CN106049411B - A kind of barged-in fill drain consolidation system and its construction method - Google Patents

A kind of barged-in fill drain consolidation system and its construction method Download PDF

Info

Publication number
CN106049411B
CN106049411B CN201610379374.8A CN201610379374A CN106049411B CN 106049411 B CN106049411 B CN 106049411B CN 201610379374 A CN201610379374 A CN 201610379374A CN 106049411 B CN106049411 B CN 106049411B
Authority
CN
China
Prior art keywords
layer
hydraulic reclamation
reclamation soil
soil layer
drain bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610379374.8A
Other languages
Chinese (zh)
Other versions
CN106049411A (en
Inventor
王哲
冯斌
严熙
许斌
胡奇超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University of Technology ZJUT
Original Assignee
Zhejiang University of Technology ZJUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University of Technology ZJUT filed Critical Zhejiang University of Technology ZJUT
Priority to CN201610379374.8A priority Critical patent/CN106049411B/en
Publication of CN106049411A publication Critical patent/CN106049411A/en
Application granted granted Critical
Publication of CN106049411B publication Critical patent/CN106049411B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

A kind of barged-in fill drain consolidation system and its construction method, the system includes at least one layer of hydraulic reclamation soil layer, at least one layer of draining tube layer, drain bar and filter membrane, hydraulic reclamation soil layer and the draining staggered layered structure of tube layer, the bottom and top are hydraulic reclamation soil layer;The surface of hydraulic reclamation soil layer described in every layer is laid with one layer of cationic active agent;Draining tube layer is made of several drainpipes, and several drainage holes are distributed on drainpipe;Filter membrane is coated on the surface of drainage hole;Drain bar is inserted into hydraulic reclamation soil layer and draining tube layer;The method is the following steps are included: complete the hydraulic reclamation soil layer and draining tube layer of the bottom, hydraulic reclamation soil layer and the draining staggered layered structure of tube layer;Drain bar is set, wherein drain bar height is higher than all hydraulic reclamation soil layer absolute altitudes.The beneficial effects of the present invention are: improving the drainability of barged-in fill by hydraulic reclamation stage by stage;The filter membrane coated on drainpipe pricks non-woven fabrics using long fine heat, has resistance to flooding, permeability performance is extremely excellent.

Description

A kind of barged-in fill drain consolidation system and its construction method
Technical field
The present invention relates to a kind of barged-in fill drain consolidation system and its construction methods.
Background technique
The Chinese patent of Publication No. CN 101235634A discloses a kind of method of reclaimed ground processing, it passes through Envelope wall is set, and in the pre-buried vacuum tube in cofferdam bottom.It is laid with the sand bedding course of one layer of suitable thickness, inside arrangement chimney filter and vacuum Pipe, surface cover geotextiles.Plastic draining board is set, and one section of drain bar crop out is tied up vertically in moso bamboo frame upwards On.Dredger fill sandy soil is to absolute altitude.Vaccum-pumping equipment is installed, vacuum diaphragm is laid with.It starts vacuum pumping pump and reaches the design degree of consolidation in the soil body Afterwards, that is, it comes to an end.Although the invention increases the consolidation process depth of vacuum preloading;Shorten the construction week of project of reclamation by pumping filling Phase;Save vacuum membrane material.But construction method is more complicated, cost is higher.
The Chinese patent of 102926376 A of Publication No. CN discloses a kind of method of reclaimed ground processing, specifically relates to And one kind is reclaimed fields from the sea region soft-soil foundation treatment method, concrete scheme is: in deep level of processing region, being formed in hydraulic reclamation soil layer Before set long plastic draining board, it is default that long plastic draining board height is made to be higher than hydraulic reclamation soil layer absolute altitude;Hydraulic reclamation soil layer shape is completed later At;Short plastic draining board is set in non-deep level of processing region later;Last large area piecemeal carries out vacuum preloading.
Although the processing of one step of this method is in place, accelerate deep Soft Soil Layer as load using barged-in fill during hydraulic reclamation The duration is saved in consolidation settlement, reduces cost, reduces the problem of conventional point multistep reprocesses waste in place.But it is carried out Discharging consolidation effect is not it is obvious that finally influencing whether our foundation stabilization.
Summary of the invention
In order to solve current reclaimed ground, there are the above problems, and the invention proposes one kind to reach well To the purpose of reinforcing, and have structure simple, low cost, convenient for the barged-in fill drain consolidation system of construction and installation and its construction Method.
A kind of barged-in fill drain consolidation system of the present invention, it is characterised in that: including at least one layer of hydraulic reclamation soil layer, extremely Few one layer of draining tube layer, drain bar and filter membrane, the hydraulic reclamation soil layer and the staggered layered structure of the draining tube layer, Wherein the bottom and top are hydraulic reclamation soil layer;Outside the hydraulic reclamation soil layer for removing top layer, hydraulic reclamation soil layer described in remaining every layer Surface be laid with one layer of cationic active agent;The draining tube layer is made of several drainpipes, is distributed on the drainpipe Several drainage holes;The filter membrane is coated on the surface of the drainage hole;The drain bar insertion hydraulic reclamation In soil layer and the draining tube layer, and drain bar height is higher than all hydraulic reclamation soil layer absolute altitudes, i.e., described drain bar The barged-in fill layer surface of top edge exposing top layer.
Cationic active agent is the substance that target solution surface tension can be made to be remarkably decreased, and can reduce by two kinds of liquid or liquid Surface tension between body-solid, greatly improves the effect of draining, and Direct Uniform is layered on barged-in fill layer surface.
The drainpipe is groined type.
The filter membrane pricks non-woven fabrics using long fine heat.
The drain bar extends vertically through the hydraulic reclamation soil layer and the draining tube layer.
A kind of construction method of barged-in fill drain consolidation system of the present invention, comprising the following steps:
1) the hydraulic reclamation soil layer of the bottom is completed, and is laid with one layer of cationic active agent on surface;
2) drainpipe is arranged on the hydraulic reclamation soil layer completed, and forms draining tube layer;
3) one layer of hydraulic reclamation soil layer is filled on the surface of draining tube layer, and is laid with one layer of cationic active agent on surface;
4) it repeats step 2), 3) forms multilayer discharge structure, guarantee that hydraulic reclamation soil layer is arranged alternately with draining tube layer, the bottom It is hydraulic reclamation soil layer with top, and outside the barged-in fill layer surface of top, the surface of hydraulic reclamation soil layer described in remaining every layer It is laid with one layer of cationic active agent;
5) drain bar is set, keeps drain bar to extend vertically through hydraulic reclamation soil layer and pvd layer, wherein drain bar height is higher than The barged-in fill layer surface that all hydraulic reclamation soil layer absolute altitudes, the i.e. top edge of the drain bar expose top layer.
The beneficial effects of the present invention are: (1) is placed on plastic drain-pipe between barged-in fill by hydraulic reclamation stage by stage, is mentioned The high drainability of barged-in fill, preferably improves the consolidation effect of reclaimed ground, with easy to process and construction and installation Advantage;The present invention is suitable for the basement process of barged-in fill;(2) filter membrane coated on drainpipe pricks non-woven fabrics using long fine heat, With resistance to flooding, permeability performance is extremely excellent.Major function is to shorten drainage distance, accelerates draining.The plastic draining board, The good vertical channel of moisture when it is basement process greatly shortens the consolidation time of soil.
Detailed description of the invention
Fig. 1 is the main view of basement process.
Fig. 2 is the top view of plastic drain-pipe.
Fig. 3 is plastic drain-pipe orthogonal view.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawing
Referring to attached drawing:
A kind of barged-in fill drain consolidation system of the present invention of embodiment 1, it is characterised in that: including three barged-in fills layer by layer Layer 1, two layers of draining tube layer 2, drain bar 3 and filter membrane, hydraulic reclamation soil layer 1 described in three layers interlock with draining tube layer 2 described in two layers It is arranged into layer structure, wherein the bottom and top are hydraulic reclamation soil layer 1;Outside the hydraulic reclamation soil layer for removing top layer, remaining is every The surface of hydraulic reclamation soil layer described in layer is laid with one layer of cationic active agent;The draining tube layer 2 is made of several drainpipes, institute Several drainage holes are distributed on the drainpipe stated;The filter membrane is coated on the surface of the drainage hole;The draining Plate 3 is inserted into the hydraulic reclamation soil layer 1 and the draining tube layer 2, and 3 height of drain bar is higher than all hydraulic reclamation soil layers 1 1 surface of hydraulic reclamation soil layer that absolute altitude, the i.e. top edge of the drain bar 3 expose top layer.
The drainpipe is groined type.
Every layer of drainpipe layer height 1m, and single groined type drainpipe height is 15cm.
The filter membrane pricks non-woven fabrics using long fine heat.
The drain bar 3 extends vertically through the hydraulic reclamation soil layer 1 and the draining tube layer 2.
A kind of construction method of barged-in fill drain consolidation system of the present invention of embodiment 2, comprising the following steps:
1) the hydraulic reclamation soil layer of the bottom is completed, and is laid with one layer of cationic active agent on surface;
2) drainpipe is arranged on the hydraulic reclamation soil layer completed, and forms draining tube layer;
3) one layer of hydraulic reclamation soil layer is filled on the surface of draining tube layer, and is laid with one layer of cationic active agent on surface;
4) it repeats step 2), 3) forms multilayer discharge structure, guarantee that hydraulic reclamation soil layer is arranged alternately with draining tube layer, the bottom It is hydraulic reclamation soil layer with top, and outside the barged-in fill layer surface of top, the surface of hydraulic reclamation soil layer described in remaining every layer It is laid with one layer of cationic active agent;
5) drain bar is set, keeps drain bar to extend vertically through hydraulic reclamation soil layer and pvd layer, wherein drain bar height is higher than The barged-in fill layer surface that all hydraulic reclamation soil layer absolute altitudes, the i.e. top edge of the drain bar expose top layer.
Content described in this specification embodiment is only enumerating to the way of realization of inventive concept, protection of the invention Range should not be construed as being limited to the specific forms stated in the embodiments, and protection scope of the present invention also includes art technology Personnel conceive according to the present invention it is conceivable that equivalent technologies mean.

Claims (3)

1. a kind of barged-in fill drain consolidation system, it is characterised in that: including at least one layer of hydraulic reclamation soil layer, at least one layer of drainpipe Layer, drain bar and filter membrane, the hydraulic reclamation soil layer and the staggered layered structure of the draining tube layer, wherein the bottom and Top is hydraulic reclamation soil layer;Outside the hydraulic reclamation soil layer for removing top layer, the surface of hydraulic reclamation soil layer described in remaining every layer is laid with one Layer cationic active agent;The draining tube layer is made of several drainpipes, and the drainpipe is groined type, the draining Several drainage holes are distributed on pipe;The filter membrane is coated on the surface of the drainage hole;The drain bar is inserted into institute In the hydraulic reclamation soil layer and the draining tube layer stated;The drain bar extends vertically through the hydraulic reclamation soil layer and the draining Tube layer, and drain bar height is higher than all hydraulic reclamation soil layer absolute altitudes, i.e. and top layer is exposed in the top edge of the drain bar Barged-in fill layer surface.
2. a kind of barged-in fill drain consolidation system as described in claim 1, it is characterised in that: the filter membrane is pricked using long fine heat Non-woven fabrics.
3. a kind of construction method of barged-in fill drain consolidation system as described in claim 1~2 any one claim, packet Include following steps:
1) the hydraulic reclamation soil layer of the bottom is completed, and is laid with one layer of cationic active agent on surface;
2) drainpipe is arranged on the hydraulic reclamation soil layer completed, and forms draining tube layer;
3) one layer of hydraulic reclamation soil layer is filled on the surface of draining tube layer, and is laid with one layer of cationic active agent on surface;
4) it repeats step 2), 3) forms multilayer discharge structure, guarantee that hydraulic reclamation soil layer is arranged alternately with tube layer is drained, the bottom and most Top layer is hydraulic reclamation soil layer, and outside the barged-in fill layer surface of top, and the surface of hydraulic reclamation soil layer described in remaining every layer is laid with One layer of cationic active agent;
5) drain bar is set, drain bar is kept to extend vertically through hydraulic reclamation soil layer and pvd layer, wherein drain bar height is higher than all Hydraulic reclamation soil layer absolute altitude, i.e., the barged-in fill layer surface of top layer is exposed in the top edge of described drain bar.
CN201610379374.8A 2016-05-31 2016-05-31 A kind of barged-in fill drain consolidation system and its construction method Active CN106049411B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610379374.8A CN106049411B (en) 2016-05-31 2016-05-31 A kind of barged-in fill drain consolidation system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610379374.8A CN106049411B (en) 2016-05-31 2016-05-31 A kind of barged-in fill drain consolidation system and its construction method

Publications (2)

Publication Number Publication Date
CN106049411A CN106049411A (en) 2016-10-26
CN106049411B true CN106049411B (en) 2019-01-08

Family

ID=57171836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610379374.8A Active CN106049411B (en) 2016-05-31 2016-05-31 A kind of barged-in fill drain consolidation system and its construction method

Country Status (1)

Country Link
CN (1) CN106049411B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100195689B1 (en) * 1996-09-14 1999-06-15 유영을 Quick consolidated method using pipe drain system
CN102220757A (en) * 2011-04-18 2011-10-19 中交四航工程研究院有限公司 Immediate processing method for drainage solidifying of super soft soil shallow surface space
CN102249581A (en) * 2011-05-17 2011-11-23 河海大学 Method for improving expansive soil by carbide slag and construction method
CN103031834A (en) * 2011-10-09 2013-04-10 徐云童 Low-position vacuum preloading rapid reinforcement method of soft foundation in hydraulic filling and reclamation
CN204418106U (en) * 2014-12-24 2015-06-24 中交天津港湾工程研究院有限公司 A kind of soft soil filling combined vacuum consolidation enclose low bank between fields structure
CN205975574U (en) * 2016-05-31 2017-02-22 浙江工业大学 Dredger fill drainage system of concreteing

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100195689B1 (en) * 1996-09-14 1999-06-15 유영을 Quick consolidated method using pipe drain system
CN102220757A (en) * 2011-04-18 2011-10-19 中交四航工程研究院有限公司 Immediate processing method for drainage solidifying of super soft soil shallow surface space
CN102249581A (en) * 2011-05-17 2011-11-23 河海大学 Method for improving expansive soil by carbide slag and construction method
CN103031834A (en) * 2011-10-09 2013-04-10 徐云童 Low-position vacuum preloading rapid reinforcement method of soft foundation in hydraulic filling and reclamation
CN204418106U (en) * 2014-12-24 2015-06-24 中交天津港湾工程研究院有限公司 A kind of soft soil filling combined vacuum consolidation enclose low bank between fields structure
CN205975574U (en) * 2016-05-31 2017-02-22 浙江工业大学 Dredger fill drainage system of concreteing

Also Published As

Publication number Publication date
CN106049411A (en) 2016-10-26

Similar Documents

Publication Publication Date Title
CN206385531U (en) A kind of pile tube device of reinforcing soft ground
CN106759274B (en) A kind of semi-hollow stake and its construction method with draining AsA -GSH cycle
CN101235634A (en) Bidirectional vacuum prepressing blowing filling soft soil foundation treatment method
KR100729567B1 (en) Method of construction for promoting drain by vacuum and pressure, and drain pipe there of
CN110042830A (en) A kind of concrete fills out the stake of core perforated pipe and construction method
CN103215945B (en) The three-dimensional assembly power drain consolidation system of heterogeneous body place soft soil foundation and method
AU2009337567A1 (en) Presetting type high vacuum compact method for treating soft ground
CN107700522A (en) A kind of retaining wall structure and its construction method
JP6426418B2 (en) Ground improvement method and ground improvement system
JP2007303270A5 (en)
CN105908695B (en) A kind of barged-in fill drain consolidation system and its construction method
CN106049411B (en) A kind of barged-in fill drain consolidation system and its construction method
CN207143963U (en) A kind of foundation ditch supporting construction of pile for prestressed pipe
EP2066845A1 (en) Method and device for inserting a drainage wick
CN203129176U (en) Moistureproof wall structure
CN205501983U (en) Decompression drainage tubular pile
CN102787608B (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN205975574U (en) Dredger fill drainage system of concreteing
CN105926396B (en) A kind of town road subgrade drainage structure and its construction method
CN205975573U (en) Dredger fill drainage system of concreteing
KR100925414B1 (en) Apparatus for reinforcing slope and drainage and method for carrying out seed spray soil using the same
CN104264656B (en) Vacuum preloading downward stabilization by drainage soft soil foundation method
KR100870465B1 (en) Preloading method by controlling of buoyancy
CN210049221U (en) Foundation treatment structure for deep silt
JPH083975A (en) Method of preventing liquefaction of ground

Legal Events

Date Code Title Description