CN105888686A - 一种可满足掘卸平行作业的卸压方法 - Google Patents

一种可满足掘卸平行作业的卸压方法 Download PDF

Info

Publication number
CN105888686A
CN105888686A CN201610325117.6A CN201610325117A CN105888686A CN 105888686 A CN105888686 A CN 105888686A CN 201610325117 A CN201610325117 A CN 201610325117A CN 105888686 A CN105888686 A CN 105888686A
Authority
CN
China
Prior art keywords
pressure relief
relief vent
rig
drilling rod
drill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610325117.6A
Other languages
English (en)
Other versions
CN105888686B (zh
Inventor
马金宝
刘虎
刘伟
梁东辉
陈帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Zhengtong Coal Industry Co Ltd
Original Assignee
Shaanxi Zhengtong Coal Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Zhengtong Coal Industry Co Ltd filed Critical Shaanxi Zhengtong Coal Industry Co Ltd
Priority to CN201610325117.6A priority Critical patent/CN105888686B/zh
Publication of CN105888686A publication Critical patent/CN105888686A/zh
Application granted granted Critical
Publication of CN105888686B publication Critical patent/CN105888686B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Remote Sensing (AREA)
  • Earth Drilling (AREA)

Abstract

本发明涉及煤矿技术领域,具体涉及一种可满足掘卸平行作业的卸压装置。其在掘进工作面保证卸压的前提下可提高掘进进尺,提高掘进施工效率。本发明的卸压方法的步骤包括:1)施工钻场;2)固定钻机;3)施工卸压孔;4)外抽钻杆;5)封孔;6)调移钻机。

Description

一种可满足掘卸平行作业的卸压方法
技术领域
本发明涉及煤矿技术领域,具体涉及一种可满足掘卸平行作业的卸压方法。
背景技术
冲击性煤层巷道在掘进过程中,必须提前对迎头卸压,当前我国冲击性煤层掘进需要掘进与卸压交替进行,主要方法是在迎头施工三个大直径卸压钻孔,钻孔深度30m,迎头卸压钻孔施工结束后,方可允许恢复掘进,预留10m保护带,故允许掘进20m,达到安全距离后停止掘进,再施工卸压钻孔30m,然后再掘进20m,按此循环。基本需要1天卸压3天掘进,大大影响了掘进效率,延长了掘进工程完成时间。
发明内容
本发明提供一种可满足掘卸平行作业的卸压方法,其在掘进工作面保证卸压的前提下可提高掘进进尺,提高掘进施工效率。
为解决现有技术存在的问题,本发明的技术方案是:一种可满足掘卸平行作业的卸压方法:其特征在于:所述的卸压方法的步骤包括:
1)施工钻场:在掘进巷道右侧施工一三角形钻场;
2)固定钻机:将大功率深孔液压钻机移至钻场,将钻机固定钻场内,调整钻机开孔方位和高度,开孔方位与巷道右侧夹角不超过11°,开孔高度为1.2-1.5m;
3)施工卸压孔:钻机调整好开孔方位、高度后,开始施工卸压孔,施工卸压孔所用钻杆为通水宽叶片钻杆,每根长度 1m,直径φ89mm,钻头材质为钢体式复合片钻头,直径为153mm,卸压孔在施工过程中,应保持钻杆匀速钻进,直至卸压孔施工至80-100m;
4)外抽钻杆:第一个卸压孔施工至80-100m后,外抽钻杆,外抽时应保持匀速;
5)封孔:钻杆全部抽出后,对卸压孔进行封孔,封孔材料为水泥、煤粉混合物,封孔长度为2m;
6)调移钻机:第一个卸压孔施工完毕,调移钻机,依次施工第二个
和第三个卸压孔,卸压孔间距为1.0-1.2m。
所述的钻场高度与巷道高度一致,钻场与巷道相通的一侧边长为7m,另一条边与迎头平行长度为5m,第三条边长度为9m。
所述的大功率深孔液压钻机的型号为ZDY4000LR。
与现有技术相比,本发明的优点如下:本发明掘卸平行作业技术的实施打破了传统的迎头卸压方法,突破了卸1天、掘3天的卸压手段,实现了掘进与卸压平行作业。通过该技术的实施,在起到防治冲击地压效果的同时大大提高了巷道掘进效率,提高了单位时间巷道掘进进尺。
附图说明
图1为本发明方法中钻场、卸压孔布置图;
图2为本发明方法中钻场、卸压孔断面布置图;
图中:1-钻场、2-卸压孔。
具体实施方式
下面结合附图对本设计做详细描述:
参见图1:一种可满足掘卸平行作业的卸压方法的步骤包括:
1)施工钻场:在掘进巷道右侧施工一三角形钻场1,所述的钻场1高度与巷道高度一致,钻场1与巷道相通的一侧边长为7m,另一条边与迎头平行长度为5m,第三条边长度为9m;
2)固定钻机:将大功率深孔液压钻机移至钻场1,大功率深孔液压钻机2的型号为ZDY4000LR;将钻机固定钻场1内,调整钻机开孔方位和高度,开孔方位与巷道右侧夹角不超过11°,开孔高度为1.2-1.5m;
3)施工卸压孔:钻机调整好开孔方位、高度后,开始施工卸压孔2,施工卸压孔2所用钻杆为通水宽叶片钻杆,每根长度 1m,直径φ89mm,钻头材质为钢体式复合片钻头,直径为153mm,卸压孔2在施工过程中,应保持钻杆匀速钻进,直至卸压孔2施工至80-100m;
4)外抽钻杆:第一个卸压孔2施工至80-100m后,外抽钻杆4,外抽时应保持匀速;
5)封孔:钻杆4全部抽出后,对卸压孔2进行封孔,封孔材料为水泥、煤粉混合物,封孔长度为2m;
6)调移钻机:第一个卸压孔2施工完毕,调移钻机,依次施工第二个和第三个卸压孔,卸压孔间距为1.0-1.2m。
运用该发明卸压方法:
1、卸压孔施工进尺由原来掘进1m巷道施工4.5m迎头卸压孔减少为2m,减少卸压孔施工2.5m。该技术自2015年3月底成功实施以来,综掘煤巷掘进6243m,累计减少卸压孔施工15608m,节约施工费用(单价27.5元/m)15608*27.5=42.922万元。
2.工作面掘卸关系由一天卸压三天掘进变为边卸边掘,提高了掘进速度,降低了人工单价。该技术实施以前开拓巷道人工费用为3600元/m,回采巷道人工费用为2800元/m;该技术实施以来开拓巷道人工费用为3300元/m,回采巷道人工费用为2240元/m,人工单价分别降低了300元/m和560元/m,该技术自2015年3月底成功实施以来,开拓巷道掘进1285m,回采巷道掘进4958m,累计节约人工费用560*4958+300*1285=316.198万元。
3.该技术共计节约资金投入42.922+316.198=359.12万元。

Claims (3)

1.一种可满足掘卸平行作业的卸压方法:其特征在于:所述的卸压方法的步骤包括:
1)施工钻场:在掘进巷道右侧施工一三角形钻场(1);
2)固定钻机:将大功率深孔液压钻机移至钻场(1),将钻机固定钻场(1)内,调整钻机开孔方位和高度,开孔方位与巷道右侧夹角不超过11°,开孔高度为1.2-1.5m;
3)施工卸压孔:钻机调整好开孔方位、高度后,开始施工卸压孔(2),施工卸压孔(2)所用钻杆为通水宽叶片钻杆,每根长度 1m,直径φ89mm,钻头材质为钢体式复合片钻头,直径为153mm,卸压孔(2)在施工过程中,应保持钻杆匀速钻进,直至卸压孔(2)施工至80-100m;
4)外抽钻杆:第一个卸压孔(2)施工至80-100m后,外抽钻杆,外抽时应保持匀速;
5)封孔:钻杆全部抽出后,对卸压孔(2)进行封孔,封孔材料为水泥、煤粉混合物,封孔长度为2m;
6)调移钻机:第一个卸压孔(2)施工完毕,调移钻机,依次施工第二个和第三个卸压孔,卸压孔间距为1.0-1.2m。
2.根据权利要求1所述的一种可满足掘卸平行作业的卸压方法:其特征在于:所述的钻场(1)高度与巷道高度一致,钻场(1)与巷道相通的一侧边长为7m,另一条边与迎头平行长度为5m,第三条边长度为9m。
3.根据权利要求1或2所述的一种可满足掘卸平行作业的卸压方法,其特征在于:所述的大功率深孔液压钻机(2)的型号为ZDY4000LR。
CN201610325117.6A 2016-05-17 2016-05-17 一种可满足掘卸平行作业的卸压方法 Expired - Fee Related CN105888686B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610325117.6A CN105888686B (zh) 2016-05-17 2016-05-17 一种可满足掘卸平行作业的卸压方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610325117.6A CN105888686B (zh) 2016-05-17 2016-05-17 一种可满足掘卸平行作业的卸压方法

Publications (2)

Publication Number Publication Date
CN105888686A true CN105888686A (zh) 2016-08-24
CN105888686B CN105888686B (zh) 2018-04-06

Family

ID=56717049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610325117.6A Expired - Fee Related CN105888686B (zh) 2016-05-17 2016-05-17 一种可满足掘卸平行作业的卸压方法

Country Status (1)

Country Link
CN (1) CN105888686B (zh)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102022133A (zh) * 2010-11-16 2011-04-20 郑州大学 区域瓦斯井下高压射流掏穴卸压防突方法
CN102086760A (zh) * 2010-12-20 2011-06-08 郑州大学 区域井下高压水力掏穴卸压开采煤层气方法
CN102094668A (zh) * 2010-12-20 2011-06-15 郑州大学 上抽巷高压水力掏穴卸压消突方法
CN102392678A (zh) * 2011-10-21 2012-03-28 河南煤业化工集团研究院有限责任公司 井上下联合压裂增透抽采瓦斯的方法
CN102587962A (zh) * 2012-04-13 2012-07-18 中国矿业大学 一种扩帮瓦斯抽采钻场的布置及支护方法
CN103306677A (zh) * 2013-05-26 2013-09-18 贵州省矿山安全科学研究院 一种快速石门揭煤工艺及防突方法
CN103362539A (zh) * 2013-07-31 2013-10-23 中国矿业大学 留巷钻场钻孔抽采卸压瓦斯的方法
CN203323801U (zh) * 2013-04-03 2013-12-04 喻希乐 井下高水压大流量水量串联式观测***
CN103982137A (zh) * 2014-05-19 2014-08-13 中国矿业大学 一种煤矿井下水力压裂钻孔方位角设计方法
CN104234685A (zh) * 2014-07-22 2014-12-24 华北科技学院 一种特厚煤层回采面防冲卸压钻孔错层布置方法

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102022133A (zh) * 2010-11-16 2011-04-20 郑州大学 区域瓦斯井下高压射流掏穴卸压防突方法
CN102086760A (zh) * 2010-12-20 2011-06-08 郑州大学 区域井下高压水力掏穴卸压开采煤层气方法
CN102094668A (zh) * 2010-12-20 2011-06-15 郑州大学 上抽巷高压水力掏穴卸压消突方法
CN102392678A (zh) * 2011-10-21 2012-03-28 河南煤业化工集团研究院有限责任公司 井上下联合压裂增透抽采瓦斯的方法
CN102587962A (zh) * 2012-04-13 2012-07-18 中国矿业大学 一种扩帮瓦斯抽采钻场的布置及支护方法
CN203323801U (zh) * 2013-04-03 2013-12-04 喻希乐 井下高水压大流量水量串联式观测***
CN103306677A (zh) * 2013-05-26 2013-09-18 贵州省矿山安全科学研究院 一种快速石门揭煤工艺及防突方法
CN103362539A (zh) * 2013-07-31 2013-10-23 中国矿业大学 留巷钻场钻孔抽采卸压瓦斯的方法
CN103982137A (zh) * 2014-05-19 2014-08-13 中国矿业大学 一种煤矿井下水力压裂钻孔方位角设计方法
CN104234685A (zh) * 2014-07-22 2014-12-24 华北科技学院 一种特厚煤层回采面防冲卸压钻孔错层布置方法

Also Published As

Publication number Publication date
CN105888686B (zh) 2018-04-06

Similar Documents

Publication Publication Date Title
CN101915083B (zh) 煤矿井上下联合抽采煤层气的方法
CN108331609B (zh) 顺层钻孔割缝卸压增透方法
CN104481578B (zh) 一种高瓦斯煤层大采高工作面瓦斯治理方法
CN108397227A (zh) 一种倾向递进消突巷道布置方法
CN108547618A (zh) 一种两步骤采矿方法遗留间柱的回收工艺
CN107060760A (zh) 一种煤矿回撤巷道预裂***放顶卸压的方法
CN109139012B (zh) 一种矿用链臂锯连续切顶造缝方法
CN103670496A (zh) 单一低透气性突出煤层沿空留巷与预抽区段煤层瓦斯方法
CN106869788B (zh) 移动式上向反井钻机
CN107524443B (zh) 不稳固特厚大矿体跨步连续自然崩落采矿方法
CN111058847B (zh) 一种厚大矿体连续大孔径深孔***机械化开采方法
CN106468177A (zh) 一种煤与瓦斯协调开采方法
CN108590649A (zh) 一种缓倾斜破碎薄矿脉中深孔开采方法
CN102678166A (zh) 单一厚煤层区域增透提高瓦斯抽采率的方法
CN108035714A (zh) 矸石零排放短面无煤柱开采法
CN102536238A (zh) 一种大倾角层状非煤固体矿床采矿方法
CN205422752U (zh) 暗挖车站中隔壁法中导洞内顶纵梁与中拱二衬同步施工结构
CN104594943A (zh) 一种用于瓦斯治理的地面复合l型钻井和瓦斯治理方法
CN108505999A (zh) 一种高突煤层工作面多巷布置方法
CN106437825A (zh) 一种高瓦斯矿井综放工作面高位钻孔的瓦斯抽采方法
CN108506000A (zh) 一种突出煤层平巷快速掘进方法
CN105240016A (zh) 缓倾斜薄层状玉石矿矿块切割条带拖曳充填采矿方法
CN104564056A (zh) 掘探一体机
RU2441167C1 (ru) Способ дегазации сближенного пласта
CN105888686B (zh) 一种可满足掘卸平行作业的卸压方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Liu Hu

Inventor after: Ma Jinbao

Inventor after: Liu Wei

Inventor after: Liang Donghui

Inventor after: Zhang Zixue

Inventor after: Mou Junkang

Inventor before: Ma Jinbao

Inventor before: Liu Hu

Inventor before: Liu Wei

Inventor before: Liang Donghui

Inventor before: Chen Shuai

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180406

Termination date: 20190517

CF01 Termination of patent right due to non-payment of annual fee