CN105862735A - X-shaped anti-floating uplift pile - Google Patents
X-shaped anti-floating uplift pile Download PDFInfo
- Publication number
- CN105862735A CN105862735A CN201610413535.0A CN201610413535A CN105862735A CN 105862735 A CN105862735 A CN 105862735A CN 201610413535 A CN201610413535 A CN 201610413535A CN 105862735 A CN105862735 A CN 105862735A
- Authority
- CN
- China
- Prior art keywords
- cone
- pile
- pile body
- floating
- enlarged
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/44—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/10—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
- E02D31/12—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2200/00—Geometrical or physical properties
- E02D2200/16—Shapes
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention belongs to the field of underground engineering construction and particularly relates to an X-shaped anti-floating uplift pile, characterized by comprising a pile body; the pile body is cylindrical, the pile body extends out to form a first cone and a second cone, the cones use the pile body as a rotational axis and are bottomless, the first cone is positioned above the second cone, vertexes of the cones are connected together, and planes of the first cone and second cone along the axis of the pile body are sections that are X-shaped after being sectioned. Bearing area of the pile is enlarged and is greater than 50% as high as a traditional pile with same section, more load may be borne, and total manufacture cost is thereby reduced; anti-floating area of the pile is enlarged, and floating of the pile is inhibited effectively; bearing area is enlarged, thereby effectively reducing length and sectional area of the pile.
Description
Technical field
The invention belongs to underground engineering construction field, particularly relate to a kind of X-type uplift pile.
Background technology
In China groundwater level region, particularly construct underground engineering in the saturated soft soil layer or silt thicker soil stratum of phreatic high all must use piling way to carry out consolidation process because being difficult to large area to carry out depths reason, but all must solve pilework and float and Carrying Capacity.
Pile foundation technology is varied, use cement mixing method, sand-gravel pile, timber in early days more, it is rarely employed at present, one is that the control management specialty such as the cement mixing method ratio of mud, defeated slurry amount and stirring number of times do not perfect, equipment is outmoded, backward in technique, there is mixing uniformity difference and pile quality instability problem;Two be sand-gravel pile in order to reinforce deeper silt soft soil foundation, long in time limit owing to existing, the problems such as post-construction deformation is big, be no longer serve as the building foundation treatment that requires of deformation;Three is that civil buildings have disabled timber basis.
Silt thicker soil basement process can also use bored concrete pile, beat bored concrete pile to hard stratum, make plummer, bored concrete pile has driven cast-in-place pile and Slurry drilled pile, but two kinds of method bored concrete piles there is also some technical barriers, and one is that driven cast-in-place pile exists pile body integrity problem in Deep Thick Soft Ground;Two is that Slurry drilled pile exists mud contamination problem, pile concrete pouring quality, pile bottom sediment cleaning and supporting course judge to be difficult to the problems such as monitoring, are susceptible to bored concrete pile foundation civil buildings differential settlement, cause wall body slit event, be owing to construction existing above-mentioned technical problem and causes.
Therefore, it is necessary to develop a kind of novel pile body structure, solve the problems referred to above.
Summary of the invention
In order to solve above-mentioned technical problem, the invention provides the X-type uplift pile of the anti-lift function area of a kind of loaded area expanding stake and stake.
The technical solution adopted in the present invention is:
A kind of X-type uplift pile, it is characterized in that, including pile body, described pile body is cylindrical, described pile body extends outside pile body and is formed with pile body as rotary shaft and without the first cone of bottom surface, the second cone, described first cone is positioned at the top of the second cone and the drift angle both it connects, described first cone, the second cone along place, pile body axis plane for cut open show face after cutting open in X-shaped.
Described first cone, the second cone size are identical.
Described first cone, the second cone are positioned at the top of described pile body.
Described first cone, the second cone are positioned at the middle part of described pile body.
Described first cone, the second cone are positioned at the bottom of described pile body.
The invention have the benefit that
1, the present invention expands the loaded area of stake, compares more traditional same cross section stake, and loaded area can increase by more than 50%, can carry more heavy load, thus reduce overall cost;
2, the present invention expands the anti-lift function area of stake, the lowest floating inhibiting stake;
3, invention increases loaded area, efficiently reduce length and the sectional area of stake.
Accompanying drawing explanation
Fig. 1 be the first cone in the present invention, the second cone be positioned at pile body bottom time main TV structure schematic diagram;
Fig. 2 be the first cone in the present invention, the second cone be positioned at pile body bottom time sectional structure schematic diagram;
Fig. 3 is the plan structure schematic diagram of the present invention;
Fig. 4-Fig. 7 be the first cone in the present invention, the second cone be positioned at pile body bottom time construction schematic diagram;
Fig. 8 be the first cone in the present invention, the second cone be positioned at pile body middle part time main TV structure schematic diagram;
Fig. 9 be the first cone in the present invention, the second cone be positioned at pile body middle part time sectional structure schematic diagram;
Figure 10-Figure 13 be the first cone in the present invention, the second cone be positioned at pile body middle part time construction schematic diagram.
Figure 14 be the first cone in the present invention, the second cone be positioned at pile body top time main TV structure schematic diagram;
Figure 15 be the first cone in the present invention, the second cone be positioned at pile body top time sectional structure schematic diagram;
Figure 16-Figure 19 be the first cone in the present invention, the second cone be positioned at pile body top time construction schematic diagram.
Detailed description of the invention
The invention will be further described below in conjunction with the accompanying drawings:
In figure, 1-pile body, 2-the first cone, 3-the second cone, 4-cylindrical hole, 5-bellmouth, 6-bellmouth, 7-ground.
Embodiment 1
As Figure 1-3, a kind of X-type uplift pile, including pile body 1, pile body 1 is cylindrical, pile body 1 extends outside pile body 1 and is formed with pile body 1 as rotary shaft and without first cone the 2, second cone 3 of bottom surface, first cone 2 is positioned at the top of the second cone 3 and the drift angle both it connects, first cone the 2, second cone 3 along place, pile body 1 axis plane for cut open show face after cutting open in X-shaped.
First cone the 2, second cone 3 size is identical.
First cone the 2, second cone 3 is positioned at the bottom of pile body 1.
As shown in figs. 4-7, Specific construction technique is as follows: (1) sequence of construction makes cylindrical hole 4 according to rotary churning pile technique;(2) in pile foundation near bottom, rig stretches out oblique churning driven, makes bellmouth 5;(3) rig up carries certain distance, stretches out reverse churning driven arm, again carries out making bellmouth 6;(4) one bottom sectional of formation is the stake holes of " X ";(5) descending reinforcing cage casting concrete becomes pile body 1.
Embodiment 2
As shown in Fig. 3,8,9, a kind of X-type uplift pile, including pile body 1, pile body 1 is cylindrical, pile body 1 extends outside pile body 1 and is formed with pile body 1 as rotary shaft and without first cone the 2, second cone 3 of bottom surface, first cone 2 is positioned at the top of the second cone 3 and the drift angle both it connects, first cone the 2, second cone 3 along place, pile body 1 axis plane for cut open show face after cutting open in X-shaped.
First cone the 2, second cone 3 size is identical.
First cone the 2, second cone 3 is positioned at the middle part of pile body 1.
As shown in figures 10-13, Specific construction technique is as follows: (1) sequence of construction makes cylindrical hole 4 according to rotary churning pile technique;(2) in the middle part of pile foundation, rig stretches out oblique churning driven, makes bellmouth 5;(3) rig up carries certain distance, stretches out reverse churning driven arm, again carries out making bellmouth 6;(4) one bottom sectional of formation is the stake holes of " X ";(5) descending reinforcing cage casting concrete becomes pile body 1.
Embodiment 3
As shown in Fig. 3,14,15, a kind of X-type uplift pile, including pile body 1, pile body 1 is cylindrical, pile body 1 extends outside pile body 1 and is formed with pile body 1 as rotary shaft and without first cone the 2, second cone 3 of bottom surface, first cone 2 is positioned at the top of the second cone 3 and the drift angle both it connects, first cone the 2, second cone 3 along place, pile body 1 axis plane for cut open show face after cutting open in X-shaped.
First cone the 2, second cone 3 size is identical.
First cone the 2, second cone 3 is positioned at the top of pile body 1.
As illustrated in figs. 16-19, Specific construction technique is as follows: (1) sequence of construction makes cylindrical hole 4 according to rotary churning pile technique;(2) in pile foundation near top, rig stretches out oblique churning driven, makes bellmouth 5;(3) rig up carries certain distance, stretches out reverse churning driven arm, again carries out making bellmouth 6;(4) one top profile of formation is the stake holes of " X ";(5) descending reinforcing cage casting concrete becomes pile body 1.
X-type uplift pile is different from general foundation pile, has the special performance of himself, is provided simultaneously with all features of anti-floating pile;Stake bottom increases loaded area, and economical, and pile body 1 can bear bigger building load pressure, and stress is transmitted at the bottom of stake from stake top;Equally, pile body 1 is resisted the dowel section area that building shifts up and is increased, and can bear bigger anti-floating power, accomplish economical and practical;But both mechanical behaviors are just the opposite.
Above 3 embodiments of the present invention are described in detail, but described content has been only presently preferred embodiments of the present invention, it is impossible to be considered the practical range for limiting the present invention.All impartial changes made according to the present patent application scope and improvement etc., within all should still belonging to the patent covering scope of the present invention.
Claims (5)
1. an X-type uplift pile, it is characterized in that, including pile body, described pile body is cylindrical, described pile body extends outside pile body and is formed with pile body as rotary shaft and without the first cone of bottom surface, the second cone, described first cone is positioned at the top of the second cone and the drift angle both it connects, described first cone, the second cone along place, pile body axis plane for cut open show face after cutting open in X-shaped.
A kind of X-type uplift pile the most according to claim 1, it is characterised in that described first cone, the second cone size are identical.
A kind of X-type uplift pile the most according to claim 1, it is characterised in that described first cone, the second cone are positioned at the top of described pile body.
A kind of X-type uplift pile the most according to claim 1, it is characterised in that described first cone, the second cone are positioned at the middle part of described pile body.
A kind of X-type uplift pile the most according to claim 1, it is characterised in that described first cone, the second cone are positioned at the bottom of described pile body.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610413535.0A CN105862735A (en) | 2016-06-14 | 2016-06-14 | X-shaped anti-floating uplift pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610413535.0A CN105862735A (en) | 2016-06-14 | 2016-06-14 | X-shaped anti-floating uplift pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105862735A true CN105862735A (en) | 2016-08-17 |
Family
ID=56649551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610413535.0A Pending CN105862735A (en) | 2016-06-14 | 2016-06-14 | X-shaped anti-floating uplift pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105862735A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1113528A (en) * | 1995-05-16 | 1995-12-20 | 张国梁 | Method and apparatus for foundation treatment |
CN101649611A (en) * | 2008-08-14 | 2010-02-17 | 张继红 | Wing-added hole-expanding pile and wing-added hole expander |
CN103362123A (en) * | 2013-07-05 | 2013-10-23 | 山东科技大学 | Reverse Y-shaped filling pile and construction method thereof |
CN103362120A (en) * | 2013-07-05 | 2013-10-23 | 山东科技大学 | Hollow hemispheric expanded-base cast-in-place pile and construction method thereof |
CN203559412U (en) * | 2013-10-22 | 2014-04-23 | 绍兴文理学院 | Anti-sidesway large-diameter composite cast-in-place concrete pile |
CN204703153U (en) * | 2015-05-23 | 2015-10-14 | 上海绿地建设(集团)有限公司 | A kind of barb type construction pile |
CN205676888U (en) * | 2016-06-14 | 2016-11-09 | 中铁隧道勘测设计院有限公司 | A kind of X-type uplift pile |
-
2016
- 2016-06-14 CN CN201610413535.0A patent/CN105862735A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1113528A (en) * | 1995-05-16 | 1995-12-20 | 张国梁 | Method and apparatus for foundation treatment |
CN101649611A (en) * | 2008-08-14 | 2010-02-17 | 张继红 | Wing-added hole-expanding pile and wing-added hole expander |
CN103362123A (en) * | 2013-07-05 | 2013-10-23 | 山东科技大学 | Reverse Y-shaped filling pile and construction method thereof |
CN103362120A (en) * | 2013-07-05 | 2013-10-23 | 山东科技大学 | Hollow hemispheric expanded-base cast-in-place pile and construction method thereof |
CN203559412U (en) * | 2013-10-22 | 2014-04-23 | 绍兴文理学院 | Anti-sidesway large-diameter composite cast-in-place concrete pile |
CN204703153U (en) * | 2015-05-23 | 2015-10-14 | 上海绿地建设(集团)有限公司 | A kind of barb type construction pile |
CN205676888U (en) * | 2016-06-14 | 2016-11-09 | 中铁隧道勘测设计院有限公司 | A kind of X-type uplift pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Tan et al. | Characteristics of a large-scale deep foundation pit excavated by the central-island technique in Shanghai soft clay. I: Bottom-up construction of the central cylindrical shaft | |
CN207109475U (en) | It is close to mountain high-filled subgrade stabilization and Deformation control structure | |
CN108035362A (en) | Mixing pile inner sleeve beats the foundation pit enclosure structure and construction method of quincunx bored concrete pile | |
CN202519694U (en) | Open caisson foundation structure under saturated water condition when geology is sludge layer | |
CN109594575A (en) | A kind of open caisson periphery grouting and reinforcing soil body construction method | |
CN109487777A (en) | A method of a reinforcing deep soft soil foundation of filling the span of a man's arms is formed using slip casing by pressure | |
CN108867673A (en) | A kind of underwater prevention method in the foundation pit based on the curtain that draws water | |
US10669687B1 (en) | Systems and methods for constructing retaining wall structure and well point in granular soils under groundwater level | |
CN205676888U (en) | A kind of X-type uplift pile | |
JP2003147782A (en) | Foundation structure for constructing new building on existing basement and its construction method | |
Al-Adhadh et al. | Reviewing the most suitable Soil Improvement Techniques for treating soft clay soil | |
CN114908782B (en) | Foundation pit dewatering construction method | |
CN105862735A (en) | X-shaped anti-floating uplift pile | |
CN213897154U (en) | Soft soil foundation pit bottom curing structure | |
RU2238366C1 (en) | Method of injection pile building | |
CN105951743A (en) | Plum blossom-shaped profile steel cement stirring wall | |
Wang et al. | Design and construction of deep excavations in Shanghai | |
CN205875128U (en) | Quincunx shaped steel cement stirring wall | |
CN106149729A (en) | A kind of building foundation pit quaternity circular section interlocking pile supporting construction | |
CN220686115U (en) | Basin-type curtain structure with strong permeable layer in pit | |
CN204491627U (en) | A kind of building foundation pit quaternity circular section interlocking pile supporting and protection structure | |
CN113668504B (en) | Grooving emergency reinforcing construction method for diaphragm underground diaphragm wall | |
CN211340768U (en) | Broken hard rock stratum reverse circulation drilling bored concrete pile | |
KR102051579B1 (en) | Soft ground improvement device and that method | |
KR20050012873A (en) | Method of constructing cantilevered continuous walls for retaining earth and cutting off water ang method of constructing wall structures while performing soil improvement at the same time.(C.R.C.W.: Cantilevered retaining cutting wall) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160817 |
|
WD01 | Invention patent application deemed withdrawn after publication |