CN105951604B - A kind of bridge pier modular system - Google Patents

A kind of bridge pier modular system Download PDF

Info

Publication number
CN105951604B
CN105951604B CN201610442985.2A CN201610442985A CN105951604B CN 105951604 B CN105951604 B CN 105951604B CN 201610442985 A CN201610442985 A CN 201610442985A CN 105951604 B CN105951604 B CN 105951604B
Authority
CN
China
Prior art keywords
branch
bridge pier
bottom plate
sizing
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610442985.2A
Other languages
Chinese (zh)
Other versions
CN105951604A (en
Inventor
张素琴
王源
李华
李玉奇
付岩石
张国锋
李雪荣
韩莉
张永福
李孟奇
张丽
李怡琳
多玉清
彭五四
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Duo Yuqing
Fu Yanshi
Han Li
Li Hua
Li Xuerong
Li Yilin
Li Yuqi
Wang Yuan
Zhang Guofeng
Zhang Li
Zhang Yongfu
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610442985.2A priority Critical patent/CN105951604B/en
Publication of CN105951604A publication Critical patent/CN105951604A/en
Application granted granted Critical
Publication of CN105951604B publication Critical patent/CN105951604B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of bridge pier modular system, including bottom plate;The lower face both sides of bottom plate are symmetrically installed there are four universal wheel;Upper surface front side, rear side, the left side of bottom plate be respectively mounted there are one sizing branch;Sizing branch includes the baffle being welded on bottom plate, baffle is equipped with leading screw by bearing, the end of leading screw is equipped with driving motor by shaft coupling, driving motor is mounted on by motor cabinet on bottom plate, the middle part of leading screw is equipped with sliding block by screw thread, the both ends of sliding block are symmetrically welded with two L-type gag lever posts, the end of two L-type gag lever posts is separately mounted on two line slide rails, two line slide rails are separately mounted on bottom plate, the upper surface of two L-type gag lever posts is respectively welded two fore-sets, and the upper end of sliding block is welded with square installing plate.The present invention can realize the fast construction function of mechanization, have many advantages, such as that easy to operate, labor intensity is small, service life is long, work efficiency is high and applied widely.

Description

A kind of bridge pier modular system
Technical field
The present invention relates to bridge construction field, more particularly to a kind of bridge pier modular system.
Background technology
In bridge construction field, it is typically a most important step to pour bridge pier, is the deciding factor for determining bridge quality, Building bridge pier usually first needs to build timber or bamboo is molecular pours shaping rack, and the material of shaping rack is required for preparing in advance It is good, and build to play and bother very much, labor intensity is big, and work efficiency is low, and very short by the service life of timber or bamboo, adds It is upper it is frequent expose to wind and rain, what service life of timber either bamboo can further reduce therefore be built by timber or bamboo Pouring the shaping rack service life also can be very low, if operator works on shaping rack is poured has very big security risk, sternly The physical safety for having influenced operator of weight.
The content of the invention
To solve the above-mentioned problems, the present invention provides a kind of bridge pier modular system, existing wooden or bamboo matter can be solved It pours shaping rack and exists and build trouble, build that speed is slow, labor intensity is big, work efficiency is low, service life is short and security risk The defects of big, can realize the fast construction function of mechanization, have it is easy to operate, labor intensity is small, service life is long, work The advantages that efficient and applied widely, and without manual operation, there is no any security risks, and the body of people is protected to be good for Health.
To achieve these goals, the present invention is realized using following technical scheme:A kind of bridge pier modular system, the bottom of including Plate is provided with bridge pier on the right side of the bottom plate and pours mouth;The lower face both sides of the bottom plate are symmetrically installed there are four universal wheel, are grasped The present invention can arbitrarily be moved by universal wheel by making personnel, easy to operate;Upper surface front side, rear side, the left side of the bottom plate are equal There are one sizing branch, the sizing branch sizing bridge pier of front side pours the leading flank of mouth, the sizing branch sizing bridge of rear side for installation Pier pours the trailing flank of mouth, and the sizing branch sizing bridge pier in left side pours the left surface of mouth;The sizing branch includes being welded on Baffle on bottom plate, the baffle are equipped with leading screw by bearing, and the end of the leading screw is equipped with driving electricity by shaft coupling Machine, the driving motor are mounted on by motor cabinet on bottom plate, and the middle part of the leading screw is equipped with sliding block, the cunning by screw thread The both ends of block are symmetrically welded with two L-type gag lever posts, and the end of two L-type gag lever posts is separately mounted to two line slide rails On, two L-type gag lever posts are mobile on two line slide rails so that sliding block can only be for linear motion in the horizontal plane, described two Line slide rail is separately mounted on bottom plate, and the upper surface of two L-type gag lever posts is respectively welded two fore-sets, the sliding block Upper end be welded with square installing plate;Square installing plate on each sizing branch is respectively mounted there are one positioning branch, is led to Positioning branch is crossed to position each face that bridge pier pours mouth.
As a preferred technical solution of the present invention, the positioning branch includes being welded on square installing plate side Fixed plate, the positioning plate are uniformly equipped with hydraulic cylinder successively from top to bottom;The every hydraulic cylinder is fixedly mounted on fixation On frame, fixed frame plays the role of supporting cylinder so that hydraulic cylinder at work can only be along specific horizontal linear direction Movement;The fixed frame is welded on square installing plate;The telescopic rod of the every hydraulic cylinder is installed on stereotype plate, sizing Each shielding surface when plate is poured as bridge pier.
As a preferred technical solution of the present invention, two fore-set upper surfaces on each sizing branch, which are supported, examines On the lower face of corresponding square installing plate, two fore-sets play the role of supporting square installing plate, prevent when pouring bridge pier The phenomenon that being difficult to support due to the excessive square installing plate of internal stress.
As a preferred technical solution of the present invention, the lower face of the stereotype plate is far below the lower face of bottom plate, but It is that the lower face height of stereotype plate is slightly above ground, the shielding surface that stereotype plate bridge pier the most pours.
In use, two bridge pier modular systems to be placed in the position of required bridge pier construction in opposite directions first, institute is determined The size and size of bridge pier are needed, the position of each sizing branch is then adjusted according to the size of required bridge pier and size, is first adjusted The position of the sizing branch in left side, driving motor are started to work, and driving motor drives leading screw to rotate, and leading screw band movable slider moves, Since two L-type gag lever posts of sliding block both sides move on two line slide rails so that sliding block can only make straight line in the horizontal plane Movement, the square installing plate above sliding block are stopped after moving to suitable position, then adjust two bridges successively again Sizing branch on the front side of pier modular system, trailing flank and right flank, after sizing branch is regulated;Start to adjust positioning Branch first starts to adjust the positioning branch in left side, and the hydraulic cylinder corresponded in fixed plate is started to work, and hydraulic cylinder drives determining for front side Template pours mouth movement in bridge pier, and hydraulic cylinder is stopped when the position of stereotype plate is adjusted to required position, then again successively The positioning branch on the front side, trailing flank and right flank of two bridge pier modular systems is adjusted, is propped up when regulating all positioning After chain, the space formed between the stereotype plate on each positioning branch is exactly the mouth that pours of required bridge pier, easy to operate, is applicable in model It encloses wide, solves existing wooden or bamboo matter and pour shaping rack and exist and build trouble, build that speed is slow, labor intensity is big, work effect The defects of rate is low, service life is short and security risk is big realizes the fast construction function of mechanization, have labor intensity it is small, The advantages that service life is grown and work efficiency is high, and without manual operation there is no any security risk, protects the body of people Body health.
The beneficial effects of the present invention are:Compared with prior art, the present invention is by individually adjusting sizing branch by the present invention Mode so that the required each sizing position of the present invention is able to quickly determine, and employs the mode of mechanization adjusting, size With size can according to demand depending on, use scope is wide, easy to operate;It is each fixed to be adjusted again after the position in the sizing face of regulating Position branch just, solve existing wooden or bamboo matter pour shaping rack exist build trouble, build speed is slow, labor intensity is big, The defects of work efficiency is low, service life is short and security risk is big realizes the fast construction function of mechanization, has work by force The advantages that small, service life is long and work efficiency is high is spent, and without manual operation, there is no any security risks, protect people Health.
Description of the drawings
The present invention is further described with reference to the accompanying drawings and examples.
Fig. 1 is the dimensional structure diagram of the present invention;
Fig. 2 is the structure diagram after present invention removal positioning branch;
Fig. 3 is the structure diagram after present invention removal positioning branch and square installing plate;
Top view when Fig. 4 is present invention work.
Specific embodiment
In order to be easy to understand the technical means, the creative features, the aims and the efficiencies achieved by the present invention, tie below Conjunction is specifically illustrating, and the present invention is further explained.It should be noted that in the case where there is no conflict, embodiment in the application and Feature in embodiment can be combined with each other.
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of bridge pier modular system, including bottom plate 1, the right side of the bottom plate 1 is provided with bridge Pier pours mouth;The lower face both sides of the bottom plate 1 are symmetrically installed there are four universal wheel 2, and operating personnel can be with by universal wheel 2 The mobile present invention of meaning, it is easy to operate;Upper surface front side, rear side, the left side of the bottom plate 1 are respectively mounted there are one sizing branch 3, preceding The sizing branch 3 sizing bridge pier of side pours the leading flank of mouth, and the sizing branch 3 sizing bridge pier of rear side pours the trailing flank of mouth, left The sizing branch 3 sizing bridge pier of side pours the left surface of mouth;The sizing branch 3 includes the baffle 31 being welded on bottom plate 1, institute It states baffle 31 and leading screw 32 is equipped with by bearing, the end of the leading screw 32 is equipped with driving motor 33 by shaft coupling, described Driving motor 33 is mounted on by motor cabinet on bottom plate 1, and the middle part of the leading screw 32 is equipped with sliding block 34, the cunning by screw thread The both ends of block 34 are symmetrically welded with two L-type gag lever posts 35, and the end of two L-type gag lever posts 35 is separately mounted to two directly On line slide 36, two L-type gag lever posts 35 are mobile on two line slide rails 36 so that sliding block 34 can only be made directly in the horizontal plane Line moves, and described two line slide rails 36 are separately mounted on bottom plate 1, and the upper surface of two L-type gag lever posts 35 is welded respectively Two fore-sets 37 are connected to, the upper end of the sliding block 34 is welded with square installing plate 38;Square peace on each sizing branch 3 Loading board 38 is respectively mounted there are one positioning branch 4, and each face that bridge pier pours mouth is positioned by positioning branch 4.
The positioning branch 4 includes being welded on fixed plate 41 on 38 side of square installing plate, and the positioning plate 41 is from upper Hydraulic cylinder 42 is uniformly installed successively under;The every hydraulic cylinder 42 is fixedly mounted on fixed frame 43, and fixed frame 43 rises To the effect of supporting cylinder 42 so that hydraulic cylinder 42 can only move at work along specific horizontal linear direction;It is described Fixed frame 43 is welded on square installing plate 38;The telescopic rod of the every hydraulic cylinder 42 is installed on stereotype plate 44, sizing Each shielding surface when plate 44 is poured as bridge pier.
Two 37 upper surfaces of fore-set on each sizing branch 3, which are supported, examines in the lower face of corresponding square installing plate 38 On, two fore-sets 37 play the role of supporting square installing plate 38, prevent when pouring bridge pier due to the excessive square peace of internal stress The phenomenon that loading board 38 is difficult to support.
The lower face of the stereotype plate 44 is far below the lower face of bottom plate 1, but the lower face of stereotype plate 44 height is slightly higher In ground, shielding surface that the bridge pier the most of stereotype plate 44 pours.
As shown in Figure 1, Figure 2, Figure 3, Figure 4, in use, being first placed in two bridge pier modular systems in opposite directions required The position of bridge pier construction determines the size and size of required bridge pier, is then adjusted according to the size of required bridge pier and size each The position of sizing branch 3 first adjusts the position of the sizing branch 3 in left side, and driving motor 33 is started to work, and driving motor 33 drives Leading screw 32 rotates, and leading screw 32 is moved with movable slider 34, since two L-type gag lever posts 35 of 34 both sides of sliding block are in two line slide rails It is moved on 36 so that sliding block 34 can only be for linear motion in the horizontal plane, when the square installing plate 38 of 34 top of sliding block moves to It is stopped after suitable position, on the front side, trailing flank and right flank for then adjusting two bridge pier modular systems successively again Sizing branch 3, when regulate sizing branch 3 after;Start to adjust positioning branch 4, first start to adjust the positioning branch in left side 4, the hydraulic cylinder 42 corresponded in fixed plate 41 is started to work, and hydraulic cylinder 42 drives the stereotype plate 44 of front side to pour mouth in bridge pier and moves Dynamic, hydraulic cylinder 42 is stopped when the position of stereotype plate 44 is adjusted to required position, then adjusts two bridges successively again Positioning branch 4 on the front side of pier modular system, trailing flank and right flank, after all positioning branch 4 are regulated, each positioning The space formed between stereotype plate 44 on branch 4 is exactly the mouth that pours of required bridge pier, easy to operate, applied widely, is solved Existing wooden or bamboo matter, which pours shaping rack and exists, builds trouble, builds that speed is slow, labor intensity is big, work efficiency is low, uses The defects of short life and big security risk, realizes the fast construction function of mechanization, has that labor intensity is small, service life is long With work efficiency it is high the advantages that, and without manual operation, there is no any security risks, protect the health of people, reach Purpose is arrived.
The basic principles, main features and advantages of the invention have been shown and described above.The technical staff of the industry should Understand, the present invention is not limited to the above embodiments, and the description in above embodiments and description simply illustrates the present invention Principle, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these change and change Into all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appended claims and its equivalent It defines.

Claims (1)

1. a kind of method of work of bridge pier modular system, it is characterised in that:The equipment includes bottom plate, and the right side of the bottom plate is set There is bridge pier to pour mouth;The lower face both sides of the bottom plate are symmetrically installed there are four universal wheel;On front side of the upper surface of the bottom plate, after Side, left side be respectively mounted there are one sizing branch;The sizing branch includes the baffle being welded on bottom plate, and the baffle passes through axis It holds and leading screw is installed, the end of the leading screw is equipped with driving motor by shaft coupling, and the driving motor is pacified by motor cabinet On bottom plate, the middle part of the leading screw is equipped with sliding block by screw thread, and the both ends of the sliding block are symmetrically welded with two L-type limits Position bar, the end of two L-type gag lever posts are separately mounted on two line slide rails, and described two line slide rails are installed respectively On bottom plate, the upper surface of two L-type gag lever posts is respectively welded two fore-sets, and the upper end of the sliding block is welded with square Installing plate;Square installing plate on the sizing branch positions branch there are one being respectively mounted;The positioning branch includes being welded on Fixed plate on square installing plate side, the fixed plate are uniformly equipped with hydraulic cylinder successively from top to bottom;The hydraulic cylinder is equal It is fixedly mounted on fixed frame;The fixed frame is welded on square installing plate;The telescopic rod of the hydraulic cylinder is installed in fixed On template;Two fore-set upper surfaces on the sizing branch are resisted against on the lower face of corresponding square installing plate;It is described fixed The lower face of template is far below the lower face of bottom plate;
Its specific method of work is as follows:In use, two bridge pier modular systems are placed in required bridge pier construction in opposite directions Position, determine needed for bridge pier size and size, each sizing branch is then adjusted according to the size of required bridge pier and size Position, first adjust left side sizing branch position, driving motor start to work, driving motor drive leading screw rotate, leading screw Band movable slider moves, since two L-type gag lever posts of sliding block both sides move on two line slide rails so that sliding block can only be in water For linear motion in plane, the square installing plate above sliding block is stopped after moving to suitable position, then adjusts successively again The sizing branch on the front side, trailing flank and right flank of two bridge pier modular systems is saved, after sizing branch is regulated; Start to adjust positioning branch, first start to adjust the positioning branch in left side, the hydraulic cylinder corresponded in fixed plate is started to work, hydraulic cylinder The stereotype plate of front side is driven to pour mouth movement in bridge pier, hydraulic cylinder stops work when the position of stereotype plate is adjusted to required position Make, then adjust the positioning branch on the front side, trailing flank and right flank of two bridge pier modular systems successively again, work as adjusting After good all positioning branches, the space that is formed between the stereotype plate on each positioning branch is exactly that required bridge pier pours mouth.
CN201610442985.2A 2016-06-21 2016-06-21 A kind of bridge pier modular system Expired - Fee Related CN105951604B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610442985.2A CN105951604B (en) 2016-06-21 2016-06-21 A kind of bridge pier modular system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610442985.2A CN105951604B (en) 2016-06-21 2016-06-21 A kind of bridge pier modular system

Publications (2)

Publication Number Publication Date
CN105951604A CN105951604A (en) 2016-09-21
CN105951604B true CN105951604B (en) 2018-05-25

Family

ID=56906732

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610442985.2A Expired - Fee Related CN105951604B (en) 2016-06-21 2016-06-21 A kind of bridge pier modular system

Country Status (1)

Country Link
CN (1) CN105951604B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107161711B (en) * 2017-07-04 2019-01-22 江苏省苏中建设集团股份有限公司 A kind of building hollow brick catcher

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001009822A (en) * 1999-06-28 2001-01-16 Sato Kogyo Co Ltd FORM APPARATUS FOR MANUFACTURING HOLLOW PCa MEMBER
JP2010173239A (en) * 2009-01-30 2010-08-12 Tiger Machine Seisakusho:Kk Mold form replacement device
CN104695979A (en) * 2015-02-16 2015-06-10 中交一航局第一工程有限公司 Method for integrally and transversely moving high and large formwork through high and large trolley
CN104984862A (en) * 2015-07-03 2015-10-21 安庆联泰电子科技有限公司 Steel pipe surface coating machine
CN204715332U (en) * 2015-06-10 2015-10-21 中交第二航务工程局有限公司 A kind of moveable gallery inner formwork system
CN105196404A (en) * 2015-09-30 2015-12-30 苏州新协力特种工业模板有限公司 Bi-directionally moving forming board mechanism

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001009822A (en) * 1999-06-28 2001-01-16 Sato Kogyo Co Ltd FORM APPARATUS FOR MANUFACTURING HOLLOW PCa MEMBER
JP2010173239A (en) * 2009-01-30 2010-08-12 Tiger Machine Seisakusho:Kk Mold form replacement device
CN104695979A (en) * 2015-02-16 2015-06-10 中交一航局第一工程有限公司 Method for integrally and transversely moving high and large formwork through high and large trolley
CN204715332U (en) * 2015-06-10 2015-10-21 中交第二航务工程局有限公司 A kind of moveable gallery inner formwork system
CN104984862A (en) * 2015-07-03 2015-10-21 安庆联泰电子科技有限公司 Steel pipe surface coating machine
CN105196404A (en) * 2015-09-30 2015-12-30 苏州新协力特种工业模板有限公司 Bi-directionally moving forming board mechanism

Also Published As

Publication number Publication date
CN105951604A (en) 2016-09-21

Similar Documents

Publication Publication Date Title
CN107662880B (en) Adjusting method of adjustable lifting appliance for lifting flat plate
CN109399432B (en) A kind of hoistway job platform that climbs certainly
CN105926459A (en) Bridge building steel frame equipment
CN202116239U (en) Lifting device for disassembling small parts
CN209169778U (en) A kind of electric equipment maintenance transport lifting device
CN207759936U (en) A kind of trolley bridge crane
CN109209459A (en) A kind of moving supporting device used for constructing tunnel
CN105951604B (en) A kind of bridge pier modular system
CN204552590U (en) A kind of car ladder for electrification railway contact net maintenance
CN202785371U (en) Novel simple girder bridge type crane
CN209618689U (en) Liftable type D type beam pacifies portal frame of disassembling and using
CN104612580B (en) A kind of car ladder for electrification railway contact net maintenance
CN208811028U (en) A kind of chain provision for disengagement
CN206645725U (en) A kind of adjustable bridge crane of span
CN213133772U (en) Spraying control device for rain test box
CN214428963U (en) Power distribution cabinet
CN206328096U (en) A kind of airduct mounting platform based on BIM technology
CN105926460B (en) A kind of special sizing frame of bridge pier modular system
CN208456077U (en) A kind of independent wall construction bracket
CN208939456U (en) A kind of 10kV distribution line construction tension-resistant rod outlet tool
CN212771758U (en) Positioning and fixing device for truss switch tie iron baffle
CN219470695U (en) Pier body top die supporting device
CN105369787B (en) A kind of water surface fence collects guider
CN221027302U (en) Span adjustable beam lifter
CN220504630U (en) Steel truss construction bearing structure encorbelments of steel construction building

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhang Suqin

Inventor after: Li Mengqi

Inventor after: Zhang Li

Inventor after: Li Yilin

Inventor after: Duo Yuqing

Inventor after: Peng Wusi

Inventor after: Wang Yuan

Inventor after: Li Hua

Inventor after: Li Yuqi

Inventor after: Fu Yanshi

Inventor after: Zhang Guofeng

Inventor after: Li Xuerong

Inventor after: Han Li

Inventor after: Zhang Yongfu

Inventor before: Peng Wusi

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20180425

Address after: No. 6, Jian Xi Street, Chuan Hui District, Zhoukou, Henan

Applicant after: Wang Yuan

Applicant after: Li Yilin

Applicant after: Duo Yuqing

Applicant after: Peng Wusi

Applicant after: Li Hua

Applicant after: Li Yuqi

Applicant after: Fu Yanshi

Applicant after: Zhang Guofeng

Applicant after: Li Xuerong

Applicant after: Han Li

Applicant after: Zhang Yongfu

Applicant after: Zhang Li

Address before: 246001 171-52 North Main Street, Daguan District, Anqing, Anhui

Applicant before: Peng Wusi

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180525

Termination date: 20190621

CF01 Termination of patent right due to non-payment of annual fee