CN105952449A - Novel dry-type stoping method for tailings in tailing pond - Google Patents

Novel dry-type stoping method for tailings in tailing pond Download PDF

Info

Publication number
CN105952449A
CN105952449A CN201610309725.8A CN201610309725A CN105952449A CN 105952449 A CN105952449 A CN 105952449A CN 201610309725 A CN201610309725 A CN 201610309725A CN 105952449 A CN105952449 A CN 105952449A
Authority
CN
China
Prior art keywords
tailings
dam
granular
road
back production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610309725.8A
Other languages
Chinese (zh)
Other versions
CN105952449B (en
Inventor
秦柯
汪斌
朱君星
周玉新
段蔚平
汪良峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Original Assignee
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinosteel Maanshan General Institute of Mining Research Co Ltd filed Critical Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority to CN201610309725.8A priority Critical patent/CN105952449B/en
Publication of CN105952449A publication Critical patent/CN105952449A/en
Application granted granted Critical
Publication of CN105952449B publication Critical patent/CN105952449B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/227Gutters; Channels ; Roof drainage discharge ducts set in sidewalks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C9/00Special pavings; Pavings for special parts of roads or airfields
    • E01C9/08Temporary pavings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Remote Sensing (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a novel dry-type stoping method for tailings in a tailing pond. The tailing pond is investigated, gravels are used for laying of temporary gravel roads (1) from tailing pond dam bodies to a tailing pond drainage well (2), and the temporary gravel roads (1) are taken as temporary construction roads; temporary drainage ditches are dug on two sides of each road by means of mechanical digging equipment; to-be-stoped tailings under tailing pond beaches (3) on two sides of each temporary gravel road (1) are dug in each area by means of a digging machine after water accumulated in the tailing pond is drained off; after stoping in one area is finished, stoping is performed in another area until the tailings in all the areas on the layer are stoped; tailings on two sides of each temporary gravel road on a lower layer are dug in each area until tailings in the tailing pond are all exploited. The stoping work of the tailings in the tailing pond is finished on a large scale quickly and efficiently, the stoping efficiency of the tailings in the tailing pond is improved, the stoping cost is reduced, and the stoping time is saved.

Description

A kind of new method of Tailings dry type back production
Technical field
The invention belongs to mine tailing actual mining technology field, be specifically related to the dry type back production side of a kind of mine tailing Method, is particularly suited for that Tailings beach face foundation bearing capacity is less, requires that the duration is shorter, tail The middle-size and small-size Tailings back production engineering that ore deposit volume of cargo in storage is little.
Background technology
At present, China in Tailings back production, the mode of mine tailing back production mainly have hydromining, Ship is adopted and dry adopts three kinds of modes.
Hydromining is by mean of water pump pressurization, produces high-velocity flow motive force and tail by giant Mine tailing is impacted avalanche by the gravity in ore deposit itself makes mine tailing broken apart out, is characterized in producing energy Power is big, and cost is relatively low, and screening debris removal equipment is simple, is particularly suitable for depositing the most cementing comparison Serious mine tailing;But the technology of hydromining requires higher, need according to production efficiency and safety Situation adjusts hydraulic giant angle and safe distance in good time.
It is to use dredger or sand dredger to exploit, before exploitation according to the dass of regulation that ship is adopted Digging order, dass width and excavating depth need to be preset, when using ship to adopt in Tailings Dam Need to keep certain water level, monolayer working thickness, typically at about 1.0m, is characterized in producing Ability is big, and labor productivity is high, and management is easy in the concentration of production;Shortcoming is that use condition compares Strictly, affected bigger by reservoir area landform, lithology and temperature.
Dry i.e. machine instruction statement mining of adopting, uses the excavation equipment such as bull-dozer and excavator excavation mine tailing, then Directly mine tailing is loaded means of transport by loading machine, be characterized in that production technology is simple, spirit Living, Comparison of Management is easy, and the suitability is the strongest, but is required to affect by foundation bearing capacity, Dry adopting generally requires after mine tailing beach face consolidation strength by the time meets plant equipment admission minimum requirements Can exploit.Such as phase " mine tailing safety coal extraction in " Modern Mineral " February the 2nd in 2013 Engineering practice " literary composition introduces mine tailing stoping scheme, this stoping scheme uses " to be excavated Dress+belt-conveying+Automobile Transportation adopted by machine " strip mining transformation mode, first enter in Tailings Dam Row draining, makes mine tailing consolidate, and makes equipment fell and transport under mine tailing drainage state, is directly loaded up Outward transport, or reprint, behind interim stockyard, twice loading is transported outward.This stoping scheme technique is simpler Single, but equally exist the problem of the time length of Tailings Dam draining, mine tailing consolidation, mine tailing drainage, The Tailings Dam back production time is long.
Summary of the invention
The purpose of the present invention is aiming at the problems referred to above that prior art exists, and provides a kind of energy Enough Tailings dry types completing Tailings back production engineering quickly, efficiently, on a large scale The new method of back production.
For realizing the purpose of the present invention, the new method of the present invention a kind of Tailings dry type back production Realized by following technique, step:
1) Tailings Dam investigation: tailings warehouse dam body stability, mode of drainning off floodwaters, flood drainage system are had Effect property, Tailings Dam beach face foundation bearing force intensity, reservoir area depth of accumulated water carry out system investigation, for Tails dry back production provides basic data.
2) construction road is laid and back production Division: use rubble from tailings warehouse dam body to mine tailing Gully direction, the storehouse interim granular-type road of laying is as temporary construction road, and have a lot of social connections 4-10m in road, Higher than Tailings Dam beach face 0.8-1.2m;The interim granular-type road laid with Tailings Dam gully is Center becomes radial arrangement to the tailings warehouse dam body of surrounding, is divided into some by whole Tailings Dam beach face Individual region, the angle between adjacent interim granular-type road is according to Tailings Dam gully and tailing dam The distance of body dam facing determines.
Angle between adjacent interim granular-type road is typically between 5-20 °.When Tailings Dam is arranged During the distance L≤100m of well and tailings warehouse dam body dam facing, between adjacent interim granular-type road Angle takes 15-20 °;Distance 100 < L when Tailings Dam gully Yu tailings warehouse dam body dam facing Angle 10-15 ° during≤150m, between adjacent interim granular-type road;When Tailings Dam gully During with the distance L > 150m of tailings warehouse dam body dam facing, the angle between adjacent interim granular-type road Take 5-10 °.
3) in Tailings Dam gully periphery 15m, mine tailing uses manually or small-sized machine excavation transports, Hand excavation's degree of depth is 0.5-1.5m, and small-sized machine cutting depth 1.0-3.0m makes Tailings Dam The minimum point of Tailings Dam beach face is become, it is simple to storehouse internal water accumulation is discharged in gully periphery 15m.
Described mini-excavator tool refers to quality < 10.0T, bucket capacity < 0.5m3Excavator.
4) excavation machinery is utilized to excavate temporary drain, temporary drain in road both sides Deep 1.0-1.5m, wide 1.0-2.0m, form 0.5%-2.0%'s to Tailings Dam gully direction Descending grade, it is simple to reservoir area beach face hydrops collects to gully direction, to accelerate storehouse internal water accumulation discharge.
Described excavation machinery refers to the excavator of various model, sliding loader etc..
5), after reservoir area internal water accumulation drains, utilize the excavation machinery that the radius of clean-up is bigger to the most broken Back production mine tailing for the treatment of under the Tailings Dam beach face of stone road both sides carries out subregion excavation, and cutting depth controls Cutting depth 3-6m in the range of 15m around 1-4m, gully, when a region completes back Enter next region after adopting and carry out back production, until this layer of all regions mine tailing back production completes.
6) after one layer of mine tailing back production terminates, interim granular-type road is excavated, take its rubble at it The interim granular-type road of lower floor is laid in side, and excavates lower floor's temporary drain, repeats above-mentioned 5) The mine tailing of step granular-type road interim to lower floor both sides carries out subregion excavation, until Tailings Full extraction terminates.
Described rubble be the one or both in waste mining rock, outsourcing block stone, refuse dump barren rock, The mixture of three, the uniaxial compressive strength of rubble is 10-60Mpa, particle diameter is 2-30cm.
The new method of the present invention a kind of Tailings dry type back production, uses above technical scheme After, have the positive effect that: by investigating Tailings Dam, temporary road is laid, excavator Tool is directly entered Tailings Dam central area and carries out tailings mining, accelerates Tailings Dam drawing speed, Shorten the exploitation duration, solve conventional dry back production effective time short problem, reduce Dry type back production requirement to foundation bearing capacity in Tailings Dam is applied, thus quickly, efficiently, greatly Complete to scale Tailings Dam tailings actual mining, improve Tailings Dam tailings back production efficiency, reduce back Adopt cost, save the back production time, there is adaptability widely.
Accompanying drawing explanation
Fig. 1 is the new method horizontal layout signal of the present invention a kind of Tailings dry type back production Figure;
Fig. 2 is A-A generalized section in Fig. 1.
Reference is: the interim granular-type road of 1-;2-Tailings Dam gully;3-Tailings Dam Beach face;4-temporary drain;5-treats back production mine tailing;The interim granular-type road of 6-lower floor;7 -lower floor temporary drain;8-tailings warehouse dam body.
Detailed description of the invention
For further describing the present invention, below in conjunction with the accompanying drawings, to one Tailings of the present invention The new method of dry type back production is for a more detailed description.
The new method planar cloth of the present invention a kind of Tailings dry type back production as shown in Figure 1 Put schematic diagram and combine Fig. 2 and find out, the new method of the present invention a kind of Tailings dry type back production Including following technique, step:
To tailings warehouse dam body stability, mode of drainning off floodwaters, flood drainage system effectiveness, Tailings Dam beach face Foundation bearing force intensity, reservoir area depth of accumulated water carry out system investigation, provide for tails dry back production Basic data.
Rubble is used to lay some temporarily from tailings warehouse dam body to Tailings Dam gully 2 direction Granular-type road 1 is as temporary construction road, and have a lot of social connections 4-10m in road, higher than Tailings Dam beach face 3 by 1 Rice;Lay interim granular-type road 1 centered by Tailings Dam gully 2 to the Tailings Dam of surrounding Dam body 8 becomes radial arrangement, and whole Tailings Dam beach face 3 is divided into several regions, adjacent faces Time granular-type road 1 between angle according to Tailings Dam gully 2 and tailings warehouse dam body 8 dam facing Distance determines.
In Tailings Dam gully 2 periphery 15m, mine tailing uses small-sized machine excavation to transport, and excavation is deep Degree 1.0-3.0m, becomes Tailings Dam beach face 3 in making Tailings Dam gully 2 periphery 15m Low spot.
Excavation machinery is utilized to excavate temporary drain 4, temporary drain 4 in road both sides Deep 1.0-1.5m, wide 1.0-2.0m, form 0.5%-2.0% to Tailings Dam gully 2 direction Descending grade (that is: the percentage ratio of the gradient height of temporary drain 4 and horizontal range ratio).
After reservoir area internal water accumulation drains, utilize the radius of clean-up at the excavation machinery of 5-15m scope to facing Time granular-type road 1 both sides Tailings Dam beach face 3 under treat that back production mine tailing 5 carries out subregion excavation, open Dig severity control at 1-4m, wherein around gully in the range of 15m cutting depth more than monolayer Tailings cutting depth 2m, enters next region after a region completes back production and carries out back production, Until this layer of all regions mine tailing back production completes.
After one layer of mine tailing back production terminates, interim granular-type road 1 is excavated, take its rubble at one The interim granular-type road of lower floor 6 is laid in side, and excavates lower floor's temporary drain 7, repeats above step The mine tailing of rapid granular-type road 6 both sides interim to lower floor carries out subregion excavation, until Tailings Full extraction terminates.

Claims (5)

1. the new method of a Tailings dry type back production, it is characterised in that by following work Skill, step realize:
1) Tailings Dam investigation: tailings warehouse dam body stability, mode of drainning off floodwaters, flood drainage system are had Effect property, Tailings Dam beach face foundation bearing force intensity, reservoir area depth of accumulated water carry out system investigation, for Tails dry back production provides basic data;
2) construction road is laid and back production Division: use rubble from tailings warehouse dam body to mine tailing Interim granular-type road (1) is laid as temporary construction road, road in storehouse gully (2) direction Wide 4-10m, higher than Tailings Dam beach face (3) 0.8-1.2m;The interim granular-type road (1) laid Radial arrangement is become to the tailings warehouse dam body (8) of surrounding centered by Tailings Dam gully (2), Whole Tailings Dam beach face (3) is divided into several regions, adjacent interim granular-type road (1) it Between angle determine according to the distance of Tailings Dam gully (2) with tailings warehouse dam body (8) dam facing;
3) in Tailings Dam gully (2) periphery 15m, mine tailing uses artificial or small-sized machine excavation Transporting, hand excavation's degree of depth is 0.5-1.5m, and small-sized machine cutting depth 1.0-3.0m makes The minimum point of Tailings Dam beach face (3) is become in Tailings Dam gully (2) periphery 15m;
4) utilize excavation machinery in road both sides excavation temporary drain (4), arrange temporarily Ditch (4) deep 1.0-1.5m, wide 1.0-2.0m, to Tailings Dam gully (2) direction shape Become the descending grade of 0.5%-2.0%;
5), after reservoir area internal water accumulation drains, utilize excavation machinery to interim granular-type road (1) both sides Back production mine tailing (5) for the treatment of under Tailings Dam beach face (3) carries out subregion excavation, and cutting depth controls Cutting depth 3-6m in the range of 15m around 1-4m, gully, when a region completes back Enter next region after adopting and carry out back production, until this layer of all regions mine tailing back production completes;
6), after one layer of mine tailing back production terminates, interim granular-type road (1) is excavated, takes its rubble Lay the interim granular-type road of lower floor (6) in its side, and excavate lower floor's temporary drain (7), Repeating above-mentioned 5) mine tailing of step granular-type road interim to lower floor (6) both sides carries out subregion and opens Dig, until Tailings full extraction terminates.
The new method of a kind of Tailings dry type back production the most as claimed in claim 1, it is special Levy and be: the described angular range between adjacent interim granular-type road (1) 5-20 ° it Between.
The new method of a kind of Tailings dry type back production the most as claimed in claim 3, it is special Levy and be: as the distance L≤100m of Tailings Dam gully (2) Yu tailings warehouse dam body (8) dam facing Time, the angle between adjacent interim granular-type road (1) takes 15-20 °;When Tailings Dam draining During the distance 100 < L≤150m of well (2) and tailings warehouse dam body (8) dam facing, adjacent temporarily Angle 10-15 ° between granular-type road (1);When Tailings Dam gully (2) and Tailings Dam During the distance L > 150m of dam body (8) dam facing, the folder between adjacent interim granular-type road (1) Angle takes 5-10 °.
4. the new side of a kind of Tailings dry type back production as described in claim 1,2 or 3 Method, it is characterised in that: described rubble is in waste mining rock, outsourcing block stone, refuse dump barren rock One or both, the mixture of three, the uniaxial compressive strength of rubble be 10-60Mpa, Particle diameter is 2-30cm.
5. the new side of a kind of Tailings dry type back production as described in claim 1,2 or 3 Method, it is characterised in that: described excavation machinery refers to excavator, and the radius of clean-up is at 5-15m model Enclose.
CN201610309725.8A 2016-05-10 2016-05-10 A kind of new method of Tailings dry type back production Active CN105952449B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610309725.8A CN105952449B (en) 2016-05-10 2016-05-10 A kind of new method of Tailings dry type back production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610309725.8A CN105952449B (en) 2016-05-10 2016-05-10 A kind of new method of Tailings dry type back production

Publications (2)

Publication Number Publication Date
CN105952449A true CN105952449A (en) 2016-09-21
CN105952449B CN105952449B (en) 2018-04-10

Family

ID=56912420

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610309725.8A Active CN105952449B (en) 2016-05-10 2016-05-10 A kind of new method of Tailings dry type back production

Country Status (1)

Country Link
CN (1) CN105952449B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905511A (en) * 2019-11-22 2020-03-24 西北矿冶研究院 Dry tailing stoping method for valley type tailing pond based on underground water drainage
CN114263460A (en) * 2021-12-06 2022-04-01 山东金岭矿业股份有限公司 Method for stoping mountainside type tailing pond

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101570822A (en) * 2009-06-15 2009-11-04 北京科技大学 Hydraulic method for constructing mine pile
CN102003185A (en) * 2010-11-05 2011-04-06 中蓝连海设计研究院 Sublevel stripe tail salt stoping dry-type filling-mining method
CN103967495A (en) * 2014-04-16 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Stoping technology for dam slope tailing of tailing dam
CN104195913A (en) * 2014-08-19 2014-12-10 中冶天工上海十三冶建设有限公司 Movable temporary road structure
CN105040711A (en) * 2015-06-25 2015-11-11 中钢集团马鞍山矿山研究院有限公司 Method for strengthening dry tailing storage yard by utilizing barren rocks

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101570822A (en) * 2009-06-15 2009-11-04 北京科技大学 Hydraulic method for constructing mine pile
CN102003185A (en) * 2010-11-05 2011-04-06 中蓝连海设计研究院 Sublevel stripe tail salt stoping dry-type filling-mining method
CN103967495A (en) * 2014-04-16 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Stoping technology for dam slope tailing of tailing dam
CN104195913A (en) * 2014-08-19 2014-12-10 中冶天工上海十三冶建设有限公司 Movable temporary road structure
CN105040711A (en) * 2015-06-25 2015-11-11 中钢集团马鞍山矿山研究院有限公司 Method for strengthening dry tailing storage yard by utilizing barren rocks

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905511A (en) * 2019-11-22 2020-03-24 西北矿冶研究院 Dry tailing stoping method for valley type tailing pond based on underground water drainage
CN110905511B (en) * 2019-11-22 2021-04-20 西北矿冶研究院 Dry tailing stoping method for valley type tailing pond based on underground water drainage
CN114263460A (en) * 2021-12-06 2022-04-01 山东金岭矿业股份有限公司 Method for stoping mountainside type tailing pond
CN114263460B (en) * 2021-12-06 2023-11-17 山东金岭矿业股份有限公司 Stoping method for mountain-side tailing pond

Also Published As

Publication number Publication date
CN105952449B (en) 2018-04-10

Similar Documents

Publication Publication Date Title
CN108457277A (en) A kind of a wide range of deep & thick silt excavation construction method
CN103388478B (en) Forming method for transportation road of bucket shovel applied to open pit coal mine
CN106014409B (en) New method suitable for flat type Tailings dry type back production
CN103397646B (en) Technique for fast filling constructed wetland in shore area
CN114293990A (en) Method for filling open pit
CN105952449A (en) Novel dry-type stoping method for tailings in tailing pond
CN112112657B (en) New construction method for digging and building inclined shaft of coal mine
CN112663558B (en) Construction process for excavating weathered rock in inland river harbor pool
CN110905511B (en) Dry tailing stoping method for valley type tailing pond based on underground water drainage
Adamo et al. Comparative study of mosul and haditha dams in Iraq: different construction materials contribute to different designs
CN105442621A (en) Stock ground mining method under complex geological condition state
CN111852554B (en) Rapid trenching method for large water inrush quantity pit open-pit mine small-block full-section deep one-time blasting
CN111852555B (en) Trenching method for one-time blasting layered shovel loading of large water inrush sunken strip mine
CN100582382C (en) Process for constructing quickly consolidated temperory horizontal platform by picking clay of lake bottom
CN1814918A (en) Earthwork construction method
RU2661950C1 (en) Hydraulic fill re-laying method
RU2261331C2 (en) Open-cast mining method
CN114263460B (en) Stoping method for mountain-side tailing pond
RU2199011C1 (en) Method of tailing dump working
CN112459552B (en) Production waste residue protection structure of large sand aggregate processing system and construction method
CN1174281A (en) Exploitation of placer mine by means of special tunnel and drainage method
CN116517546A (en) Tailing pond tailing mixed recovery process method
CN111022062B (en) Construction method for clay layer section of ramp
Černoch et al. Preparations for remediation of a former surface mine–a technical reclamation area
Lane et al. Tuttle Creek Dam of rolled shale and dredged sand

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666

Patentee after: MAANSHAN Mine Research Institute Co.,Ltd.

Address before: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666

Patentee before: SINOSTEEL MAANSHAN INSTITUTE OF MINING RESEARCH Co.,Ltd.

CP01 Change in the name or title of a patent holder