installation soil pressure cell, foundation pit earth pressure value is gathered in real time;Foundation soil Foundation soil threedimensional model is identified according to foundation pit earth pressure value in work progress, the color of the bigger mark of numerical value is deeper; When foundation pit earth pressure value exceedes earth pressure theory value, then correspondence position in foundation soil threedimensional model is highlighted early warning, it is no Then carry out piping lane cushion construction process;
During piping lane cushion construction, strain transducer is laid between piping lane bed course and foundation soil, in piping lane bed course bottom Water pressure sensor, water-level gauge are laid, gathers hydraulic pressure force value, the level of ground water of piping lane bed course bottom of piping lane bed course in real time;Root According to the strain value at the top of the foundation soil of collection, judge whether piping lane bed course has strain value mutation, be, then pipe gallery has generation The risk of differential settlement, early warning is highlighted at the mutation in piping lane bed course threedimensional model, and position is believed at output mutation Breath, otherwise, does not occur the risk of differential settlement;
When piping lane bed course somewhere level of ground water exceedes piping lane elevation of bottom, antifloating computation is carried out according to hydraulic pressure force value, if checking computations It is unqualified, this is in piping lane bed course threedimensional model and is highlighted early warning, and output position information, so that workmen is dropped Water process, otherwise, carry out the construction of piping lane liner structure;
In piping lane liner structure work progress, in piping lane liner structure cover top surface and lower surface, piping lane liner structure riser Inner surface and outer surface mount stress sensor, Reinforcement Stress-count is installed on the steel bar stress in piping lane liner structure, in real time Gather the stress value of piping lane liner structure top plate and stress value, the reinforcement stresses value of piping lane liner structure of riser;If piping lane serves as a contrast Build the stress of structure roof, the stress of riser or reinforcement stresses value and exceed given threshold, then piping lane liner structure threedimensional model Corresponding site is highlighted early warning, and otherwise, pipe gallery information early warning terminates.
CN201610363092.9A 2016-05-26 2016-05-26 A kind of pipe gallery information early warning system and method Active CN106049558B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610363092.9A CN106049558B (en) 2016-05-26 2016-05-26 A kind of pipe gallery information early warning system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610363092.9A CN106049558B (en) 2016-05-26 2016-05-26 A kind of pipe gallery information early warning system and method

Publications (2)

Publication Number Publication Date
CN106049558A CN106049558A (en) 2016-10-26
CN106049558B true CN106049558B (en) 2017-12-29

Family

ID=57175371

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610363092.9A Active CN106049558B (en) 2016-05-26 2016-05-26 A kind of pipe gallery information early warning system and method

Country Status (1)

Country Link
CN (1) CN106049558B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108877156A (en) * 2018-09-06 2018-11-23 东北大学 A kind of slope instability early warning system and method
CN109183866A (en) * 2018-11-14 2019-01-11 吉林建筑大学 Assemble superposed type pipe gallery shaketalle test device and preparation method thereof
CN112211199A (en) * 2020-04-06 2021-01-12 广东华星建设集团有限公司 Large deep foundation pit supporting construction structure and method thereof
CN113684811B (en) * 2021-08-31 2022-09-16 中煤科工集团重庆智慧城市科技研究院有限公司 Urban underground pipe gallery surrounding rock health monitoring system and method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3150562B2 (en) * 1995-02-22 2001-03-26 戸田建設株式会社 Water-blocking structure, method of detecting water leakage and method of repairing water leakage part
CN2938029Y (en) * 2006-07-28 2007-08-22 中国科学院武汉岩土力学研究所 Device for monitoring tunnel type engineering deformation
CN201901875U (en) * 2010-12-17 2011-07-20 上海市电力公司 Excavation environment controlling and protecting monitoring unit for large-scale ultra-deep foundation pit
CN204832898U (en) * 2015-07-08 2015-12-02 新疆北新路桥集团股份有限公司 Mountain area highway tunnel deformation characteristic remote monitering system that is under construction
CN105040667B (en) * 2015-09-06 2017-09-08 兰州理工大学 High roadbed deforms wireless remote comprehensive monitor system and installs monitoring method

Also Published As

Publication number Publication date
CN106049558A (en) 2016-10-26

Similar Documents

Publication Publication Date Title
CN112985304B (en) Tunnel construction auxiliary monitoring system
CN106049558B (en) A kind of pipe gallery information early warning system and method
CN102943459B (en) Remote smart monitoring and three-dimensional early warning method and system for deformation stability of deep foundation pit
CN109000158B (en) Pipeline leakage early warning system and method based on Internet of things and BIM and application thereof
CN114894154B (en) Method and equipment for judging stability of shield construction section
CN103866769B (en) Based on 3D geological model and real-time monitoring dam grouting engineering analysis control method
CN108180885B (en) Automatic monitoring system and method for tunnel deformation
CN102979071B (en) Remote intelligent monitoring and three-dimensional early warning method and system for stress stability of deep foundation pit
CN103352483A (en) Deep foundation pit monitoring and early warning system
CN103425054B (en) A kind of based on digitized electric power tunnel construction control method
CN210154614U (en) Foundation pit and settlement monitoring device of peripheral stratum thereof based on BIM
CN113090274B (en) Automatic cruise shield advance geological prediction system based on big data and working method
CN103031862A (en) Three-dimensional digital prewarning method and facility for remote intelligent monitoring of deep foundation pit deformation stability
CN202969361U (en) Remote intelligent monitoring and three-dimensional pre-warning system for deformation stability of deep foundation pit
CN110083989B (en) Safety data monitoring method in pipe gallery underground excavation engineering based on BIM technology
CN104196035B (en) Pipeline foundation ditch predeformation method for protecting support
CN103046525A (en) Facility and method for mechanical stability remote intelligent monitoring and three-dimensional early warning of deep foundation pit
CN103061322A (en) Method and system for remote intelligent monitoring and three-dimensional digital comprehensive warning of deep foundation pit stability
Liu et al. City pipe network intelligent service based on GIS and internet of things
CN208172969U (en) A kind of high slope surface deformation monitoring and warning system
CN115369885A (en) BIM and unmanned aerial vehicle-based dynamic monitoring method for deep foundation pit construction
CN109269434B (en) Direct-attached rock wall deformation laser scanning system and application method thereof
CN112837022A (en) System and method for transforming urban water supply and drainage pipe network of GIS
CN112381675A (en) BIM-based real estate construction project construction method
CN114151129B (en) Tunnel pumping and drainage indoor test system and test method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20161026

Assignee: Jilin Sanwei Geotechnical Engineering Co.,Ltd.

Assignor: Northeastern University

Contract record no.: X2023210000300

Denomination of invention: A comprehensive pipe gallery information early warning system and method

Granted publication date: 20171229

License type: Common License

Record date: 20231213