CN105908738A - Large-dimension steel and concrete combined hollow anti-slide pile and construction method thereof - Google Patents

Large-dimension steel and concrete combined hollow anti-slide pile and construction method thereof Download PDF

Info

Publication number
CN105908738A
CN105908738A CN201610480910.3A CN201610480910A CN105908738A CN 105908738 A CN105908738 A CN 105908738A CN 201610480910 A CN201610480910 A CN 201610480910A CN 105908738 A CN105908738 A CN 105908738A
Authority
CN
China
Prior art keywords
pile
steel
concrete
section
stake holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610480910.3A
Other languages
Chinese (zh)
Other versions
CN105908738B (en
Inventor
高涌涛
许强
赵建军
赵晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Univeristy of Technology
Original Assignee
Chengdu Univeristy of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Univeristy of Technology filed Critical Chengdu Univeristy of Technology
Priority to CN201610480910.3A priority Critical patent/CN105908738B/en
Publication of CN105908738A publication Critical patent/CN105908738A/en
Application granted granted Critical
Publication of CN105908738B publication Critical patent/CN105908738B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to geotechnical engineering, in particular to a large-dimension steel and concrete combined hollow anti-slide pile and a construction method thereof. The large-dimension steel and concrete combined hollow anti-slide pile comprises a plurality of pile sections which form a square framework by virtue of steel products, wherein concrete covers the inner side and the outer side of the square framework; the steel products are exposed from the upper end and the lower end of the concrete at the inner side; the pile sections are stacked up and down; a connecting point is formed between the steel products of upper and lower adjacent pile sections; and the connecting point is provided with a secondary concrete layer. The large-dimension steel and concrete combined hollow anti-slide pile provided by the invention is mounted in stages in a hole forming process, the mounted pile sections can be used as a protective structure, and are also used as one part of an anti-slide engineering pile, so that the construction speed is shortened, and the materials are saved; and the large-dimension steel and concrete combined hollow anti-slide pile has greater bending rigidity and better structure ductility, so that greater anti-slide bearing capacity can be obtained when the wall thickness is relatively small.

Description

Heavy-gauge steel and the hollow friction pile of Combined concrete and construction method thereof
Technical field
The present invention relates to Geotechnical Engineering, specially heavy-gauge steel and the hollow friction pile of Combined concrete.
Background technology
In Geotechnical Engineering, Rock And Soil can produce slip deformation under other effects such as additional load, deadweight, water, earthquake, for eliminating These deformation can use some antiskid structures, and wherein conventional a kind of antiskid structure is exactly friction pile, and friction pile can utilize its anchor Gu the part in stable Rock And Soil is as its fixing end, utilize its strength of materials to ensure that it does not destroys under load action, profit Obtain certain rigidity by its heavy in section size, thus ensure that it does not produce big deformation under load action, thus ensure sliding The stability of slope body.
The sectional dimension of the friction pile used at present is generally all at more than 2m, and material is substantially all employing armored concrete, and cross section is adopted By rectangle or square solid section form, stake holes typically uses manually digging hole, for ensureing stake safety in pore forming process, needs The supporting construction of stake holes is made stage by stage to ensure the safety of pore-forming personnel and equipment in pore forming process.
Reinforced concrete anti-slide pile is relatively big due to sectional dimension, comes down in addition and is mostly typically in the field of remote districts, uses The mode of mechanical hole building is relatively difficult, so great majority all use manual pore-forming's mode.The solid friction pile of existing armored concrete Deficiency have 5 points: first, during manual pore-forming, hole wall likely produces landslide under various loads and effect, therefore just needs Want limit pore-forming limit supporting, so can affect construction speed;Second, stake just must can water coagulation when pore-forming to absolute altitude at the bottom of stake Soil, construction speed to be affected;3rd, solid reinforced concrete anti-slide pile is analyzed from the ultimate principle of the mechanics of materials, wherein Near the heart, the material in a certain scope can not play a role, and wastes material;4th, if piled anchor composite construction to be done, Anchor head must be outside stake;5th, it is impossible to use precast construction, it is impossible to realize construction industry metaplasia and produce.
Summary of the invention
For above-mentioned technical problem, the present invention provides a kind of prefabricated friction pile, accelerating construction progress.
Concrete technical scheme is:
Heavy-gauge steel and the hollow friction pile of Combined concrete, including multiple pile sections, described pile section is formed quadra by steel, In described quadra, outside is surrounded by concrete;Described inner side concrete upper and lower side exposes steel, described pile section levels Folded, form junction point between the steel of neighbouring pile section, at junction point, have second coagulation soil LIFT.
Described steel are steel plate or shaped steel.
This heavy-gauge steel and the construction method of the hollow friction pile of Combined concrete, including procedure below:
(1) in the prefabricated pile section of precasting yard;
(2) digging in-situ stake holes, the stake holes degree of depth is a pile section;
(3) pile sinking joint in stake holes, then open next joint stake holes;
(4) after having excavated, just putting second section pile section, second section pile section is connected formation junction point 4 with first segment pile section, connects Rear pouring junction concrete forms second coagulation soil LIFT 3;
(5) the next stake holes of excavation is continued, the most repeatedly until whole pile installs.
Heavy-gauge steel and the hollow friction pile of Combined concrete that the present invention provides, uses built-in steel plate or shaped steel, external wrapping concrete Combinative structure form, can carry out prefabricated according to design drawing at the scene, and it can be installed in pore forming process stage by stage, peace The pile section installed both can have been worked as safeguard structure and use, and is again a part for Anti-slide engineering stake, kills two birds with one stone;And the installation of pile section Carry out with manual pore-forming simultaneously, save the duration;Hollow parts not only can become the working place of pore-forming workman, and Also save material;Compared to reinforced concrete section, under equal conditions, steel and Combined concrete cross section have bigger bending resistance firm Degree and better structure ductility, can obtain bigger antiskid bearing capacity in the case of less wall thickness.Heavy-gauge steel and coagulation local soil type Close hollow friction pile, have safety good, save material, good mechanical property, short construction period, can realize industry metaplasia Several big advantages such as product.
Accompanying drawing explanation
Fig. 1 is the cross-sectional structure schematic diagram of the present invention;
Fig. 2 is the construction schematic diagram of the present invention.
Detailed description of the invention
The detailed description of the invention of the accompanying drawings present invention.
Heavy-gauge steel and the hollow friction pile of Combined concrete, including multiple pile sections, described pile section is formed quadra by steel 1, In described quadra, outside is surrounded by concrete 2;Described inner side concrete upper and lower side exposes steel 1, and described pile section is upper and lower Stacking, forms junction point 4, has second coagulation soil LIFT 3 at junction point 4 between the steel of neighbouring pile section.
Described steel are steel plate or shaped steel.
The combinative structure that pile section is made up of the concrete bi-material of built-in steel plate or shaped steel and outsourcing, its steel 1 thickness is general about Being 2~5mm, strength grade of concrete typically uses more than C25, and the two forms combinative structure, and concrete parts can limit steel The outer unstability of the material 1 plane under horizontal shear effect, to ensure that steel 1 bearing capacity planar can obtain good performance, Can also protect steel non-corrosive, steel 1 are in close contact with concrete 2 can limit concrete cracking, improves concrete simultaneously Durability.The cross section of heavy-gauge steel and the hollow friction pile of Combined concrete is as shown in Figure 1.
Heavy-gauge steel and the work progress of the hollow friction pile of Combined concrete, as in figure 2 it is shown, first at precasting yard according to structural design drawing The prefabricated peg board of paper and pile section, be then manually started into stake holes, just can save by pile sinking, at this moment stake when the stake holes degree of depth is a pile section length Joint is the safety support fender pile of next section of stake holes pore-forming, is again a part for antiskid structure.After completing Deng next joint pore digging, Just putting second section pile section, second section pile section is connected formation junction point 4 with first segment pile section, waters junction concrete and formed after connection Second coagulation soil LIFT 3, then proceedes to excavate stake holes, the most repeatedly until whole pile installs.

Claims (3)

1. heavy-gauge steel and the hollow friction pile of Combined concrete, it is characterised in that: including multiple pile section, described pile section is by steel In forming quadra, described quadra, outside is surrounded by concrete;Described inner side concrete upper and lower side exposes steel, institute The pile section stacked on top of one another stated, forms junction point, has second coagulation soil LIFT at junction point between the steel of neighbouring pile section.
Heavy-gauge steel the most according to claim 1 and the hollow friction pile of Combined concrete, it is characterised in that: described steel For steel plate or shaped steel.
Heavy-gauge steel the most according to claim 1 and 2 and the construction method of the hollow friction pile of Combined concrete, it is characterised in that: Including procedure below:
(1) in the prefabricated pile section of precasting yard;
(2) digging in-situ stake holes, the stake holes degree of depth is a pile section;
(3) pile sinking joint in stake holes, then open next joint stake holes;
(4) after having excavated, just putting second section pile section, second section pile section is connected formation junction point 4 with first segment pile section, connects Rear pouring junction concrete forms second coagulation soil LIFT 3;
(5) the next stake holes of excavation is continued, the most repeatedly until whole pile installs.
CN201610480910.3A 2016-06-24 2016-06-24 Heavy-gauge steel and the hollow friction pile of Combined concrete and its construction method Expired - Fee Related CN105908738B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610480910.3A CN105908738B (en) 2016-06-24 2016-06-24 Heavy-gauge steel and the hollow friction pile of Combined concrete and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610480910.3A CN105908738B (en) 2016-06-24 2016-06-24 Heavy-gauge steel and the hollow friction pile of Combined concrete and its construction method

Publications (2)

Publication Number Publication Date
CN105908738A true CN105908738A (en) 2016-08-31
CN105908738B CN105908738B (en) 2017-11-24

Family

ID=56758651

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610480910.3A Expired - Fee Related CN105908738B (en) 2016-06-24 2016-06-24 Heavy-gauge steel and the hollow friction pile of Combined concrete and its construction method

Country Status (1)

Country Link
CN (1) CN105908738B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374410A (en) * 2018-03-29 2018-08-07 中铁上海设计院集团有限公司 A kind of waveform sheet metal-Combined concrete hollow section pile pile and its manufacturing method
CN110144881A (en) * 2019-05-10 2019-08-20 中国建筑西南勘察设计研究院有限公司 One kind is drowned oneself type precast hollow friction pile and its construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5934329A (en) * 1982-08-17 1984-02-24 Fujita Corp Pile
JP2008184822A (en) * 2007-01-30 2008-08-14 Nihon Samicon Co Ltd Load bearing material
CN103046543A (en) * 2013-01-09 2013-04-17 中国地质大学(武汉) Antiskid pile with hollow outer isosceles trapezoid cross section and in unequal interval arrangement
CN204151798U (en) * 2014-09-24 2015-02-11 沈阳建筑大学 A kind of steel reinforced concrete anti-slide pile structure
CN104762980A (en) * 2015-04-07 2015-07-08 兰州理工大学 Energy dissipation, shock absorption and anti-liquefaction rigid and flexible slide-resistant pile and construction method
CN204456141U (en) * 2014-12-09 2015-07-08 甘肃建筑职业技术学院 A kind of pre-stress hollow antislide pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5934329A (en) * 1982-08-17 1984-02-24 Fujita Corp Pile
JP2008184822A (en) * 2007-01-30 2008-08-14 Nihon Samicon Co Ltd Load bearing material
CN103046543A (en) * 2013-01-09 2013-04-17 中国地质大学(武汉) Antiskid pile with hollow outer isosceles trapezoid cross section and in unequal interval arrangement
CN204151798U (en) * 2014-09-24 2015-02-11 沈阳建筑大学 A kind of steel reinforced concrete anti-slide pile structure
CN204456141U (en) * 2014-12-09 2015-07-08 甘肃建筑职业技术学院 A kind of pre-stress hollow antislide pile
CN104762980A (en) * 2015-04-07 2015-07-08 兰州理工大学 Energy dissipation, shock absorption and anti-liquefaction rigid and flexible slide-resistant pile and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374410A (en) * 2018-03-29 2018-08-07 中铁上海设计院集团有限公司 A kind of waveform sheet metal-Combined concrete hollow section pile pile and its manufacturing method
CN110144881A (en) * 2019-05-10 2019-08-20 中国建筑西南勘察设计研究院有限公司 One kind is drowned oneself type precast hollow friction pile and its construction method

Also Published As

Publication number Publication date
CN105908738B (en) 2017-11-24

Similar Documents

Publication Publication Date Title
JP6613358B2 (en) Ground improvement foundation structure
KR101530871B1 (en) Retaining Wall Having Natural Rock And Construction Method Thereof
KR101394235B1 (en) Method for constructing complex pile for great soft ground
CN105155554A (en) Deep foundation pit of arched supporting system
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
KR20130006420A (en) Method of constructing underground structure to be newly built
JP5259510B2 (en) Retaining wall and its construction method
JP6832101B2 (en) Reinforcement structure of embankment and reinforcement method of embankment
CN100513704C (en) Superposition pile for engineering reconstruction and pile forming method
CN105908738A (en) Large-dimension steel and concrete combined hollow anti-slide pile and construction method thereof
KR101187170B1 (en) Application of under pinning method in remodeling
JP6445892B2 (en) Method for constructing subsidence structure and subsidence structure
JP2019100070A (en) Foundation structure of offshore wind power generation facility, and construction method of the same
JP5228862B2 (en) Underground structure, construction method of underground structure
RU87718U1 (en) Injection Pile
KR20210047482A (en) Core wall structure of independent cassion for offshore runway
CN112832252B (en) Deep foundation pit supporting construction method with large height difference of two sides
JP6656901B2 (en) Construction method of segments and submerged structures
JP4438540B2 (en) Stress bearing material and construction method for underground continuous wall
CN211816333U (en) Circular parallelly connected friction pile
JP2018100508A (en) Building construction method
CN114396042A (en) Construction method of uplift pile in granite area
JP6948908B2 (en) Construction method of segments, buried structures and buried structures
KR20170129327A (en) Phc pile
JP4749858B2 (en) Method for enhancing bearing capacity in extension or reconstruction of superstructures of existing buildings

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171124

Termination date: 20200624

CF01 Termination of patent right due to non-payment of annual fee