Prior art keywords
template
steel
stirrup
reinforcement cage
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510752765.5A
Other languages
Chinese (zh)
Other versions
CN106032692A (en
Inventor
刘付钧
李盛勇
黄忠海
郭伟亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
RBS Partners S&T Co Ltd
Original Assignee
RBS Partners S&T Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by RBS Partners S&T Co Ltd filed Critical RBS Partners S&T Co Ltd
Priority to CN201510752765.5A priority Critical patent/CN106032692B/en
Publication of CN106032692A publication Critical patent/CN106032692A/en
Application granted granted Critical
Publication of CN106032692B publication Critical patent/CN106032692B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses a kind of integral type pouring molding construction method of reinforced column, the integral type pouring molding construction method of this reinforced column, post steel reinforcement cage is formed by some stirrups and post steel reinforcement cage vertical reinforcement, and the termination of the skeleton reinforcing steel bar of the stirrup by forming post steel reinforcement cage sets external screw thread, outboard template is fixed through template, each Side shuttering forms the monoblock type template assembly structure with self-balancing performance after fixing respectively, the convenient monoblock type formwork structure for completing assembly, which is lifted to job site, is constructed, this construction method simplifies the site operation flow of concrete column, and the globality of structure is good, this is invented for the realm of building construction.

Description

A kind of integral type pouring molding construction method of reinforced column
Technical field
The present invention relates to the realm of building construction, is constructed more particularly to a kind of integral type pouring molding of reinforced column Method.
Background technology
Colligation vertical reinforcement and stirrup form post steel reinforcement cage to ordinary reinforced concrete post first at the construction field (site), then are cut in post Support template around face, after-pouring concrete, after concrete setting and reaching some strength requirement, then remove around column section Template.Site operation step is more, and flow is complicated, and site operation is long in time limit.
Traditional prefabricated reinforced concrete column completes above-mentioned steps in factory, and completely prefabricated reinforced column is transported Defeated then to lift installation to behind job site, the weight of transport and lifting installation is larger, and the connecting structure between prefabricated components Complexity, the stress performance and globality of structure be not good enough.
The content of the invention
To solve the above problems, present invention offer one kind can be quick by concreting after the completion of formwork structure assembly Complete the integral type pouring molding construction method of the reinforced column of construction.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of integral type pouring molding construction method of reinforced column, comprises the following steps:
1st, post steel reinforcement cage and monoblock type template assembly structure are made;
a), along concrete column length direction set some post steel reinforcement cage Vertical bar connections some along concrete column length side The stirrup be arrangeding in parallel to each other forms post steel reinforcement cage, and both ends are equipped with each stirrup and are stretched out to outside and with externally threaded skeleton Reinforcing bar;
b), post steel reinforcement cage periphery installation it is some along concrete column length direction set templates, each template by from The nut and the external screw thread connection of skeleton reinforcing steel bar that outside penetrates realize and fixed that template is stretched out at the both ends of each post steel reinforcement cage vertical reinforcement Termination;
c), the vertical shaped steel of putting more energy into being fixedly connected with two side templates is set between two adjacent templates, and by from mould The skeleton reinforcing steel bar termination that plate passes is fixed through vertical shaped steel of putting more energy into from outside by nut;
d), installation be looped around the sash shaped steel set on the outside of each template, and the skeleton reinforcing steel bar by being passed from template Termination passes through sash shaped steel, and is fixed from outside by nut, forms the concrete column reinforcing bar cage template assembly of self-balancing Structure;
2nd, the concrete column reinforcing bar cage template assembly structure is transported to job site and lifted in place;
3rd, the post steel reinforcement cage vertical reinforcement of connecting pole steel reinforcement cage;
The 4th, suspension column template and suspension column template and the shaped steel of putting more energy into of column template connecting portion are installed;
5th, the casting concrete on the inside of template, concrete and template one coagulation forming form reinforced column;
6th, after concrete setting reaches predetermined strength, vertical put more energy into shaped steel and the sash type of temperature pier template are removed Steel, move to floor recycling above.
It is further used as the improvement of technical solution of the present invention, stirrup includes some skeleton reinforcing steel bars overlapped in length and breadth, on stirrup It is additionally provided with the another plus stirrup being connected with multiple spot on stirrup.
Be further used as the improvement of technical solution of the present invention, another plus stirrup include it is some longitudinally of one another or horizontal reinforcing bar The entirety to be formed is welded and fixed, the tie point of another plus stirrup and skeleton reinforcing steel bar passes through welding or banding fixed.
The improvement of technical solution of the present invention is further used as, another plus stirrup bends the steel ring formed, steel for one by reinforcing bar Rib ring is fixed on stirrup with the dislocation of each skeleton reinforcing steel bar, and steel ring and the tie point of each skeleton reinforcing steel bar are consolidated by welding or colligation It is fixed.
The improvement of technical solution of the present invention is further used as, some sash types are provided with along the periphery of template is equidistant Steel, each sash shaped steel are close to template and vertical shaped steel of putting more energy into, and nut passes through sash shaped steel, vertical put more energy into shaped steel and mould Plate is connected with the skeleton reinforcing steel bar ends screw of stirrup both sides.
It is further used as the improvement of technical solution of the present invention, in step 1, the template passes through skeleton reinforcing steel bar with post steel reinforcement cage Both ends to draw connection formed self-balancing entirety.
It is further used as the improvement of technical solution of the present invention, is combined to form in step 1, after concreting with template whole Body, whole Transporting and lifting are installed.
Beneficial effects of the present invention:The integral type pouring molding construction method of this reinforced column, passes through some stirrups Post steel reinforcement cage is formed with post steel reinforcement cage vertical reinforcement, and the termination setting of the skeleton reinforcing steel bar of the stirrup by forming post steel reinforcement cage is outer Screw thread, outboard template is fixed through template, each Side shuttering forms the entirety with self-balancing performance after fixing respectively Formula template assembly structure, the convenient monoblock type formwork structure for completing assembly, which is lifted to job site, is constructed, this construction party Method simplifies the site operation flow of concrete column, and the globality of structure is good.
Brief description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is first embodiment of the invention overall structure top view;
Fig. 2 is second embodiment of the invention overall structure top view;
Fig. 3 is overall structure front view of the embodiment of the present invention;
Fig. 4 is that construction process of the present invention sets up process first state structural representation;
Fig. 5 is that construction process of the present invention sets up process the second status architecture schematic diagram.
Embodiment
1~Fig. 5 of reference picture, the present invention are a kind of integral type pouring molding construction method of reinforced column, including with Lower step:
1st, post steel reinforcement cage and monoblock type template assembly structure are made;
a), along concrete column length direction to set some post steel reinforcement cage vertical reinforcements 7 to connect some along concrete column length The stirrup 4 that direction is set parallel to each other forms post steel reinforcement cage, and both ends are equipped with each stirrup 4 and are stretched out to outside and with externally threaded Skeleton reinforcing steel bar 41;
b), post steel reinforcement cage periphery installation it is some along concrete column length direction set templates, each template by from The nut 5 that outside penetrates is connected realization with the external screw thread of skeleton reinforcing steel bar 41 and fixed, and the both ends of each post steel reinforcement cage vertical reinforcement 7 are stretched out The termination of template;
c), the vertical shaped steel of putting more energy into being fixedly connected with two side templates is set between two adjacent templates, and by from mould The termination of skeleton reinforcing steel bar 41 that plate passes is fixed through vertical shaped steel 6 of putting more energy into from outside by nut 5;
d), installation be looped around the sash shaped steel 8 set on the outside of each template, and the skeleton reinforcing steel bar by being passed from template 41 terminations pass through sash shaped steel 8, and are fixed from outside by nut 5, form the concrete column reinforcing bar cage template of self-balancing Splicing structure;
2nd, the concrete column reinforcing bar cage template assembly structure is transported to job site and lifted in place;
3rd, the post steel reinforcement cage vertical reinforcement of connecting pole steel reinforcement cage;
The 4th, suspension column template and suspension column template and the shaped steel of putting more energy into of column template connecting portion are installed;
5th, the casting concrete on the inside of template, concrete and template one coagulation forming form reinforced column;
6th, after concrete setting reaches predetermined strength, vertical put more energy into shaped steel and the sash type of temperature pier template are removed Steel, move to floor recycling above.
The integral type pouring molding construction method of this reinforced column, passes through some stirrups 4 and post steel reinforcement cage vertical steel Muscle 7 forms post steel reinforcement cage, and the termination of the skeleton reinforcing steel bar 41 of the stirrup 4 by forming post steel reinforcement cage sets external screw thread, through mould Outboard template is fixed plate, and each Side shuttering forms the monoblock type template assembly knot with self-balancing performance after fixing respectively Structure, the convenient monoblock type formwork structure for completing assembly, which is lifted to job site, is constructed, and this construction method simplifies concrete The site operation flow of post, and the globality of structure is good.
As the preferred embodiment of the present invention, stirrup 4 includes some skeleton reinforcing steel bars 41 overlapped in length and breadth, is gone back on stirrup 4 Provided with the another plus stirrup 42 being connected with multiple spot on stirrup 4.
As the preferred embodiment of the present invention, another plus stirrup 42 include it is some longitudinally of one another or horizontal reinforcement welding The fixed entirety formed, another plus stirrup 42 and the tie point of skeleton reinforcing steel bar 41 pass through welding or banding fixed.
As the preferred embodiment of the present invention, another plus stirrup 42 bends the steel ring formed, steel ring for one by reinforcing bar It is fixed on the dislocation of each skeleton reinforcing steel bar 41 on stirrup 4, steel ring and the tie point of each skeleton reinforcing steel bar 41 pass through welding or colligation It is fixed.
Each stirrup 4 is overlapped and is welded in length and breadth before post steel reinforcement cage is assembled into by skeleton reinforcing steel bar 41, is set on each stirrup 4 Another plus stirrup 42 is put, each another plus stirrup 42 primarily serves the intensity auxiliary humidification overall to stirrup 4, another plus stirrup 42 to set Putting can be realized by above diversified forms.
As the preferred embodiment of the present invention, some sash shaped steel 8, each water are provided with along the periphery of template is equidistant Flat shaped steel 8 of putting more energy into is close to template and vertical shaped steel 6 of putting more energy into, and nut 5 passes through sash shaped steel 8, vertical put more energy into shaped steel 6 and template It is connected with the ends screw of skeleton reinforcing steel bar 41 of the both sides of stirrup 4.
Vertical shaped steel 6 of putting more energy into is arranged between two adjacent templates, and is fixedly connected with the template of both sides, may be such that entirety Formula template forms an entirety sealed around, prevents that concrete is revealed in concreting process, meanwhile, monoblock type can be strengthened The connectivity robustness of template.
The threaded connection that the template of surrounding is provided with by termination between externally threaded skeleton reinforcing steel bar 41 and nut 5 is fixed, By being attached between adjacent template by shaped steel 6 of vertically putting more energy into, it may be such that the template of post steel reinforcement cage and periphery is formed from flat The entirety of weighing apparatus, there is more preferable stability, conveniently transported the reinforced column integrated template structure that assembly is completed, Transfer and lifting.
As the preferred embodiment of the present invention, in step 1, both ends that the template passes through skeleton reinforcing steel bar with post steel reinforcement cage To draw connection formed self-balancing entirety, can whole Transporting and lifting install, job site be not required to set template temporary support.
As the preferred embodiment of the present invention, in step 1, entirety is combined to form with template after concreting, is constructed After the completion of be not required to form removal.
Certainly, the invention is not limited to above-mentioned embodiment, and those skilled in the art are without prejudice to originally Equivalent variations or replacement can be also made on the premise of spirit, these equivalent modifications or replacement are all contained in the application right It is required that in limited range.

Claims (7)

1. a kind of integral type pouring molding construction method of reinforced column, comprises the following steps:
1st, post steel reinforcement cage and monoblock type template assembly structure are made;
A), along concrete column length direction set some post steel reinforcement cage Vertical bar connections some along concrete column length direction that This stirrup be arrangeding in parallel forms post steel reinforcement cage, and both ends are equipped with each stirrup and are stretched out to outside and with externally threaded skeleton Reinforcing bar;
B), lead in some templates set along concrete column length direction of the periphery of post steel reinforcement cage installation, each template Fixation, the both ends of each post steel reinforcement cage vertical reinforcement are realized in the external screw thread connection for crossing the nut penetrated from outside and skeleton reinforcing steel bar Stretch out the termination of template;
Characterized in that, it is further comprising the steps of,
C), the vertical shaped steel of putting more energy into being fixedly connected with two side templates is set between the two adjacent templates, and by from mould The skeleton reinforcing steel bar termination that plate passes is fixed through vertical shaped steel of putting more energy into from outside by nut;
D), installation is looped around the sash shaped steel set on the outside of each template, and the skeleton reinforcing steel bar termination by being passed from template Fixed through sash shaped steel, and from outside by nut, form the concrete column reinforcing bar cage template assembly structure of self-balancing;
2nd, the concrete column reinforcing bar cage template assembly structure is transported to job site and lifted in place;
3rd, the post steel reinforcement cage vertical reinforcement of connecting pole steel reinforcement cage;
The 4th, suspension column template and suspension column template and the shaped steel of putting more energy into of column template connecting portion are installed;
5th, the casting concrete on the inside of template, concrete and template one coagulation forming form reinforced column;
6th, after concrete setting reaches predetermined strength, vertical put more energy into shaped steel and the sash shaped steel of temperature pier template are removed, Move to floor recycling above.
2. the integral type pouring molding construction method of reinforced column according to claim 1, it is characterised in that:It is described Stirrup includes some skeleton reinforcing steel bars overlapped in length and breadth, and the another plus stirrup being connected with multiple spot on stirrup is additionally provided with the stirrup.
3. the integral type pouring molding construction method of reinforced column according to claim 2, it is characterised in that:It is described Another plus stirrup include it is some longitudinally of one another or horizontal reinforcement welding fixes the entirety to be formed, it is described separately plus stirrup and skeleton steel The tie point of muscle passes through welding or banding fixed.
4. the integral type pouring molding construction method of reinforced column according to claim 2, it is characterised in that:It is described Another plus stirrup is a steel ring formed by reinforcing bar bending, and the steel ring is fixed on stirrup with the dislocation of each skeleton reinforcing steel bar, institute State steel ring and the tie point of each skeleton reinforcing steel bar passes through welding or banding fixed.
5. the integral type pouring molding construction method of reinforced column according to claim 1, it is characterised in that:Along institute State template periphery it is equidistant be provided with some sash shaped steel, each sash shaped steel is close to template and vertical type of putting more energy into Steel, the nut pass through sash shaped steel, vertical shaped steel and template and the skeleton reinforcing steel bar ends screw company of stirrup both sides of putting more energy into Connect.
6. the integral type pouring molding construction method of reinforced column according to claim 1, it is characterised in that:It is described In step 1, the template and post steel reinforcement cage by the both ends of skeleton reinforcing steel bar to drawing connection to form self-balancing entirety, whole Transporting and Lifting installation.
7. the integral type pouring molding construction method of reinforced column according to claim 1, it is characterised in that:It is described In step 1, entirety is combined to form with template after concreting.
CN201510752765.5A 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column Active CN106032692B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510752765.5A CN106032692B (en) 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510752765.5A CN106032692B (en) 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column

Publications (2)

Publication Number Publication Date
CN106032692A CN106032692A (en) 2016-10-19
CN106032692B true CN106032692B (en) 2018-01-09

Family

ID=57148999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510752765.5A Active CN106032692B (en) 2015-11-06 2015-11-06 A kind of integral type pouring molding construction method of reinforced column

Country Status (1)

Country Link
CN (1) CN106032692B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107288261A (en) * 2017-07-03 2017-10-24 广州容联建筑科技有限公司 A kind of construction method of reinforced column cavity
CN107435415A (en) * 2017-07-03 2017-12-05 广州容联建筑科技有限公司 A kind of reinforced column and construction method for building industrialization
CN107313554A (en) * 2017-08-10 2017-11-03 滨州学院 A kind of reinforced column constructing device of free removal template
TWI661109B (en) * 2017-08-17 2019-06-01 Ruentex Engineering & Construction Co., Ltd. Method of assembling column stirrups
CN110206227A (en) * 2019-05-10 2019-09-06 中天建设集团有限公司 A kind of superelevation column template reinforcing bar integral hoisting construction method
CN110206230B (en) * 2019-06-10 2023-05-16 上海建工四建集团有限公司 Concrete column reinforcement cage and formwork system integrated structure and construction method
CN110206229B (en) * 2019-06-10 2023-07-18 上海建工四建集团有限公司 Concrete column assembly structure and construction method thereof
CN110552497A (en) * 2019-09-19 2019-12-10 武汉悉道建筑科技有限公司 light steel keel building template and manufacturing method thereof
CN110512860A (en) * 2019-09-19 2019-11-29 武汉悉道建筑科技有限公司 A kind of reinforcing bar integrated template system and preparation method thereof
CN114482550B (en) * 2021-12-31 2024-03-22 华能国际电力股份有限公司上海石洞口第一电厂 Concrete ultra-high column pouring construction method
CN115288507B (en) * 2022-07-25 2023-09-12 中建八局深圳科创发展有限公司 Cast-in-situ river stone landscape column and construction method thereof
CN115110576B (en) * 2022-07-26 2024-03-01 中铁广州工程局集团有限公司 Integral forming construction method for frame column and base layer of underground garage
CN115492309B (en) * 2022-10-31 2023-06-13 中国十九冶集团有限公司 Reinforcement cage expansion structure and construction method for installing box-type steel column in reinforcement cage

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1876996A (en) * 2006-07-04 2006-12-13 朱秦江 Integrally-cast mould-detachment-free concrete structure system and construction method thereof
CN101818539A (en) * 2010-06-04 2010-09-01 北京万科企业有限公司 Assembled integral building and construction method thereof
CN201649631U (en) * 2010-04-07 2010-11-24 南通建工集团股份有限公司 T-shaped pole template system protruding from the exterior wall
CN201826439U (en) * 2010-10-18 2011-05-11 清华大学 Assembled self-compaction steel tube concrete combined structure
CN103938797A (en) * 2014-04-04 2014-07-23 北京工业大学 Heat-preserving recycled concrete rectangular column with dismantling-free high performance cement mortar mold plate and manufacturing method
CN105019600A (en) * 2015-08-04 2015-11-04 万保金 Disassembly-free precast concrete frame column template

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7882669B2 (en) * 2006-05-18 2011-02-08 Ping Qu Composite concrete shear wall for heat insulation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1876996A (en) * 2006-07-04 2006-12-13 朱秦江 Integrally-cast mould-detachment-free concrete structure system and construction method thereof
CN201649631U (en) * 2010-04-07 2010-11-24 南通建工集团股份有限公司 T-shaped pole template system protruding from the exterior wall
CN101818539A (en) * 2010-06-04 2010-09-01 北京万科企业有限公司 Assembled integral building and construction method thereof
CN201826439U (en) * 2010-10-18 2011-05-11 清华大学 Assembled self-compaction steel tube concrete combined structure
CN103938797A (en) * 2014-04-04 2014-07-23 北京工业大学 Heat-preserving recycled concrete rectangular column with dismantling-free high performance cement mortar mold plate and manufacturing method
CN105019600A (en) * 2015-08-04 2015-11-04 万保金 Disassembly-free precast concrete frame column template

Also Published As

Publication number Publication date
CN106032692A (en) 2016-10-19

Similar Documents

Publication Publication Date Title
CN106032692B (en) A kind of integral type pouring molding construction method of reinforced column
CN106032706B (en) A kind of integral type pouring molding construction method of reinforced concrete shear wall
CN106906955B (en) Shear wall integral prefabricated reinforcement mesh structure and construction method thereof
CN108867943A (en) Prefabricated sandwich wall and prefabricated sandwich wall production method
CN108867935A (en) L shape connecting structure of wall and assembled arthitecutral structure system
CN107460993A (en) A kind of construction method of reinforced beam for building industrialization
CN205153536U (en) Structure is assembled to self -balancing integral template of reinforced concrete roof beam
CN107345434A (en) Construction method for the reinforced concrete wall of building industrialization
CN110747736A (en) Rigid skeleton integrated device integrated with lifting appliance and steel reinforcement cage lifting construction method
CN106049719B (en) A kind of self-balancing monoblock type template assembly structure of reinforced concrete shear wall
CN205153535U (en) Structure is assembled to reinforced concrete column's self -balancing integral template
CN106032705B (en) A kind of integral type pouring molding construction method of reinforced concrete floor
CN206941959U (en) A kind of reinforced beam cavity body structure
CN106032701B (en) A kind of self-balancing monoblock type template assembly structure of reinforced column
CN212405468U (en) Stiff concrete structure beam column core area structure
CN108867934A (en) T shape connecting structure of wall and assembled arthitecutral structure system
CN207739390U (en) Overlap wall and horizontal member connecting node
CN206971556U (en) A kind of reinforced column cavity body structure
CN106032702B (en) A kind of self-balancing monoblock type template assembly structure of reinforced beam
CN207647031U (en) A kind of reinforced column shaft segment structure for building industrialization
CN207079770U (en) A kind of T-shaped reinforced concrete wall cavity body structure
CN207686134U (en) A kind of armored concrete girder construction for building industrialization
CN107471423A (en) A kind of construction method of reinforced beam cavity
CN211473348U (en) Scaffold wall connecting piece
CN205153221U (en) Structure is assembled to self -balancing integral template of reinforced concrete shear force wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant